Agency on Bay Management Al Taylor Gulfstream – Phase IV Expansion

advertisement
Agency on Bay Management
Gulfstream – Phase IV Expansion
July 13, 2006
Al Taylor
Vice President, Operations
1
Company Overview - Introduction
Placed into service in May 2002, Gulfstream is a stateof-the-art interstate natural gas transmission system
owned 50% by Duke Energy and 50% by Williams
The Company is under the joint management of Duke
Energy, which provides the business functions, and
Williams, which provides the technical functions
Gulfstream was specifically designed to serve peninsula
Florida (1.1 Bcfd)
The Pipeline consists of 692 total miles: onshore in
Florida (242 miles), Alabama and Mississippi (15 miles)
and offshore in the Gulf of Mexico (435 miles)
Compression consists of three Rolls Royce
compressors, one of which serves solely as back –up
(113,700 total horsepower) – located in Coden, AL
0605-11265 2
Company Overview: Map of Operations
0605-11265 3
Market Overview: Strong population growth and natural
gas demand 2004 - 2014
Florida’s population is growing 2% annually
Electric demand is growing 3% annually
Natural gas continues as fuel of choice for
new generation in the near term
Central and Southern Florida accounts for
most of the load growth –the market
Gulfstream was designed to serve
Population and power generation growth in Gulfstream’s market is expected to drive increased demand for natural gas
0605-11265 4
Recent History
Ê
2005
■
■
■
Ê
Phase II placed in service: February 2, 2005
Increased delivery points from 17 to 19
Contracted long-term firm transportation service,
increased to 753,000 Dth/d
2006
■
■
■
Phase III with FP&L announced March 2006
Phase IV with Progress Energy announced May 31, 2006
Contracted long-term firm transportation service increases
to 1,253,000 Dth/d
0605-11265 5
Market Projects
●
Phase III: Florida Power & Light
Ê
The project will sell out Gulfstream’s initial mainline capacity
Ê
Project summary:
■
■
■
■
●
35 mile, 30” diameter pipeline extension to FP&L’s new greenfield
2200 MW West County Energy Center in west Palm Beach County
Completion of facilities in 2008
Phase IV: Progress Energy
Ê
Project expands mainline capacity to 1,253,000 Dth/d
Ê
Project summary:
■
■
■
■
■
■
18 miles; 20” diameter pipeline extension to Progress Energy’s
“repowered” Bartow power plant in Pinellas County
45,000 h.p. compression addition to existing Gulfstream sites near
Coden, Alabama, and in Manatee County, Florida
Completion of facilities in 2008
0605-11265 6
Gulfstream Market Area
0605-11265 7
Company Overview: Summer Operations
2004 & 2005 Gulfstream experienced seven storms directly
impacting its market area and/or making landfall near Coden,
Alabama
Ê
Ê
Ê
Bonnie, Arlene and Dennis crossed our offshore pipeline
Charlie, Frances, and Jeanne crossed our market system
Ivan made landfall near Mobile Bay and our compressor operations
Gulfstream’s pipeline facilities sustained no material damage
Required surveys indicate offshore pipeline has not moved
Post 2004 Gulfstream purchased & installed additional emergency
generation at key communication points
Gulfstream’s electric generation at Coden, AL and Gas Treating
Facilities were critical components of reliable service
June 1, 2006 fuel retention reduced from 1.53% to 1.34%
0605-11265 8
Operations
Safety
• 24-hour monitoring
• Hydro test to 150% of MAOP
• Integrity Management Plan
• Remote control of critical system valves
• Patrols by air & ground
• Coordination with ER officials
• Participation in Florida One Call
• No Lost Time Accidents since Commissioning
0605-11265 9
Phase IV Overview
Progress
Energy
Bartow
Plant
Tampa
Bay
Proposed
20”
Lateral
Existing Gulfstream 36”
Natural Gas Pipeline
0605-11265 10
Preferred and Alternative Routes
0 1 2 Miles
0605-11265 11
Field Surveys - Conducted To Date
0 1 2 Miles
0605-11265 12
Field Surveys - Findings To Date
0 1 2 Miles
0605-11265 13
Field Surveys - Findings To Date
0
2,000 Feet
0605-11265 14
Route Variations
0 1 2 Miles
0605-11265 15
Field Surveys - Pending To Date
0 1 2 Miles
0605-11265 16
Preliminary Construction Plan
Interconnect
Hot tap to pipeline
0 1 2 Miles
0605-11265 17
Preliminary Construction Plan
HDD installation – Channel Crossings
Drilling support barge
Ch
an
ne
l
Dredged
Entrance Pit
Pipe pre-laid on bottom
n
tio
c
e
l
Dir f pul
o
Transition pipe ditch
Enlarged exit pit
Drill string
Not to scale
Drilling support barges
0605-11265 18
Preliminary Construction Plan
HDD installation –Shoreline Crossing
Drilling rig exit site limits
Sh
o re
lin
Wa
e
ter
Dredged
entrance pit
R.O
Drilling support
barges
Pipeline
on
i
t
ec ull
r
i
D fp
o
Drill string
.W
it
m
i
.l
Not to scale
0605-11265 19
Preliminary Construction Plan
Pre-Pipelay Dredging
O
R.
.W
t
mi
i
l
.
Not to scale
Dredge barge
Spoil
on
i
t
ec vel
r
i
D T ra
of
Pipe trench
Pipe
Spuds
Spoil
O
R.
.W
t
mi
i
l
.
Note: Spoil mounds will
alternate sides of the trench
as necessary to prevent
currents from re-filling trench
0605-11265 20
Preliminary Construction Plan
Conventional Pipe lay (Shallow Water)
Spuds for Station Keeping
O
R.
.W
it
m
i
.l
Not to scale
Tug Boat
t
mi
i
l
.
Pipeline
W
O.
.
R
Spoil (Side Cast to Either Side)
Dredged Trench
0605-11265 21
Tampa Bay Ship Channel
Channel Profile – Cut C
0
500 1,000 feet
0605-11265 22
Gulfstream Phase IV Schedule
0605-11265 23
Contact Information
Gulfstream Natural Gas System, L.L.C.:
Al Taylor, Vice President Operations, 941-723-7101,
al.taylor@williams.com
1-888-GAS-4-FLA
www.gulfstreamgas.com
FERC Certificate Process:
• FERC pre-filing Docket No. PF06-29-000
• Office of External Affairs, 1-866-208-3372
• www.ferc.gov/ for-citizens/my-rights/ process.asp
0605-11265 24
Download