Department of EnvironmentalProtection Jeb Bush Governor To: From: Date: Re: Colleen M. Castille Secretary Suzanne Cooper, Agency on Bay Management John A.Coates, P. E. July 11, 2006 Piney Point –StatusUpdate January throughApril,2006 The following isa statusupdate on Piney Point for distribution to the interestedparties. Closure: The following are the Engineer’srecommendednear term andlong term processwater consumption ratesto facilitate closure for the site: May -December 2006: After January 2007: 1. 0MGD * 0. 18MGD * Basedon current water levelsat the site, the site engineer iscontinuing the recommendedoverallwater consumpti on rate of1. 0MGD.The recommendedconsumpti on rate i ncl udesbothtreateddi schargesand spray evaporati on andi sbasedon an updatedwater bal ance projecti onsi ssuedby the Engi neer i n Apri l 2006. W orkduring May andJune continuedin the southcompartment ofthe SouthCooling Pond (SCP-S)to construct the 10-acre processwater sump.During early May construction efforts were focusedon building the partition dike that formsthe western wallofthe processwater sump.The first photographbelow showsthe early stagesofthe processwater sump on May 18 where the dike andsump bottom are beginning to take shape.Also during May, workersmoved to complete the last workon the Phase Iditchesincluding completion ofthe buriedseepage collection drain along the southwallofthe OldGypsum Stack(OGS), followedby construction ofthe linedstormwater ditchabove the burieddrain.The secondphotographbelow showsa portion ofthe linedstormwater ditchnear the southwest corner ofthe OGS, on May 18, being brought to finalgrade prior to liner installation. W hile the workwasongoing to complete the finalportionsofthe Phase Idrainsandditches, contractorswere also making goodprogresswithgypsum earthworkandgrading ofthe Phase II side slopesalong the outer face ofthe southandeast wallsofthe New Gypsum Stack(NGS). The thirdphotographbelow isan aerialofthe site on June 7focusing on the southeast corner of the NGS showing the ongoing gypsum earthworkon the southandeastern side slopesofthe NGS andthe initialworkon the Phase IIstormwater ditchesanddrains. During June, the partition dike for the processwater sump in the SCP-S compartment was completedallowing workto focuson the remaining dikesandplacement offillin the sump bottom to bring itto finaldesign grade.Similarly, the last ofthe liner hadbeen placedin the Phase Istormwater ditcheswithonly finaldetailing andacceptance remaining for early July, 2006.The fourthandfifthphotographsbelow show the progressin the processwater sump on June 23andthe completedliner installedin the Phase Iditchesnear the southwest corner ofthe OGS on June 29, respectively.Finally, the last photographbelow showsan egret on June 29on one ofthe cap areasthat wascompletedandgrassedearlier thisyear on top ofthe OGS after some beneficialrainsanda recent maintenance mowing. "More Protection, Less Process” Printed on recycled paper. Piney Point – Status Update July 11, 2006 Page 2 of 8 Printed on recycled paper. Piney Point – Status Update July 11, 2006 Page 3 of 8 Printed on recycled paper. Piney Point – Status Update July 11, 2006 Page 4of 8 Printed on recycled paper. Piney Point – Status Update July 11, 2006 Page 5of 8 Inches of Rainfall Runoff Storage Capacity and Water Inventory: During the most recent period through the end of June 2006, the total nominal water storage capacity at the site has remained fairly constant ending with just over 1,396 million gallons on July 3, 2006. This capacity corresponds to a nominal water storage capacity at the site of just over 112 inches of rainfall run-off over the watershed. Including emergency freeboard, these numbers increase to 1,456 million gallons or about 117 inches of rainfall run-off. The storage levels are more than adequate to contain multiple 100 year-24 hour storm events. The following figure shows the changes in nominal storage capacity since January 2003. 120 110 100 90 80 70 60 50 40 30 20 10 0 Nominal Storage Capacity 3 3 3 3 3 3 4 4 4 4 4 4 5 5 5 5 5 5 6 6 6 6 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 /0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 / 0 01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 /01 / 01 03 05 07 09 11 01 03 05 07 09 11 01 03 05 07 09 11 01 03 05 07 Figure 1* * Figure 1 shows the availability of approximately 1960 acre-feet of surge storage capacity in the lined NGS south compartment starting on September 1, 2005. Based on the availability of this third lined, but currently unused, water storage compartment, the calculation of rainfall runoff values was adjusted to consist of rainfall over the entire process watershed of approximately 457 acres. Bishop Harbor: During May and June 2006, water treatment and discharge to Bishop Harbor averaged just under 0.7 MGD which is increased compared to the average for the first four months of 2006. As ammonia removal efficiencies have increased with daily temperatures, the daily concentration of ammonia-nitrogen has decreased slightly from 5.0 mg/L earlier in 2006 to 3.8 mg/L during the most recent period. Similarly, the average ammonia nitrogen loading during the past two months was increased from just under 22 to 25mg/L. However, by the end of June, the 30-day average had decreased to a minimum for the period of just over 12 lb/d. During the past two months contractors increased treatment rates to further reduce process water levels and went above the guideline of 20 pounds per day for a limited amount of time. Contractors at the site continue to balance the need for consuming process water with maintaining low concentrations and ammonia nitrogen loading rates based in order to meet the recommended long-term water consumption rate of 1.0 MGD (including spray evaporation). Contractors at the site are continuing to closely monitoring performance of the treatment system and daily ammonia nitrogen loading in relation to the ongoing contractual guideline of 20 pounds per day and the upper target loading limit of 50 pounds per day as for ammonia-nitrogen. Printed on recycled paper. Piney Point – Status Update July 11, 2006 Page 6 of 8 During the most recent period, Department staff have continued to observe the presence of Ruppia, a variety of seagrass, near the Bishop Harbor sampling sites. Information on Bishop Harbor Water quality, sediment, seagrass, macroalgae and other data can be reviewed and downloaded from a Web Site constructed and maintained by Janicki & Associates. The information on the Web Site is updated on a routine basis and can be found at: http://www.janickienvironmental.com/bishopharbor/index.html The figure below shows the 15-day and 30-day ammonia nitrogen loadings since January 2004, as well as the revised target loading limit of 50 pounds per day or less. Average Ammonia-Nitrogen Loading - Since January 2004 300 250 Target loading,lbs/day 15-day Average NH3-N loading,lbs/day 30-day Average NH3-N loading,lbs/day 200 150 100 50 0 4 4 4 4 4 4 4 4 4 4 4 4 5 5 5 5 5 5 5 5 5 5 5 5 6 6 6 6 6 6 6 - 0 b - 0 r - 0 r - 0 y - 0 n - 0 l - 0 g - 0 p - 0 t - 0 v - 0 c - 0 n - 0 b - 0 r - 0 r - 0 y - 0 n - 0 l - 0 g - 0 p - 0 t - 0 v - 0 c - 0 n - 0 b - 0 r - 0 r - 0 y - 0 n - 0 l- 0 n J a F e M a A p M a J u J u A u S e O c N o D e Ja F e M a A p M a J u J u A u S e O c N o D e J a F e M a A p M a Ju Ju Figure 2 Total Process Water Consumption: The spray evaporation system in the NGS-N reservoir has been operating since May 2005 followed by additional spray evaporation systems that were placed into service in July 2005. During the months of May and June 2006, the spray evaporation systems continued to remove process water from the site;however, a small number of the sprays from the floating system in the NGS-N reservoir were dismantled in response process water levels that were too low to float all of the spray system’s header pipes. During the period of May 2006 through July 3, 2006, 17.4 million gallons of water was consumed by spray evaporation. Overall calculated evaporation rates were increasing during this period due to seasonal increases in temperature. Including consumption from spray evaporation, the total consumption rate during this period was approximately 76.8 million gallons, or approximately 1.2 MGD;thus, total consumption for this past period averaged higher than the current recommended rate of 1.0 MGD. Printed on recycled paper. Piney Point – Status Update July 11, 2006 Page 7 of 8 The water consumption rates, shown in Figure 3 below for the period through July 3, 2006, reflect the seasonal increase in spray evaporation along with water treatment and discharge which declined slightly through this period. The figure below shows the weekly spray evaporation amounts beginning in May 2005, along with the weekly volumes of treatment discharges to Bishop Harbor since January 1, 2004. Process Water Consumption 20,000,000 R. Osmosis Treatment Double Lime Treatment Spray Evaporation Total Consumption G allons per Week 15,000,000 10,000,000 5,000,000 01 /0 1 03 /0 4 /0 1/ 05 0 4 /0 1 07 /0 4 /0 1/ 09 0 4 /0 1/ 11 0 4 /0 1 01 /0 4 /0 1 03 /0 5 /0 1/ 05 0 5 /0 1 07 /0 5 /0 1/ 09 0 5 /0 1/ 11 0 5 /0 1 01 /0 5 /0 1 03 /0 6 /0 1 05 /0 6 /0 1/ 07 0 6 /0 1/ 06 0 Figure 3 Rainfall: During the first six months through June 2006, rainfall at Piney Point was approximately 10 inches below normal rainfall totals. Similarly, for the 2005 calendar year, rainfall at the site was from 10 to 11 inches below normal. Most recently, in the month of June, actual rainfall was just above normal by approximately 0.3 inches. Actual and predicted monthly rainfall is shown for the period since January 2004 through June 2006, in the figure below: Printed on recycled paper. Inches of Rain Piney Point – Status Update July 11, 2006 Page 8 of 8 10 9 8 7 6 5 4 3 2 1 0 Piney Point Rainfall Predicted Actual 04 0 4 04 04 04 -04 05 0 5 05 05 05 -05 06 0 6 06 06 n- ar- ay- ul- ep- ov a n- ar- ay- ul- ep- ov a n- ar- ay- ula J J S J S J J M M M M N M M J N Figure 4 Please contact me at (850) 488-8217, if there are any questions. cc: Mike Sole Deborah Getzoff Mimi Drew Rick Cantrell Phil Coram Louis Timchak Printed on recycled paper.