HABITAT IMPROVEMENT Fishery Division PROJECT P. 0. BOX 3503

advertisement

HABITAT IMPROVEMENT

PROJECT

Fishery Division

WOE CC MMINIl1

OREGON STATE GAME COMMISSION

P. 0. BOX 3503

PORTLAND, OREGON 97208

Clear Creek Projeat

Number 11

COLUMBIA RIVER FISHERY DEVELOPMENT PROGRAM

Closing Report

AGENCY: Oregon State Game Commission

PROJECT TITLE: Habitat Improvement to Enhance Anadromous Fish Production

PROJECT NO: 221.2-0G-2.2

CONTRACT NO 14-17-0001-1014

PERIOD COVERED: December 1960 through June 30, 1965

By Duane C. West, James A. Reeher, Jr., James A. Hewkin

ABSTRACT

Clear Creek, tributary of North Fork John Day River, is a mountain stream located in the Blue Mountains of eastern Oregon.

It joins Granite Creek about

1.5 miles below the old abandoned mining town of Granite.

Gravel removed from

Clear Creek by gold dredging activity was replaced in a 3.37-mile section of the stream in 1961.

The purpose of this work was to provide new spawning areas and resting pools to accommodate adult spring chinook salmon.

A total of 123 hours was required to move an estimated 13,158 cubic yards of gravel into the channel.

The cost was $1,470 or 110 per cubic yard.

Physical stream surveys indicated that a considerable amount of the introduced gravel washed from the areas of introduction but in most cases was still usable.

Log barriers worked satisfactorily as a means of stabilizing the gravel.

At the peak of the spawning period each year, observations were conducted to determine the amount of spring chinook activity on the introduced and natural gravels of the stream.

These observations indicated that the run of salmon increased during the study period.

One chinook redd was examined periodically to determine the rate of development and approximate time of fry emergence from the gravel.

The young salmon remained in the gravel for eight months before emerging.

The slow rate of development is attributed to low temperatures during the winter months.

A limited number of intragravel dissolved oxygen samples were also taken

® 2 during the time of egg development.

The dissolved oxygen content was satisfactory for egg and fry development.

REPORT OF OPERATIONS

During the spring of 1961 the project area was selected for the study on the lower portion of Clear Creek.

The stream section 3,37 miles in length had been left almost entirely devoid of spawning gravel by past gold dredging operations

(see Figure 1).

After selection of the site, particular attention was given to the composition of the tailings adjacent to the stream and plots were chosen accordingly.

Tailings that were selected generally consisted of gravel ranging from 0.25 to 2.5 inches in diameter with some scattered larger rocks.

A D-7 tractor operated eight hours a day spreading gravel in the channel to a depth of two to three feet.

The width of the channel varied considerably throughout but averaged 21 feet.

A total of 123 hours was required to move an estimated

13,158 cubic yards of gravel.

At the rate of $12.00 an hour for the tractor and operator, the cost of moving the gravel was $1,470 or 110 a cubic yard.

Large quantities of gravel tailings adjacent to the stream were readily available.

Forty-eight plots 1,772 yards in length were established and numbered in three groups.

The "A" plots were located in the lower 1.5 miles of the project area and numbered from the upstream end downstream.

The "B" plots started at the mouth of Congo Gulch

200 yards upstream from plot A-1 and were numbered from the downstream end upstream.

The "C" plot was located between plots A-1 and B-1.

In the 3.37 miles of stream the drop in elevation was 218.24 feet and the overall gradient 1.21 percent.

Table 1 presents the 1961 and 1964 survey data, and shows the elevation and gradient differences before and after the addition of gravel.

During the spring runoff the following years, a portion of the gravel washed from the lower end of the plots.

In some cases the gradients were improved and the gravel located in a more stable position.

Generally, the B plots in the upper stream had a higher percentage of washing than did the A and C plots in the

3

Table 1

Gradient and Elevation Survey, Clear Creek, 1961 1964

Plot

Number

Length of

Plot ft,

1961 Elevation 1964 Elevation

U stream Downstream U stream Downstream

1961 Gradient

ercent

1964 Gradient ercent

21A

20A

19A

18A

17A

16A

15A

14A

13A

12A

11A

10A

9A

8A

7A

6A

5A

4

3A

2A

1A

39

18

210

1,179

48

36

120

45

54

30

72

180

111

555

42

24

114

18

117

330

6o

100

90.54

101,45

-

103,71

105.91

-

115,70

118,87

-

126,08

144 92

-

148,68

151,33

155.10

157.73

160,60

162.91

167.70

172,14

185,13

90,13

98,14

-

103.37

103,91

-

115.24

116.61

-

125,09

128.16

-

148.18

149.17

154,17

157.61

160,58

159.40

165.31

170.63

175,85

_ 1C

-

1B

2B

3B

4B

5B

6B

14B

15B

16B

17B

18B

19B

20B

21B

22B

7B

8B

9B

10B

11B

12B

13B

23B

24B

25B

26B

48

51

36

60

51

192

96

42

42

60

60

66

66

51

15

63

30

285

102

60

60

87

81

66

21

120

202,71

205,34

-

213,09

220,03

-

-

224,86

226.12

229.01

232,48

236.93

-

244,16

-

260.13

-

-

-

-

-

_

o

-

202.64

205.06

-

209.91

216,14

-

-

222,87

225.34

228,93

231.35

235.04

-

243.79

-

257.61

-

-

-

-

-

_

m

233,12

236,20

241.39

245.36

247.39

261,60

265.38

273,70

276,22

281,29

285,04

290,01

293,16

297.19

200,82

202,33

203.72

205,99

208,28

213.21

219,08

220.49

222,32

225.94

228,44

230.25

(Stream elevations are taken on the streambed.)

91,19

98.86

104.00

105,42

108,21

114,58

116,58

119,92

125.48

129,77

145,96

148,54

150.20

154.27

156,69

159,30

161.69

164,90

169,75

173,58

186,62

189,17 187.67

241,25

244,31

246.99

258,36

264,22

267.77

274,81

279,08

282,90

288,17

291,98

294.10

199.65

201.41

202.81

204.72

207.14

208.83

217,07

219.92

221,11

223,62

227,16

228.71

232.23

235.53

90,22

97,09

101,95

104,92

105.93

109,01

115,92

119.62

123.87

127.07

129.58

147 35

149,63

150.23

154.87

158,76

161,24

163.42

165.83

171,44

176,16

0.98

13.80

1,89

1.71

0.77

5.80

0,47

1,42

-

-

0,19

0,47

-

1,65

5,89

-

-

3,32

1.30

0.12

1,71

3.72

-

-

-

-

-

-

-

-

0,59

-

0.88

-

1.39

1.80

2,06

0,22

0,07

4,88

1.33

1.37

1,67

2.31

6,63

1.80

2.78

1,95

1.69

1.10

0.77

8.95

1.29

1.38

2.49

1.58

3.37

4.05

1,00

1.5o

2.03

2.18

1.93

1.89

0.50

2.44

1.80

2.52

2,12

2,24

2,29

2,10

1.36

2,89

3.87

2.14

2.34

1.35

1,31

0.93

1,67

1.33

1,14

1.14

9,88

2,35

2.54

2,64

2.79

5.62

2. 8

- 4 lower area.

This was due in part to the steeper gradient in the upper project area.

In most cases where the gravel was moved from the plot it was deposited immediately downstream and was still usable.

In several cases the gravel was deposited in large gravel bars located above the September water level, making the gravel unavailable for Chinook use.

The formation of these bars usually occurred where the stream did not have a restricted channel.

A oonsiderable amount of gravel was deposited in bars out of the channel around a point or obstruction which caused an eddy.

On two plots the technique of installing a log across the stream was used to stabilize the movement of the gravel.

Some difficulty was experienced in anchoring the log to,prevent the current from washing under and around it.

All plots of introduced gravel were visually surveyed twat years after installation to determine the square yards of good and marginal gravel remaining.

The gravel that washed from the plots was surveyed and listed as either good, marginal or dry.

The dry category included all gravel of desirable size which was deposited above the

September water level.

Plots

A

B

Total

Length

(yds.)

1,134

638

100

1,872

Table 2

Status of Introduced Gravel

Square Yards Gravel

Good on Plots

Marginal

367

92

250

709

398

92

100

590

Square Yards Gravel Washed

Good from Plots

Marginal Dry__

622

122

37

781

937

215

46

1,198

1,230

1,530

240

3,000

Most of the gravel loss occurred in the steeper areas of the B plots.

Perhaps additional log barriers could have prevented this.

Seven holding pools were provided by gravel placements in the upper half of the project where a large percentage of the area was too steep for good spawning habitat.

These areas remained relatively stable during the study period and provided good resting and holding areas for

adult chinook salmon during the summer period.

During the first week of September observations were made to determine the amount of spring chinook spawning activity on the introduced and natural gravels of the stream.

The majority of the spawning occurred in the lower two miles below

Congo Gulch in the A and C sections.

Table 3 shows the spawning data by plot number.

Table 4 summarizes the 1958-64 spawning data and shows heavy use of the

Plot Number lA

2

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

20

21

1C

1B

2

9

10

11

12

13

14

15

3

4

5

6

7

8 introduced gravel by spawning chinook.

Table 3

14

100

16

17

12

14

20

20

22

22

17

5

20

17

64

32

14

Length of ds.

Clear Creek Spawning Data by Plots

Redds on Plots

31

Redds on Washed Gravel

62

16

"

1 61

1

1 62

4

6 2

4 7 185

4 37

60

4 4 1 2

1 7 5 2 3

2 24

10 1 2

3

2

18 3

1

2

3

2

1 40 2 3

2

1 12 1 1

4

10

16

393

70

1

22

1

24

6

27

3 5

4

1

6 10 6

6 2

13 2 1 1 2

1

20 1 3

6

3

5

2

2 2

110

39

6

1

5

4

1 2

6

1

1 5

5

3

38

8

5 5

1

3

11

1 7

5

6 3

lo

1

3

1

1

4

1

13

1

1

1

3

2

1

1

1

2

1

1

1

1

3

1

2

4

1

1

1

3

5

2

1

1

5

6

Table 3 Continued

Redds on Plots

1961 1962 1963 1964

Redds on Washed Gravel

1962 1963 1964

1

1

Year

1958

72//

1959 tii

196o -/

1961

1962

1963

1964

Table 4

Clear Creek Spawning Data

No. of Fish

Observed

4

26

47

14

461

292

327

Number of Redds

Introduced Gravel 1/ Natural Gravel

-

9

154

104

154

10

13

49

1

44

13

45

-I/ Includes gravel washed from plots and redeposited.

Counts made previous to study.

During the winter of 1963 one chinook redd located in natural gravel was selected and examined periodically to determine the development and time of emergence.

Table 5 shows age and growth information obtained from the examination of this redd.

Emergence required approximately eight months.

The slow rate of development is attributed to anchor ice in the streambed and low temperatures during the winter months.

7

Date

November 29

January 21

February 15

March 14 1/

April 15 -I

2.1 Fry emergence.

Table 5

Growth of Chinook Fry at Clear Creek

Length in Millimeters Length in Inches

24.5

25.5

27.3

30.5

33.3

0.96

1.00

1.07

1.20

1,31

Water Temperature

32.0

32.5

36.0

36.0

42.0

Intragravel dissolved oxygen samples were also taken in conjunction with the egg development study.

Samples were drawn from 19 standpipes located at random on what appeared to be good chinook spawning gravel.

data collected.

Table 6 summarizes the

The dissolved oxygen content of the stream was 12.8 ppm and the average dissolved oxygen content of intragravel water was 10.68 ppm, which appeared to be sufficient for successful chinook spawning.

Table 6

Dissolved Oxygen in Intragravel Water at Clear Creek

Sample Number Location Dissolved Oxygen (ppm)

3

4

5

6

7

8

9

10

11

12

13

14

15

16

17

18

19

1

2

Plot 19A

Plot 16A

Plot 11A

Natural gravel

II It

II

It

11

Plot lA

,,

,t

Plot 10B

I, tl

Plot 16B

14.50

11.50

11.04

11.50

10.88

10.88

11.00

...

11.50

11.50

10.04

1.84

9.66

10.58

11.50

13.34

9.66

Figure 1.

Gravel removed from Clear Creek by dredging activity.

Figure 2.

Upper end of gravel plot 19A.

Note log placed across plot to stabilize gradient.

Figure 3.

Closeup of chinook spawning gravel on plot 11A.

Figure 4.

Gravel plot 1B.

This plot was installed primarily to create a chinook resting pool.

Figure 5.

Upper end of plot 23B0 gravel washed from plot.

All spawning

Figure 6.

Gravel plot 19A.

The spawning gravel has been washed from the lower half of plot.

Above the log the gravel is still in place.

1

I

CLEASZ, CrZLE.V... 4M5ITAT IMPROVEMENT

APPENDIX I

CONGO

IG U LCI-.1

ILTAWN

CHECKED

SCALE

0111116mill'

CLEA12. CZEL14_

HABITAT

0

IMP IZOVEMENT

21:0

400

&CC, &DO

SCALE. 1,4 CELT

INTRODUCED GRAVEL

OREGON STATE GAME COMMISSION

PORTLAND. OREGON

DESIGNED

APPENDIX II

APPROVED By

CHIEF ENG1NEER

APPROVED BY

DECCTOR

SHEET

0

SHEETS

I DRAWING NO

115 6

Download