Construction and Engineering Alert November 17, 2010 Authors: Carleton O. Strouss carleton.strouss@klgates.com +1.717.231.4503 C. Grainger Bowman grainger.bowman@klgates.com +1.717.231.5817 George A. Bibikos george.bibikos@klgates.com +1.717.231.4577 K&L Gates includes lawyers practicing out of 36 offices located in North America, Europe, Asia and the Middle East, and represents numerous GLOBAL 500, FORTUNE 100, and FTSE 100 corporations, in addition to growth and middle market companies, entrepreneurs, capital market participants and public sector entities. For more information, visit www.klgates.com. Contractors Beware: Court Vacates $1 Million Award That Exceeded Government Contract Funding Authorization The United States Court of Appeals for the Third Circuit recently vacated a $1 million award to a contractor for extra work it performed on a moving services contract because the award would have exceeded the funding authorization of the project owner, Wayne Moving & Storage of New Jersey, Inc. v. The School District of Philadelphia.1 The case is a cautionary tale for contractors and subcontractors. In it, a subcontractor asserted that it should be paid extra costs that exceeded the project funding authorization. It asserted that representations by the government should estop it from being able to rely on the statutory defense that the funding was not authorized. The Third Circuit concluded that the doctrine of equitable estoppel may be asserted against governmental entities in Pennsylvania. However, in applying the doctrine to the case before it, the Third Circuit found that the contractor seeking compensation from the governmental entity had failed to meet the elements of an estoppel claim. Therefore, it reversed the District Court which had granted the claim and vacated an award in excess of $1 million. The case is a powerful reminder that parties dealing with a governmental entity do so at their peril, and it could have broad application to a variety of government contracts beyond the services at issue there. While claims based on the concepts of unjust enrichment, quantum meruit, and equitable estoppel may be asserted against governmental entities in Pennsylvania and most jurisdictions, contractors must be able to prove the substantial elements required to establish such claims. In order to avoid the hazards inherent in such claims, contractors must be cognizant of the limitations on the powers of the governmental entities and the governmental agents with whom they deal, and contractors should, whenever possible, insist that the governmental agents obtain legal authorization for payment before performing extra work. In Wayne Moving, the plaintiff brought suit against the School District of Philadelphia and The School Reform Commission (“School District”) for moving services that Wayne Moving had performed as a subcontractor to Facility Strategies, LLC (“Facility Strategies”). In September of 2004, Facility Strategies and the School District entered into a contract in an amount not to exceed $1,396,865.68 with respect to the relocation of the School District headquarters to 440 North Broad Street. The award had been predicated on a $1.4 million funding authorization approved by the School District. Facility Strategies, in turn, entered into a subcontract with Wayne Moving not to exceed $840,115.68 for related moving services. 1 rd 2010 U.S. App. LEXIS 22263 (3 Cir. 2010). Construction and Engineering Alert The move to 440 North Broad Street encountered numerous difficulties involving non-functioning elevators, unanticipated work, and delays due to the School District’s disputes with a third party. According to testimony offered by Facility Strategies, it sought assurance of additional compensation from the School District for the additional expenses, and the School District represented that payment would be made if the costs were documented. Also according to testimony offered by Facility Strategies, the School District exhorted Facility Strategies to get the job done on schedule notwithstanding the difficulties. After the work was completed, Facility Strategies submitted invoices to the School District which included $830,071.18 for additional expenses incurred by Wayne Moving. The School District refused to pay the additional expenses of Wayne Moving, contending that the claimed amount would cause total payments to exceed the $1.4 million authorization by the School Reform Commission which essentially was a cap on the amount that the School District was authorized to spend on the project. The School District asserted that Section 508 of the Pennsylvania Public School Code,2 which requires authorization by school directors of any contract expenditure in excess of $100, barred any claim beyond the $1.4 million authorization. The District Court rejected the School District’s contention and held that, under the doctrine of equitable estoppel, the School District was prevented from raising the defense of §508 as a shield to Wayne Moving’s claim. The District Court noted that, under Pennsylvania law, the elements of estoppel are: 1) misleading words, conduct, or silence by the party against whom the estoppel is asserted; 2) unambiguous proof of reasonable reliance upon the misrepresentation by the party asserting the estoppel; and 3) the lack of a duty to inquire on the party asserting the estoppel. Applying those elements to the evidence before it, the District Court concluded that the School District was estopped from asserting the defense of §508.3 The District Court next considered whether Wayne Moving was entitled to payment on its unjust enrichment claim. The District Court noted that, to establish an unjust enrichment claim, the plaintiff must show: 1) benefits conferred on defendant by plaintiff; 2) appreciation of such benefits by the defendant; and 3) acceptance and retention of such benefit under such circumstances that it would be inequitable for the defendant to retain the benefit without payment of value. Again, the District Court found that Wayne Moving had satisfied the elements, holding that it would be inequitable for the School District to retain the benefit of the additional moving services under the circumstances.4 The District Court entered a judgment of $1,003,908.33 in favor of Wayne Moving. On appeal, the Third Circuit reversed the judgment of the District Court and thereby vacated the award to Wayne Moving. The Third Circuit began by noting that §508 applied to both express written contracts and implied contracts (the unjust enrichment or quantum meruit award was based on an implied in law contract since Wayne Moving did not have an express contract directly with the School District).5 It then considered whether Wayne Moving had established the elements of equitable estoppel in order to avoid the defense asserted by the School District under §508. Although the Third Circuit agreed that the District Court had correctly stated the elements of equitable estoppel, it disagreed with the District Court’s analysis of the facts and denied equitable estoppel. Rather, the Third Circuit concluded that the School District had not misled Wayne Moving by words, conduct or silence and that there was no unambiguous proof that Wayne Moving had reasonably relied on any such conduct by the School District. The Third Circuit noted that the representations, if any, were essentially made to Facility Strategies (not Wayne Moving). Further, it found the absence of fundamental injustice since, according to the Third Circuit, Facility Strategies was aware of the limitations on the funding of its contract with the 2 24 P.S. §5-508. Wayne Moving & Storage of New Jersey v. The School District of Philadelphia, 2008 U.S. Dist. LEXIS 820 (E.D. Pa. 2008) at *24. 3 4 5 Id. at *26-*27. Wayne Moving, 2010 U.S. App. LEXIS 22263 at *16. November 2010 2 Construction and Engineering Alert School District. Consequently, there was no reasonable reliance by Facility Strategies on any statements made by the School District, and any reliance by Wayne Moving was based on the directive to proceed that it received from Facility Strategies, not based on the conduct of the School District.6 Experienced legal counsel may be of substantial assistance in improving the likelihood for a successful outcome in these difficult situations. Wayne Moving dramatically illustrates the risks accepted by contractors and subcontractors who continue to provide services for governmental entities in the face of substantial additional costs for which they will seek additional compensation. Unfortunately, these circumstances frequently arise (as they did in Wayne Moving) at a time when substantial work is being performed (and cost is being incurred) and when the cumbersome governmental approval process may not move quickly enough to obtain legally required authorizations. Faced with these circumstances, contractors and subcontractors encounter the dilemma of proceeding with the work and risking non-payment or refusing to proceed with the work and suffering repercussions associated with alleged liquidated damages or threats to prequalification status or delay claims from other parties to the project. In these circumstances, the contractor (or subcontractor) should think this dilemma through, and not just plunge forward expecting that it will be paid for the extra work. The contractor may be able to “improve the odds” through communications with the governmental entity that either (1) unambiguously demonstrate the entitlement to payment, or (2) clearly justify the cessation of work until appropriate payment authorization is provided. “Written” communication is often the best way to prove either or both of these alternatives. Wayne Moving also illustrates a circumstance where a contractor (and even more so a subcontractor) may be subject to risks not necessarily apparent from the contract documents. Here, the fundamental hazard was the absence of a sufficiently large funding authorization by the governmental entity. Contractor representatives may be unaware of the funding status of a project and whether certain change orders, while ostensibly authorized, may not ultimately result in payment. 6 Id. at *16 to *23. November 2010 3 Construction and Engineering Alert Anchorage Austin Beijing Berlin Boston Charlotte Chicago Dallas Dubai Fort Worth Frankfurt Harrisburg Hong Kong London Los Angeles Miami Moscow Newark New York Orange County Palo Alto Paris Pittsburgh Portland Raleigh Research Triangle Park San Diego San Francisco Seattle Shanghai Singapore Spokane/Coeur d’Alene Taipei Tokyo Warsaw Washington, D.C. K&L Gates includes lawyers practicing out of 36 offices located in North America, Europe, Asia and the Middle East, and represents numerous GLOBAL 500, FORTUNE 100, and FTSE 100 corporations, in addition to growth and middle market companies, entrepreneurs, capital market participants and public sector entities. For more information, visit www.klgates.com. K&L Gates comprises multiple affiliated entities: a limited liability partnership with the full name K&L Gates LLP qualified in Delaware and maintaining offices throughout the United States, in Berlin and Frankfurt, Germany, in Beijing (K&L Gates LLP Beijing Representative Office), in Dubai, U.A.E., in Shanghai (K&L Gates LLP Shanghai Representative Office), in Tokyo, and in Singapore; a limited liability partnership (also named K&L Gates LLP) incorporated in England and maintaining offices in London and Paris; a Taiwan general partnership (K&L Gates) maintaining an office in Taipei; a Hong Kong general partnership (K&L Gates, Solicitors) maintaining an office in Hong Kong; a Polish limited partnership (K&L Gates Jamka sp.k.) maintaining an office in Warsaw; and a Delaware limited liability company (K&L Gates Holdings, LLC) maintaining an office in Moscow. K&L Gates maintains appropriate registrations in the jurisdictions in which its offices are located. A list of the partners or members in each entity is available for inspection at any K&L Gates office. This publication is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. ©2010 K&L Gates LLP. All Rights Reserved. November 2010 4