LAWYERS TO THE PROJECTS INDUSTRY www.klng.com Autumn 2006 Projects Bulletin International PPP accelerates in the United States For a number of reasons, Public Private Partnerships ("PPP") as understood in the UK and in other European markets such as Ireland, the Netherlands and Germany, have been slow to develop in the US. However in the last couple of years there has been increasing activity in that market and we are beginning to see the growth of what could be a very substantial PPP sector. Fragmentation in the market One of the factors making the development of PPP techniques difficult in the US is the fragmented nature of the governmental and legal structure. In the UK when the Thatcher Government decided to introduce PFI it was relatively easy for central Government to ensure that all central Government departments adopted the financing technique - this was achieved by restricting other opportunities for authorities to obtain the necessary financial support for capital expenditure. In the case of local authorities, they were encouraged to use PFI by a mixture of carrot (the availability of PFI credits from central Government) and stick (the lack of any other source of Government support for the necessary spending). In the United States on the other hand each individual state has its own elected politicians and parliamentary structure; its own judicial system; and its own procurement legislation. Although there are numerous federal agencies, most of them situated in or around Washington, they do not have the same ability to bring about the wholesale adoption of a new approach to procurement, even if that was something they wanted to promote. Accordingly progress towards PPP structures in the US has been patchy, with some states appearing to embrace the concept with a degree of enthusiasm and others showing considerable hostility. It is noteworthy that approval of the Indiana Toll Road project, referred to below, only managed to secure a very narrow majority in the Indiana Congress, which split on party lines, despite the fact that it was actively promoted by the Governor. Another reason for the comparative fragmentation of the market is that there is no such thing as a national health service or a unified public school system - it is hard to envisage a programme such as LIFT or Building Schools for the Future being "rolled out nationally" in the US. Recent road projects Progress to date has occurred mainly in the road sector. Here the structure adopted is very different from that used in the UK, or most other markets Welcome to the Autumn Edition of the Projects Bulletin. US PPP have been somehow slow to develop but we are now seeing increasing activity in this sector. You will find more on this potentially substantial market in this bulletin, as well as news on recovery of PFI bid costs (page 6), the implications of avian ‘flu on contracts entered into under FIDIC red book (page 4), standstill period in public procurement and the Rapiscan case (page 10) and planning considerations on amendments to PFI projects (page 11). Contents PPP accelerates in the US 1 Bird flu and the FIDIC Red Book 4 Birmingham healthcare PFI project 6 Recovery of bid costs 6 EU proposals for increased 7 confidence in public procurement rules Rapiscan and the standstill period 10 Amendments to PFI projects and planning considerations 11 Who to contact 12 Projects Bulletin adopting PPP techniques. The financing relies on the fact that there is a network of existing publicly owned tolled highways in the US, where users are already accustomed to paying cash tolls. Invariably the public authority, which could be a state government or city council, is short of cash for the ongoing maintenance and operation of the road and is unwilling for political reasons to increase the cash tolls payable by motorists. Traditionally the funding for maintaining public sector roads has come from the "gas tax" but with gasoline prices spiralling upwards there is no room for increases in gas taxes. In a number of recent projects, a private sector consortium has agreed to "buy" the road from the relevant public authority for a fixed period of time (75 or 99 years is normal) by making a large capital payment on day 1. This leaves the public authority in possession of a large amount of cash (always attractive to politicians), which can be used for its road programme generally or on other projects which are necessary in that particular locality. The consortium operates the road and is required to make improvements in terms of modernising the toll collection system; the consortium secures its return by collecting the cash tolls over the life of the concession. The consortium is permitted to raise the tolls and from the point of view of the municipality or state government it is politically more advantageous to have a private sector operator raise tolls than for the municipality to do so. Most projects have some degree of regulation in the contract limiting the extent to which the operator may push up the toll rates. Toll roads with high usage by out of state users (i.e. cross state highways) are easier to impose higher tolls on, since the burden is borne by users who do not vote locally. 2 AUTUMN 2006 Recent deals with this structure include: Chicago Skyway Project The eight mile Chicago Skyway has been leased for 99 years to a consortium led by Cintra and Macquarie. The upfront payment was $1.8 billion. The private sector operator has installed an electronic toll system which is proving popular with users and reportedly in the last six months of 2005 traffic volumes rose by 5% and revenue increased by 33%. Indiana Toll Road Project A 75 year lease has been granted to a consortium led by Cintra and Macquarie. The upfront payment is $3.8 billion. The Indiana Toll Road does not currently have an electronic toll collection system but the private sector operator will introduce one. According to the Governor, Mitch Daniels, it is currently costing the public sector 34 cents to collect each 15 cent toll! Trans Texas Corridor This is an innovative scheme under which a package of potential projects will be scoped, specified and implemented. A consortium led by Cintra and Zachry (a Texas based contractor) are leading the advisory/implementation team. Pocahontas Parkway Project A lease of this nine mile road in Virginia was sold to Transurban, an Australian toll road operator, for USD 611 million. Nationwide It has been estimated that the toll roads and bridges in the US have a combined annual revenue exceeding USD 6 billion. www.klng.com Other sectors Outside the road sector, there has been some work done studying the possibility of using PPP techniques for the development of new hospitals in Louisiana. This is stimulated by the fact that Louisiana, unusually for American states, has a state-wide network of hospitals designed to provide a fallback for those citizens who are unable to access privately funded hospitals. The state of Louisiana is now considering using PPP financing to update these hospitals and the lead project is the University Hospital in Baton Rouge. There are also projects for light rail and metro, such as the project currently being bid to extend the Bay Area Rapid Transit ("BART") out to Oakland Airport in California. Chicago is promoting a form of PPP, linked to commercial property development opportunities, to develop a rail link between downtown Chicago and O'Hare Airport. Most of the running has to date been made by companies originating from outside the United States, since they have experience of PPP in other countries. Macquarie and Cintra have been very successful in winning highway projects and their success is causing domestic US contractors and finance houses to take this market seriously. We can expect to see a growing presence of US domestic contractors joining bid teams for PPP deals. What about a unitary charge structure? The UK structure, incorporating a monthly unitary charge, has not really featured so far in the US. However this structure offers a number of advantages for public sector awarding authorities which they do not gain from the current US structure. For example, where a large capital sum is received up-front, it may be difficult to impose suitable checks and balances on the use of the cash. It is not out of the question that an incoming administration, perhaps composed of a different political makeup, may squander the cash which has been carefully set aside by the original administration. Also there is less ability to impose controls on the operator when all the consideration has passed from the operator to the awarding authority on day one. Under the unitary charge mechanism, where payments are made monthly by the awarding authority to the operator, there is the opportunity each month to make deductions for unavailability or poor performance and this in itself provides a control mechanism for the public sector client throughout the life of the concession. Increasingly, domestic US institutions (building contractors, banks) will participate in, or lead, bidding consortia. To date most of the running has been made by non-US entities. More projects will adopt a unitary charge mechanism, which in itself will lead to a change in the financing structure. We will see an increase in the number of federal or national pilot programmes, such as the Penta P programme being developed by the Federal Transit Administration. For further information please contact Christopher Causer. From our discussions with various public sector authorities in the US, it is clear that a number of them are now looking hard at the unitary charge mechanism and one of the reasons behind this is the ability to impose a degree of control throughout the life of the contract through the deductions mechanism. This in itself makes the transaction easier to sell to taxpayers. Moreover the unitary charge is the most obvious structure where a new road needs to be constructed, as opposed to transferring a road with existing cash tolls. Future developments With eleven offices in the United States, we are actively engaged in promoting PPP in a number of states. Looking into our crystal ball for the next year our predictions are as follows: AUTUMN 2006 3 Projects Bulletin Bird Flu and the FIDIC red book Pandemic Scenario Loss and expense Aside from the quality of the finished works, an Employer's chief concern in any project is for the works to be completed on time and to budget. Pandemic influenza (flu) poses a threat to both of these goals. This article focuses on one of the most popular forms of engineering contract, the FIDIC Red Book Conditions of Contract for Works of Civil Engineering Construction, fourth edition, incorporating amendments 1988 and 1992 ("the Red Book"). Imagine a scenario where a Contractor is engaged under the Red Book and has commenced work on site. A pandemic then occurs and the Contractor stops work, or is instructed to stop in order to protect the Employer's process/manufacturing capacity. The Red Book specifies certain events as "Employer's Risks" (Clause 20.4). If such events occur the Contractor is entitled to its loss and expense in rectifying the damage caused. A pandemic is not specifically listed as an Employer's Risk. Clause 20.4(h) refers to “any operation of the forces of nature against which an experienced contractor could not reasonably have been expected to take precautions”, but it is unlikely that this phrase will cover pandemics as its more literal interpretation is by reference to natural phenomena such as extreme weather events, earthquakes, volcanic eruptions etc. The Red Book also specifies certain events as "Special Risks" for which the Contractor bears no liability (Clause 65). A pandemic is not a Special Risk. What is the risk? Pandemic flu occurs where a strain of flu arises which is so different from those already in existence that the global population has no resistance to it. Such a strain of flu will spread more quickly and infect more people than ordinary flu. Fear of pandemic flu is high at the moment because of the risk that the bird flu virus H5N1 will mutate into a form which can be transferred from human to human. In the event of a flu pandemic, the UK government expects 25% of the population to become ill and is warning businesses to allow for staff absences of 15%. A vaccine will not be available until at least 4 to 6 months after the first outbreak in the UK. Even if anti-viral drugs are available at the start of the outbreak (and prove effective) they will not provide a cure, only ease the symptoms. The worst case scenario is that half the population falls ill and over 700,000 people die. 4 AUTUMN 2006 Given that pandemics do not fall into the category of either Employer's or Special Risks, the Contractor does not have an automatic right to claim loss and expense arising from the occurrence of a pandemic. Delay Clause 44.1 sets out the events in which the Contractor can claim an extension of time for completion of the Works. Delay caused by pandemics is not specifically referred to but is probably caught by clause 44.1(e), which refers to "other special circumstances which may occur [emphasis added] other than through a default of or breach of contract by the Contractor or for which he is responsible". This means that the Contractor will be able to claim an extension of time if the Works are delayed by a pandemic. Protection of manufacturing Where the Employer halts the Works in order to protect its manufacturing ability, it will do so by asking the Engineer to suspend the Works, as he is entitled to do under Clause 40.1. Under Clause 40.1, where a suspension is ordered to protect the Works, there is no cost consequence to the Employer. However, a suspension which is ordered to protect the Employer's manufacturing ability cannot be said to be necessary for the safety of the Works themselves. In this case the Contractor will be entitled to an extension of time and loss/expense under clause 40.2. Clause 40.3 deals with suspensions which continue for over 84 days. If the Works are suspended for more than 84 days, then the Contractor can notify the Employer that the contract will be terminated if the Works are not resumed within a further 28 days. Such a termination will be treated as an event of default by the Employer, meaning that the Contractor will be entitled to payment of all outstanding sums due to it, payment for any goods it has already ordered and any loss or damage arising out of the termination. This could include its loss of profit and other indirect or consequential losses. Where the suspension relates to part of the Works only, the contract will not be terminated but the suspended works will be treated as if they have been omitted from the Works by the Employer, with the Contract Price being adjusted accordingly. Release from performance Under Clause 66.1 the parties are released from performance "if any circumstance outside the control of the www.klng.com parties arises… which renders it impossible or unlawful for either or both parties to fulfil his or their contractual obligations…". Where the Engineer does not order a suspension under Clause 40.1 but work is prevented by the outbreak of a pandemic, the Contractor might seek to rely on this clause to extricate itself from the contract. However, in order to take advantage of this clause the Contractor would have to show that the pandemic made it impossible for it to complete the Works or it was unlawful to continue working, e.g. for health and safety reasons, not just that it delayed the works. In the event of the Contractor being released from its obligations under Clause 66.1, it would only be entitled to payments due to date and payments for goods already ordered. It would not be entitled to payment for any other losses arising from termination. Possible amendments to the Red Book It is unlikely that contractors will accept any significant change to the overall risk allocation adopted by the Red Book. It seems fair that delay caused by an uncontrollable event such as a pandemic should entitle the Contractor to an extension of time. Equally, it is fair that any loss and expense should not be passed on to the Employer. However, the Employer's need to protect its manufacturing ability can be catered for without significantly altering this balance. Clause 40.2(d) could be expanded to include suspensions ordered to protect the Employer's manufacturing ability as well as those necessary to protect the Works. The following wording would achieve this: "Unless such suspension is:……(d) necessary for the proper execution of the Works or for the safety of the Works or any part thereof or to protect and/or maintain in operation the Employer's manufacturing capability at any location adjoining or in the vicinity of the Site (save to the extent that such necessity arises from any act or default by the Engineer or Employer or from any of the risks defined in Sub-Clause 20.4). Sub-Clause 40.2 shall apply." [Proposed new wording appears in italics]. The effect of this amendment is that the Contractor will retain its right to an extension of time under Clause 44.1, but will not be able to claim loss/expense or terminate the contract under Clause 40.3 if the suspension lasts for over 84 days. Given that the government predicts that a flu pandemic would come in one or more waves, each lasting around 15 weeks, employers might also consider specifying a period longer than 84 days (12 weeks). Part II of the Red Book contains optional clauses which the parties can choose to add to the contract. Optional clauses for Clause 34 include the following: “In the event of any outbreak of illness of an epidemic nature, the Contractor shall comply with and carry out such regulations, orders and requirements as may be made by the Government, or the local medical or sanitary authorities, for the purpose of dealing with and overcoming the same.” This clause should be incorporated into the contract. Whilst it does not change the entitlement of the Contractor in the event of a suspension being ordered by the Engineer, this clause clarifies the Contractor's obligations regarding its own staff and labour. Conclusion It is possible for employers to protect against the risk of pandemic flu without altering the basic risk allocation of the Red Book. Employers can do so by ensuring that any rights of termination for prolonged suspension allow sufficient time for a pandemic to pass. Also, specific provisions can be inserted into contracts requiring the Contractor to take steps to minimise the risk to the Works. Key points Delay caused to the Contractor by a pandemic can be claimed as an extension of time. However, the Contractor cannot claim its loss/expense. If the Employer suspends the Works to protect its manufacturing ability, the Contractor will be entitled to an extension of time and loss/expense. If the suspension continues for more than 84 days, then the Contractor can, after giving notice, terminate the contract and is entitled to payment for any loss or damage it incurs. If a pandemic renders performance of the Works impossible or unlawful, then the Contractor can terminate the contract. However, a mere delay caused by a pandemic is not enough; performance has to be impossible or unlawful. There are amendments which can be made to the Red Book to cater for pandemic risk without radically altering the risk allocation between Contractor and Employer. For further information please contact Yassir Mahmood. AUTUMN 2006 5 Projects Bulletin £553m major healthcare PFI project signed by Balfour Beatty Construction and Haden Young A team from Kirkpatrick & Lockhart Nicholson Graham led by projects partner Christopher Causer advised a joint venture composed of Balfour Beatty Construction Limited and Haden Young Limited on the £553 million PFI construction contract for the design and construction of new hospitals in Birmingham. Financial close was reached on 14 June 2006. The second largest bond deal after Bart's, the Birmingham project is financed by EIB and a bond issue guaranteed by FGIC. The new hospitals, based at the Queen Elizabeth Hospitals site in Birmingham, will be the second largest PFI healthcare facility after Bart's. Once operational in 2010, it will provide 1,213 new beds, a 108-bed specialist psychiatric hospital and teaching facility and a separate 32bed mental health local facility. The project is challenging as it is spread over two sites, with a very complex and intricate allocation of property between landowners. It involves two trusts, one being a foundation trust, and requires works on the trusts' retained estate. The construction work has been under way since last summer, including demolition of existing Victorian healthcare buildings and the removal of hogweed and Japanese knotweed. Causer (partner - head of projects group) and projects associate Sophie Charveron included Steven Cox (partner - property), Kevin Greene (partner - construction), Jonathan Lawrence (partner - banking), Sebastian Charles (partner - planning and environment), Yassir Mahmood (associate - projects) and Eleanor Smith (associate - property). For further information please contact Sophie Charveron. The Kirkpatrick & Lockhart Nicholson Graham LLP team led by Christopher Recovery of bid costs The industry has long been concerned with the cost (and time) of closing deals and the recent hiatus in the health service PFI/PPP has caused real hardship to bidders. For those that are not given the green light, with large amounts at stake, bidders will want to know the prospects of recovering those costs. Sir Malcolm Bates, in his first review of the PFI process in 1997, recommended that "where a decision is made not to proceed with a project and that decision is not related to the viability of tenders received, contractors' bidding costs should be refunded". Although this recommendation has no legal force, it is assumed that all responsible government organisations 6 AUTUMN 2006 (central and local) will follow it. What options does a bidder have to recover its costs in the event the Bates' recommendation does not apply, or an Authority will not abide by it, or there is no preferred bidder's letter dealing with costs? There are four areas worth considering. Restitution/Unjust Enrichment For a claim to be successful the other party must normally have received a benefit. This may be the case, for example, where planning permission has been obtained and the Authority can take the benefit. There is also some support for the argument that a party can receive a benefit where it requests services even though those services could be described as preparatory to performance Countrywide Communication Limited v ICL Pathway Limited [2000] CLC. Estoppel Estoppel is a rule of law which prevents a party alleging a fact in support of its claim if it has previously by word or conduct represented the contrary to the other party. Estoppel is said to be "a shield and not a sword". However, as Brandon LJ stated in Amalgamated Investment & Property Co Ltd v Texas Commercial International Bank Ltd [1982] QB, "While a party cannot found a cause of action on an estoppel, he may, as a result of being able to rely on an estoppel, succeed on a cause of action on which, without being able to rely on that estoppel, he would necessarily have failed". Projects Bulletin www.klng.com Misrepresentation / Negligent Misstatement Implied Contractual Promise Economic loss is only recoverable in tort if there is a negligent misstatement by one party where a duty of care existed and the other party relied on and was entitled to rely on the statement. Having invited bids and chosen a preferred bidder knowing that significant costs will be incurred in working up the scheme, there are fertile grounds for arguing that there is an implied contractual promise that the Authority will act in accordance with the parties' reasonable expectations, at least not dissimilar to the Bates guidelines. A duty of care would not generally exist in a tender situation and the invitation to negotiate generally contains disclaimer provisions. However, the PFI process is such that it is not beyond legal principles that in certain situations such a duty might arise. In such circumstances, deliberately withholding information or indeed providing false information may well give rise to a cause of action. Conclusion Having an express contractual right in the preferred bidder letter is the only sure way of recovering bid costs in the event of cancellation of a project. Following the current trouble in the NHS bidders will also now want to consider negotiating compensation for additional funding of the bid costs where the scheme is delayed through no fault of their own. Failing any such express contractual right, the Bates recommendation may allow recovery of bid costs "ex gratia" where a project is cancelled. If neither of these apply the circumstances of the deal may give rise to a cause of action for the recovery of some, if not all, of the wasted bid costs. For further information please contact Trevor Nicholls. EU proposals for increased confidence in public procurement rules Fairer and more efficient remedies As announced in our previous issue, after simplifying the rules applicable to the procurement of public contracts, the EU Commission now turns its attention to the remedies available in case of breach of these rules. Many of you encountered difficulties when using the existing remedies to challenge unlawful awards of public contracts. The biggest difficulty was that, until the Public Contracts Regulations 2006 ("Regulations") were adopted on 31 January 2006, the only remedy available to unsuccessful bidders after a contract award was damages. Public contracts awarded in breach of the procurement rules could not be set aside, cancelled or declared void, so claims had to be brought to court before the contract was awarded (with the exception of collusion and bad faith). Frequently, some contracting authorities were tempted to engage in a race to sign the contract as soon as possible, in order to make it irreversible. As in the UK, the decision to award a public contract and the execution of the contract are usually contemporaneous. In Alcatel and Others (C-81/98 [1999] ECR 1-7671), the ECJ held that it is unacceptable for contracting authorities to rush to execute a public contract following a known or alleged infringement of the procurement rules, as a measure to secure the preferred bidder. Since the Regulations came into force, a claimant is now entitled to require a court to suspend a contract until the AUTUMN 2006 7 Projects Bulletin judges decide on the breach of procurement law claim. The only condition is to submit the claim within 10 days of the award decision, during which period (the "standstill period") the contracting authority is not allowed to execute the contract. Whilst mandatory standstill periods are already implemented in some Member States, they are not widespread in the EU. This means that an English contractor bidding for a public works contract in another Member State may find it more difficult to bring a claim against an illegal award of contract if different practices and rules apply elsewhere. Acknowledging these difficulties, the EU organised an extensive consultation on the functioning of the current remedies in the classical and utilities sectors. The EU Commission then published a proposal for reform of the current Remedies Directive making standstill periods compulsory, on 4 May 2006. Authorities must give reasons for nonselection Under the current Regulations, it is only on the request of an unsuccessful bidder that contracting authorities must give the reason why its bid failed to meet the award criteria (Regulation 32(4) and (9)). Any economic operator that has either applied to be selected in a tender or submitted a tender is entitled to bring a claim for infringement of public procurement rules. It may become compulsory for all contracting authorities in the EU to provide reasons for non-selection to all bidders if the reform is adopted. Where a contracting authority receives a 8 AUTUMN 2006 request from an unsuccessful bidder asking for the reasons why its bid was not successful, the authority would have to reply at least three days before the end of the standstill. Will this greatly improve the economic operators' confidence in public procurement rules and encourage authorities to comply with the procurement rules more readily? Pre-contractual notification and automatic suspension A claimant must inform the contracting authority of the alleged breach and its intention to submit a claim. In the UK, proceedings must be brought within three months from when the ground for the claim arose (Regulation 47(7)). The High Court has the necessary power to review alleged claims before full proceedings are brought. A serious weakness of the current remedies is the absence of a period of time to review award decisions before the contract is executed. Contracting authorities may be granted an immunity from challenge and suspension when the "general interest of non-commercial and economic nature" requires it (for instance where urgent works must be carried out to school buildings before the school year begins). It is disappointing that the Commission did not address the issue of long, protracted negotiations for complex projects such as PFI contracts, and does not define at what point in a tender process the award decision is communicated. According to the OGC guidance on the standstill period, the earliest point in time that an award decision can be communicated to all tenderers in a negotiated award or a competitive dialogue is when the contracting authority "ceases dialogue or discussions with other bidder(s) and announces the appointment of the preferred bidder" (OGC guidance note on the ten-day mandatory standstill period, March 2006). It is at this point that the standstill period commences under English law. Ten-day standstill period Contracting authorities and preferred bidders have to wait at least 10 calendar days from the communication of the award decision before executing the contract (Regulation 32(3)). The Commission suggests extending the obligation to enforce standstill periods to all Member States. The standstill period would be: applicable to all categories of public contracts; short: ten calendar days (7 calendar days for urgency, call-offs from framework agreements and dynamic purchasing); and not applicable in circumstances of extreme urgency. There would be discretionary derogations for: framework agreements concluded with a single economic operator; call-offs without competition; open procedure awarded to single bidder; and restricted or negotiated procedure where tenders are excluded for a reason other than failing to meet the contract award criteria. Sanctions Contracts awarded in breach of the precontractual notification obligation or the standstill period would be invalid i.e. without any contractual effect. The invalid contract could however still have certain effects as between the www.klng.com parties or in relation to third parties, up to a period of six months from the conclusion of the contract. This may cover circumstances such as where orders for materials must be made as early as possible or until a replacement contractor is selected under a new award procedure. should give potential bidders and lenders more confidence in the fairness and effectiveness of the procurement rules. For further information please contact Sophie Charveron. Derogations would be available when the national review board or courts find that "overriding reasons based on general interest of non-economic nature" require that the effects of a contract already executed are not challenged, despite an infringement of procurement rules. Should the proposal go ahead, the risk is that excessive use of such derogations may render the reform worthless, as it would allow illegally awarded contracts to remain as they stand. Is it likely that this reform will take place? The Commission's proposal is now with the European Parliament and the Council of Ministers, awaiting their "co-decision" (in other words, consensus). The reform would consolidate the first steps put into place by the Classical Directive 2004 for better and more effective rules. The compulsory standstill period aims at preventing contracting authorities from racing to execute public contracts immediately after the award decision. Some will deplore that the proposal does not go far enough and does not impose an obligation on contracting authorities to notify participants of other decisions made during the procedure, such as the decision not to select them. In our view, this reform should encourage contracting authorities to award contracts in compliance with the procedures and, more importantly, it AUTUMN 2006 9 Projects Bulletin Rapiscan and the standstill period Rapiscan Systems Limited v HM Revenue and Customs 2006 EWHC 2067 (QB) The Public Contracts Regulations 2006, which came into force on 31 January 2006, created a mandatory tenday "standstill" period between a contract award and the conclusion of a contract with the successful tenderer. The decision in the case of Rapiscan Systems Limited v HM Revenue and Customs [2006] EWHC 2067 (QB) shows that unsuccessful bidders have a right to delay the contracting authority from entering into the contract pending a full and proper debriefing. The case HMRC put out a tender for the supply of scanners to scan large vehicles when they enter the UK, advertised in July 2005 under the 1995 Public Supply Contracts Regulations. HMRC also adopted certain aspects of the new Public Contracts Regulations 2006, including a standstill period. The contract award was decided on 14 July 2006 and Rapiscan was unsuccessful in its bid. HMRC planned to execute the contract on 26 July 2006 and provide information to unsuccessful bidders at a debrief meeting on 1 August 2006. Rapiscan requested information regarding the award decision and pending receipt of that information, it sought to extend the standstill period by a few more days and defer the execution of the contract. HMRC refused the extension and gave information on the reasons why Rapiscan's tender was not successful on 21 July 2006. Rapiscan brought proceedings before the High Court to prevent the execution of the contract from going ahead. HMRC replied that it had no obligation to provide 10 AUTUMN 2006 information because Rapiscan's request had no procedural basis in the Regulations. It argued that if Rapiscan was entitled to request further information, its case had been answered by a letter of 21 July 2006. The judgment found in favour of Rapiscan only seven days after Rapiscan had requested further information and only six days after receiving a response from HMRC. The judgment The Judge held that Rapiscan's concern that the award procedure had not been carried out as set out in the tender documentation was valid and the criteria marking mechanism was unclear. Further information was needed to clarify the criteria. She rejected HMRC's claim that they had clarified the position by a letter dated 21 July 2006. Reasons for a contract award must be provided to a tenderer within 15 days of a request. However the requirement to ensure transparency is overriding and when there is still time to set aside a contract award, the ten day standstill period can be applied. HMRC should have extended the standstill period as the contract was not urgent and Rapiscan had indicated that further information might avoid proceedings. Dobbs J held an injunction would be ordered if undertakings were not offered by HMRC. Lessons to learn Bidders unsure as to why they were unsuccessful should write to the authority immediately, clearly stating information and clarification sought. If not clarified within the ten-day standstill period, the tenderer can apply to court to restrain the conclusion of the contract. Contracting authorities must endeavour to answer clearly and as fully as possible to requests for reasons from unsuccessful bidders received within a standstill period. Their response should give clear reasons for the decision not to award the contract to that bidder. Contracting authorities can also extend the standstill period when appropriate. They should be aware that any lack of transparency will persuade the courts to order that the execution of the contract is retrained. For further information please contact Christopher Causer or Sophie Charveron. www.klng.com Amendments to PFI projects and planning considerations It has been hitting the headlines that several high profile PFI projects have, as financial close approaches, been forced to reconsider the original scope and scale of the project due to financial or "affordability" pressures. For example dropping buildings from the project or reducing the scale of what is built may be proposed to save costs. Often, this review occurs after planning permission for the project has been granted. When such decisions are being made it is crucial to be aware of the planning and hence cost and timescale implications. If the result is that a new planning resubmission is needed, or that the proposal becomes susceptible to a third party judicial challenge, then the consequences are serious. A third party challenge to a planning permission may be brought by local objectors, or even potentially disappointed bidders for the project. Even if unsuccessful a considerable delay may arise, and that risk alone may necessitate re-starting the planning process. Re-starting the planning process may itself contain risks of delay, for example if planning policy has changed since the time of the first application, or local circumstances have altered, affecting the need for the project. Below are just a few of the issues that need to be considered when making decisions about changes to PFI schemes. Minor amendments The first issue is the question of whether the changes proposed can be agreed as "minor amendments" to the original scheme, or whether what is proposed is sufficiently different that a new planning application will need to be made. It has been the practice of local planning authorities to allow "nonmaterial" amendments to a permitted development without obtaining fresh planning permission. If the change to the project is a minor amendment, the sponsor may go ahead and make the change without consulting the Local Planning Authority ("LPA"). However on a large project, the sponsor may opt to seek a letter from the LPA that the change contemplated can be viewed as a minor amendment. Any project should be cautious in relying on such a letter following the decision of the Court in Reprotech (Pebsham Ltd) v East Sussex CC [2002] 4 ALL ER 58. In Reprotech the Court ruled that although the opinions of planning officers are helpful, the only way a Developer can get a binding determination as to whether planning permission is required, is to make a formal planning application. Developers, in light of the recent increase in third party challenges to planning permissions, must be certain that what is contemplated really is a non-material change as the informal indication of the LPA cannot be relied upon as binding in the event of third party challenge. If an amendment is material, in practice, not all LPAs will require a full application involving the resubmission of all plans. Whilst all planning permissions are subject to an implied time limit in which development must be commenced, there is no time limit implied for completion of a development, unless provided. Therefore, if a project sponsor chooses to build out only part of the scheme, it could argue that it is not in breach of planning. The planning permission will cease to have effect after a period of not less than 12 months from the date the notice is issued. This means that the building work must be completed in that time, or run the risk of the partially completed development potentially becoming unauthorised. In such circumstances the LPA may decide to take enforcement action requiring the developer to remove the partially completed structure and make good the site. However, in practice, the risk of a completion notice being served is probably small as they are very rarely used and can be appealed. The more likely alternative if there is no condition relating to completion, is for the LPA to take enforcement action within 4 years for a development not being in accordance with approved plans. Both issues are a concern, especially if the project has become contentious. Implementation of a project in part Environmental Impact Assessment If a sponsor deletes certain elements he may be able to argue that the scheme is being implemented in accordance with the original planning permission in part, rather than being amended. In making a decision as to whether an amendment to the scheme is " minor " or "material", one other consideration of particular importance, is the effect the amendment will have on the AUTUMN 2006 11 Projects Bulletin Environmental Statement ("ES") submitted with the original application, in accordance with the requirements of the Town and Country Planning (Environmental Impact Assessment) (England and Wales) Regulations 1999 ("the Regulations"). Environmental Impact Assessment ("EIA") is the process by which environmental issues are taken into account during the planning process, i.e. by requiring applicants to produce an ES to describe the likely significant effects of the development in question on the environment and proposed mitigation measures. been met. A project may have gone through an EIA process on the basis that a building comprised in part of the scheme would be built to screen a row of nearby houses from visual and noise impacts of the main development. If the scheme is altered to drop this building, the visual and noise impacts may need to be considered afresh through changes to the original ES. EIA issues are one of the hot spots for third party challenge in planning, causing significant delays to the projects in question. It could mean restarting the planning powers with all the potential for delay that entails, especially if, since the original permission was granted, there have been changes in local circumstances, including the need for the project or a change in planning policy, which since the Planning Compulsory Purchase Act 2004, is more fluid than ever before. For further information please contact Sebastian Charles The ES is circulated to statutory consultation bodies and made available to the public for comment. Not all developments are subject to EIA. The Regulations apply to large-scale developments where there is obvious potential for environmental damage. Almost all of the types of project for which PFI will be used will require EIA. Planning permission cannot be granted unless the decision-making body has not only taken into account the specified information about the environmental effects of the proposal, but has also stated in its decision that it has done so. Permission can be quashed if this requirement has not Who to Contact Kirkpatrick & Lockhart For further information contact the following Christopher Causer ccauser@klng.com Nicholson Graham LLP T: +44 (0)20 7360 8147 110 Cannon Street Stuart Borrie sborrie@klng.com T: +44 (0)20 7360 8155 London EC4N 6AR Trevor Nicholls tnicholls@klng.com T: +44 (0)20 7360 8177 www.klng.com Kevin Greene kgreene@klng.com T: +44 (0)20 7360 8188 T: +44 (0)20 7648 9000 David Race drace@klng.com T: +44 (0)20 7360 8106 F: +44 (0)20 7648 9001 Sebastian Charles scharles@klng.com T: +44 (0)20 7360 8205 Kirkpatrick & Lockhart Nicholson Graham (K&LNG) has approximately 1,000 lawyers and represents entrepreneurs, growth and middle market companies, capital markets participants, and leading FORTUNE 100 and FTSE 100 global corporations nationally and internationally. K&LNG is a combination of two limited liability partnerships, each named Kirkpatrick & Lockhart Nicholson Graham LLP, one qualified in Delaware, U.S.A. and practicing from offices in Boston, Dallas, Harrisburg, Los Angeles, Miami, Newark, New York, Palo Alto, Pittsburgh, San Francisco and Washington and one incorporated in England practicing from the London office. This publication/newsletter is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. Data Protection Act 1988 - We may contact you from time to time with information on Kirkpatrick & Lockhart Nicholson Graham LLP seminars and with our regular newsletters, which may be of interest to you. We will not provide your details to any third parties. Please e-mail london@klng.com if you would prefer not to receive this information. 12 AUTUMN 2006 © 2006 KIRKPATRICK & LOCKHART NICHOLSON GRAHAM LLP. ALL RIGHTS RESERVED.