LAWYERS TO THE CONSTRUCTION & ENGINEERING INDUSTRIES www.klng.com Spring 2006 In Site Through the hoops The London Olympic Games and Paralympic Games Bill is due to receive the Royal Assent and once passed, will bring into existence the Olympic Delivery Authority (ODA) with responsibility for coordinating and delivering the contracts for the Olympic and Paralympic Games. Word on the street is that the ODA will let the venue contracts, such as those for the construction of the new sailing facilities at Weymouth and rowing facilities at Eton, and Transport Operators (the DLR and TfL) will let the major transport infrastructure contracts. The DLR will be extending its platforms to accept 3-car trains and procuring new rolling stock. TfL will be carrying out modifications to the Northern Line and undertaking the East London Line, part of which will be paid for out of Olympic funds. Other major works will be undertaken which will help to realise the Olympic dream, such as the upgrading of Terminals 1, 2 and 3 at Heathrow. The ability of the UK construction industry to meet the challenge is not in doubt but with so many major projects being undertaken at the same time in the South East, it is essential that there is proper planning to meet the July 2012 deadline and that as far as possible contracts are standardised. The ODA has a key role to play in this process. It will need to decide early on which standard forms of contract to promote. The new NEC3 must be a frontrunner as the Office of Government Commerce has already recommended its use on public sector contracts and in July 2005 Sir Michael Latham 'commended its adoption by any private sector client wishing to procure their construction work on time, within budget and without litigation. The procurement race is about to start - I can think of no other contract form better suited to winning it than NEC'. However, NEC3 is not the only contestant. DLR has its own bespoke form of procurement contract and the building sector has a new JCT standard form of building contract which may be suitable for the venue contracts and discrete new builds. There is also the question of whether there are sufficient trained project managers familiar with NEC3 to ensure that it is applied properly. Whatever form of contract is promoted by the ODA, there will need to be specific Olympic clauses to ensure standardisation and compliance by the UK with its obligations to the International Olympic Committee. There are strong arguments for using NEC3. It can be used for building as well as infrastructure works and the Welcome to the Spring edition of In Site. In this edition we consider the choice of contracts for large scale Olympics projects and look briefly at the outcome of the most recent round of the DTI Construction Act consultation process. We also examine recent developments in adjudication case law, Building Regulations and employment law. Contents Olympics 1 Construction Act review 2 Adjudication Update 3 Other recent developments 4 Who to Contact 4 In Site continued from page 1 NEC suite of contracts already includes a short form of engineering and construction contract, a subcontract and a professional services contract. All of these contracts are compatible. The recent changes introduced by NEC3, such as the risk-reduction and key date provisions, emphasise the dynamic approach taken by NEC to dealing with risk. Unlike under the JCT Building Contract, claims are not rolled up and dealt with during final account negotiations, but are dealt with as the works proceed through the compensation event procedure. There are now time limits under NEC3 for notifying compensation events and for dealing with such notifications. The compensation event assessment procedure is ideally suited to dealing with situations where the scope of work is unclear or likely to change. Where NEC3 falls down is over partnering. The timely delivery of the Olympic contracts will be dependent upon effective supply chain management and it is unrealistic to expect this to be achieved through twoparty partnering agreements as envisaged by NEC. If the ODA promotes NEC3 it will have to find a way of overcoming this problem. One possible solution is to require the principal contractor and core members of his supply chain to enter into a multi-party Alliancing Agreement. The ODA could also be a party to this Agreement and share the risk. Its principal purpose would be to incentivise the members of the Alliance through a gainshare/painshare mechanism to achieve the project objectives set by the ODA, such as a stretch completion date. Work is currently being undertaken by the Strategic Forum and other interested parties in devising a new type of single project financial loss insurance policy which supports integrated team working and therefore, alliancing. This kind of policy would respond in the event of a cost overrun, above an agreed deductible, without having to apportion blame. The deductible would either be shared by the members of the alliance or charged to the project. In order for underwriters to take this risk, they would have to be involved from the outset in agreeing targets and setting up systems of technical/cost control to manage the risk. They might also require to be represented on the alliance board. It is essential for the success of the Games that the ODA considers these issues in order to reduce disputes and increase the chances of projects being completed on time and within budget. Any disputes arising between the members of an alliance could then be referred to an over-arching Dispute Review Board promoted and set up by the ODA. Experience would be shared across the alliances through the DRB. The ODA will need to get its spikes on! Construction Act review The Department of Trade and Industry (the "DTI") published its muchanticipated Analysis of the consultation on proposals to amend Part II of the Housing Grants Construction and Regeneration Act 1996 (the "Act") and Scheme on 16 January 2006. The only proposals which the DTI intends to take forward to propose actual drafting changes are: Payment 2 Introducing a requirement that certification of the sum due becomes an essential feature of an adequate payment mechanism; SPRING 2006 Removing the requirement in section 110(2) of the Act for a payment notice (separate to the section 111 withholding notice); Introducing a right to apply for payment where a certificate is not issued by the due date; and Enhancing the existing right of suspension under the Act to allow the suspending party to claim for loss and expense. Adjudication Providing the right to payment for adjudicators upon resignation in response to a challenge to jurisdiction; Prohibiting the use of trustee stakeholder accounts; and Making "final and conclusive" clauses unenforceable where they apply to decisions under the contract that are of substance to interim payments only. We will be considering these proposals, and those which the DTI is not taking forward, in greater detail in an electronic Alert to be published shortly. www.klng.com Adjudication update Adjudication of the same issue? The facts in David McLean Contractors Ltd v The Albany Building Ltd [2005] were that Albany had issued notices of non-completion and deducted liquidated and ascertained damages under their contract with their contractor, McLean. McLean adjudicated, contending that Albany were not entitled to make such deductions. The adjudicator agreed, deciding that Albany's withholding notice was invalid. The same adjudicator had conducted a previous adjudication, also regarding liquidated and ascertained damages under the contract, and where he had found that the withholding notice had been valid. The primary issues to be decided by the judge were whether: the same issue (i.e. Albany's entitlement to deduct liquidated and ascertained damages) had been decided in the previous adjudication (in which case, under the CIC rules incorporated into the contract, he had no jurisdiction to deal with the second adjudication); and Albany had the right to refuse payment on the basis of a cross-claim that it would be entitled to liquidated damages (having been successful in the first adjudication). were different, so there was no duplication and the CIC conditions did not deprive the adjudicator of any jurisdiction. Secondly, the judge decided that it was inconsistent with the policy of the adjudication scheme to allow an adjudicator's award to be effectively rendered nugatory by raising a cross-claim that might or might not succeed. As such, the adjudicator's award was upheld and McLean was granted summary judgment for the total sum plus interest. Costs The judge held that the point actually decided in the first adjudication was the narrow issue of the validity of the withholding notice. In contrast, the second adjudication dealt with the broader issue of whether Albany was entitled to deduct liquidated and ascertained damages at all, having regard to the notices. Therefore the two issues The issue of payment of parties' costs in the event of a discontinued adjudication was considered in the TCC case of John Roberts Architects Ltd v Parkcare Homes (No2) Ltd. Neither the Act or Scheme provide for one party to pay the other party's costs of an adjudication, but providing adjudicators with the discretion to award costs is a provision frequently written into contracts, such as in the present case. The referring party (Parkcare) had discontinued the adjudication (on the basis that the adjudicator lacked jurisdiction as a dispute had not yet arisen) and as a result Roberts claimed its abortive costs in defending the adjudication. The Court held that the clear meaning of the contractual clause giving the adjudicator the discretion to award costs was that this discretion only arose in the context of deciding the substantive issues in an adjudication. The adjudicator was not entitled to make a decision regarding costs where the adjudication had been abandoned, as he had not in these circumstances made a decision on the matters set out in the notice of adjudication. SPRING 2006 3 In Site Other recent developments Heating and Ventilation New Building Regulations dealing with ventilation and conservation of fuel and power come into force on 6 April. These new Regulations affect energy conservation and will help to countermand climate change by aiming to save more than 1 million tonnes of carbon each year. New buildings will have to be better insulated and make use of more efficient heating systems. Neither Part requires particular technologies to be used, which it is hoped will give designers and builders some flexibility on how to meet the new standards. The new Part F seeks to be much less prescriptive than the previous regulations, and more guidance has been given for domestic mechanical and natural ventilation systems and also for the ventilation of basements in dwellings. Employment Issues Under Part L, new buildings are to be energy performance-rated by applying a whole-building calculation formula. The energy performance of the new building needs to be demonstrated before construction. Before hand-over, all of the parameters as installed and tested need to be inputted into the formula. The building must then attain the required carbon emission target. The recent employment cases in the House of Lords, Lawson v Serco, Botham v Ministry of Defence and Crofts v Veta Limited are of relevance to construction and engineering firms deploying British staff to overseas locations. These combined cases decided the important question of whether employees who spend part of their time working abroad can bring unfair dismissal claims in the UK. The Employment Rights Act 1996 states that the right to claim unfair dismissal only applies to “employment in Great Britain”. The House of Lords overruled previous cases and stressed that this concept was to be treated as a general principle rather than an absolute rule, and identified some cases where expatriates working abroad might be able to bring unfair dismissal claims, which included employees posted abroad by a British employer for the purposes of a business carried on in Great Britain. As a result of these cases, more employees are likely to be able to claim unfair dismissal than was previously the case. Who to Contact Kirkpatrick & Lockhart For further information contact the following Nicholson Graham LLP Christopher Causer Kevin Greene James Hudson Linda Kent Trevor Nicholls David Race ccauser@klng.com kgreene@klng.com jhudson@klng.com lkent@klng.com tnicholls@klng.com drace@klng.com T: +44 (0)20 7360 8147 T: +44 (0)20 7360 8188 T: +44 (0)20 7360 8150 T: +44 (0)20 7360 8151 T: +44 (0)20 7360 8177 T: +44 (0)20 7360 8106 110 Cannon Street London EC4N 6AR www.klng.com T: +44 (0)20 7648 9000 F: +44 (0)20 7648 9001 Kirkpatrick & Lockhart Nicholson Graham (K&LNG) has approximately 1,000 lawyers and represents entrepreneurs, growth and middle market companies, capital markets participants, and leading FORTUNE 100 and FTSE 100 global corporations nationally and internationally. K&LNG is a combination of two limited liability partnerships, each named Kirkpatrick & Lockhart Nicholson Graham LLP, one qualified in Delaware, U.S.A. and practicing from offices in Boston, Dallas, Harrisburg, Los Angeles, Miami, Newark, New York, Palo Alto, Pittsburgh, San Francisco and Washington and one incorporated in England practicing from the London office. This publication/newsletter is for informational purposes and does not contain or convey legal advice. The information herein should not be used or relied upon in regard to any particular facts or circumstances without first consulting a lawyer. Data Protection Act 1998 - We may contact you from time to time with information on Kirkpatrick & Lockhart Nicholson Graham LLP seminars and with our regular newsletters, which may be of interest to you. We will not provide your details to any third parties. Please e-mail cgregory@klng.com if you would prefer not to receive this information. 4 SPRING 2006 © 2006 KIRKPATRICK & LOCKHART NICHOLSON GRAHAM LLP. ALL RIGHTS RESERVED.