Appendix J Project Schedule Activity ID Activity Name Orig Rem Start Dur Dur Finish Predecessors 2013 Nov Dec Jan Feb Mar Apr May Jun 2014 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Project_Schedule Design USEPA Pre-Final Design Review 08-Jan-13 620 USEPA Pre-Final Design Review 100 Receive USEPA / NJDEP Pre-Final Design Comments 100 USEPA Pre-Final Design Review 34 34 30-Nov-12 105 Receive USEPA / NJDEP Pre-Final Design Comments 0 0 08-Jan-13 110 Discuss Pre-Final Design Comments with USEPA 0 0 30-Jan-13 105 Discuss Pre-Final Design Comments with USEPA 115 USEPA Pre-Final Design Approval 0 0 30-Jan-13 110 USEPA Pre-Final Design Approval Prepare Draft Final Design Report 42 25-Feb-13 105 Final Design 120 42 08-Jan-13 Prepare Draft Final Design Report Submit Geotechnical Data to USEPA for Review 125 Submit Geotechnical Data to USEPA for Review 0 0 11-Feb-13 110 130 Submit Draft Final Design Report 0 0 25-Feb-13 120, 125 27-Mar-13 130, 115 USEPA Draft Final Design Review 27-Mar-13 135 Receive USEPA Comments on Draft Final Design Report 10-Apr-13 140 Revise Draft Final Design Report 13-Apr-13 140, 145, 190 USEPA Final Design Approval Submit Draft Final Design Report USEPA Final Design Review 135 USEPA Draft Final Design Review 26 140 Receive USEPA Comments on Draft Final Design Report 145 Revise Draft Final Design Report 150 USEPA Final Design Approval 0 12 26 26-Feb-13 0 12 28-Mar-13 0 0 Field and Lab Work to Refine Cap Design 105 Submit RTC Table for QAPP Addendum D to USEPA 01-Feb-13 155 USEPA Approved QAPP Addendum D 11-Feb-13 160 6 04-Mar-13 09-Mar-13 165 Pore Water Extraction 18 18 11-Mar-13 30-Mar-13 170 Analytical Results 12 12 01-Apr-13 13-Apr-13 175 Evaluate Analytical Results 13-Apr-13 175, 180 Hg- Breakthrough Tests (QAPP-G) Recommendation 13-Apr-13 185 Propose Final Design of Cap's Active Layer 155 Submit RTC Table for QAPP Addendum D to USEPA 0 0 01-Feb-13 160 USEPA Approved QAPP Addendum D 0 0 165 Collect Sediment Samples 9 9 01-Feb-13 170 Pore Water Extraction 6 175 Analytical Results 180 Evaluate Analytical Results 185 Hg- Breakthrough Tests (QAPP-G) Recommendation 0 0 190 Propose Final Design of Cap's Active Layer 0 0 195 Groundwater Seepage Velocity Invest & Analysis 26 26 18-Apr-13 17-May-13 185 20-Mar-13 660 Collect Sediment Samples Groundwater Seepage Velocity Invest & Analysis Water Quality Monitoring Plan 200 Prepare WQM Plan 22 22 23-Feb-13 205 Meeting with USEPA to Discuss WQM Comments 0 0 04-Mar-13 210 Submit WQM Plan to USEPA / NJDEP 0 0 215 USEPA / NJDEP Review WQM Plan 26 220 USEPA/NJDEP Approval WQM Plan 0 0 200 Prepare WQM Plan Meeting with USEPA to Discuss WQM Comments Submit WQM Plan to USEPA / NJDEP 20-Mar-13 200, 205 19-Apr-13 210 USEPA / NJDEP Review WQM Plan 0 19-Apr-13 215 USEPA/NJDEP Approval WQM Plan 0 04-Mar-13 130 29-Mar-13 225 26 21-Mar-13 Long Term Monitoring and Maintenance Plan (LTMMP) 225 Submit Outline to USEPA for LTMMP 230 Prepare LTMMP 235 240 245 USEPA / NJDEP Review LTMMP 28 250 USEPA / NJDEP Approval LTMMP 0 22 22 05-Mar-13 Meeting with USEPA to Discuss LTMMP Comments & Scope 0 0 12-Mar-13 Submit LTMMP to USEPA / NJDEP 0 0 28 30-Mar-13 0 230 Submit Outline to USEPA for LTMMP Prepare LTMMP Meeting with USEPA to Discuss LTMMP Comments & Scope Submit LTMMP to USEPA / NJDEP 29-Mar-13 230, 235 01-May-13 240 USEPA / NJDEP Review LTMMP 01-May-13 245 USEPA / NJDEP Approval LTMMP RM 10.9 Procurement Dredging, Stabilization & Capping 255 Issue RFP - Dredging, Stabilization & Capping 0 0 21-Dec-12 260 Dredging Subcontractors Prepare Proposals 35 35 21-Dec-12 100 30-Jan-13 255, 265 265 Mandatory Site Walk 0 0 04-Jan-13 255 270 Issue Response to Questions 4 4 07-Jan-13 10-Jan-13 265 275 Receive Subcontractor Proposals 0 0 30-Jan-13 270, 260 Remaining Level of Effort River Mile 10.9 Removal Action Milestone Actual Level of Effort Lower Passaic River Study Area Actual Work Planned Work Appendix J, p. 1 of 4 Issue RFP - Dredging, Stabilization & Capping Dredging Subcontractors Prepare Proposals Mandatory Site Walk Issue Response to Questions Receive Subcontractor Proposals Project_Schedule Start Date: 29-Nov-12 FinishDate: 11-Feb-14 Layout: Client Data Date: 29-Nov-12 Filter(s):TASK filter: All Activities Page 1 of 4 Run Date: 27-Feb-13 Jun Jul Aug Activity ID Activity Name Orig Rem Start Dur Dur 22 22 31-Jan-13 Finish Predecessors 2013 Nov 280 Evaluate Proposals / Select Dredging Contractor 25-Feb-13 275 285 Submit Written Recomendation to CPG 0 0 04-Mar-13 280 290 Award Contract - Dredging 0 0 26-Apr-13 565, 140 0 0 21-Dec-12 Dec Jan Feb Mar Apr May Jun 2014 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Evaluate Proposals / Select Dredging Contractor Submit Written Recomendation to CPG Award Contract - Dredging Transportation & Disposal Issue RFP - Transportation & Disposal 295 Issue RFP - Transportation & Disposal 300 T & D Subcontractors Prepare Proposals 37 37 21-Dec-12 01-Feb-13 295 305 Mandatory Site Visit by Jan 11th 1 1 11-Jan-13* 11-Jan-13 300 Mandatory Site Visit by Jan 11th 310 Issue Response to Questions 0 0 15-Jan-13 305 Issue Response to Questions 315 Receive T&D Contractor Proposals 0 0 01-Feb-13 300, 310 320 Evaluate Proposals / Select T&D Contractor 25-Feb-13 315 325 Submit Written Recomendation to CPG 0 0 04-Mar-13 320 330 Award Contract - T& D 0 0 26-Apr-13 565, 140 Award Contract - T& D 26-Apr-13 340 RM 10.9 Task Order Summary 20 20 02-Feb-13 100 T & D Subcontractors Prepare Proposals Receive T&D Contractor Proposals Evaluate Proposals / Select T&D Contractor Submit Written Recomendation to CPG RM 10.9 Task Order RM 10.9 Task Order Summary 335 RM 10.9 Task Order Summary 91 91 11-Jan-13 RM 10.9 Task Order Bench Scale S/S Testing - Stabilization Facility Prepare Work Plan 570 Discuss S/S Testing with facilities 575 Facilities Prepare S/S Testing Work Plans 580 CH2M HILL Review/Comment 585 Submit to NJDEP for Review 590 NJDEP for Review 15 15 12-Feb-13 595 Revise Work Plan 2 600 NJDEP Accepted Work Plan Approach 0 Discuss S/S Testing with facilities 0 0 09-Jan-13 11 11 09-Jan-13 21-Jan-13 570 Facilities Prepare S/S Testing Work Plans 2 2 22-Jan-13 23-Jan-13 575 CH2M HILL Review/Comment 0 11-Feb-13 580 28-Feb-13 585 NJDEP for Review 2 01-Mar-13 02-Mar-13 590 Revise Work Plan 0 02-Mar-13 595 NJDEP Accepted Work Plan Approach 0 620 Submit to NJDEP for Review Bench Scale Testing 605 Conduct Bench Scale Testing 12 12 04-Mar-13 16-Mar-13 600, 165 610 Receive TCLP Analytical Results 18 18 18-Mar-13 06-Apr-13 605 615 Summary Report 5 5 08-Apr-13 12-Apr-13 610 Conduct Bench Scale Testing Receive TCLP Analytical Results Summary Report Permit Equivalency Applications Initial Meeting With NJDEP 620 Initial Meeting With NJDEP 0 0 29-Nov-12 625 Call with NJDEP 0 0 06-Feb-13 740 9 9 10-Dec-12 19-Dec-12 620 Prepare Potential To Emit (PTE) Calculations 0 0 19-Dec-12 630 Submit PTE Calculations to NJDEP 1 1 20-Dec-12 20-Dec-12 635 NJDEP Review of PTE 21 21 21-Dec-12 14-Jan-13 640 28-Feb-13 645 15-Feb-13 620 Call with NJDEP CPG Dredging PTE 630 Prepare Potential To Emit (PTE) Calculations 635 Submit PTE Calculations to NJDEP 640 NJDEP Review of PTE 645 Respond to NJDEP Comments 650 NJDEP Acceptance of PTE 0 Waterfront Development Permit 655 Prepare WFD Permit Equivalency Package 68 0 68 29-Nov-12 Respond to NJDEP Comments NJDEP Acceptance of PTE Prepare WFD Permit Equivalency Package 660 Submit WFD Permit Equivalency Package to NJDEP 0 0 22-Feb-13 655, 700, 625 Submit WFD Permit Equivalency Package to NJDEP 665 Distribute Notification and Permission Letters 0 0 22-Feb-13 660 Distribute Notification and Permission Letters 670 Review Status Meeting with NJDEP 0 0 15-Mar-13 660 Review Status Meeting with NJDEP 22-Mar-13 660 Completenes Determination 22-Mar-13 675 Conditional Approval NJDEP Review & Approval 675 Completenes Determination 680 24 Conditional Approval Remaining Level of Effort 0 24 23-Feb-13 0 River Mile 10.9 Removal Action Milestone Actual Level of Effort Lower Passaic River Study Area Actual Work Planned Work Appendix J, p. 2 of 4 Project_Schedule Start Date: 29-Nov-12 FinishDate: 11-Feb-14 Layout: Client Data Date: 29-Nov-12 Filter(s):TASK filter: All Activities Page 2 of 4 Run Date: 27-Feb-13 Jun Jul Aug Activity ID Activity Name Orig Rem Start Dur Dur Finish Predecessors 2013 Nov Dec Jan Feb Mar Apr May Jun 2014 Jul Aug Sep 685 Receive AUD in Support of WFD 0 0 07-May-13 790 Receive AUD in Support of WFD 690 Final Approval 0 0 07-May-13 685, 220, 650, 665, 150 Final Approval 0 0 14-Dec-12 6 6 14-Dec-12 20-Dec-12 695 55 55 21-Dec-12 22-Feb-13 700 Prepare Tidelands Equivalency Package 22-Feb-13 705 Submit Tidelands Equivalency Package 12-Mar-13 710 Tidelands 695 Send Lot Information to NJDEP 620 Oct Nov Dec 705 Prepare Tidelands Equivalency Package 710 Submit Tidelands Equivalency Package 715 NJDEP Review of Tidelands Equivalency Package 720 Request to be included on Tidelands Commission Agenda 0 0 22-Mar-13 680, 715 Request to be included on Tidelands Commission Agenda 725 Submit Conditional WFD Approval to Tidelands Commission 0 0 22-Mar-13 680, 720 Submit Conditional WFD Approval to Tidelands Commission 730 Tidelands Commission Hearing and Approval 0 0 01-May-13* 725 0 15 23-Feb-13 Mar Apr May NJDEP Determines Ownership of Sediment NJDEP Determines Ownership of Sediment 0 Feb Send Lot Information to NJDEP 700 15 Jan NJDEP Review of Tidelands Equivalency Package Tidelands Commission Hearing and Approval Stabilization Facility Air Permit 735 Contact S/S Facilities 740 Prepare PTE Calculations 745 CH2M HILL Review 750 Submit PTE Calculations to NJDEP 755 NJDEP Review of PTE 760 765 0 0 08-Jan-13 26 26 08-Jan-13 06-Feb-13 735 4 4 07-Feb-13 11-Feb-13 740 0 0 620 Contact S/S Facilities Prepare PTE Calculations CH2M HILL Review Submit PTE Calculations to NJDEP 08-Mar-13 745, 285, 325 12 12 09-Mar-13 22-Mar-13 750 Respond to NJDEP Comments 7 7 23-Mar-13 30-Mar-13 755 Respond to NJDEP Comments NJDEP Acceptance 0 0 30-Mar-13 760 NJDEP Acceptance 02-Apr-13 285, 325 Prepare AUD 0 06-Apr-13 770, 610 0 13-Apr-13 775 07-May-13 775, 780 NJDEP Review NJDEP Approval Authorized Use Determination 770 Prepare AUD 25 0 25 05-Mar-13 775 Submit AUD to NJDEP 780 Meeting to Discuss AUD Application 785 NJDEP Review 26 790 NJDEP Approval 0 0 07-May-13 785, 615 0 26 08-Apr-13 NJDEP Review of PTE Submit AUD to NJDEP Meeting to Discuss AUD Application Construction End of Local Rowing Season 795 End of Local Rowing Season 0 0 17-Jun-13* 620 800 End of Lower Passaic River Fish Window 0 0 30-Jun-13* 620 End of Lower Passaic River Fish Window 805 Passaic Regatta 3 3 11-Oct-13* 13-Oct-13 620 Passaic Regatta 29-Jun-13 825, 290 Implementation Mobilization 810 Prepare Project Plans & Submittals 55 55 27-Apr-13 Prepare Project Plans & Submittals Deployment of Water Quality Monitoring Buoys 815 Deployment of Water Quality Monitoring Buoys 4 4 25-May-13 29-May-13 220 820 Baseline WQ Monitoring 25 25 01-Jun-13 29-Jun-13 815, 730, 195 Baseline WQ Monitoring 825 Mobilization of Dredging Contractor 22 22 01-Jun-13 26-Jun-13 290, 765, 330, 790, 690, 140 Mobilization of Dredging Contractor 830 Dredge Barge Preparation & Assembly 20 20 06-Jun-13 28-Jun-13 810 Dredge Barge Preparation & Assembly 835 Dredge Moved to Location 3 3 27-Jun-13 29-Jun-13 830 Dredge Moved to Location 840 Silt Curtain Deployment and Maintenance 99 99 27-Jun-13 19-Oct-13 835 845 Pre-Dredge Survey 3 3 27-Jun-13 29-Jun-13 835 Dredging (20,000 CY @ 462 CY/Day; 6 days/wk) 850 Dredging 855 40 Anticipated Dredging Delays Treatment/Stabilization 860 Plant Mobilization & Modification 865 Processing 870 Anticipated Processing Delays Remaining Level of Effort 15-Aug-13 800, 795, 820, 670, 810, 835, 845 5 5 16-Aug-13 21-Aug-13 850 22 22 03-Jun-13 27-Jun-13 810 40 40 02-Jul-13 16-Aug-13 850, 860 22-Aug-13 865, 855 5 40 01-Jul-13 5 17-Aug-13 River Mile 10.9 Removal Action Milestone Actual Level of Effort Lower Passaic River Study Area Actual Work Planned Work Appendix J, p. 3 of 4 Silt Curtain Deployment and Maintenance Pre-Dredge Survey Dredging Anticipated Dredging Delays Plant Mobilization & Modification Processing Anticipated Processing Delays Project_Schedule Start Date: 29-Nov-12 FinishDate: 11-Feb-14 Layout: Client Data Date: 29-Nov-12 Filter(s):TASK filter: All Activities Page 3 of 4 Run Date: 27-Feb-13 Jun Jul Aug Activity ID Activity Name Orig Rem Start Dur Dur Transportation & Disposal 875 Mobilization of T&D Contractor 880 Site Setup at Stabilization Facility 885 Transportation & Disposal 890 Demobilization of T&D Contractor 0 5 44 Finish 5 28-Jun-13 2013 Nov 0 28-Jun-13 44 04-Jul-13 Predecessors Dec 330, 860 03-Jul-13 875 23-Aug-13 875, 880, 850, 870, 865 Jan Feb Mar Apr May Jun 2014 Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Mobilization of T&D Contractor Site Setup at Stabilization Facility Transportation & Disposal Demobilization of T&D Contractor 5 5 24-Aug-13 29-Aug-13 885 Capping Mobilization 10 10 22-Aug-13 02-Sep-13 855 900 Capping 36 36 03-Sep-13 14-Oct-13 895, 905 905 Passaic Regatta - Move Equipment Upstream of RM11 1 1 11-Oct-13 11-Oct-13 805 910 Anticipated Capping Delays 5 5 15-Oct-13 19-Oct-13 900, 840 915 Demobilization Dredging/Capping Contractor 8 8 21-Oct-13 29-Oct-13 900, 910 Demobilization Dredging/Capping Contractor 920 Construction Completion 0 0 29-Oct-13* 890, 915 Construction Completion Capping 895 Final Report 925 Prepare Final Report Capping Mobilization Capping Passaic Regatta - Move Equipment Upstream of RM11 Anticipated Capping Delays 11-Feb-14 920 Prepare Final Report 930 Submit Final Report 0 0 11-Feb-14 925 Submit Final Report 999 Task Order 2 Completion 0 0 11-Feb-14* 930 Task Order 2 Completion Remaining Level of Effort 90 90 30-Oct-13 River Mile 10.9 Removal Action Milestone Actual Level of Effort Lower Passaic River Study Area Actual Work Planned Work Appendix J, p. 4 of 4 Project_Schedule Start Date: 29-Nov-12 FinishDate: 11-Feb-14 Layout: Client Data Date: 29-Nov-12 Filter(s):TASK filter: All Activities Page 4 of 4 Jun Run Date: 27-Feb-13 Jul Aug