NAS Infrastructure Management ATO Technical Operations Presented to: NEXTOR and FAA Conference at The National Academies By: Juaida Norrell Date: September 9, 2005 Federal Aviation Administration NAS Buildings and Building Systems • NAS building and building systems infrastructure is made up of: – 9,000 General National Airspace unstaffed facilities – Power systems • 3800 engine generators • 587 uninterruptible power supply systems – – – – – – 21 Air Route Traffic Control Centers (ARTCCs) 3 Center Radar Approach Control (CERAPs) 1 Combined facility (ATCT/TRACON/CERAP) 519 Terminal facilities 3 Automated Flight Service Stations (Alaska) 14 Flight Service Stations (Alaska) NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 2 Surveillance NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 3 Navigation Aids NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 4 Communications NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 5 Facility Assessments Facility Condition Index (FCI) FCI = Dollar value of backlog (Maintenance & repair) Current replacement value NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 6 Shelter Replacement NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 7 HVAC Replacement NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 8 Structural Towers NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 9 Access Roads NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 10 Roofing NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 11 NAS Power Systems have Multiple Components Lightning Protection Service Life - 20 Years UPS Service Life - 10 Years Grounding Service Life - 20 Years Cable Distribution Service Life - 20 Years Engine Generator Service Life - 20 Years Transformer Service Life - 20 Years Switchboard Service Life - 20 Years NAS Infrastructure Management September 9, 2005 Utility Service Service Distribution Cable Federal Aviation Administration 12 Critical Power Distribution System (CPDS) Have Multiple Complex Subsystems NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 13 Both GNAS and ARTCC Batteries Must Be Replaced before They Fail GNAS Battery Bank “Wet Cells” ARTCC UPS Batteries “VRLA Cells” NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 14 NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 15 DC Systems Replace Standby Generators Before After NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 16 Legacy Engine Generators: Overdue To Be Replaced Vintage E/G in NAS service Current engine generator NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 17 Airport Buried Power Cable: Failure Causes Delays Philadelphia Airport Power and Data Cable Outage, July 2005 FAULT LOCATION FAULT COM MANHOLE POWER LINE AND COM ROUTE PVC DUCT 13.2 KV POWER MANHOLE NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 18 Proper Grounding Is Critical •Phoenix TDWR TVSS •Chicago ATCT UPS Lightning seeks elevated objects such as ATCTs, Radars, Antennas, fences NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 19 Commercial and Standby power outages are increasing Commercial and Standby Power Outage Count Note: The actual count of commercial power outage exceeds those reported here due to standby power systems preventing loss of service. 500 450 400 Power Outage Count 350 Service outages due to loss of commercial power 300 250 200 150 100 50 Service outages due to loss of FAA power 0 1/0 0 4/0 0 7/0 0 10 1 /00 /01 4/0 1 7/0 1 10 1 /01 /02 4/0 2 7/0 2 10 1 /02 /03 4/0 3 7/0 3 1 10 /03 /04 4/0 4 7/0 4 10 1 /04 /05 4/0 5 7/0 5 Date NAS Infrastructure Management September 9, 2005 Federal Aviation Administration 20