UNDER CONSTRUCTION
Betty Coleman
WATER QUALITY ENHANCEMENT PROJECT
Dear Resident:
June 2012
Construction is underway for Charlotte-Mecklenburg Storm Water Services’
Betty Coleman Water Quality Enhancement Project. On-Site Development,
LLC was awarded the construction contract and began work in February.
Construction update:
• Principal spillway and filter diaphragm has been completed.
• The dam has been backfilled to its finish elevation.
• Water is now flowing from the pond directly through the new pipe.
• Construction has begun on the emergency spillway. Upon completion
of the spillway, final grading and seeding will begin to establish ground
cover.
• Temporary erosion control measures will remain in place until ground
cover is established.
• The bottom drain valve will remain open until final acceptance is made.
Upon acceptance, the valve will be closed and the pond will return to
normal surface elevation.
For more information about this project, please visit our website to view
project updates and exhibits at: http://stormwater.charmeck.org. Click
on Storm Water Projects drop down menu in the green bar, then Active
Projects and Betty Coleman.
Contractors work on emergency spillway for Betty
Coleman Pond. New dam outlet endwall with 48” RCP
exit pipe shown in background.
If you have any questions, please contact one of the following team
members:
On-site Construction Inspector:
Charlotte Drzewiecki: 704-432-0964
E-mail: cdrzewiecki@charlottenc.gov
Construction Manager:
Project Manager:
Gary Stansbury: 704-336-2667
Matthew Anderson: 704-336-7923
E-mail: gstansbury@charlottenc.gov manderson@charlottenc.gov
A construction inspector will be on site daily to address any questions or concerns.
Please note efforts are taken to minimize disruption to nearby properties.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202