storm drainage improvement project
YOUR STORM WATER FEES AT WORK
June 6, 2008
Dear Resident,
Charlotte-Mecklenburg Storm Water Services (Storm Water) held
a public meeting on May 8, 2008 at Christ Episcopal Church for the
Cherokee/Scotland Storm Drainage Improvement Project.
•
The meeting discussed the recommended project alternative for
the Cherokee/Scotland Project and gathered additional feedback.
Meeting highlights:
•
•
•
•
Mr. Troy Eisenberger, Project Manager, discussed the
organization of the project team and provided a general
overview of the Storm Water Services Program.
The planning phase is complete. The proposed alternative
was presented at the meeting. This alternative was
developed to ensure improvements will be implemented in
the most appropriate locations.
He emphasized that community involvement is imperative to
the success of the project and the team wanted to hear any
concerns.
The Design Phase is anticipated to begin during the summer
of 2008, which includes developing construction drawings
•
for the proposed improvements. This phase typically lasts 18
to 24 months. A third public meeting will be held when the
design plans are 70% complete.
Mr. Eisenberger noted that construction is a maximum of two
years.
The meeting concluded with breakout sessions that invited
citizens to interact with the project team one-on-one.
For more information about this project, detailed meeting
minutes or project exhibits please visit our website at
http://stormwater.charmeck.org and click on Storm Water
Projects, Storm Water Projects again, then Cherokee/Scotland.
If you have any questions about this project, please contact
the Project Manager, Troy Eisenberger at 704-336-4835 or
teisenberger@ci.charlotte.nc.us.
Engineering & Property Management
Storm Water Services Division
600 East Fourth Street
Charlotte, North Carolina 28202