Relevant ITU-T Recommendations for the Protection of Base Stations Ahmed ZEDDAM,

advertisement
ITU Workshop on
“Tackling climate change and Specific Absorption
Rate (SAR) Measurement”
(Cotonou, Benin, 19 July 2012)
Relevant ITU-T Recommendations
for the Protection of Base Stations
Ahmed ZEDDAM,
ITU-T SG5 Chair
France Telecom Orange
Cotonou, Benin, 19 July 2012
Outline
 INTRODUCTION
 LIGHTNING

PROTECTION
RECOMMENDATION ITU-T K.56

Need of Protection

Earthing and Bonding procedures

Use of SPDs
 DECOUPLING

WITH POWER NETWORK
CONCLUSION
Cotonou, Benin, 19 July 2012
2
Introduction
Protection of an installation may
require a combination of:
Lightning protection for the building
Protection on incoming lines
Resistibility of equipment
Earthing and bonding of installation
This presentation is about the protection
of equipment within a base station
3
Cotonou, Benin, 19 July 2012
SG 5 role in equipment protection
SG 5 is unique SDO in overvoltage
protection
Ensures coordination of the equipment and
external protection
Considers installation practices and their
effect on resistibility requirements
4
Cotonou, Benin, 19 July 2012
Resistibility and protection
Preventing equipment damage may
require a combination of resistibility
and protection
Resistibility is
The ability of the equipment to withstand an
overvoltage or overcurrent
Protection is
The addition of primary protection to prevent
damage from larger surges
Need to check that the protector operates and
protects the equipment
5
Cotonou, Benin, 19 July 2012
Lightning Protection
Lightning
discharges
can reach a
telecommunication
system by the
following
mechanisms:
6
Cotonou, Benin, 19 July 2012
Lightning Protection
Direct strikes
7
Cotonou, Benin, 19 July 2012
Lightning Protection
Coupling through
the earth
8
Cotonou, Benin, 19 July 2012
Lightning Protection
Coupling through
electromagnetic fields
9
Cotonou, Benin, 19 July 2012
Lightning Protection
 If adequate protection is missing, the lightning
surges can be very dangerous to telecommunications
systems, threatening :
 Terminal equipment
 Station equipment
 And even human beings
 In order to protect the telecommunications systems
against the effects of lightning discharges, the ITU-T
SG-5 produced Handbooks and a set of Series K
Recommendations:
10
Cotonou, Benin, 19 July 2012
Recommendation ITU-T K.56 :
Protection of radio base stations against
lightning discharges
Presents the techniques applied to a telecom. radio base
station in order to protect it against lightning discharges
The need of protection is obtained from the methodology
contained in IEC 62305-2, which is used to determine the
relevant lightning protection level (LPL) for the installation
The protection techniques for the external area cover the
lightning protection system (LPS), bonding procedures,
earthing and the installation of surge protective devices
(SPDs) at the power meter station
The protection techniques for the equipment building cover
the feeder and lighting cables, the electric power conductors,
the telecommunication cabling and the earthing/bonding
procedures applied to cable trays and equipment frames
Cotonou, Benin, 19 July 2012
11
Need of protection
The risk assessment of the RBS shall be performed according to
[IEC 62305-2] in order to determine a Lightning Protection Level (LPL) for
the design of the protection procedures.
Table 1 shows some lightning flash parameters associated with each LPL.
LPL
Parameter
Unit
I
II
III
IV
kA
200
150
100
100
kA/s
200
150
100
100
Radius of electro-geometric sphere
m
20
30
45
60
Probability of flash
%
99
98
95
90
Maximum peak current
Maximum current rate of rise
Table 1 – Lightning flash parameters from [IEC 62305-1]
Cotonou, Benin, July 2012
12
Earthing and bonding procedures
applied to the external area
Figure 1 – General view of earthing and bonding procedures
in the external area
Cotonou, Benin, July 2012
13
Earthing configuration
Fence earthing ring
Building
earthing ring
Fence
Bonding between
fence and ring
Feeder tray
Gate
earthing
Tower earthing ring
RBS building
Vertical
rod
Power meter
station
K.56(10)_F05
Figure 5 – Earthing system of the RBS
Cotonou, Benin, July 2012
14
Earthing configuration
A bare conductor forms a ring electrode around the building and another ring
around the tower. Multiple earthing conductors are used to interconnect the two
rings (three, in the figure).
The distance of the buried conductor from the associated structure shall be
approximately 1.0 m, and the depth of the conductor shall be at least 0.5 m.
Vertical rods should be installed along the ring electrode, as shown in Figures 1
and 5. These rods should be made of steel covered with copper or made of
galvanized steel, and they shall be attached to the earth electrode by appropriate
connectors.
The legs of a metallic tower (or the down conductors of a non-metallic tower) shall
be bonded through short connections to the tower's earthing ring. The steel
reinforcement of the tower's basement, if any, shall also be connected to the
earthing ring (see Figures 1 and 5).
The steel reinforcement of the building's structure shall be bonded to the earthing
ring at least at its four corners. If the building is metallic, its feet shall be bonded to
the earthing ring.
The earthing ring of the building shall be connected to the main earthing bar (MEB)
located inside the building, preferably on the wall that faces the tower. The
earthing conductor shall be as short as possible and have 50 mm2 as the minimum
cross-section area.
All conductors in contact with the earth should be made of copper or steel covered
with copper and have 50 mm2 as the minimum cross-section area. Galvanized steel
conductors could also be used, with 90 mm2 as the minimum cross-section area.
 A fence usually surrounds the terrain where the RBS is located. If the fence is
metallic, some precautions have to be taken in order to minimize the hazard due to
the voltages transferred by the fence.
15
Cotonou, Benin, July 2012
Bonding at the feed-through window
Figure 6 – Example of earthing the feeder cable at the feed-through window
Cotonou, Benin, July 2012
16
Use of SPDs
Figure 7 – Diagram of the electric board
Cotonou, Benin, July 2012
17
Installation of SPD in the electric board
Figure 8 – Scheme for SPD installation on TT power systems
The SPDs shall comply with [IEC 61643-11]
 The SPD installed in the electric board shall coordinate with the SPD
installed in the power meter station [see IEC 61643-12 for coordination]
Annex A of [ITU-T K.66] gives information on SPD installation
for different power systems.
Cotonou, Benin, July 2012
18
Protection of telecommunication lines
Telecommunication cable
To the equipment
SPD
Fail safe
To the main
earthing bar
Distribution frame
earthing bar
K.56(10)_F11
Figure 11 – Installation of SPD in the distribution frame
 The procedures for the protection of telecommunication lines
against direct and indirect lightning discharges can be found
in [ITU-T K.47] and [ITU-T K.46], respectively, taking into
account [ITU-T K.72].
Cotonou, Benin, July 2012
19
Example of earthing and bonding
configuration inside an RBS
 More information on the implementation of earthing and bonding
configurations can be found in [ITU-T K.27] and [ITU-T K.35
Cotonou, Benin, July 2012
20
Decoupling with power network
D1 : Distance entre la prise de terre des masses du poste de transformation HTA/BT et la prise de
terre du Neutre BT,
D2 : La distance entre a prise de terre des masses du poste de transformation HTA/BT et la prise
de terre du Site de Radiocommunication,
D3 : Distance entre a prise de terre du Neutre BT et la prise de terre du Site Radiocommunication
Cotonou, Benin, July 2012
21
Decoupling with power network
Cotonou, Benin, July 2012
22
CONCLUSION
Protection of Base Stations is based on the
combination of :
Lightning protection for the building
Protection on incoming lines (SPDs)
Resistibility of equipment
Earthing and bonding of installation
Decoupling with power network
Recommendation ITU-T K.56 provides useful
information for the protection of RBS and
refers to other relevant Recommendations
Cotonou, Benin, July 2012
23
Thank you
Cotonou, Benin, 19 July 2012
24
Download