Procurement Management Division On-Call Airport Communication Cabling Installation Services RFP #269-2016-042 Addendum #3 To: All Prospective Proposers Date: February 24, 2016 Subject: Addendum #2 – RFP # 269-2016-042 – On-Call Airport Communication Cabling Installation Services Please note the specification changes/modifications below for the RFP. Item # 1 Page # 16 Section # Form 3, C. – Certifications / Memberships / Credentials Specification(s) Change(s) Modification(s) For the Proposer’s Technicians, Bullet #2 Modification: The Second Bullet is modified to read as follows: • BICSI ITS Technician Certification and Panduit/Corning/CommScope training current, and completed within the last two (2) years for a minimum of one (1) lead installation technician. Proposer Question: Please clarify the differences between the two types of references. 2 3 15 10 Form 3, A., 4. Experience and Qualifications Addendum 1, Exhibit E - CDIA Communications Infrastructure Standard General: Contractor Requirements and Responsibilities: Communications Contractor Requirements and Qualifications, Bullets 1 – 4 Answer: CLT requests that each proposer provide three references that can speak to the company’s operational performance and three that can speak to the company’s financial ability to meet the operational needs set forth in this RFP. Proposer Question: Are these requirements for each technician or for the Proposer as an entity? Answer: Please reference Form 3, Section C. of the RFP, which states these are requirements for the Proposer. The information in Addendum 1, Exhibit E is provided for reference purposes only, and is subject to change. Procurement Management Division Management and Financial Services/City of Charlotte 600 East Fourth Street Phone: 704/336-2256 Fax: 704/336-2258 1 Charlotte, NC 28202-2850 Item # 4 5 6 7 Page # 10 10 10 11 Section # Specification(s) Addendum 1, Exhibit E - CDIA Communications Infrastructure Standard General: Contractor Requirements and Responsibilities: Communications Contractor Requirements and Qualifications, Bullet #5 Addendum 1, Exhibit E - CDIA Communications Infrastructure Standard Addendum 1, Exhibit E - CDIA Communications Infrastructure Standard Addendum 1, Exhibit E - CDIA Communications Infrastructure Standard General: Contractor Requirements and Responsibilities: Communications Contractor Requirements and Qualifications, Bullet #7 General: Contractor Requirements and Responsibilities: Communications Contractor Requirements and Qualifications, Bullet #8 General: Contractor Requirements and Responsibilities: Communications Contractor Additional Qualifications, Bullet #2 Change(s) Modification(s) Proposer Question: The Cisco Silver Business Partner certification required here has been retired as of April 2015. How does this affect the standards? Answer: The information in Addendum 1, Exhibit E is provided for reference purposes only, and is subject to change. Qualifications for Proposers can be found in Form 3, Section C of the RFP. Proposer Question: Are Proposers who have not worked with CLT previously automatically disqualified? Answer: No, it is not required for a Proposer to have had previous work with CLT. Please note, the information in Addendum 1, Exhibit E is provided for reference purposes only, and is subject to change. Qualifications for Proposers can be found in Form 3, Section C of the RFP. Proposer Question: Is a Proposer’s technician who has just completed the BICSI ITS training and certification prohibited from working on site because the technician didn’t have the certification 2 years prior? Answer: No, please reference the Modification in Item #1 above, which states these requirements must have been completed by at least one lead installation technician within the past two years. Also, please note, the information in Addendum 1, Exhibit E is provided for reference purposes only, and is subject to change. Qualifications for technicians can be found in Form 3, Section C of the RFP. Proposer Question: This requirement seems to automatically disqualify Proposers if their company is less than five years old. Is that correct? Answer: That is incorrect. Please reference Form 3, Section A. of the RFP, which details the Experience and Qualifications that should be included by the Proposer in its proposal. Please note, the information in Addendum 1, Exhibit E is provided for reference purposes only, and is subject to change. In order to constitute a complete proposal response you must acknowledge receipt of this addendum with the Acknowledgement of Addenda found in Form 2, Section C. of the RFP in your Proposal. Procurement Management Division Management and Financial Services/City of Charlotte 600 East Fourth Street Phone: 704/336-2256 Fax: 704/336-2258 2 Charlotte, NC 28202-2850 Any Service Provider not acknowledging receipt of an issued addendum may not be considered. In the event additional changes or clarifications to this RFP are warranted, all Proposers are responsible for monitoring http://charmeck.org/city/charlotte/Airport/AboutCLT/Pages/AdsForBids.aspx or www.ips.state.nc.us for additional addenda. We appreciate your interest in doing business with the City of Charlotte and look forward to receiving a proposal from your company. Sincerely, Philip Keller Procurement Officer cc: File Procurement Management Division Management and Financial Services/City of Charlotte 600 East Fourth Street Phone: 704/336-2256 Fax: 704/336-2258 3 Charlotte, NC 28202-2850