Cleaning Up the Lower Passaic River An Overview of the Options for Cleaning up Contaminated Sediment in the Lower Eight Miles May 2014 The Proposed Plan and the Focused Feasibility Study report have a considerable amount of detail on the cleanup options that were considered. They are available at www.ourpassaic.org In early 2015 the EPA expects to make a decision about how to clean up the sediment of the lower eight miles of the Passaic after considering public comments on the Proposed Plan. After completion of the on-going study of the 17-mile, tidal stretch of the Lower Passaic the EPA expects to propose a plan that addresses the entire Lower Passaic River. Evaluating Cleanup Options The EPA conducted a multi-year “Focused Feasibility Study” of an eight mile section of the Lower Passaic River. The study evaluated three cleanup options (also referred to as “Remedial Alternatives”) to address contaminated sediment in this area of the river, as well as a fourth option of taking no action. Information collected during a larger The Passaic River’s study of the entire 17-mile Polluted Past fact stretch of the Lower Passaic sheet contains River, from Newark Bay to an overview of the Dundee Dam in Garfield, the problems which is ongoing, showed that and the Remedial contaminated sediment in the Investigation lower eight miles, as deep as Report for the 15 feet, is a major source of lower eight miles contamination to the rest of provides details the river and Newark Bay. on the history and On April 11, 2014, the EPA nature and extent issued for public review of contamination. and comment a “Proposed Plan” outlining the Agency’s preferred cleanup plan for the lower eight miles of the river. The EPA’s preferred cleanup plan is “Capping with Dredging for Flooding & Navigation” with “Off-Site Disposal of Dredged Materials”, described in the Focused Feasibility Study and Proposed Plan as “Alternative 3 with Dredged Materials Management Scenario B.” Cleanups under Superfund must protect human health and the environment. A cleanup option is considered protective if it reduces current and potential future risks associated with the pathways by which people and wildlife are, or will be, exposed to site contaminants to acceptable levels. The EPA uses nine criteria to evaluate cleanup options. Page 26 of the Proposed Plan provides more details about these criteria Superfund Remedy Evaluation Criteria 1 Overall Protection of Human Health and the Environment 2 3 Compliance with Applicable or Relevant and Appropriate Requirements 4 Reduction of Toxicity, Mobility, or Volume of Contaminants through Treatment 5 6 7 8 9 Long-term Effectiveness and Permanence Short-term Effectiveness Implementability Cost State Acceptance Community Acceptance www.ourpassaic.org 1 Elements Common to Cleanup Options All of the cleanup options (i.e., options other than “No Action”) contain some common elements: Dredging. Refers to the method for removing sediment from the river bottom. “Mechanical” and “Hydraulic” are two common types of dredging. The actual method used would be decided during the design. Capping/Backfilling. Refer to the method of covering the river bed to isolate the contaminated sediment from the food chain. Cap and backfill material both typically consist of coarse-grained sand acquired locally. Backfill refers to sand placed on the river bed after dredging that is intended to mitigate the impact of remaining contaminated sediment and would not be maintained after placement. An engineered cap is a physical barrier constructed primarily of sand and stone that would be placed over the dredged areas to protect against erosion or other physical disturbances and would be maintained in perpetuity. Fish Consumption Advisories. The New Jersey Department of Environmental Protection (NJDEP) fish and crab consumption advisories currently in place would continue under all of the alternatives. Enhanced outreach efforts would be conducted in municipalities on both shores of the Passaic River to educate community members about the advisories and to emphasize that they will remain in place during and after cleanup until cleanup goals are reached. Controls to Protect the Cap Following Cleanup. Cleanup options which rely on an engineered cap for protectiveness require additional institutional controls to maintain cap integrity in perpetuity. Such controls might include: prohibitions on anchoring vessels, restrictions on dredging except in the federally-authorized navigation channel, and/or bulkhead maintenance agreements or deed restrictions. Dredged Material Management (DMM). Refers to the method for disposing of contaminated sediment after being dredged from the river. Scenario A: A confined aquatic disposal (CAD) site in Newark Bay is a pit dug in the tight clay bottom of the bay into which dredged sediment can be disposed. After the pit is filled, an engineered cap would be placed over it to isolate the dredged sediment from the bay. Scenario B: Off-site disposal would involve barging the dredged sediment to a facility on the shores of the Passaic River or Newark Bay to be dewatered, loaded onto trains and sent to incinerators and landfills in the U.S. or Canada. Scenario C: Decontamination would involve barging the dredged sediment to a facility on the shores of the Passaic River or Newark Bay to be treated through technologies that would separate the sediment particles from the contaminants. The contaminants would be disposed of in landfills in the U.S. or Canada and the cleaner sediment particles could be beneficially re-used. 2 www.ourpassaic.org Cleanup Options (Remedial Alternatives) Four alternatives were evaluated by EPA: Alternative 1: No Action. The Superfund program requires that the No Action alternative be considered as a baseline for comparison with the other remedial alternatives. Alternative 1 would not result in any risk reduction for people who consume fish and crabs, therefore this alternative fails to meet the protectiveness standard for Superfund cleanups. Alternative 2: Deep Dredging with Backfill and Alternative 3: Capping with Dredging for Flooding and Navigation. Alternatives 2 and 3 are considered to be protective because the risk of people getting cancer from consuming fish and crabs would be reduced by ten times after cleanup and monitoring would be implemented to make sure that contaminant concentrations continue to go down towards protective goals. Approximately 10 years after construction, EPA could recommend that NJDEP start relaxing the stringency of fish and crab consumption advisories to allow one fish meal per month, as opposed to the current advisory of eat none. Alternative 4: Focused Capping with Dredging for Flooding. Alternative 4 is not considered to be protective because dredging and capping only 220 out of 650 acres in the lower eight miles is unlikely to lead to substantial decreases in concentrations of major contaminants and the risk of people getting cancer from consuming fish and crabs would continue for the forseeable future. Key Features of Cleanup Options (Alternatives) Alternative 2 Alternative 3 Alternative 4 Brief Description Deep Dredging with Backfill is a bank-to-bank cleanup with dredging all 9.7 million cubic yards of contaminated fine-grained sediment in the lower eight miles followed by placement of two foot thick layer of backfill. Capping with Dredging for Flooding and Navigation is a cleanup with placement of a two foot thick bank-to-bank engineered cap (or backfill) in the lower eight miles. The cap would be placed after dredging 4.3 million cubic yards of contaminated fine grained sediment to avoid additional flooding and accommodate use of navigation channel. Focused Capping with Dredging for Flooding is a cleanup over discrete areas that release the most contaminants into the water in the lower eight miles. A two foot thick engineered cap would be placed over these areas after dredging 1 million cubic yards of contaminated fine-grained sediment to avoid additional flooding. Federally Authorized Navigation Channel. The channel between River Mile 0 and River Mile 8.3 would be restored. Continued use from River Mile 0 to River Mile 2.2. Modification from River Mile 1.2 to River Mile 2.2. De-authorization from River Mile 2.2 to River Mile 8.3. No dredging to accommodate channel. De-authorization between River Mile 0 and River Mile 8.3. Cost with CAD $1.34 billion $0.95 billion $0.37 billion Cost with Off-Site Disposal $3.25 billion Cost with Sediment Decontamination $2.62 billion $1.59 billion $0.61 billion Volume Dredged 9.7 million cubic yards 4.3 million cubic yards 1 million cubic yards Area Dredged / Capped/ Backfilled 650 acres 650 acres 220 acres Estimated Volume contained with CAD 9.7 million cubic yards in CAD cells 4.3 million cubic yards in CAD cells 1 million cubic yards in CAD cells Estimated Volume Treated/Landfilled with Off-Site Disposal 10% incinerated 90% landfilled Estimated Volume Treated/Landfilled with Sediment Decontamination 10% thermal treatment 88% sediment washing 2% solidification 7% thermal treatment 92% sediment washing 1% solidification 4% thermal treatment 94% sediment washing 2% solidification Construction Time 11 years 5 years 2 years Cancer Risk Reduction By a factor of 10 to reach protective levels 30 years after construction By a factor of 10 to reach protective levels 30 years after construction By half but would not reach protective levels 30 years after construction Non-Cancer Hazard Reduction Not enough to meet protective levels 30 years after construction Not enough to meet protective levels 30 years after construction Not enough to meet protective levels 30 years after construction NJDEP Fish Consumption Advisories May be able to relax stringency May be able to relax stringency Would not be able to relax 10 years after construction 10 years after construction stringency in foreseeable future In-River Cap Protection Controls There is no cap $1.73 billion 7% incinerated 93% landfilled Maintained in perpetuity $0.61 billion 4% incinerated 96% landfilled Maintained in perpetuity River Miles are depicted on the map on the reverse side. www.ourpassaic.org 3 10 Authorized and 9Proposed Navigation Channel Dimensions EPA’s Preferred Cleanup Plan: Capping with Dredging for Flooding and Navigation with Off-Site Disposal of Dredged Materials 14 15 Despite fish and shellfish advisories warning against eating local fish and shellfish, some people ignore the advisories or are unaware of them and catch and eat local fish and crab out of cultural practice or to put food on the table for their families. Lower Eight Miles of the Lower Passaic River ³ 8 15 Alternative 2 14 7 13 13 The EPA’s cleanup proposal would: 6 12 11 5 2 4 2.Reduce the risks to wildlife by reducing the concentrations of contaminants in 10 miles. the sediment of the lower eight 10 3.Reduce the migration of contaminated sediment from the lower eight miles to 9 upstream portions of the Lower Passaic River and to Newark Bay and the New York-New Jersey Harbor Estuary. ³ 3 1.Reduce cancer risks and non-cancer 1 2 health hazards for people eating fish and shellfish by reducing the concentrations 11 of the of contaminants in the sediment lower eight miles. 1 Depth 9 Numbers in orange refer to river miles 0 Copyright:© 2013 ESRI, i-cubed, GeoEye 8 8 Alternative 3 Authorized and Proposed Navigation Lower Eight Miles of the Lo Off-site Disposal Process 1 Dredging 7 Off-site Disposal 7 6 5 6 3 5 Dewatered material for 4 offsite treatment/ disposal 6 3 2 Water Treatment2 Plant Scow Transport SEDIMENT Hydraulic Offloading Dewatering 2 4 0 Depth of Navigation Channel Copyright:© 2013 ESRI, i-cubed, GeoEye www.ourpassaic.org 5 *There would be no navigation channel maintained above RM2.2 WATER 14 3 4 (Feet 10 16 20 25 30 (Feet below Mean Low Water) 10 16 20 25 30 Authorized and Proposed Navigation Channel Dimensions Lower Eight Miles of the Lower Passaic River 1 0 Copyright:© 2013 ESRI, i-cubed, GeoEye 2014