Appendix H: Cost Estimates

advertisement
Appendix H:
Cost Estimates
LOWER EIGHT MILES OF THE LOWER PASSAIC RIVER
COST ESTIMATES
TABLE OF CONTENTS
1
Introduction .......................................................................................................... 1-1
2
Capital Costs ........................................................................................................ 2-1
3
2.1
A. Pre-Construction Activities ..................................................................... 2-1
2.2
B. Mobilization and Demobilization ............................................................ 2-8
2.3
C. Testing and Monitoring During Dredging and Backfilling/Capping ..... 2-10
2.4
D. Dredging ................................................................................................ 2-13
2.5
E. Backfill and/or Engineered Cap ............................................................. 2-15
Dredged Material Management Capital Costs ..................................................... 3-1
3.1
CAD (DMM Scenario A) .............................................................................. 3-1
3.1.1
F1. Pre-Construction Activities for DMM ............................................ 3-1
3.1.2
G1. CAD Excavation............................................................................. 3-6
3.1.3
H1. Upland Support Facility ................................................................. 3-9
3.1.4
I1. CAD Closure.................................................................................. 3-12
3.1.5
J1. Site Decommissioning/Restoration ............................................... 3-14
3.2
Off-Site Disposal (DMM Scenario B) ......................................................... 3-14
3.2.1
F2. Pre-Construction Activities for DMM .......................................... 3-14
3.2.2
G2. Upland Sediment Processing Facility........................................... 3-17
3.2.3
H2. Equipment Costs........................................................................... 3-23
3.2.4
I2. Processing and Disposal ................................................................ 3-23
3.2.5
J2. Site Decommissioning/Restoration ............................................... 3-26
3.3
Local Decontamination and Beneficial Use (DMM Scenario C) ................ 3-26
3.3.1
F3. Pre-Construction Activities for DMM .......................................... 3-27
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
i
2014
4
3.3.2
G3. Upland Sediment Processing Facility........................................... 3-30
3.3.3
H3. Equipment Costs........................................................................... 3-35
3.3.4
I3. Local Decontamination .................................................................. 3-36
3.3.5
J3. Site Decommissioning/Restoration ............................................... 3-39
Dredged Material Management O&M Costs ....................................................... 4-1
4.1
5
K. DMM Site O&M....................................................................................... 4-1
4.1.1
CAD (DMM Scenario A) ....................................................................... 4-1
4.1.2
Off-Site Disposal (DMM Scenario B) ................................................... 4-3
4.1.3
Local Decontamination and Beneficial Use (DMM Scenario C) .......... 4-5
Long Term O&M Costs ....................................................................................... 5-1
5.1
Annual O&M ................................................................................................. 5-1
5.1.1
L. Annual Monitoring Activities ............................................................ 5-1
5.1.2
M. Annual Maintenance Activities ........................................................ 5-4
5.2
Periodic O&M ............................................................................................... 5-5
5.2.1
N. Periodic Monitoring Activities .......................................................... 5-5
5.2.2
O. Periodic Maintenance Activities ....................................................... 5-6
6
Acronyms ............................................................................................................. 6-1
7
References ............................................................................................................ 7-1
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
ii
2014
LOWER EIGHT MILES OF THE LOWER PASSAIC RIVER
COST ESTIMATES
Table 1-1
LIST OF TABLES
Summary of Present Value Cost Estimates
Table 1-2
Cost Estimate: Alternative 2 with DMM Scenario A – Deep Dredging
with Backfill, CAD Disposal
Table 1-3
Cost Estimate: Alternative 2 with DMM Scenario B – Deep Dredging with
Backfill, Off-site Disposal
Table 1-4
Cost Estimate: Alternative 2 with DMM Scenario C – Deep Dredging with
Backfill, Local Decontamination and Beneficial Use
Table 1-5
Cost Estimate: Alternative 3 with DMM Scenario A – Capping with
Dredging for Flooding and Navigation, CAD Disposal
Table 1-6
Cost Estimate: Alternative 3 with DMM Scenario B – Capping with
Dredging for Flooding and Navigation, Off-site Disposal
Table 1-7
Cost Estimate: Alternative 3 with DMM Scenario C – Capping with
Dredging for Flooding and Navigation, Local Decontamination and
Beneficial Use
Table 1-8
Cost Estimate: Alternative 4 with DMM Scenario A – Focused Capping
with Dredging for Flooding, CAD Disposal
Table 1-9
Cost Estimate: Alternative 4 with DMM Scenario B – Focused Capping
with Dredging for Flooding, Off-site Disposal
Table 1-10
Cost Estimate: Alternative 4 with DMM Scenario C – Focused Capping
with Dredging for Flooding, Local Decontamination and Beneficial Use
Table 1-11
Cash Flow Analysis for Present Value Calculations
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
iii
2014
LOWER EIGHT MILES OF THE LOWER PASSAIC RIVER
COST ESTIMATES
LIST OF FIGURES
Figure 1-1
Anticipated Project Schedule
Figure 1-2
Process Flow Diagram - DMM Scenario A: CAD Disposal
Figure 1-3
Process Flow Diagram – DMM Scenario B: Off-Site Disposal
Figure 1-4
Process Flow Diagram – DMM Scenario C: Local Decontamination and
Beneficial Use
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
iv
2014
1
INTRODUCTION
This appendix presents the cost estimates for the remedial alternatives being evaluated in
the Focused Feasibility Study (FFS) for the lower eight miles of the Lower Passaic River
(FFS Study Area), as follows (see FFS Chapter 4 for more detail on the alternatives):
•
Alternative 1: No Action
•
Alternative 2: Deep Dredging with Backfill
•
Alternative 3: Capping with Dredging for Flooding and Navigation
•
Alternative 4: Focused Capping with Dredging for Flooding
Each of the three active remedial alternatives (i.e., alternatives other than No Action) has
three dredged material management (DMM) scenarios (see FFS Chapter 4):
•
DMM Scenario A: Confined Aquatic Disposal (CAD)
•
DMM Scenario B: Off-site Disposal
•
DMM Scenario C: Local Decontamination and Beneficial Use
Cost estimates were developed in accordance with U.S. Environmental Protection
Agency (USEPA) guidance for developing cost estimates for feasibility studies (USEPA,
2000).
The estimated cost for each active remedial alternative includes preconstruction costs,
dredging and capping costs, DMM capital and operation and maintenance (O&M) costs,
and operation and long-term O&M costs. Note that Alternative 1 does not involve any
active remediation and has no monetary cost. Preliminary cost estimates are based on
January 2014 costs. The Engineering News Record (ENR) Construction Cost Index at the
time the estimates were finalized was 9664.45 (ENR, 2014). For comparison purposes,
costs for each remedial alternative were converted to Present Value 1 based on the project
1
Note that Net Present Value and Net Present Worth are other commonly used terms.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1-1
2014
schedule shown in Figure 1-1. A seven percent discount rate was selected based on
USEPA guidance (USEPA, 1993).
Table 1-1 presents a summary of the present value for each remedial alternative.
Tables 1-2 through 1-10 provide summaries of the estimated cost for each remedial
alternative. Figures 1-2 through 1-4 show the process flow for the three dredged materials
management (DMM) scenarios. Table 1-11 presents the cash flow analysis for each
active remedial alternative. The basis of cost for each of the cost items is summarized in
the following sections of this appendix.
Unit prices were taken from a variety of published and unpublished sources including
RS Means, internal cost databases, and communications with contractors, suppliers,
vendors and other professional engaged in similar activities. Where appropriate, costs
were based on delivery of goods and services in Newark, New Jersey. Costs do not
include USEPA oversight.
Costs for acquisition of property for the upland processing facility are included in the cost
estimate. Costs associated with acquiring a leasehold or other interest in Newark Bay for
construction of the CAD are not included. Due to the opposition voiced by the state of
New Jersey to construction of a CAD in the bay, it was not possible to develop an
estimate of such costs.
Remediation costs for the upland processing site are not included in the cost estimate.
Because it is likely that upland support or sediment processing facility sites would be in
close proximity to the river, and potentially located on a former industrial site, it is not
unreasonable to assume that some remedial activities would be required at the site.
However, due to the unknown scope of this work, it is not possible to estimate the cost.
Similarly, costs for structural improvements to the soil at the site were not included in the
cost estimate. In addition, a variety of soil conditions exist in upland sites along the
Lower Passaic River which would affect site development; it is not possible at this stage
of the project to determine which conditions are likely to apply to the selected site. These
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1-2
2014
conditions would impact each of the remedial alternatives evaluated since each DMM
scenario includes an upland support or sediment processing facility. There would be a
greater impact on DMM scenarios with larger upland sites and a smaller impact on DMM
scenarios with smaller upland sites. These factors would be evaluated during the site
selection process. Assuming an appropriate site selection process, these conditions would
not impact the relative costs of the various remedial alternatives.
Cost estimates in this appendix are provided so that comparisons among remedial
alternatives may be made in the FFS. Should a remedy be selected, detailed scopes of
work would be developed and project-specific costs developed.
Uncertainty of Cost Estimates
Estimated costs are expected to be within -30 to +50 percent of the actual costs.
However, a number of variables introduce a degree of uncertainty into the estimated costs
for the active remedial alternatives and DMM scenarios:
•
Uncertainty related to volume estimates (Appendix G). This arises to the inherent
need to project conditions over the FFS Study Area based on a limited number of
sampling points. Unidentified conditions could impact the volume of material to
be handled; actual volumes could either increase or decrease.
•
Uncertainty regarding project duration and schedule. A number of things could
impact the project duration including general weather conditions, natural and
man-made disasters, labor disputes, fish windows or other conditions identified
during the predesign investigation.
•
Uncertainty in the dredging productivity estimates based on site conditions
(Appendix F). Dredging productivity estimates were developed based on sitespecific conditions, information from vendors, pilot study results, and experience
at other major sediment projects in the area. If unforeseen conditions are
encountered during dredging, productivity could change.
•
Uncertainty in market conditions that would affect vendor pricing. In preparing
the cost estimate, information was obtained from vendors on various components
in the conceptual design. These prices are subject to change based on market
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1-3
2014
conditions (e.g., the number and size of other dredging projects in the
northeastern United States) at the time the project contracts are let.
•
Uncertainty in inflation and interest rates (actual discount rate). Project costs will
ultimately be impacted by inflation rates and change in interest rates during
project implementation. Alternative 2, because it has the longest project duration,
is likely to be the most affected by changes in inflation and interest rates.
Alternative 3, because it requires long-term care of the engineered cap in
perpetuity, is also likely to be impacted by changes in interest rates and inflation
although the impact may not be as significant as for Alternative 2.
The impact of these and other major factors are evaluated in the sensitivity analysis
presented in Chapter 5 of the FFS.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1-4
2014
2
CAPITAL COSTS
General Assumptions

Construction performed under multiple prime contracts held by client, not by single
prime/general contractor

Ten percent construction management fee applied to construction phase capital costs
(not including Pre-Construction Activities costs)

Twenty five percent contingency on all costs except construction management
2.1 A. Pre-Construction Activities
Design:

Six percent of construction phase capital costs (not including Pre-Construction
Activities costs)

Covers design analysis, plans, specifications, and engineer’s cost estimate
Regulatory Requirements, Legal, and Community Outreach:

Permitting or if on-site, establishing compliance with substantive requirements

Two percent construction phase capital costs (not including Pre-Construction
Activities costs)
Contractor Work Plans and Submittals:

Lump sum charge of $355,000 for contractor submittals and project specific Health
and Safety Plan
Pre-Construction Support Facility:

Facility/property used for contractor job trailers, core/sample processing facility,
equipment storage employee parking, etc.

Lease existing warehouse space with or near to water access.

Size - five acres

Monthly lease rate - $10,000 [Internal database]

Lease period - 12 months
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-1
2014
Pre-Construction Oversight:

Monthly charge of $48,000 for two staff to oversee coring/processing operations

Monthly charge includes labor, equipment and supplies, transportation, per diem,
quality assurance (QA) sampling and analysis performed in addition to the sample
specified, etc.

Field investigation takes 12 months to complete
General Survey and Coring Vessels Mobilization:

One time cost for mobilization [Contractor communications]
•
One geophysical vessel - $6,000
•
Video survey vessel - $4,000
•
Vibracoring vessel:
o Alternative 2 - $6,900 per vessel (18-foot to 28-foot cores); three vessels
o Alternative 3 (RM0 to RM2.2) - $3,500 (12-foot to 18-foot cores)
o Alternative 3 (RM2.2 to RM8.3) - $2,800 (less than 12-foot cores)
o Alternative 4 - $2,800 (less than 12-foot cores)
•
Barge-auger - $12,600
Pre-Design Investigation – Chemical, Waste Characterization, and Geological Sample
Collection:

Daily rate for vibracoring vessel and equipment [Contractor communications]:
•
Alternative 2 - $7,300 (18-foot to 28-foot cores)
•
Alternative 3 (RM0 to RM2.2) - $6,900 (12-foot to 18-foot cores)
•
Alternative 3 (RM2.2 to RM8.3) - $3,700 (less than 12-foot cores)
•
Alternative 4 - $3,700 (less than 12-foot cores)

Daily rate for vibracoring vessel crew (labor) - $1,600 [Contractor communications]

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contractor communications]

Vibracoring equipment would be selected for a coring range approximately two feet
longer than targeted core length
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-2
2014

Sampling rate:
•
Alternative 2 - five 16-foot cores collected per vessel per 12 hour day
•
Alternative 3 (RM0 to RM2.2) - eight 10-foot cores collected per 12 hour day
Alternative 3 (RM2.2 to 8.3 - twenty 4-foot cores collected per 12 hour day
•

Alternative 4 - twenty 4-foot cores collected per 12 hour day
Cores collected in a triangular pattern – 80-foot spacing for chemical cores and
160-foot spacing for waste characterization and geological samples

Samples for Alternatives 2 and 3 would be collected over the FFS Study Area;
samples for Alternative 4 would be collected over a number of separate areas as
shown in FFS Figure 4-2

Ten percent additional cores collected as samples of opportunity

Ten percent additional cores collected for chemical analysis and waste
characterization for confirmation or delineation of dredged material management
waste streams

Sample processing rate of $130 per man hour

Five man hours processing time for 16-foot cores (includes transport, sectioning, and
packaging for shipment of core)

Four man hours processing time for 10-foot cores (includes transport, sectioning, and
packaging for shipment of core)

One man hour processing time for two 4-foot cores (includes transport, sectioning,
and packaging for shipment of core)

Additional 25 percent of processing time to account for time to process additional
samples at the 160-foot grid level

Core processing performed at support facility

Process and decontamination water containerized for later processing at wastewater
treatment plant

Investigation derived waste (IDW) transportation and disposal cost of $630 per cubic
yard [Internal database]

IDW volume calculated assuming 4-inch core diameter and half of the core volume is
disposed
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-3
2014
Pre-Design Investigation - Geotechnical Sample Collection:

Daily rate for barge-auger - $8,200 [Contractor communications]

Four cores collected at each transect for Alternatives 2 and 3 and two cores for
Alternative 4; transects spaced at 0.5 miles intervals

Ten percent additional cores collected as samples of opportunity

One core collected per day; three samples taken per core

Undisturbed sample collection and processing cost - $500 per sample [Internal
database]

Core processing performed at support facility

Process and decontamination water containerized for later processing at wastewater
treatment plant

IDW transportation and disposal cost of $630 per cubic yard [Internal database]

IDW volume calculated assuming 6-inch boring diameter, 20-foot boring depth and
half of the boring volume is disposed
Pre-Design Investigation - Chemical Analysis:

Samples collected at 2-foot intervals of core

Additional sample collected in 4-foot cores for Alternatives 3 and 4

Samples analyzed for dioxins, metals (including mercury), and Polyaromatic
hydrocarbons (PAHs)

Ten percent of samples analyzed for “full suite” of chemicals (Target Analyte
List/Target Compound List [TAL/TCL] plus cyanide)


Analytical and validation cost per sample [Internal database]:
•
Metals - $275
•
PAHs - $250
•
Dioxins - $940
•
TAL/TCL plus cyanide - $625
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Pre-Design Investigation – Waste Characterization Analysis:

Samples collected at 2-foot intervals of core
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-4
2014

Additional sample collected in 4-foot cores for Alternatives 3 and 4

Samples analyzed for Polychlorinated biphenyls (PCBs) Aroclors, Toxicity
Characteristic Leaching Procedure (TCLP) for waste characterization, and Resource
Conservation Recovery Act (RCRA) criteria (corrosivity, ignitability, and reactivity).

Analytical and validation cost per sample [Internal database]:
•
PCBs - $188
•
TCLP - $1063
•
RCRA disposal criteria (ignitability, corrosivity, reactivity) - included in TCLP
price

Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Pre-Design Investigation - Geological Analysis:

Samples collected at 2-foot intervals of core

Additional sample collected in 4-foot cores for Alternatives 3 and 4

Samples analyzed for grain size (sieve and hydrometer), moisture content, and total
organic carbon (TOC)


Analytical and validation cost per sample [Internal database]:
•
Grain size (sieve and hydrometer) - $150
•
Moisture content - $32
•
TOC – $63
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Pre-Design Investigation - Geotechnical Analysis:

Three samples collected per boring

Samples analyzed for Atterberg limits, percent solids, specific gravity, grain size
(sieve and hydrometer), consolidation tests and strength tests

Analytical and validation cost per sample [Internal database]:
•
Atterberg limits - $85
•
Percent solids- $50
•
Specific gravity- $75
•
Grain size (sieve and hydrometer) - $150
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-5
2014

•
Consolidation- $600
•
Strength - $250
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Biological Monitoring Baseline Studies:

Terrestrial vegetation surveys

Avian community surveys

Fish community surveys

Benthic invertebrate surveys

Biological tissue-residual testing

Toxicity testing

Lump sum cost of $2,800,000
Pore Water Evaluation:

Pore water evaluation conducted for Alternatives 3 and 4 (which incorporate an
engineered cap); not required for Alternative 2 because this alternative targets the
entire contaminant inventory for removal and does not include an engineered cap

Samples collected concurrent with chemical/geological investigation samples

Elutriate tests and particulate organic carbon (POC) and dissolved organic carbon
(DOC) performed on 10 percent of cores


Analytical and validation cost per sample [Internal database]:
•
Elutriate - $630
•
POC - $188
•
DOC - $219
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Sub-bottom Geophysics and Bathymetric Survey:

Daily rate for geophysical vessel - $1,600 (labor) and $6,600 (vessel and equipment)
[Contractor communications]

Survey rate - one river mile per day
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-6
2014
Video Survey for Debris Identification:

Daily rate for video survey vessel - $1,600 (labor) and $6,600 (vessel and equipment)
[Contractor communications]

Survey rate - one river mile per day
Habitat Survey (in river):

Lump sum cost of $100,000

Mapping and presentation of existing data

No additional field work
Cultural Survey (in river):

Phase I study - Lump sum cost of $40,000

Phase II study - Lump sum cost of $500,000
Fish Spawning Study:

Lump sum cost of $50,000

Compilation and assessment of existing information that has been collected
previously for the Lower Passaic River; no additional field investigation

To be used to determine fish windows and other restrictions on in-water operations
Borrow Site Pre-Screening:

Three borings per five acres collected using standard drill rig (air rotary, sonic, etc.)

Borings extend to a depth of 25 feet below ground surface

Three samples per borehole

Samples analyzed for grain size (sieve and hydrometer) and metals

Cost per sample (including collection and shipping) - $3,000 [Internal database]

Ten borrow sources evaluated – average of 50 acres per site
Borrow Material Characterization:

One sample per 5,000 cubic yard of fine grained soils (mudflat reconstruction
material)
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-7
2014

One sample per 10,000 cubic yard of granular soil (engineered cap and backfill
materials)

Samples collected using standard drill rig (air rotary, sonic, etc.)

Samples analyzed for grain size (sieve and hydrometer), TOC, and metals

Ten percent of samples analyzed for dioxin, PCBs, and pesticides

Analytical and validation cost per sample [Internal database]:

•
Grain size - $150
•
TOC - $63
•
Metals - $275
•
Dioxin - $940
•
PCBs - $188
•
Pesticides - $1063
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Cap Erosion Modeling for Armor Placement Design:

Alternatives 3 and 4 only

Lump sum cost of $18,000

Computer modeling of final cap design [Internal database]
2.2 B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization:


One time mobilization charge of $237,000 per dredge [Contractor communications]:
•
Two dredges for Alternative 2
•
Two dredges for Alternative 3
•
Two dredges for Alternative 4
Equipment onsite for either duration of dredging or capping activities (not including
the armor placement duration), whichever is greater
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-8
2014
Backfilling/Capping Equipment Mobilization/Demobilization:

One time mobilization charge of $237,000 per clamshell [Contractor
communications] :
•
Two clamshells for Alternative 2
•
Two clamshells for Alternative 3
•
Two clamshells for Alternative 4

Capping equipment used for backfilling activities

Equipment onsite for either duration of dredging or capping activities (not including
the armor placement duration), whichever is greater
Monitoring Equipment Mobilization/Demobilization:

One time mobilization charge for monitoring equipment for each Alternative
[Contractor communications]:

•
Two Water quality vessels - $2,500 each
•
Geophysical vessel - $6,000
•
Small vibracoring vessel - $2,800
Equipment onsite for duration of project
Debris Removal Equipment Mobilization/Demobilization:

One-time mobilization charge of $60,000 (each Alternative)

Equipment onsite for either duration of dredging or capping activities (not including
the armor placement duration), whichever is greater
Shoreline Protection Equipment Mobilization/Demobilization:

One time mobilization charge of $237,000 for each Alternative [Internal database]

Shoreline protection equipment used to protect utilities, if necessary

Equipment onsite for either duration of dredging or capping activities (not including
the armor placement duration), whichever is greater
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-9
2014
New Season Restart:

Annual charge (starting in second year) of 25 percent of equipment
mobilization/demobilization costs to cover shutdown and restart of operations each
dredging season

Dredging operation duration:
•
Alternative 2 - 11 years total, 10 new season restart charges
•
Alternative 3 - 5 years total, 4 new season restart charges
•
Alternative 4 - 2 years total, 1 new season restart charges
2.3 C. Testing and Monitoring During Dredging and Backfilling/Capping
Monitoring and testing activities performed throughout duration of construction and
dredging activities. Assume dredging/capping operations occur 40 weeks per year, 6 days
per week. For cost estimating purposes this is equivalent to approximately 240 days per
year or 20 days per month.
Bathymetric Survey:

Daily rate for geophysical vessel - $1,600 (labor) and $2,800 (vessel and equipment)
for bathymetric survey only [Contractor communications]

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contractor communications]

Equipment rate scaled by a factor of 12 to calculate yearly rate.

Bathymetric surveys at each dredging unit would include pre-dredging, postdredging, and post-capping surveys to confirm target elevations and assess
dredging/capping performance.
Water Quality Monitoring:

Daily rate for two water quality vessels - $2,400 (labor) and $2,000 (vessel and
equipment) [Contactor communications]

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contactor communications]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-10
2014

Equipment rate scaled by a factor of 12 to calculate yearly rate.

Two vessels collect water quality samples continuously during dredging operations;
one vessel located upstream and one located downstream of dredge operations

Ten water column samples collected per day, or 200 samples per month

Water column samples analyzed for Total Suspended Solids (TSS)

Two composite water samples per day analyzed for Total Petroleum Hydrocarbons
(TPH) and lead (surrogate chemical parameters)

Ten percent of daily composite water samples analyzed for “full suite” of analytes
(dioxin, pesticides, and TAL/TCL plus cyanide)

Analytical and validation cost per sample [Internal database]:
•
TSS - $50
•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625

Sample processing rate of $130 per man hour

Process/ship three samples per man hour

Shipping cost $100 per cooler; four samples per cooler [Internal database]
Sediment Monitoring:

Conducted for all alternatives

Grab samples collected from dredge

Eight sediment samples collected per acre

Average acres completed per month:
•
Alternative 2 - 5 acres
•
Alternative 3 - 11 acres
•
Alternative 4 - 10 acres

Samples analyzed for TPH and lead (surrogate chemical parameters).

Ten percent of the samples analyzed for the “full suite” of chemicals (dioxin,
pesticides, and TAL/TCL plus cyanide).
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-11
2014

Analytical and validation cost per sample [Internal database]:
•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625

Sample processing rate of $130 per man hour

Process/ship three samples per man hour

Shipping cost $100 per cooler, four samples per cooler [Internal database]
Biological Monitoring:

Biological monitoring conducted monthly throughout dredging operations

Monthly surveys may include all or some of the following elements:

•
Terrestrial vegetation surveys
•
Avian community surveys
•
Fish community surveys
•
Benthic invertebrates survey
•
Biological tissue-residual testing
•
Toxicity testing
Average monthly cost of approximately $112,500 or approximately $1,350,000 per
year [Internal calculation/database]
Air Monitoring:

Air monitoring at dredge site(s) for VOCs and odors - $5000 per month per dredge

Includes labor, sample analysis, equipment maintenance
Monitoring Reports (including Laboratory Reporting):

Annual cost of $355,000 monitoring reports during dredging [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-12
2014
2.4 D. Dredging
Mechanical Dredging:

Dredging limits for Alternatives 2 and 3 are assumed to be the 2008 New Jersey
Department of Environmental Protection shoreline (i.e., within the FFS Study Area)
as shown in the FFS concept designs (see Figures 4-6 and 4-7 of the FFS)

Dredging limits for Alternative 4 are assumed to be select areas within the FFS Study
Area as determined by modeling results (refer to Chapter 4 in the FFS for additional
details [see FFS Figure 4-8])

Existing structures would not be removed - dredging would be conducted as close as
possible without damaging structures

Mechanical dredging operations - $25 per cubic yard [Contractor communications]

Dredge production rate - 2,000 cubic yards per day per dredge

Dredging season - 40 weeks per year

Dredging operations conducted 24 hour days, 6 work days per week during season
(240 days per year)

Once design depths achieved, additional dredging for residuals cleanup performed, on
average, in one pass (applies to locations where all inventory is targeted, not in areas
where capping is planned)
Large Debris Removal, Off-loading, Transport, and Disposal:

DMM Scenario A (CAD Disposal) - large debris removed and off-loaded for disposal
in the CAD; $30 per ton

DMM Scenarios B and C (incorporating an upland processing site) - large debris
removed, off-loaded, decontaminated (e.g., via high pressure washing), and
transported off-site for disposal - $200 per ton [Contractor communications].

Volume of material removed during dredging operations:
•
Alternative 2 - 8,000 tons total
•
Alternative 3 - 6,000 tons total
•
Alternative 4 - 2,000 tons total
•
Quantity estimated based on review of site-specific geophysical surveys
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-13
2014
Utility Protection:

To prevent undercutting utility lines - Alternative 2 only

Sheetpiling driven to 35-foot depth on average, on each side of utility line

Cost of $100 per square foot of sheeting for installation and removal following
dredging operations [Internal database]

One utility crossing requiring protection per river mile; approximate river width 500 feet at each crossing
Bridge/Abutment/Bulkhead Protection:

To prevent undercutting of structures - Alternative 2 only

Cost of protection -$4,100 per linear foot [Internal database]

Approximately 20 percent of existing linear pier/bulkheads to be reinforced
Barge Transport of Dredged Material:

Barge transport cost - $10 per cubic yard [Contractor communications]

Dredged material transported in 1,500 - 4,000 cubic yard hopper scows and delivered
to upland processing site or CAD

Estimate of volume of material to be transported based on process flow calculations
Shallow Water Sediments - Double Handling:

Applies to dredging in shallow water areas such as Kearny Mudflats and areas
upstream of RM8.1

Applicable to Alternatives 3 and 4 where these materials represent a greater portion
of total volume of material

Small equipment required for shallow water access with transfer to large barges for
transport to upland sediment processing facility or CAD
Additional costs for transfer and barge transport - $5 per cubic yard
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-14
2014
Hydraulic Offloading of Dredged Material:

Hydraulic offloading cost - $10 per cubic yard for DMM Scenarios B and C only
[Internal calculation/database, Contractor communications]

Estimate of volume of material to be offloaded based on process flow calculations
Controls for Quality of Life Impacts:

Includes odor controls, light shielding, sound abatement, vector management and
related costs

Approximately one percent of cost for dredging and backfill/capping activities
2.5 E. Backfill and/or Engineered Cap
Backfill/Engineered Cap Material Purchase and Delivery:

Backfill/engineered cap material purchased and delivered in hopper scow directly to
dredge site

Cost of material - $30 per cubic yard [Contractor communications]

Backfill/engineered cap material volume:
•
Backfill sand thickness - two feet, used when dredging depth exceeds depth of
fine-grained sediments (Alternative 2 and portions of Alternative 3)
•
Engineered cap design thickness - two feet used when dredging depth does not
remove entire depth of fine-grained sediments (Alternative 3 and 4)

Overplacement allowance of up to 0.5 feet.
Backfill/Engineered Cap Material Placement:

Cost to place backfill material (Alternative 2) - $20 per cubic yard [Contractor
communications]

Cost to place engineered cap material (Alternatives 3 and 4) - $30 per cubic yard
[Contractor communications]

Material placement rate - 2,000 cubic yard per day [Contractor communications]
Armor Material Purchase and Delivery:

Alternative 3 and 4 only
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-15
2014

Armor layer purchased and delivery to site in hopper scow - $30 per cubic yard
[Contractor communications]

Armor material volume:
•
Armor placed over engineered sand cap in high erosional areas (refer to
Appendix F) - 0.5 feet thick
•
Coverage: Alternative 3 - 119 acres; Alternative 4 - 56 acres
•
Overplacement allowance of up to 0.5 feet
Armor Layer Placement:

Cost to place armor material - $30 per cubic yard [Contractor communications]

Material placement rate - 2,000 cubic yard per day [Contractor communications]
Confirmation Coring:

Alternatives 3 and 4 only

Three-foot long cores collected to verify proper placement of cap layer (assessment of
mixing during cap placement)

Seven cores collected along each transect; transects placed at 0.125 miles intervals

Twenty cores collected per day

Daily rate for small vibracoring vessel - $1,600 (labor) and $3,700 (vessel and
equipment) [Contractor communications]

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contactor communications]

One man hour processing time per two cores (includes transport, sectioning , and
packaging for shipment of core)
Sediment Recontamination Monitoring:

Samples taken from confirmation coring, three samples per core

All samples analyzed for TPH and lead (surrogate chemical parameters).

Ten percent of the samples analyzed for the “full suite” of chemicals (dioxin,
pesticides, and TAL/TCL plus cyanide).

Analytical and validation cost per sample [Internal database]:
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-16
2014

•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625
Shipping cost $100 per cooler, four samples per cooler [Internal database]
Mudflat Backfill/Engineered Cap:

Backfill or cap mudflats (i.e., areas which are intermittently exposed and submerged
based on tidal action) disturbed through dredging operations and regrade to original
bathymetry

Top one foot of mudflat will be reconstructed with suitable habitat material (see
Mudflat Reconstruction below)

Alternative 2:
•
Dredged to the depth of contamination (refer to Appendix G)
•
Disturbed area approximately 101 acres
•
Backfill to one foot below original grade
•
Cost to purchase, deliver, and place backfill material - $50 per cubic yard
[Internal database]

Alternatives 3 and 4:
•
Dredged to accommodate engineered cap elements
•
Disturbed area approximately 101 acres for Alternative 3 and 51 acres for
Alternative 4
•
Cap with one foot of capping material for chemical isolation layer (Appendix F)
•
Cost to purchase, deliver, and place backfill material - $80 per cubic yard
[Internal database]

Overplacement allowance of up to 0.25 feet
Mudflat Reconstruction:

One foot thick layer of suitable material placed in disturbed mudflats areas (see
Mudflat Backfill/Engineered Cap above)
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-17
2014

Overplacement allowance of up to 0.25 feet

Cost to purchase and deliver mudflat reconstruction material - $100 per cubic yard
[Internal database]

Cost to place mudflat reconstruction material - $50 per cubic yard [Internal database].
Natural Shoreline Reconstruction:

Required only with Alternative 2

Twenty foot wide area of shoreline to be restored with backfill. Side slopes to be
constructed with a 3 horizontal to 1 vertical (3H:1V) slope

Approximately 5,560 feet of natural shorelines to be reconstructed

Estimate cost of backfill (purchase, delivery and placement) - $50 per cubic yard
Natural Shoreline Biostabilization:

Required only with Alternative 2

Twenty foot wide area of shoreline to be stabilized

Cost for two coir rolls, wedges, twine, and biodegradable erosion control matting $30 per linear foot

Twenty wetland plants planted per linear foot at $3 per plant, or $60 per linear foot

Two hours of labor for two laborers to install one lineal foot of erosion control
matting, coir roll, and plants at a cost of $65 per hour
Riprapped Shoreline Repairs and Replacement:


Allowance to repair or replace riprap slope protection
•
Alternative 2 - approximately 10,000 square yards
•
Alternative 3 – approximately 5,000 square yards
•
Alternative 4 – approximately 2,500 square yards
Cost for riprap installation - $75 per square yard
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2-18
2014
3
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
3.1 CAD (DMM Scenario A)
General Assumptions

Construction performed under multiple prime contracts held by client, not by a single
prime/general contractor

Ten percent construction management fee applied to DMM construction phase capital
costs (not including Pre-Construction Activities costs)

Twenty five percent contingency on all costs except construction management
3.1.1 F1. Pre-Construction Activities for DMM
Design:

Six percent of DMM construction phase capital costs (not including DMM PreConstruction Activities costs)

Covers design analysis, plans, specifications, and engineer’s cost estimate
Regulatory Requirements, Legal, and Community Outreach:

Permitting or if on-site, establishing compliance with substantive requirements

Two percent of DMM construction phase capital costs (not including DMM PreConstruction Activities)
Land Acquisition:

Site selection study for upland support facility

Site to include water access

Land purchased for upland support facility under Alternatives 2, 3, and 4

Facility size - five acres

Estimated cost for property acquisition - $510,000 per acre
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-1
2014
Contractor Work Plans and Submittals:

Lump sum charge of $119,000 for contractor submittals and project specific Health
and Safety Plan
Pre-Construction Oversight:

Monthly charge of $48,000 for two staff to oversee coring/processing operations at
disposal site

Monthly charge includes labor, equipment and supplies, transportation, per diem

Field investigation takes two months to complete for each of the alternatives
Upland Support Facility Site Investigation – Geotechnical:

Samples collected using standard drill rig (air rotary, sonic, or other)

Cost for sampling and processing - $1,800 per core

Borings extend to depth of 25 feet below ground surface

Two borings per acre for all sites with upland component; three samples per core

Samples are analyzed for Atterberg limits, percent solids, specific gravity, grain size
(sieve and hydrometer)

Consolidation tests and strength tests performed on 10 percent of the samples

Analytical and validation cost per sample [Internal database]:

•
Atterberg limits - $85
•
Percent solids - $50
•
Specific gravity - $75
•
Grain size (sieve and hydrometer) - $150
•
Consolidation - $600
•
Strength - $250
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Upland Support Facility Site Investigation – Chemical:

Conduct Phase I/II Due Diligence investigation of upland site

Estimated cost per acre for Phase I/II Due Diligence investigation is $1,000
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-2
2014

Samples taken from Geotechnical Investigation borings, one boring per acre; three
samples per boring

Samples analyzed for metals

Ten percent of samples analyzed for dioxin, PCBs, and pesticides

Analytical and validation cost per sample [Internal database]:

•
Metals - $275
•
Dioxin - $940
•
PCBs - $188
•
Pesticides - $1,063
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Topographic Survey – Upland Support Facility Site:

Topographic survey prepared for uplands support facility site plus additional 10
percent of acreage to include surrounding areas for design purposes

Topographic map tied to State Plane coordinates with two foot contour interval tied to
North American Vertical Datum (NAVD)

One day of ground survey to establish ground control for aerial survey

Daily rate for survey crew - $4,000 [Internal database]

Topographic map prepared by aerial survey of site - $500 per acre for flight

Drawing cost for contour map - $100 per acre
Pre-Design Investigation of CAD Site – Chemical Sample Collection:

Daily rate for vibracoring vessel - $1,600 (labor) and $7,300 (vessel and equipment)
[Contractor communications] Daily rate scaled by factor of 1.5 to calculate 12 hour
daily rate [Contractor communications]

Five 16-foot cores collected per 12 hour day in contaminated sediment layer

One core collected per 5,000 cubic yard in contaminated sediment layer

Five man hours processing time per 16-foot core (includes transport, sectioning, and
packaging for shipment of core)

Assumes excess sediment (i.e., IDW) is transported/disposed at cost of $630 per
cubic yard [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-3
2014
Pre-Design Investigation of CAD Site – Geotechnical Sample Collection:

Daily rate for barge-auger - $8,200 [Contractor communications]

One core collected per five acres of disposal area, minimum five cores; three samples
per core:

•
Alternative 2 - 33 cores
•
Alternative 3 - 15 cores
•
Alternative 4 - 5 cores
Undisturbed sample collection and processing cost - $500 per sample [Internal
database]
Pre-Design Investigation of CAD Site – Chemical Analysis:

One sample per 5,000 cubic yard of dredged materials

Samples analyzed for PAHs, dioxin, and TAL/TCL plus cyanide.

Analytical and validation cost per sample [Internal database]:

•
PAHs - $250
•
Dioxin - $940
•
TAL/TCL plus cyanide - $625
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Pre-Design Investigation of CAD Site – Geotechnical Analysis:

Samples analyzed for Atterberg limits, percent solids, specific gravity, grain size
(sieve and hydrometer), consolidation tests and strength tests


Analytical and validation cost per sample [Internal database]:
•
Atterberg limits - $85
•
Percent solids - $50
•
Specific gravity - $75
•
Grain size (sieve and hydrometer) - $150
•
Consolidation - $600
•
Strength - $250
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-4
2014
Pre-Design Investigation of CAD Site – Historic Area Remediation Site (HARS)
Disposal Determination:

Toxicology assessment of material quality

Lump sum cost of $200,000 for sample collection and analysis
Habitat Survey (upland support facility site):

Lump sum cost of $5,000
Cultural Survey (upland support facility site):

Lump sum cost of $5,000
Elutriate Evaluation:

Samples collected concurrent with chemical core sampling.

One core collected per 5,000 cubic yard of dredged materials

Elutriate tests and POC, DOC analyses performed on 10 percent of cores

Analytical and validation cost per sample [Internal database]:

•
Elutriate tests - $630
•
POC - $188
•
DOC - $219
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Sub-bottom Geophysics and Bathymetric Survey:

Daily rate for geophysical vessel - $1,600 (labor) and $6,600 (vessel and equipment)
[Contractor communications]

Survey rate - one day for CAD (each alternative)
Miscellaneous Tests for DMM Design:

Samples taken cores and borings collected for chemical and geotechnical analyses

Dredged material slurry simulations - 20 tests at (@) $1,900

Dredge elutriate tests - 20 tests @ $600 each
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-5
2014

Settling tests - 20 tests @ $1,200
3.1.2 G1. CAD Excavation
Dredge Mobilization/ Demobilization:

One time mobilization charge for each cell constructed of $237,000 per dredge for
both navigation and environmental dredges. Separate mobilizations for each disposal
cell

Dredge usage:
•
Alternative 2 - two navigation dredges; two environmental dredges, three cells
•
Alternative 3 - two navigation dredges; two environmental dredges, two cells
•
Alternative 4 - two navigation dredges; two environmental dredges, one cell
Monitoring Equipment and Debris Removal Mobilization/Demobilization:

Monitoring Equipment Mobilization/Demobilization:
•
One time mobilization charge for monitoring equipment for each Alternative for
each cell [Contractor communications]:
o Two Water quality vessels - $2,500 each
o Geophysical vessel - $6,000
o Small vibracoring vessel - $2,800

Debris Removal Equipment Mobilization/Demobilization
•

One-time mobilization charge of $59,000 (Alternatives 2, 3, and 4)
Equipment usage:
•
Alternative 2 - three cells
•
Alternative 3 - two cells
•
Alternative 4 - one cell
Large Debris Removal:

Debris removed, off-loaded, decontaminated (e.g., via high pressure washing), and
transported off-site for disposal at cost of $300 per ton [Contractor communications]

Volume removed during dredging operations based on previous survey results:
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-6
2014
•
Alternatives 2 - 1,000 tons total
•
Alternative 3 - 500 tons total
•
Alternative 4 - 200 tons total
Contaminated Sediment Dredging (First Cell):

Includes material removed from both CAD site and entrance channel

Cost for dredging, amending, and upland disposal of dredged sediment - $200 per
cubic yard:
•
Alternative 2 - 388,000 cubic yards
•
Alternative 3 - 278,000 cubic yards
•
Alternative 4 - 148,000 cubic yards
Contaminated Sediment Testing and Disposal (First Cell):

Includes material removed from both CAD site and entrance channel

Analysis cost [Internal database]:

•
TCLP - $1,063
•
Paint filter - $25
One sample per 5,000 cubic yards dredged materials
Contaminated Sediment Dredging and Disposal (Subsequent Cells):

Includes material removed from both CAD site and entrance channel

No additional testing required (disposed in existing CAD cell)

Cost for dredging and CAD placement of dredged sediment - $35 per cubic yard
•
Alternative 2 - 786,000 cubic yards
•
Alternative 3 - 278,000 cubic yards
•
Alternative 4 - not applicable
Clay Dredging/Transport/Disposal at HARS:

Cost to dredge, transport, and dispose of dredged material at HARS - $25 per cubic
yard [Internal database]
•
Alternative 2 - 11,153,000 cubic yards
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-7
2014

•
Alternative 3 - 5,062,000 cubic yards
•
Alternative 4 - 1,121,000 cubic yards
Average dredge production rate - 5,000 cubic yards per day per dredge (average rate
decreases with depth)

Site conditions allow excavation to required depth without removal of bedrock
Containment System Installation:

Construct containment wall around CAD area consisting of a combination of
kingpiles (62 feet in length) and sheet piles (25 feet in length)

Total length of berm
•
Alternative 2 - 365,000 square feet
•
Alternative 3 - 220,000 square feet
•
Alternative 4 - 107,500 square feet

Scour protection (sand and riprap)

Cost - $235 per square foot (materials and installation)
Silt Curtain at CAD Entrance Channel:

Silt curtain to close entrance area during dumping operations

Entrance Channel opening - 150 feet

Height of water - 15 feet with 5 foot allowance for tidal variations

Provisions for opening and closing silt curtain during placement operations.

Material purchase and installation cost - $100 per square feet
Air Monitoring During Construction:

Monitoring for VOCs and odors - $5000 per month

Includes labor, sample analysis, equipment maintenance
Testing and Monitoring:

Daily rate for geophysical vessel - $1,600 (labor) and $6,600 (vessel and equipment)

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contactor communications]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-8
2014

Two rounds of bathymetric surveys performed after dredging to specified elevation

Daily rate for two water quality vessels - $2,400 (labor) and $2,000 (vessel and
equipment)

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contactor communications]

Two sampling vessels (one located upstream and one downstream of the dredge)
collecting water quality samples continuously during dredging operations.

Ten water column samples collected per day, or 200 samples per month (240 days per
year of dredging operations averaged over 12 months, or approximately 20 days per
month of operations)

Water column samples analyzed for TSS

Two composite water samples per day analyzed for TPH and lead (surrogate chemical
parameters)

Ten percent of daily composite water samples analyzed for “full suite” of analytes
(dioxin, pesticides, and TAL/TCL plus cyanide)

Analytical and validation cost per sample [Internal database]:
•
TSS - $50
•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625

Process/ship three samples per man hour

Shipping cost $100 per cooler, four samples per cooler [Internal database]

Lump sum data reporting cost of $63,000 [Internal database]
3.1.3 H1. Upland Support Facility
Mobilization/Demobilization:

Ten percent of construction costs for uplands facility [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-9
2014
Layout and Documentation Survey:

Daily rate for survey crew - $4,000 [Internal database]

Surveying performed periodically during construction - 10 days total
Fencing:


Material purchase and installation - $60 per lineal foot [Internal database]:
•
Alternative 2 - 1,900 linear feet
•
Alternative 3 - 1,900 linear feet
•
Alternative 4 - 1,900 linear feet
Increase fencing quantity by two percent to account for cost of gates
Exterior Lighting:

Material purchase and installation - $50,000 per acre [Internal database]:
•
Alternative 2 - five acres
•
Alternative 3 - five acres
•
Alternative 4 - five acres
Security:

Lump sum cost of $20,000 for each alternative [Internal database]
Buildings:

Administrative
•
Size - 10,000 square feet
•
Cost - $100 per square foot not including amenities [Internal database]
•
Amenities (laboratory, shower, locker room), mechanical, electrical – Lump sum $125,000 [Internal database]

Guard shack -Lump sum - $15,000 [Internal database]

Truck wash facility - Lump sum - $20,000 [Internal database]
Utilities:

Sewer connection - $50,000
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-10
2014

Water connection - $25,000

Electrical connection - $50,000 [Internal database]
Earthwork:

Site suitable for construction of wastewater treatment facility and other support
facilities without major earthwork

Grading cost - $12 per cubic yard [Internal database]

Average one foot cut across relatively flat site

No demolition or site remediation costs included
Stormwater Management:

Contact water drains to decontamination pad or truck wash

Stormwater system design intensity - 24-hour, 10-year storm event:

•
Grading costs - $15 per cubic yard [Internal database]
•
Retention basin for non-contact water - 2,500 cubic yards
•
Perimeter drainage ditches for non-contact water - 1,400 cubic yards
Lump sum for miscellaneous piping and catch basins - $10,000
Paving:

Filter fabric installed above native soils

Installed cost of filter fabric - $2 per square yard [Internal database]

Six inches subgrade material placed over filter fabric

Installed cost of subgrade material - $40 per cubic yard [Internal database]

Plant mix asphalt paving - 3 inches bearing course and 1.5 inches wearing course

Installed cost of plant mix asphalt paving - $20 per square yard [Internal database]

Paved area - 17,300 square yards
Pier/Dock Structure:

Docking facilities provided for docking of monitoring and sampling equipment

Size - 15,000 square feet

Material cost and installation - $160 per square foot [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-11
2014
Wastewater Treatment System for Contact Water:

Contact water from decontamination of sampling equipment/utensils

Rental rate - $10,000 per month

Rental Period:
•
Alternative 2 - 125 months
•
Alternative 3 - 60 months
•
Alternative 4 - 16 months
3.1.4 I1. CAD Closure
Cap Material Purchase and Delivery:

Engineered cap material purchased and delivered in hopper scow directly to dredge
site


Cap material:
•
Alternative 2 - 930,000 cubic yards
•
Alternative 3 - 420,000 cubic yards
•
Alternative 4 - 90,000 cubic yards
Cost of material - $30 per cubic yard [Contractor communications]
Engineered Cap Material Placement:

Material placement rate - 2,000 cubic yard per day [Contractor communications]

Engineered cap design thickness - 3 feet

Overplacement allowance of up to 0.5 feet.

Installation cost - $30 per cubic yard [Internal database]
Confirmation Coring:

Three-foot long cores collected to verify proper placement of cap layer (assessment of
mixing during cap placement)

Twenty cores collected per day; five cores per acre

Daily rate for small vibracoring vessel - $1,600 (labor) and $3,700 (vessel and
equipment) [Contractor communications]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-12
2014

Daily equipment rate (not including labor) scaled by factor of 1.5 to calculate 12 hour
daily rate and 9 to calculate monthly rate [Contactor communications]

One man hour processing time per two cores (includes transport, sectioning, and
packaging for shipment of core)

Collect three samples from each core and analyze samples for TPH and lead
(surrogate chemical parameters)

Ten percent of the samples analyzed for the “full suite” of chemicals (dioxin,
pesticides, and TAL/TCL plus cyanide)


Analytical and validation cost per sample [Internal database]:
•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625
Shipping cost $100 per cooler, four samples per cooler [Internal database]
Remove Containment System:

Sheeting removed at an estimated cost of $36 per square foot
Bathymetric Survey:

Daily rate for survey crew - $8,200 [Internal database]

Survey crew on-site periodically totaling two days per cell
Additional Habitat Mitigation:


Disturbed acres
•
Alternative 2 - 171 acres
•
Alternative 3 - 80 acres
•
Alternative 4 - 19 acres
Cost for off-site mitigation – see Table 2-3 in Appendix F of the FFS
•
Alternative 2 - $102,751,000
•
Alternative 3 - $63,770,000
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-13
2014
•
Alternative 4 - $12,950,000
3.1.5 J1. Site Decommissioning/Restoration

Site restoration/demolition/decommissioning of upland support facility - $30,000 per
acre
3.2 Off-Site Disposal (DMM Scenario B)
General Assumptions

Construction performed under multiple prime contracts held by client, not by a single
prime/general contractor

Ten percent construction management fee applied to DMM construction phase capital
costs (not including Pre-Construction Activities costs)

Twenty-five percent contingency on all costs except construction management
because of technical complexity of the operations
3.2.1 F2. Pre-Construction Activities for DMM
Design:

Six percent of DMM construction phase capital costs (not including DMM PreConstruction Activities costs)

Covers design analysis, plans, specifications, and engineer’s cost estimate
Regulatory Requirements, Legal, and Community Outreach:

Permitting or if on-site, establishing compliance with substantive requirements

Two percent of DMM construction phase capital costs (not including DMM PreConstruction Activities )
Land Acquisition:

Site selection study for upland sediment processing facility

Site to include water access and rail spur/siding or ability to construct rail spur or
siding
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-14
2014

Land purchased for upland sediment processing facility under Alternatives 2, 3, and 4

Estimated cost for property acquisition @ $510,000 per acre:
•
Alternative 2 - 27.5 acres
•
Alternative 3 - 26 acres
•
Alternative 4 - 26 acres
Contractor Work Plans and Submittals:

Lump sum charge of $119,000 for contractor submittals and project specific Health
and Safety Plan
Pre-Construction Oversight:

Monthly charge of $48,000 for two staff to oversee site investigation of processing
site

Monthly charge includes labor, equipment and supplies, transportation, per diem

Field investigation takes three months to complete for each of the alternatives
Upland Sediment Processing Facility Site Investigation - Geotechnical:

Samples collected using standard drill rig (air rotary, sonic, or other)

Cost for core sampling and processing - $1,800 per core [Internal database]

Cores extend to depth of 25 feet below ground surface

Two cores per acre collected for all sites with upland component; three samples taken
per core

Samples analyzed for Atterberg limits, percent solids, specific gravity, grain size
(sieve and hydrometer)

Consolidation tests and strength tests performed on 10 percent of the samples

Analytical and validation cost per sample [Internal database]:
•
Atterberg limits - $85
•
Percent solids - $50
•
Specific gravity - $75
•
Grain size (sieve and hydrometer) - $150
•
Consolidation - $600
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-15
2014
•

Strength - $250
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Upland Sediment Processing Facility Site Investigation – Chemical:

Conduct Phase I/II Due Diligence investigation of upland sediment processing facility
site

Estimated cost per acre for Phase I/II Due Diligence investigation is $1,000

Samples taken from Geotechnical Investigation borings, one boring per acre; three
samples per boring

Samples analyzed for metals

Ten percent of samples analyzed for dioxin, PCBs, and pesticides

Analytical and validation cost per sample [Internal database]:

•
Metals - $275
•
Dioxin - $940
•
PCBs -$188
•
Pesticides - $1,063
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Topographic Survey – Upland Sediment Processing Facility Site:

Topographic survey prepared for upland sediment processing facility site plus
additional 10 percent of acreage to include surrounding areas for design purposes

Topographic map tied to State Plane coordinates with two foot contour interval tied to
NAVD

Two days of ground survey to establish ground control for aerial survey

Daily rate for survey crew - $4,000 [Internal database]

Topographic map prepared by aerial survey of site:
•
Cost for aerial survey flight - $500 per acre
•
Cost for drawing contour map - $100 per acre
Habitat Survey (upland sediment processing facility site):

Lump sum cost of $42,000
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-16
2014
Cultural Survey (upland sediment processing facility site):

Lump sum cost of $42,000
Miscellaneous Tests for DMM Design:

Samples taken from cores and borings collected for chemical and geotechnical
analyses

Dredged material slurry simulations - 20 tests @ $1,900

Dredge elutriate tests - 20 tests @ $600 each

Paint filter tests - 20 tests @ $25 each

Jar testing/settling tests - 20 tests @ $1,300

Optimum polymer doses - 3 tests@ $1,900

Mechanical dewatering tests - 1 test @ $1,300

Multimedia filter tests - 20 tests @ $600 each

TCLP Testing - 10 @ $1,063 each
3.2.2 G2. Upland Sediment Processing Facility
Mobilization and Demobilization:

Ten percent of DMM construction phase capital costs (not including DMM PreConstruction Activities costs) [Internal database]
Mechanical and Electrical:

Ten percent of DMM construction phase capital costs (not including DMM PreConstruction Activities costs) [Internal database]
Layout and Documentation Survey:

Daily rate for survey crew - $4,000 [Internal database]

Surveying performed periodically during construction - 2 days per week over
12 month construction period
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-17
2014
Fencing:

Material purchase and installation - $60 per linear foot [Internal database]:
•
Alternative 2 - 8,600 linear feet (4,400 feet for site boundary; 4,200 feet for
exclusion zone)
•
Alternative 3 - 8,300 linear feet (4,300 feet for site boundary; 4,000 feet for
exclusion zone)
•
Alternative 4 - 8,300 linear feet (4,300 feet for site boundary; 4,000 feet for
exclusion zone)

Increase fencing quantity by two percent to account for cost of gates
Exterior Lighting:

Material purchase and installation - $50,000 per acre [Internal database]:
•
Alternative 2 - 27.5 acres
•
Alternative 3 - 26 acres
•
Alternative 4 - 26 acres
Security:

Lump sum cost of $100,000 [Internal database]
Buildings:

Processing Building
•
Size:
o Alternative 2 - 5.6 acres
o Alternative 3 - 5.5 acres
o Alternative 4 - 5.5 acres

•
Cost - $100 per square foot not including amenities [Internal database]
•
Amenities - Lump sum for laboratory, shower, and locker facility - $100,000
Additional cost for Administrative/Laboratory Area of Processing Building - 30,000
square feet @ $50 per square foot

Wastewater treatment system included in Processing Building (equipment costs
elsewhere)
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-18
2014

Guard shack - 150 square feet @ $100 per square foot [Internal database]

Truck wash - Lump sum $100,000 [Internal database]

Assumes site soils are stable and capable of supporting building and equipment loads
without piling or major soil modifications
Utilities:

Sewer connection - $500,000

Water connection - $250,000

Electrical connection - $500,000 [Internal database]

Costs assumes an undeveloped site and all new utility connections
Earthwork:

Grading and clearing of site prior to construction - assume minimal effort required
(up to three foot cut/fill across site)

Cost - $12 per cubic yard based on on-site disposal of soil

Continuous footings required around building perimeter along with pads for major
equipment

No other costs for soil improvements required
Stormwater Management:

Perimeter drainage ditch diverts non-contact water to a sedimentation basin for
treatment prior to discharge to the river

Roof leaders are connected to perimeter drainage system

Water in the exclusion zone is captured and treated/reused before being discharged to
river in accordance with regulatory requirements

Lump sum cost of $163,000 for Alternative 2 and $151,000 for Alternatives 3 and 4
Paving:

Filter fabric installed over native soil

Installed cost of filter fabric - $2 per square yard [Internal database]

Six inches subgrade material placed over the filter fabric
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-19
2014

Installed cost of subgrade material - $40 per cubic yard [Internal database]

Plant mix asphalt paving - 3 inches bearing course and 1.5 inches wearing course

Installed cost of plant mix asphalt paving - $20 per square yard [Internal database]

Paved area:
•
Alternative 2 - approximately 74,000 square yards
•
Alternative 3 - approximately 73,000 square yards
•
Alternative 4 - approximately 73,000 square yards
Pier/Dock Structure:

Frontage wharf along shore of upland sediment processing facility – 50,000 square
feet

Wharf intended for temporary use during hydraulic offloading.

The length of the wharf is intended to provide space for two barges at a time.

Material cost and installation - $160 per square foot [Internal database]
Pre-fabricated Building (Sprung Structure) for Dewatered Sediment Storage:

Enclosed on-site storage of dewatered solids

Approximately six months of storage provided for material to be shipped off-site for
thermal treatment to allow flexibility in production schedules; approximately three
months of storage provided for materials to be shipped off-site for disposal in landfill

Negative pressure maintained in structure to control emission; vapors routed through
granular activated carbon before discharge


Approximate storage requirements:
•
Alternative 2 - 230,000 square feet
•
Alternative 3 - 185,000 square feet
•
Alternative 4 - 185,000 square feet
Installed cost for insulated structure - $40 per square foot [Contactor
communications]
Storage Area – Concrete Slab and Push Walls:

Structure installed on concrete slab with eight foot push walls
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-20
2014

Installed costs for concrete slabs - $600 per cubic yard [Internal database]
Storage Area – Subgrade Material:

Installed cost for subgrade material under slab - $40 per cubic yard [Internal
database]
Storage Area – Filter Fabric:

Installed cost for filter fabric under slab - $2 per square yard [Internal database]
Storage Area –Vapor Emissions Control:

Maintain negative pressure within storage structure to control emissions (dust and
odors)

One unit for approximately 10,000 cubic yards of storage capacity

Vapors routed through a granular activated carbon (GAC) filter units prior to
discharge to atmosphere:

•
Alternative 2 - 20 units
•
Alternative 3 - 16 units
•
Alternative 4 - 16 units
Installed cost per unit - $5,000 [Internal database]
Piping:

Includes exterior piping and appurtenances (e.g., storm drains, catch basins, culverts,
etc.) and interior piping in processing building

Exterior piping (stormwater and ancillary piping) - 25,000 linear feet for Alternative
2 and 23,500 linear feet for Alternatives 3 and 4

Interior piping (dewatering system) - 4,800 linear feet for Alternative 2 and 4,600
linear feet for Alternatives 3 and 4

Installed/delivered cost - $25 per linear foot for exterior piping and $15 per linear foot
for interior piping [Internal database]

Add 25 percent for joints, tees, wyes, other connections and fittings
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-21
2014
Upfront Storage and Recycle Water Tanks:

Upfront Storage Tank - provide temporary storage of sediment in case of plant upsets
or shutdown

Recycle Water Tank - provide temporary storage of water used for the hydraulic
offloading of barges

Storage capacity provided for each tank - 12 hours [Internal database]
Loadout Facility:

Lump sum - $500,000 [Internal database]
Rail Line Spur/Railcar Storage:

Provide siding/spur capacity adequate for staging rail cars

Five miles of railroad spur/siding constructed at site

Installed cost - $1,000,000 per mile [Internal database]
Temporary Bunkers for Loadout Facility:

Two bunkers at $10,000 each [Internal database]
Hazardous Material Storage Area:

Temporary storage of material prior to shipment off site

Includes decontamination pad for medium and large debris processing

Lump sum[Internal database]:
•
Alternative 2 - $124,000
•
Alternative 3 - $93,000
•
Alternative 4 - $33,000
Air Monitoring During Construction:

Fugitive dust monitoring - $5,000 per month

Other constituents based on site soil characterization data

Includes labor, sample analysis, equipment maintenance
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-22
2014
3.2.3 H2. Equipment Costs
Operating Equipment:

Equipment purchased for site operators:
•
3 Front end loaders ($124,000 each)
•
1 Skidsteer ($25,000 each)
•
1 Excavator ($200,000 each)
•
4 Dump trucks ($80,000 each)
•
1 Water truck ($50,000 each)
•
1 Street Sweeper ($100,000 each)
Wastewater Treatment Plant:

Wastewater treatment plant (WWTP) includes the following components:
equalization tank, sedimentation tank with combined oil-water separator, multimedia
filter, carbon filter, and bag filter

Where feasible water would be treated and reused in the process minimizing the
overall water consumption


Cost includes fixed and variable components:
•
Fixed costs (structure, design, contractor overhead, etc.)
•
Variable costs (based on flow in million gallons per day [MGD])
Treatment plant sizes:
•
Alternative 2 - 1.0 MGD
•
Alternative 3 - 1.0 MGD
•
Alternative 4 - 1.0 MGD
3.2.4 I2. Processing and Disposal
Mechanical Dewatering Using Filter Presses:

Treatment includes screening, coarse and fine sand separation, pre-thickening,
chemical addition, and mechanical dewatering,

Cost includes equipment capital costs and operating costs (including labor)

Unit costs - $50 per cubic yard [Contractor communications]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-23
2014
Dewatered Material Testing for Disposal:

One sample per 5,000 cubic yards of dewatered material

Analytical cost [Internal database]:
•
TCLP - $1,063
•
Paint filter - $25
Transport Off-site to Thermal Treatment:

Rail transportation through long-term leasing of rail cars

Based on evenly distributed usage of all treatment facilities (see Appendix G),
average transportation cost is approximately $240 per ton
Thermal Treatment and Disposal (Off-site Facility):

Four thermal treatment facilities identified in United States that could potentially treat
contaminated sediment; facilities include:
•
Veolia Environmental Services’ Gulf Coast Incineration Facility, Port Arthur,
Texas

•
Clean Harbors’ Aragonite Incineration Facility, Salt Lake City, Utah
•
Clean Harbors’ Deer Park Incineration Facility, La Porte, Texas
•
Clean Harbors’ Kimball Incineration Facility, Kimball, Nebraska
Information on sites provided for estimation purposes only and would have to be
verified during site design; details on sites presented in Appendix G

Disposal cost at United States facilities for RCRA waste - approximately $400 per
ton (varies based on material characteristics)

On-site storage at the upland sediment processing facility (described elsewhere)

Dewatered mass of material to be thermally treated
•
Alternative 2 – 740,000 tons
•
Alternative 3 – 180,000 tons
•
Alternative 4 – 30,000 tons
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-24
2014
Transport to Subtitle C Landfill (Off-site Facility):

Rail transportation through long-term leasing of rail cars

Based on use of multiple facilities, average transportation cost is approximately
$130 per ton
Off-Site Disposal in Subtitle C Landfill:

Fifteen Subtitle C landfills identified in United States that could potentially accept
contaminated sediment. Three facilities: Lake Charles, Lone Mountain and
Grandview, have a combined total of approximately 12.7 million cubic yards in
available capacity.

Information on sites provided for estimation purposes only and would have to be
verified during site design; details on sites presented in Appendix G.

Landfill Tipping Fee - $100 per ton – will vary based on waste characteristics
[Contractor communications]

Dewatered mass of material to be disposed at a Subtitle C Landfill:
•
Alternative 2 - 6,630,000 tons
•
Alternative 3 - 2,460,000 tons
•
Alternative 4 - 600,000 tons
Decontamination and Disposal of Medium-Sized Debris:

Debris removed during screening, decontaminated (via high pressure washing), and
transported off-site for disposal at cost of $200 per cubic yard [Contractor
communications]

In-situ volume of debris removed during dredging operations:
•
Alternatives 2 - 534,000 cubic yards
•
Alternative 3 - 238,000 cubic yards
•
Alternative 4 - 56,000 cubic yards
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill:

Generally small sized organic debris and gravel removed by fine screening or
microfiltration during processing
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-25
2014

Debris containerized and shipped to a Subtitle C landfill for disposal at a cost of
$230 per ton.

In-situ mass of debris:
•
Alternatives 2 - 55,000 tons total
•
Alternative 3 - 24,000 tons total
•
Alternative 4 - 6,000 tons total
Reclaimed Sand Processing, Transport, and Beneficial Use:

Reclaimed sand recovered during sediment processing to be used beneficially

Cost for transportation and beneficial use - $50 per ton.

Dewatered mass of reclaimed sand:
•
Alternatives 2 – 1,600,000 tons total
•
Alternative 3 - 600,000 tons total
•
Alternative 4 - 100,000 tons total
3.2.5 J2. Site Decommissioning/Restoration

Site restoration/demolition/decommission - $30,000 per acre
3.3 Local Decontamination and Beneficial Use (DMM Scenario C)
General Assumptions:

Construction performed under multiple prime contracts held by client, not by single
prime/general contractor

Ten percent construction management fee applied to DMM construction phase capital
costs (not including Pre-Construction Activities costs)

Twenty-five percent contingency on all costs except construction management
because of technical complexity of the operations
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-26
2014
3.3.1 F3. Pre-Construction Activities for DMM
Design:

Six percent of DMM construction phase capital costs (not including DMM PreConstruction Activities costs)

Covers design analysis, plans, specifications, and engineer’s cost estimate
Regulatory Requirements, Legal, and Outreach:

Permitting or if on-site, establishing compliance with substantive requirements

Two percent of DMM construction phase capital costs (not including DMM
Pre-Construction Activities )
Land Acquisition:

Site selection study for upland sediment processing facility

Site to include water access

Land purchased for upland sediment processing facility under Alternatives 2, 3, and 4

Estimated cost for property acquis ition @ $510,000 per acre:
•
Alternative 2 - 39.5 acres
•
Alternative 3 - 36 acres
•
Alternative 4 - 36 acres
Contractor Work Plans and Submittals:

Lump sum charge of $119,000 per alternative for contractor submittals and project
specific Health and Safety Plan
Pre-Construction Oversight:

Monthly charge of $48,000 for two staff to oversee coring/processing operations at
disposal site

Monthly charge includes labor, equipment and supplies, transportation, per diem

Field investigation takes three months to complete for each of the alternatives
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-27
2014
Upland Sediment Processing Facility Site Investigation - Geotechnical:

Samples collected using standard drill rig (air rotary, sonic, or other)

Cost for core sampling and processing - $1,800 per core [Internal database]

Cores extend to depth of 25 feet below ground surface

Two cores per acre collected for all sites with upland component; three samples taken
per core

Samples analyzed for Atterberg limits, percent solids, specific gravity, grain size
(sieve and hydrometer)

Consolidation tests and strength tests performed on 10 percent of the samples

Analytical and validation cost per sample [Internal database]:

•
Atterberg limits - $85
•
Percent solids - $50
•
Specific gravity - $75
•
Grain size (sieve and hydrometer) - $150
•
Consolidation - $600
•
Strength - $250
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Upland Sediment Processing Facility Site Investigation – Chemical:

Conduct Phase I/II Due Diligence investigation of upland sediment processing facility
site

Estimated cost per acre for Phase I/II Due Diligence investigation is $1,000

Samples taken from Geotechnical Investigation borings, one boring per acre; three
samples per boring

Samples analyzed for metals

Ten percent of samples analyzed for dioxin, PCBs, and pesticides

Analytical and validation cost per sample [Internal database]:
•
Metals - $275
•
Dioxin – $940
•
PCBs -$188
•
Pesticides - $1,063
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-28
2014

Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Topographic Survey – Uplands Sediment Processing Facility Site:

Topographic survey prepared for uplands site plus an additional 10 percent of acreage
to include surrounding areas for design purposes

Topographic map tied to State Plane coordinates with two foot contour interval tied to
NAVD.

Two days of ground survey to establish ground control for aerial survey

Daily rate for survey crew - $4,000 [Internal database]

Topographic map prepared by aerial survey of site:
•
Cost for aerial survey flight - $500 per acre
•
Cost for drafting contour map - $100 per acre
Habitat Survey (upland site):

Lump sum cost of $42,000
Cultural Survey (upland site):

Lump sum cost of $42,000
Miscellaneous Tests for DMM Design:

Samples taken from cores and boring materials collected for chemical and
geotechnical analyses

Dredged material slurry simulations - 20 tests @ $1,900

Dredge elutriate tests - 20 tests @ $600 each

Paint filter tests - 20 tests @ $25 each

Jar testing/settling tests - 20 tests @ $1,200

Optimum polymer doses - 3 tests@ $1,900

Mechanical dewatering tests - 1 test @ $1,200

Multimedia filter tests - 20 tests @ $600 each

TCLP Testing - 10 @ $1,063 each
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-29
2014
3.3.2 G3. Upland Sediment Processing Facility
Mobilization and Demobilization:

Ten percent of DMM construction phase capital costs (not including DMM PreConstruction Activities costs) [Internal database]
Mechanical and Electrical:

Ten percent of DMM construction phase capital costs (not including DMM PreConstruction Activities and Mobilization costs) [Internal database]
Layout and Documentation Survey:

Daily rate for survey crew - $4,000 [Internal database]

Surveying performed periodically during construction – 2 days per week over
12 month construction period
Fencing:

Material purchase and installation - $60 per linear foot [Internal database]:
•
Alternative 2 - 10,300 linear feet (5,200 feet for site boundary; 5,100 feet for
exclusion zone)
•
Alternative 3 - 9,800 linear feet (5,000 feet for site boundary; 4,800 feet for
exclusion zone)
•
Alternative 4 - 9,800 linear feet (5,000 feet for site boundary; 4,800 feet for
exclusion zone)

Increase fencing quantity by two percent to account for cost of gates
Exterior Lighting:

Material purchase and installation - $50,000 per acre [Internal database]:
•
Alternative 2 - 39.5 acres
•
Alternative 3 - 36 acres
•
Alternative 4 - 36 acres
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-30
2014
Security:

Lump sum cost of $100,000 [Internal database]
Buildings:

Processing Building
•
Size:
o Alternative 2 - 8.5 acres
o Alternative 3 - 8.2 acres
o Alternative 4 - 8.2 acres

•
Cost - $100 per square foot not including amenities [Internal database]
•
Amenities - Lump sum for laboratory, shower, and locker facility - $100,000
Additional cost for Administrative/Laboratory Area of Processing Building 30,000 square feet @ $50 per square foot

Wastewater treatment system included in Processing Building (equipment costs
elsewhere

Guard shack - 150 square feet @ $100 per square foot [Internal database]

Truck wash - Lump sum $100,000 [Internal database]

Assumes site soils are stable and capable of supporting building and equipment loads
without piling or major soil modifications
Utilities:

Sewer connection - $500,000

Water connection - $250,000

Electrical connection - $500,000 [Internal database]

Costs assumes an undeveloped site and all new utility connections
Earthwork:

Grading and clearing of site prior to construction - assume minimal effort required
(up to three foot cut/fill across site)

Cost - $12 per cubic yard based on on-site disposal of soil
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-31
2014

Continuous footings required around building perimeter along with pads for major
equipment

No other costs for soil improvements required
Stormwater Management:

Perimeter drainage ditch diverts non-contact water to a sedimentation basin for
treatment prior to discharge to the river

Roof leaders are connected to perimeter drainage system

Water in the exclusion zone is captured and treated/reused before being discharged to
river in accordance with regulatory requirements

Lump sum cost of $219,000 for Alternative 2 and $168,000 for Alternatives 3 and 4
Paving:

Filter fabric installed over native soil

Installed cost of filter fabric - $2 per square yard [Internal database]

Six inches subgrade material placed over the filter fabric

Installed cost of subgrade material - $40 per cubic yard [Internal database]

Plant mix asphalt paving - 3 inches bearing course and 1.5 inches wearing course

Installed cost of plant mix asphalt paving - $20 per square yard [Internal database]

Paved area:
•
Alternative 2 - approximately 81,000 square yards
•
Alternative 3 - approximately 73,000 square yards
•
Alternative 4 - approximately 73,000 square yards
Pier/Dock Structure:

Frontage wharf along shore of upland sediment processing facility – 50,000 square
feet

Wharf intended for temporary use during hydraulic offloading

The length of the wharf is intended to provide space for two barges at a time

Material cost and installation - $160 per square foot [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-32
2014
Pre-fabricated Building (Sprung Structure) for Dewatered Sediment Storage:

Enclosed on-site storage of dewatered solids

Approximately six months of storage provided for dewatered hazardous material to
allow flexibility in production schedules; approximately six months of storage for
treated materials (thermal treatment and sediment washing)

Negative pressure maintained in structure to control emission; vapors routed through
granular activated carbon before discharge


Approximate storage requirements:
•
Alternative 2 - 351,000 square feet
•
Alternative 3 - 283,000 square feet
•
Alternative 4 - 283,000 square feet
Installed cost for insulated structure - $40 square foot [Contactor communications]
Storage Area – Concrete Slab and Push Walls:

Structure installed on concrete slab with eight foot push walls

Installed costs for concrete slabs - $600 per cubic yard [Internal database]
Storage Area – Subgrade Material:

Installed cost for subgrade material under slab - $40 per cubic yard [Internal
database]
Storage Area – Filter Fabric:

Installed cost for filter fabric under slab - $2 per square yard [Internal database]
Storage Area –Vapor Emissions Control:

Maintain negative pressure within storage structure to control emissions (dust and
odors)

One unit for approximately 10,000 cubic yards of storage capacity

Vapors routed through GAC filter units prior to discharge to the atmosphere:
•
Alternative 2 - 30 units
•
Alternative 3 - 24 units
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-33
2014
•

Alternative 4 - 24 units
Installed cost per unit - $5,000 [Internal database]
Piping:

Includes exterior piping and appurtenances (e.g., storm drains, catch basins, culverts,
etc.) and interior piping in processing building

Exterior piping (stormwater and ancillary piping) - 37,000 linear feet for Alternative
2 and 33,500 linear fit for Alternatives 3 and 4

Interior piping (treatment system) - 7,100 linear feet for Alternative 2 and 6,900
linear feet for Alternatives 3 and 4

Installed/delivered cost - $25 per linear foot for exterior piping and $15 per linear foot
for interior piping [Internal database]

Add 25 percent for joints, tees, wyes, other connections and fittings
Upfront Storage and Recycle Water Tanks

Upfront Storage Tank: provide temporary storage of sediment in case of plant upsets
or shutdown

Recycle Water Tank: provide temporary storage of water used for the hydraulic
offloading of barges

Storage capacity provided for each tank- 12 hours [Internal database]
Loadout Facility:

Lump sum - $500,000 [Internal database]
Transfer Vehicle Storage:

Approximately 2.8 to 3.4 acres of storage area for transfer vehicles; provide storage
for 5 to 10 days of vehicle storage

Storage area can be on a separate parcel away from the rest of the upland sediment
processing facility as long as it is located in the general area

Paved surface for parking area

Installed cost per square yard - $30 [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-34
2014
Temporary Bunkers for Loadout Facility:

Two bunkers at $10,000 each [Internal database]
Hazardous Material Processing and Storage Area:

Includes decontamination pad for medium and large debris processing

Lump sum[Internal database]:
•
Alternative 2 - $124,000
•
Alternative 3 - $93,000
•
Alternative 4 - $33,000
Air Monitoring During Construction

Fugitive dust, odors, VOCs monitoring - $5,000 per month

Includes labor, sample analysis, equipment maintenance
3.3.3 H3. Equipment Costs
Operating Equipment:

Equipment purchased for site operators:
•
3 Front end loaders ($124,000 each)
•
1 Skidsteer ($25,000 each)
•
1 Excavator ($200,000 each)
•
4 Dump trucks ($80,000 each)
•
1 Water truck ($50,000 each)
•
1 Street Sweeper ($100,000 each)
Wastewater Treatment Plant:

Wastewater treatment plant (WWTP) includes the following components:
equalization tank, sedimentation tank with combined oil-water separator, multimedia
filter, carbon filter, and bag filter.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-35
2014

Where feasible water would be treated and reused in the process minimizing the
overall water consumption


Cost broken down into fixed and variable components
•
Fixed costs (structure, design, contractor overhead, etc.)
•
Variable costs (based on flow in MGD)
Treatment plant sizes:
•
Alternative 2 - 1.8 MGD
•
Alternative 3 - 1.6 MGD
•
Alternative 4 - 1.6 MGD
3.3.4 I3. Local Decontamination
Mechanical Dewatering Using Filter Presses:

Treatment includes screening, coarse and fine sand separation, pre-thickening,
chemical addition, and mechanical dewatering,

Cost includes equipment capital costs as well as operating costs

Unit costs: $50 per cubic yard [Contractor communications]
Dewatered Material Testing for Disposal:

One sample per 5,000 cubic yards of material

Analytical cost [Internal database]:
•
TCLP - $1,063
•
Paint filter - $25
Thermal Treatment (On-site/Local Facility):

Thermal treatment systems potentially suitable for FFS Study Area sediments include
the following:
•
Cement-Lock® Technology
•
JCI/Upcycle Associates, LLC’s Rotary Kiln
•
Minergy’s Glass Furnace Technology
•
WPC’s Vitrification Technology
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-36
2014

Information on technologies provided for estimation purposes only and performance
would have to be verified during site design; details on sites presented in Appendix G

Thermal Treatment unit (e.g., GTI/Volcano) constructed at the processing site or in
the general area for treatment of heavily contaminated sediment

Byproduct of the treatment process (e.g., CementLock®) would meet beneficial use
requirements in the state of New Jersey

Income derived from the sale of the byproduct would offset marketing and
transportation costs for the material

Treatment cost of $370 per dewatered ton for Alternatives 2 and 3 [Contractor
communications]

Treatment cost of $640 per dewatered ton for Alternative 4. Cost adjusted to reflect
that a dedicated thermal treatment facility may not be commercially viable
[Contractor communications].


Dewatered mass of material to be thermally treated
•
Alternative 2 - 740,000 tons
•
Alternative 3 - 180,000 tons
•
Alternative 4 - 30,000 tons
Storage requirements addressed elsewhere
Sediment Washing:

Sediment washing systems potentially suitable for FFS Study Area sediments include
the following:

•
Pear Technologies
•
Biogenesis®
Information on technologies provided for estimation purposes only and performance
would have to be verified during site design; details on sites presented in Appendix G

Sediment washing system (e.g., Biogenesis®) constructed at the processing site for
treatment of medium contaminated sediment; washed sediment stabilized using
Portland cement, Cement Kiln Dust (CKD) or other similar material to meet
beneficial use requirements in the state of New Jersey

Treated sediment would be hauled to a landfill for beneficial use as cover material
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-37
2014

Treatment/transportation and landfill cost is $150 per cubic yard.

In-situ volumes of material
•
Alternative 2 - 6,160,000 cubic yards
•
Alternative 3 - 2,890,000 cubic yards
•
Alternative 4 - 710,000 cubic yards
Sediment Amendment:

Sediment that is lightly contaminated would be stabilized using Portland cement,
CKD or other similar material to meet beneficial use requirements in the state of
New Jersey

Treated sediment would be hauled to a landfill for beneficial use as cover material

Treatment/transport/fee at landfill cost totals $80 per dewatered ton

Dewatered mass of material being amended
•
Alternative 2 - 140,000 tons
•
Alternative 3 - 20,000 tons
•
Alternative 4 - 11,000 tons
Decontamination and Disposal of Medium-Sized Debris:

Debris removed during screening, decontaminated (via high pressure washing), and
transported off-site for disposal at cost of $200 per cubic yard [Contractor
communications]

In-situ volume of debris removed during dredging operations:
•
Alternatives 2 - 534,000 cubic yards total
•
Alternative 3 - 238,000 cubic yards total
•
Alternative 4 - 56,000 cubic yards total
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill:

Generally small sized organic debris and gravel removed by fine screening or
microfiltration during processing

Debris containerized and shipped to a Subtitle C landfill for disposal at a cost of
$230 per ton
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-38
2014

In-situ mass of debris:
•
Alternatives 2 - 55,000 tons total
•
Alternative 3 - 24,000 tons total
•
Alternative 4 - 6,000 tons total
Reclaimed Sand Processing, Transport, and Beneficial Use:

Reclaimed sand recovered during sediment processing to be used beneficially

Cost for transportation, and beneficial use - $50 per ton.

Dewatered mass of reclaimed sand:
•
Alternatives 2 - 1,600,000 tons total
•
Alternative 3 - 600,000 tons total
•
Alternative 4 - 100,000 tons total
3.3.5 J3. Site Decommissioning/Restoration

Site restoration/demolition/decommissioning - $30,000 per acre
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3-39
2014
4
DREDGED MATERIAL MANAGEMENT O&M COSTS
4.1 K. DMM Site O&M
4.1.1 CAD (DMM Scenario A)
General Assumptions:

Construction performed under multiple prime contracts held by client, not by single
prime/general contractor

Ten percent construction management fee applied to DMM construction phase capital
costs (not including Pre-Construction Activities costs)

Twenty five percent contingency on all costs except construction management

Duration of Dredging and Capping Operations:
•
Alternative 2 - 11 years
•
Alternative 3 - 5 years
•
Alternative 4 - 2 years
Operational Testing:

One to two water column samples collected per day, or 30 samples per month (240
days per year of dredging operations averaged over 12 months, or approximately
20 days per month of operations)

Water column samples analyzed for TSS

Two composite water samples per month analyzed for TAL/TCL plus cyanide and
dioxin per month

Analytical and validation cost per sample [Internal database]:
•
TSS - $50
•
Dioxin - $940
•
TAL/TCL - $625

Process/ship three samples per man hour

Shipping cost $100 per cooler, four samples per cooler [Internal database]
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-1
2014
Upland Support Facility O&M:


Staffed operations in upland support facility:
•
24 hour per day operations during dredging and capping
•
Staffing does not include dredging contractor workforce
Site operations support staff:
•
Site Manager - one person @ $131,000 per year
•
Shift Supervisors - three people @ 102,000 per year (each)
•
Site Health and Safety Officer - one person @ 102,000 per year
•
Mechanics - three people @ $80,000 per year (each)
•
Laborers - two people @ $44,000 per year (each)
•
Laboratory Technician - one person @ $58,000 per year
•
Administrative Support - one person @ $36,000 per year
•
Site Security - four people @ $29,000 per year (each)

Annual wages/salaries including 40 percent benefits

Utilities/Fuel - $20,000 to 30,000 per year

Insurance - $100,000 per year

Miscellaneous Equipment - $25,000 per year
Operations Management/Coordination:


Site operational staffing:
•
Program Manager - one person @ $204,000 per year
•
Operations Leaders - three people @ $131,000 per year (each)
•
Senior QA - one person @ $204,000 per year (half time)
•
Program Management Support - three people @ $80,000 per year
Annual wages/salaries including 40 percent benefits
Air Monitoring:

Fugitive dust, odors, VOCs monitoring - $5,000 per month

Includes labor, sample analysis, equipment maintenance
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-2
2014
4.1.2 Off-Site Disposal (DMM Scenario B)
General Assumptions:

Construction performed under multiple prime contracts held by client, not by single
prime/general contractor

Ten percent construction management fee applied to Long Term O&M costs

Twenty five percent contingency on all costs except construction management

Duration of Dredging and Capping Operations:
•
Alternative 2 - 11 years
•
Alternative 3 - 5 years
•
Alternative 4 - 2 years
Wastewater Treatment Plant O&M:

Annual operation and maintenance cost – ten percent of the capital wastewater
treatment plant costs

Covers chemical and supplies, regeneration of activated carbon, waste disposal,
electrical

Treated wastewater discharged to Newark Bay in accordance with regulatory
requirements
Sediment Processing Site O&M:

Includes labor, fuel, utilities, site maintenance and site security for upland processing
site

Staffed operations during dredging and processing:
•
24 hour per day operations during dredging and processing
•
Staffing does not include dredging contractor workforce or dewatering contractor
workforce at upland sediment processing facility

Site operational staffing:
•
Site Manager - one person @ $131,000 per year
•
Shift Supervisors - three people @ $102,000 per year (each)
•
Site Health and Safety Officer - one person @ $102,000 per year
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-3
2014
•
Equipment/WWTP Operators - four people @ $80,000 per year (each)
•
Mechanics - four people @ $80,000 per year (each)
•
Laborers - four people @ $44,000 per year (each)
•
Laboratory Technician - two people @ $58,000 per year (each)
•
Administrative Support - two people @ $36,000 per year (each)
•
Site Security - four people @ $29,000 per year (each)

Annual wages/salaries including 40 percent benefits

Insurance - $100,000 per year

Utilities/Fuel - $20,000 per year

GAC storage/recycle cost
•
Alternative 2 - $40,000 per year
•
Alternative 3 - $30,000 per year
•
Alternative 4 - $10,000 per year

Annual equipment operations and maintenance - 10% of total equipment costs

Miscellaneous equipment - $25,000 per year
Operations Management/Coordination:


Site operational staffing:
•
Program Manager - one person @ $204,000 per year
•
Operations Leaders - three people @ $131,000 per year (each)
•
Senior QA - one person @ $204,000 per year (half time)
•
Program Management Support - three people @ $80,000 per year
Annual wages/salaries including 40 percent benefits
Wastewater Testing:


Monthly sampling and analysis
•
TSS - 30 samples
•
TAL/TCL plus cyanide - 2 samples
•
Dioxins - 2 samples
Analytical and validation cost per sample:
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-4
2014

•
TSS - $50
•
Dioxin - $940
•
TAL/TCL plus cyanide - $625 [Internal database]
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Air Monitoring:

Fugitive dust, VOCs and odors - $5000 per month [Internal database]

Includes labor, sample analysis, equipment maintenance
4.1.3 Local Decontamination and Beneficial Use (DMM Scenario C)
General Assumptions:

Construction performed under multiple prime contracts held by client, not by single
prime/general contractor

Ten percent construction management fee applied to Long Term O&M costs

Twenty five percent contingency on all costs except construction management

Duration of Dredging and Capping Operations:
•
Alternative 2 - 11 years
•
Alternative 3 - 5 years
•
Alternative 4 - 2 years
Wastewater Treatment Plant O&M:

Annual operation and maintenance cost - 10% of the capital wastewater treatment
plant costs

Includes chemical and supplies, regeneration of activated carbon, waste disposal,
electrical

Treated wastewater discharged to Newark Bay in accordance with regulatory
requirements
Sediment Processing Site O&M:

Includes labor, fuel, utilities, site maintenance and site security for upland processing
site
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-5
2014

Staffed operations during dredging and processing:
•
24 hour per day operations during dredging and processing
•
Staffing does not include dredging contractor workforce or dewatering contractor
workforce at upland sediment processing facility

Site operational staffing:
•
Site Manager - one person @ $131,000 per year
•
Shift Supervisors - three people @ $102,000 per year (each)
•
Site Health and Safety Officer - one person @ $102,000 per year
•
Equipment/WWTP Operators - six people @ $80,000 per year (each)
•
Mechanics - five people @ $80,000 per year (each)
•
Laborers - five people @ $44,000 per year (each)
•
Laboratory Technician - two people @ $58,000 per year (each)
•
Administrative Support - two people @ $36,000 per year (each)
•
Site Security - four people @ $29,000 per year (each)

Annual wages/salaries including 40 percent benefits

Insurance - $100,000 per year

Utilities/Fuel - $20,000 per year

GAC storage/recycle cost:
•
Alternative 2 - $40,000 per year
•
Alternative 3 - $30,000 per year
•
Alternative 4 - $10,000 per year

Annual equipment operations and maintenance - 10% of total equipment costs

Miscellaneous equipment - $25,000 per year
Operations Management/Coordination:

Site operational staffing:
•
Program Manager - one person @ $204,000 per year
•
Operations Leaders - three people @ $131,000 per year (each)
•
Senior QA - one person @ $204,000 per year (half time)
•
Program Management Support - three people @ $80,000 per year
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-6
2014

Annual wages/salaries including 40 percent benefits
Wastewater Testing:



Monthly sampling and analysis:
•
TSS - 30 samples
•
TAL/TCL plus cyanide - 2 samples
•
Dioxins - 2 samples
Analytical and validation cost per sample:
•
TSS - $50
•
Dioxin - $940
•
TAL/TCL plus cyanide - $625 [Internal database]
Shipping cost of $100 per cooler; four samples per cooler [Internal database]
Air Monitoring:

Fugitive dust, VOCs and odors - $5000 per month [Internal database]

Includes labor, sample analysis, equipment maintenance
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4-7
2014
5
LONG TERM O&M COSTS
General Assumptions:

Ten percent construction management fee applied to Long Term O&M costs

Twenty five percent contingency on all costs except construction management

Alternative 2 has fewer annual O&M requirements because of the reduced volume of
remaining contaminant inventory and the lack of engineered cap in the river
5.1 Annual O&M
5.1.1 L. Annual Monitoring Activities
Community Outreach:

Includes public meetings, fact sheet development, maintenance of administrative
record, and other efforts to communicate with the public on the status of work and
conditions in the FFS Study Area

Alternative 2 (DMM Scenario A only) and Alternatives 3 and 4 (all DMM Scenarios)

Lump sum of $95,000 per year [Internal database]
Mobilization and Demobilization of Monitoring Equipment:

Annual mobilization charge for monitoring equipment [Contractor communications]:
•
Two water quality vessels - $2,500 each
•
Geophysical vessel - $6,000
•
Small vibracoring vessel - $2,800
•
Sediment profile imaging (SPI) vessel - $13,100
Bathymetric Survey:

Daily rate for geophysical vessel of $1,600 (labor) and $6,600 (vessel and equipment)
[Contractor communications]

Survey rate - one river mile surveyed per day plus one additional day to survey CAD
cell (DMM Scenario A only)
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
5-1
2014
Water Column Sampling and Analysis:

All Alternatives - Two samples taken for two tidal cycles per river mile

DMM Scenario A - Four additional samples for two tidal cycles per CAD cell

Ten percent additional samples collected as samples of opportunity

Daily rate for two water quality vessels of $2,400 (labor) and $2,000 (vessel and
equipment) [Contractor communications]

Ten water quality samples collected per day

Samples are analyzed for TPH and lead (surrogate chemical parameters).

Ten percent of the samples are analyzed for the “full suite” of chemicals (dioxin,
pesticides, and TAL/TCL plus cyanide).

Analytical and validation cost per sample [Internal database]:
•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625

Process/ship three samples per man hour

Shipping cost $100 per cooler; four samples per cooler [Internal database]
Sediment Sampling and Analysis:

Sediment sampling for evaluation of remedy and/or cap performance:
•
Alternative 2 - Five samples collected at each transect; transects spaced at
0.125 mile intervals; surface sediment sampling only
•
Alternatives 3 and 4 - Five cores collected at each transect; transects spaced at
0.1 mile intervals; 6-foot cores on average; four samples per core
•
DMM Scenario A - Five cores per CAD cell; 6-foot cores on average; 4 samples
per core

Daily rate for small vibracoring vessel of $1,600 (labor) and $3,700 (vessel and
equipment) [Contractor communications]

Twenty sediment samples collected per day

Samples analyzed for TPH and lead (surrogate chemical parameters)
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
5-2
2014

Ten percent of samples analyzed for “full suite” of chemicals (dioxin, pesticides, and
TAL/TCL plus cyanide)

Analytical and validation cost per sample [Internal database]:
•
TPH - $207
•
Lead - $25
•
Dioxin - $940
•
Pesticides - $1,063
•
TAL/TCL - $625

Process/ship three samples per man hour

Shipping cost $100 per cooler; four samples per cooler [Internal database]
Biological Monitoring:

Biological monitoring conducted monthly throughout long term O&M period;
surveys may include all or some of the following elements:

•
Avian community surveys
•
Fish community surveys
•
Benthic invertebrates surveys
•
Biological tissue-residual testing
•
Toxicity testing
Average monthly cost of $112,500, or approximately $1,400,000 per year [Internal
calculation/database] for surveying the lower 8.3 river miles

Average monthly cost for monitoring cost at the CAD cell:
•
Alternative 2 - equal to 20 percent of average monthly cost for surveying in the
lower 8.3 miles
•
Alternatives 3 - equal to 10 percent of average monthly cost for surveying in the
lower 8.3 miles
•
Alternative 4 - equal to 3 percent of average monthly cost for surveying in the
lower 8.3 miles
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
5-3
2014
Habitat Recolonization using SPI:

All Alternatives - Approximately 10 SPI locations per river mile, 20 percent of the
river each year

DMM Scenario A - Four additional locations per CAD cell

Imaging, processing and reporting - $2,300 per SPI location
Annual Monitoring Reports:

Laboratory reporting cost - $35,000

Report preparation - 400 hours at $175 per hour to complete draft and final
monitoring reports
5.1.2 M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment:

Alternative 2 (DMM Scenario A only) and Alternatives 3 and 4 (all DMM Scenarios)

Cost based on use of more conventional and readily available equipment compared to
precision equipment used to construct cap initially
Ice Scour Evaluation for Cap along Shoreline:

Alternatives 3 and 4 only

Visual cap inspection during low tide in the spring to evaluate winter season ice
impacts - three person crew; five 8-hour days - $15,000

Reporting costs - $6,000
Annual Cap Maintenance:

Annual cap maintenance performed on an as-needed based on conditions observed
during routine maintenance; estimate provided for budgetary purposes
•
Alternative 2, DMM Scenario A - 0.2 percent of cap material at CAD cell
replaced annually
•
Alternatives 3 and 4, all DMM Scenarios – 0.2 percent of cap material at CAD
cell and in river replaced annually

Cap material cost (installed) - $50 per cubic yard
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
5-4
2014

No maintenance required in backfill and armor areas
5.2 Periodic O&M
General Assumptions:

Periodic or supplemental O&M activities to occur approximately every five years
5.2.1 N. Periodic Monitoring Activities
Community Outreach:

Includes public meetings, fact sheet development, maintenance of administrative
record, and other efforts to communicate with the public on the status of work and
conditions in the FFS Study Area

Alternative 2 (DMM Scenarios B and C only)

Lump sum of $95,000 per year [Internal database]
Supplemental Biological Monitoring:

Supplemental biological monitoring conducted periodically; surveys may include all
or some of the following elements:

•
Avian community surveys
•
Fish community
•
Benthic invertebrates
•
Biological tissue-residual testing
•
Toxicity testing
Approximate cost for complete assessment $2,800,000 [Internal calculation/database]
less work performed on an annual basis for an additional periodic cost of
approximately $1,400,000
Supplemental Habitat Recolonization using SPI:

All Alternatives - approximately 10 SPI locations per river mile, additional 80 percent
of the river

DMM Scenario A - additional six locations per CAD cell
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
5-5
2014

Imaging, processing and reporting - $2,300 per SPI location
Performance Review Report:

Additional laboratory report cost - $15,000

Report preparation - 2000 hours at $175 per hour to complete draft and final
monitoring reports
5.2.2 O. Periodic Maintenance Activities
Periodic Cap Maintenance:

Periodic expanded maintenance of engineered cap:
•
Alternative 2, DMM Scenario A - five percent of cap material at CAD cell
replaced periodically
•
Alternatives 3 and 4, all DMM Scenarios - five percent of cap material at CAD
cell and in river replaced periodically

Installed cap material costs - $50 per cubic yard

No maintenance required in backfill and armor areas
Natural Shoreline Maintenance:

Replace dying and diseased plantings

Replant ten percent of natural shoreline - approximately 2300 linear feet

Replanting cost - $200 per linear foot
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
5-6
2014
6
@
at
CAD
Confined Aquatic Disposal
CKD
cement kiln dust
DMM
Dredge Materials Management
DOC
dissolved organic carbon
ENR
Engineering News Record
FFS
Focused Feasibility Study
GAC
Granulated Activated Carbon
H:V
horizontal to vertical
HARS
Historic Area Remediation Site
IDW
investigation derived waste
MGD
million gallons per day
NAVD
North American Vertical Datum
O&M
Operations and Maintenance
PAH
polycyclic aromatic hydrocarbon
PCB
polychlorinated biphenyl
POC
particulate organic carbon
QA
quality assurance
RCRA
Resource Conservation and Recovery Act
RM
river mile
S/S
solidification/stabilization
SVOC
semi-volatile organic compounds
TAL/TCL
Target Analyte List/Target Compound List
TCLP
Toxicity Characteristic Leaching Procedure
TOC
total organic carbon
TPH
total petroleum hydrocarbons
TSS
total suspended solids
USEPA
United States Environmental Protection Agency
VOC
volatile organic compounds
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6-1
ACRONYMS
2014
Unit Acronyms Presented in Tables
CY
cubic yards
EA
each
LF
linear feet
LS
lump sum
SF
square feet
SY
square yard
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6-2
2014
7
REFERENCES
Engineering News-Record (ENR), 2014. “Current Costs”. Available at:
http://enr.construction.com/economics/current_costs/Default.asp. Accessed on: January
14, 2014, updated January 1, 2011.
USEPA, 2000. “A Guide to Developing and Documenting Cost Estimates During the
Feasibility Study.” EPA 540-R-00-002. OSWER 9355.0-75. U.S. Army Corps of
Engineers, Hazardous, Toxic, and Radioactive Waste Center of Expertise, Omaha, NE.
U.S. Environmental Protection Agency, Office of Emergency and Remedial Response,
Washington, D.C. July 2000.
USEPA, 1993. “Revisions to OMB Circular A-94 on Guidelines and Discount Rates for
Benefit-Cost Analysis.” OSWER 9355.3-20. U.S. Environmental Protection Agency,
Washington, D.C. June 1993.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
7-1
2014
Tables
Table 1-1 Summary of Present Value Cost Estimate
Present Value Costs1
Alternative
Capital2
DMM3,4
O&M5
Contingency
Total
$0
$0
$0
$0
$0
Alternative 2 with DMM Scenario A: Deep Dredging
with Backfill, CAD
$549,000,000
$522,000,000
$18,000,000
$252,000,000
$1,341,000,000
Alternative 2 with DMM Scenario B: Deep Dredging
with Backfill, Off-Site Disposal
$657,000,000
$1,967,000,000
$13,000,000
$608,000,000
$3,245,000,000
Alternative 2 with DMM Scenario C: Deep Dredging
with Backfill, Local Decontamination and Beneficial
Use
$657,000,000
$1,460,000,000
$13,000,000
$491,000,000
$2,621,000,000
Alternative 3 with DMM Scenario A: Capping with
Dredging for Flooding and Navigation, CAD
$408,000,000
$322,000,000
$45,000,000
$179,000,000
$953,000,000
$463,000,000
$903,000,000
$41,000,000
$324,000,000
$1,731,000,000
$463,000,000
$784,000,000
$41,000,000
$297,000,000
$1,585,000,000
Alternative 4 with DMM Scenario A: Focused Capping
with Dredging for Flooding, CAD
$140,000,000
$116,000,000
$41,000,000
$68,000,000
$365,000,000
Alternative 4 with DMM Scenario B: Focused
Capping with Dredging for Flooding, Off-Site Disposal
$154,000,000
$306,000,000
$39,000,000
$115,000,000
$614,000,000
Alternative 4 with DMM Scenario C: Focused Capping
with Dredging for Flooding, Local Decontamination
and Beneficial Use
$154,000,000
$299,000,000
$39,000,000
$113,000,000
$606,000,000
Alternative 1: No Action
Alternative 3 with DMM Scenario B: Capping with
Dredging for Flooding and Navigation, Off-Site
Disposal
Alternative 3 with DMM Scenario C: Capping with
Dredging for Flooding and Navigation, Local
Decontamination and Beneficial Use
Notes:
1. Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1 (refer to Section 1 of Appendix H). Values are rounded to the nearest million.
2. Capital Costs includes Construction Management
3. DMM = Dredged Material Management (includes Construction Management)
4. Total DMM Costs = DMM Capital Cost + DMM O&M Costs
5. O&M = Operation and Maintenance
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 1
2014
Table 1-2 Cost Estimate: Alternative 2 with DMM Scenario A
Deep Dredging with Backfill, Confined Aquatic Disposal
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Backfilling Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
New Season Restart
Total Mobilization and Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$43,300
671,524,810
671,524,810
1
12
12
1
Core
Boring
Sample
Sample
Sample
Sample
LS
Day
Day
LS
LS
LS
Sample
Sample
$1,810
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
5,478
77
43,824
11,280
10,344
231
1
9
9
1
1
1
300
343
EA
EA
LS
EA
EA
Year
$237,000
$237,000
$13,800
$60,000
$237,000
$310,000
2
2
1
1
1
10
Cost
$40,290,000
$13,430,000
$355,000
$120,000
$576,000
$43,300
$9,915,180
$750,750
$68,365,440
$14,438,400
$2,896,320
$286,440
$2,800,000
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$898,660
$156,903,090
$474,000
$474,000
$13,800
$60,000
$237,000
$3,100,000
$4,358,800
2014
Table 1-2 Cost Estimate: Alternative 2 with DMM Scenario A
Deep Dredging with Backfill, Confined Aquatic Disposal
Component
C. Testing and Monitoring During Dredging and Backfilling
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Utility Protection
Bridge/Abutment/Bulkhead Protection
Barge Transport of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Backfill
Backfill Material Purchase and Delivery
Backfill Material Placement
Mudflat Backfill
Mudflat Reconstruction
Natural Shoreline Reconstruction
Natural Shoreline Biostabilization
Riprapped Shoreline Repairs and Replacement
Total Backfill
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$270,360
$1,350,000
$120,000
$355,000
11
11
11
11
11
11
$9,213,600
$16,000,600
$2,973,960
$14,850,000
$1,320,000
$3,905,000
$48,263,160
CY
Ton
SF
LF
CY
Percentage
$25
$30
$100
$4,100
$10
1%
9,681,000
8,000
290,500
6,100
15,635,000
664,870,000
$242,025,000
$240,000
$29,050,000
$25,010,000
$156,350,000
$6,650,000
$459,325,000
CY
CY
CY
CY
CY
LF
SY
$30
$20
$50
$150
$50
$220
$75
1,799,000
1,799,000
712,500
203,500
30,093
5,560
10,000
$53,970,000
$35,980,000
$35,625,000
$30,525,000
$1,504,650
$1,223,200
$750,000
$159,577,850
Percentage
Percentage
10%
25%
671,524,810
828,427,900
$828,427,900
$67,150,000
$207,107,000
$1,102,684,900
2 of 6
2014
Table 1-2 Cost Estimate: Alternative 2 with DMM Scenario A
Deep Dredging with Backfill, Confined Aquatic Disposal
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F1. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Support Facility Site Investigation - Geotechnical
Upland Support Facility Site Investigation - Chemical
Topographic Survey - Upland Support Facility Site
Pre-Design Investigation of CAD Site - Chemical Sample Collection
Pre-Design Investigation of CAD Site - Geotechnical Sample Collection
Pre-Design Investigation of CAD Site - Chemical Analysis
Pre-Design Investigation of CAD Site - Geotechnical Analysis
Pre-Design Investigation of CAD Site - HARS Disposal Determination
Habitat Survey (upland support facility site)
Cultural Survey (upland support facility site)
Elutriate Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G1. CAD Excavation
Dredge Mobilization/Demobilization
Monitoring Equipment and Debris Removal Mobilization/Demobilization
Large Debris Removal
Contaminated Sediment Dredging and Disposal (First Cell)
Contaminated Sediment Testing for Disposal (First Cell)
Contaminated Sediment Dredge and Disposal (Subsequent Cells)
Clay Dredging/Transport/Disposal at HARS
Containment System Installation
Silt Curtain at CAD Entrance Channel
Air Monitoring During Construction
Testing and Monitoring
Total CAD Excavation
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
Core
Boring
Sample
Sample
LS
LS
LS
Sample
Day
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$1,330
$1,650
$9,700
$1,850
$1,240
$200,000
$5,000
$5,000
$1,040
$8,200
$76,000
665,172,040
665,172,040
5
1
2
10
5
5.5
235
33
235
99
1
1
1
24
1
1
$39,910,000
$13,300,000
$2,550,000
$119,000
$96,000
$32,200
$12,800
$7,315
$387,750
$320,100
$434,750
$122,760
$200,000
$5,000
$5,000
$24,960
$8,200
$76,000
$57,611,835
EA
EA
Ton
CY
Sample
CY
CY
SF
SF
Month
Month
$237,000
$72,800
$300
$200
$1,090
$35
$25
$235
$100
$5,000
$294,020
12
3
1,000
388,000
78
786,000
11,153,000
365,000
11,250
36
36
$2,844,000
$218,400
$300,000
$77,600,000
$85,020
$27,510,000
$278,825,000
$85,775,000
$1,125,000
$180,000
$10,584,720
$485,047,140
2014
Table 1-2 Cost Estimate: Alternative 2 with DMM Scenario A
Deep Dredging with Backfill, Confined Aquatic Disposal
Component
H1. Upland Support Facility
Mobilization/Demobilization
Layout and Documentation Survey
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Wastewater Treatment System for Contact Water
Total Upland Support Facility
I1. CAD Closure
Cap Material Purchase and Delivery
Engineered Cap Material Placement
Confirmation Coring
Remove Containment System
Bathymetric Surveys
Additional Habitat Mitigation
Total CAD Closure
J1. Site Decommissioning/Restoration
Total Site Decommissioning/Restoration
Subtotal DMM Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Percentage
Day
LF
Acre
LS
SF
LS
CY
SF
SY
SF
Month
10%
$4,000
$60
$50,000
$20,000
$120
$125,000
$12
$18
$30
$160
$10,000
6,105,800
10
1,940
5
1
10,150
1
8,100
3,900
17,300
15,000
125
CY
CY
Core
SF
Day
LS
$30
$30
$1,830
$36
$8,200
$102,751,000
930,000
930,000
830
365,000
6
1
Acre
$30,000
5
Percentage
Percentage
10%
25%
665,172,040
722,783,875
Cost
$610,000
$40,000
$116,400
$250,000
$20,000
$1,218,000
$125,000
$97,200
$70,200
$519,000
$2,400,000
$1,250,000
$6,715,800
$27,900,000
$27,900,000
$1,518,900
$13,140,000
$49,200
$102,751,000
$173,259,100
$150,000
$150,000
$722,783,875
$66,520,000
$180,700,000
$970,003,875
4 of 6
2014
Table 1-2 Cost Estimate: Alternative 2 with DMM Scenario A
Deep Dredging with Backfill, Confined Aquatic Disposal
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Operational Testing
Upland Support Facility O&M
Operations Management/Coordination
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Month
Year
Year
Month
$6,820
$1,220,000
$939,000
$5,000
12
1
1
12
$81,840
$1,220,000
$939,000
$60,000
Percentage
Percentage
10%
25%
2,300,840
2,300,840
$2,300,840
$230,000
$575,000
$3,105,840
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
Year
Year
Day
Sample
Sample
Year
Location
Year
$95,000
$26,900
$8,200
$1,000
$830
$1,680,000
$2,300
$105,000
1
1
10
63
431
1
29
1
Year
CY
$54,000
$50
1
1,900
Percentage
Percentage
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
10%
25%
2,625,330
2,625,330
$95,000
$26,900
$82,000
$63,000
$357,730
$1,680,000
$66,700
$105,000
$2,476,330
$54,000
$95,000
$149,000
$2,625,330
$263,000
$656,000
$3,544,330
5 of 6
2014
Table 1-2 Cost Estimate: Alternative 2 with DMM Scenario A
Deep Dredging with Backfill, Confined Aquatic Disposal
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Location
Year
$1,400,000
$2,300
$365,000
1
84
1
$1,400,000
$193,200
$365,000
$1,958,200
Year
LF
$50
$200
47,000
2,300
$2,350,000
$460,000
$2,810,000
Percentage
Percentage
TOTAL PERIODIC O&M
10%
25%
4,768,200
4,768,200
Cost
$4,768,200
$477,000
$1,192,000
$6,437,200
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-3 Cost Estimate: Alternative 2 with DMM Scenario B
Deep Dredging with Backfill, Off-site Disposal
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Backfilling Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
New Season Restart
Total Mobilization and Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$43,300
830,814,810
830,814,810
1
12
12
1
Core
Boring
Sample
Sample
Sample
Sample
LS
Day
Day
LS
LS
LS
Sample
Sample
$1,810
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
5,478
77
43,824
11,280
10,344
231
1
9
9
1
1
1
300
343
EA
EA
LS
EA
EA
Year
$237,000
$237,000
$13,800
$60,000
$237,000
$310,000
2
2
1
1
1
10
Cost
$49,850,000
$16,620,000
$355,000
$120,000
$576,000
$43,300
$9,915,180
$750,750
$68,365,440
$14,438,400
$2,896,320
$286,440
$2,800,000
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$898,660
$169,653,090
$474,000
$474,000
$13,800
$60,000
$237,000
$3,100,000
$4,358,800
2014
Table 1-3 Cost Estimate: Alternative 2 with DMM Scenario B
Deep Dredging with Backfill, Off-site Disposal
Component
C. Testing and Monitoring During Dredging and Backfilling
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Utility Protection
Bridge/Abutment/Bulkhead Protection
Barge Transport of Dredged Material
Hydraulic Off-loading of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Backfill
Backfill Material Purchase and Delivery
Backfill Material Placement
Mudflat Backfill
Mudflat Reconstruction
Natural Shoreline Reconstruction
Natural Shoreline Biostabilization
Riprapped Shoreline Repairs and Replacement
Total Backfill
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$270,360
$1,350,000
$120,000
$355,000
11
11
11
11
11
11
$9,213,600
$16,000,600
$2,973,960
$14,850,000
$1,320,000
$3,905,000
$48,263,160
CY
Ton
SF
LF
CY
CY
Percentage
$25
$200
$100
$4,100
$10
$10
1%
9,681,000
8,000
290,500
6,100
15,635,000
15,635,000
822,584,810
$242,025,000
$1,600,000
$29,050,000
$25,010,000
$156,350,000
$156,350,000
$8,230,000
$618,615,000
CY
CY
CY
CY
CY
LF
SY
$30
$20
$50
$150
$50
$220
$75
1,799,000
1,799,000
712,500
203,500
30,093
5,560
10,000
$53,970,000
$35,980,000
$35,625,000
$30,525,000
$1,504,650
$1,223,200
$750,000
$159,577,850
Percentage
Percentage
10%
25%
830,814,810
1,000,467,900
$1,000,467,900
$83,080,000
$250,120,000
$1,333,667,900
2 of 6
2014
Table 1-3 Cost Estimate: Alternative 2 with DMM Scenario B
Deep Dredging with Backfill, Off-site Disposal
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F2. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Sediment Processing Facility Site Investigation - Geotechnical
Upland Sediment Processing Facility Site Investigation - Chemical
Topographic Survey - Upland Sediment Processing Facility Site
Habitat Survey (upland sediment processing facility site)
Cultural Survey (upland sediment processing facility site)
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G2. Upland Sediment Processing Facility
Mobilization and Demobilization
Mechanical and Electrical
Layout and Documentation Surveys
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Prefabricated Building (Sprung Structure) for Dewatered Sediment Storage
Storage Area - Concrete Slab and Push Walls
Storage Area - Subgrade Material
Storage Area - Filter Fabric
Storage Area - Vapor Emissions Control
Piping
Upfront Storage and Recycle Water Tanks
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
LS
LS
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$870
$42,000
$42,000
$106,130
2,771,016,000
2,771,016,000
27.5
1
3
55
28
30.5
1
1
1
Percentage
Percentage
Day
LF
Acre
LS
LS
LS
CY
LS
SY
SF
SF
CY
CY
SY
Unit
LF
LS
10%
10%
$4,000
$60
$50,000
$100,000
$26,320,000
$1,250,000
$12
$163,000
$30
$160
$40
$600
$40
$2
$5,000
$29
$2,052,000
65,727,400
65,727,400
104
8,800
27.5
1
1
1
151,000
1
74,000
50,000
230,000
9,000
4,300
25,600
20
29,800
1
Cost
$166,260,000
$55,420,000
$14,025,000
$119,000
$144,000
$177,100
$71,680
$26,535
$42,000
$42,000
$106,130
$236,433,445
$6,570,000
$6,570,000
$416,000
$528,000
$1,375,000
$100,000
$26,320,000
$1,250,000
$1,812,000
$163,000
$2,220,000
$8,000,000
$9,200,000
$5,400,000
$172,000
$51,200
$100,000
$864,200
$2,052,000
2014
Table 1-3 Cost Estimate: Alternative 2 with DMM Scenario B
Deep Dredging with Backfill, Off-site Disposal
Component
Loadout Facility
Rail Line Spur/Railcar Storage
Temporary Bunkers for Loadout Facility
Hazardous Material Storage Area
Air Monitoring During Construction
Total Upland Sediment Processing Facility
H2. Equipment Costs
Operating Equipment
Wastewater Treatment Plant
Total Equipment Costs
I2. Processing and Disposal
Mechanical Dewatering Using Filter Presses
Dredged Material Testing for Disposal
Transport Off-site Thermal Treatment
Thermal Treatment and Disposal (Off-site Facility)
Transport to Subtitle C Landfill (Off-site Facility)
Off-site Disposal in Subtitle C Landfill
Decontamination and Disposal of Medium-sized Debris
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill
Reclaimed Sand Processing, Transport, and Beneficial Use
Total Processing and Disposal
J2. Site Decommissioning/Restoration
Total Decommissioning/Restoration
Subtotal Dredged Material Management Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
LS
Mile
Unit
LS
Month
$500,000
$1,000,000
$10,000
$124,000
$5,000
1
5
2
1
12
$500,000
$5,000,000
$20,000
$124,000
$60,000
$78,867,400
LS
LS
$1,067,000
$6,679,000
1
1
$1,067,000
$6,679,000
$7,746,000
CY
5000 CY
Ton
Ton
Ton
Ton
CY
Ton
Ton
$50
$1,088
$240
$400
$130
$100
$200
$230
$50
9,681,000
1,450
740,000
740,000
6,630,000
6,630,000
534,000
55,000
1,600,000
Acre
$30,000
27.5
Percentage
Percentage
10%
25%
2,771,016,000
3,007,449,445
$484,050,000
$1,577,600
$177,600,000
$296,000,000
$861,900,000
$663,000,000
$106,800,000
$12,650,000
$80,000,000
$2,683,577,600
$825,000
$825,000
$3,007,449,445
$277,100,000
$751,860,000
$4,036,409,445
4 of 6
2014
Table 1-3 Cost Estimate: Alternative 2 with DMM Scenario B
Deep Dredging with Backfill, Off-site Disposal
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Wastewater Treatment Plant O&M
Sediment Processing Site O&M
Operations Management/Coordination
Wastewater Testing
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Year
Month
Month
$667,900
$2,746,000
$939,000
$5,430
$5,000
1
1
1
12
12
Percentage
Percentage
10%
25%
4,478,060
4,478,060
$667,900
$2,746,000
$939,000
$65,160
$60,000
$4,478,060
$450,000
$1,120,000
$6,048,060
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
Year
Day
Sample
Sample
Year
Location
Year
$26,900
$8,200
$1,000
$830
$1,400,000
$2,300
$105,000
1
9
37
365
1
17
1
M. Annual Maintenance Activities
Total Annual Maintenance Activities
$26,900
$73,800
$37,000
$302,950
$1,400,000
$39,100
$105,000
$1,984,750
$0
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
Percentage
Percentage
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
10%
25%
1,984,750
1,984,750
$1,984,750
$200,000
$500,000
$2,684,750
5 of 6
2014
Table 1-3 Cost Estimate: Alternative 2 with DMM Scenario B
Deep Dredging with Backfill, Off-site Disposal
Component
N. Periodic Monitoring Activities
Community Outreach
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Location
Year
$95,000
$1,400,000
$2,400
$365,000
1
1
66
1
LF
$200
2,300
Percentage
Percentage
TOTAL PERIODIC O&M
10%
25%
2,478,400
2,478,400
Cost
$95,000
$1,400,000
$158,400
$365,000
$2,018,400
$460,000
$460,000
$2,478,400
$250,000
$620,000
$3,348,400
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-4 Cost Estimate: Alternative 2 with DMM Scenario C
Deep Dredging with Backfill, Local Decontamination and Beneficial Use
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Backfilling Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
New Season Restart
Total Mobilization and Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Percentage
Percentage
LS
Month
Month
LS
Core
Boring
Sample
Sample
Sample
Sample
LS
Day
Day
LS
LS
LS
Sample
Sample
6%
2%
$355,000
$10,000
$48,000
$43,300
$1,810
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
830,814,810
830,814,810
1
12
12
1
5,478
77
43,824
11,280
10,344
231
1
9
9
1
1
1
300
343
EA
EA
LS
EA
EA
Year
$237,000
$237,000
$13,800
$60,000
$237,000
$310,000
2
2
1
1
1
10
Cost
$49,850,000
$16,620,000
$355,000
$120,000
$576,000
$43,300
$9,915,180
$750,750
$68,365,440
$14,438,400
$2,896,320
$286,440
$2,800,000
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$898,660
$169,653,090
$474,000
$474,000
$13,800
$60,000
$237,000
$3,100,000
$4,358,800
2014
Table 1-4 Cost Estimate: Alternative 2 with DMM Scenario C
Deep Dredging with Backfill, Local Decontamination and Beneficial Use
Component
C. Testing and Monitoring During Dredging and Backfilling
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Utility Protection
Bridge/Abutment/Bulkhead Protection
Barge Transport of Dredged Material
Hydraulic Off-loading of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Backfill
Backfill Material Purchase and Delivery
Backfill Material Placement
Mudflat Backfill
Mudflat Reconstruction
Natural Shoreline Reconstruction
Natural Shoreline Biostabilization
Riprapped Shoreline Repairs and Replacement
Total Backfill
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$270,360
$1,350,000
$120,000
$355,000
11
11
11
11
11
11
$9,213,600
$16,000,600
$2,973,960
$14,850,000
$1,320,000
$3,905,000
$48,263,160
CY
Ton
SF
LF
CY
CY
Percentage
$25
$200
$100
$4,100
$10
$10
1%
9,681,000
8,000
290,500
6,100
15,635,000
15,635,000
822,584,810
$242,025,000
$1,600,000
$29,050,000
$25,010,000
$156,350,000
$156,350,000
$8,230,000
$618,615,000
CY
CY
CY
CY
CY
CY
LF
$30
$20
$50
$150
$50
$220
$75
1,799,000
1,799,000
712,500
203,500
30,093
5,560
10,000
$53,970,000
$35,980,000
$35,625,000
$30,525,000
$1,504,650
$1,223,200
$750,000
$159,577,850
Percentage
Percentage
10%
25%
830,814,810
1,000,467,900
$1,000,467,900
$83,080,000
$250,120,000
$1,333,667,900
2 of 6
2014
Table 1-4 Cost Estimate: Alternative 2 with DMM Scenario C
Deep Dredging with Backfill, Local Decontamination and Beneficial Use
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F3. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Sediment Processing Facility Site Investigation - Geotechnical
Upland Sediment Processing Facility Site Investigation - Chemical
Topographic Survey - Upland Sediment Processing Facility Site
Habitat Survey (upland sediment processing facility site)
Cultural Survey (upland sediment processing facility site)
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G3. Upland Sediment Processing Facility
Mobilization and Demobilization
Mechanical and Electrical
Layout and Documentation Survey
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Prefabricated Building (Sprung Structure) for Dewatered Sediment Storage
Storage Area - Concrete Slab and Push Walls
Storage Area - Subgrade Material
Storage Area - Filter Fabric
Storage Area - Vapor Emissions Control
Piping
Upfront Storage and Recycle Water Tanks
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
LS
LS
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$870
$42,000
$42,000
$106,130
2,005,047,300
2,005,047,300
39.5
1
3
79
40
44
1
1
1
Percentage
Percentage
Day
LF
Acre
LS
LS
LS
CY
LS
SY
SF
SF
CY
CY
SY
Unit
LF
LS
10%
10%
$4,000
$60
$50,000
$100,000
$38,620,000
$1,250,000
$12
$219,000
$30
$160
$40
$600
$40
$2
$5,000
$29
$2,085,500
83,763,700
83,763,700
104
10,500
40
1
1
1
218,000
1
81,000
50,000
351,000
14,000
6,600
39,100
30
44,000
1
Cost
$120,300,000
$40,100,000
$20,145,000
$119,000
$144,000
$254,380
$102,400
$38,280
$42,000
$42,000
$106,130
$181,393,190
$8,380,000
$8,380,000
$416,000
$630,000
$1,975,000
$100,000
$38,620,000
$1,250,000
$2,616,000
$219,000
$2,430,000
$8,000,000
$14,040,000
$8,400,000
$264,000
$78,200
$150,000
$1,276,000
$2,085,500
2014
Table 1-4 Cost Estimate: Alternative 2 with DMM Scenario C
Deep Dredging with Backfill, Local Decontamination and Beneficial Use
Component
Loadout facility
Transfer Vehicle Storage
Temporary Bunkers for Loadout Facility
Hazardous Material Processing and Storage Area
Air Monitoring During Construction
Total Upland Sediment Processing Facility
H3. Equipment Costs
Operating Equipment
Wastewater Treatment Plant
Total Equipment Costs
I3. Local Decontamination
Mechanical Dewatering Using Filter Presses
Dredged Material Testing for Disposal
Thermal Treatment (On-Site/Local Facility)
Sediment Washing
Sediment Amendment
Decontamination and Disposal of Medium-sized Debris
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill
Reclaimed Sand Processing, Transport, and Beneficial Use
Total Local Decontamination
J3. Site Decommissioning/Restoration
Total Decommissioning/Restoration
Subtotal Dredged Material Management Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
LS
SY
Unit
LS
Month
$500,000
$30
$10,000
$124,000
$5,000
1
17,000
2
1
12
LS
LS
$1,067,000
$8,194,000
1
1
CY
5000 CY
Tons
CY
Ton
CY
Ton
Ton
$50
$1,088
$370
$150
$80
$200
$230
$50
9,681,000
1,450
740,000
6,160,000
140,000
534,000
55,000
1,600,000
Acre
$30,000
39.5
Percentage
Percentage
10%
25%
2,005,047,300
2,186,440,490
Cost
$500,000
$510,000
$20,000
$124,000
$60,000
$100,523,700
$1,067,000
$8,194,000
$9,261,000
$484,050,000
$1,577,600
$273,800,000
$924,000,000
$11,200,000
$106,800,000
$12,650,000
$80,000,000
$1,894,077,600
$1,185,000
$1,185,000
$2,186,440,490
$200,500,000
$546,610,000
$2,933,550,490
4 of 6
2014
Table 1-4 Cost Estimate: Alternative 2 with DMM Scenario C
Deep Dredging with Backfill, Local Decontamination and Beneficial Use
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Wastewater Treatment Plant O&M
Sediment Processing Site O&M
Operations Management/Coordination
Wastewater Testing
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Year
Month
Month
$819,400
$3,201,000
$939,000
$5,430
$5,000
1
1
1
12
12
$819,400
$3,201,000
$939,000
$65,160
$60,000
Percentage
Percentage
10%
25%
5,084,560
5,084,560
$5,084,560
$510,000
$1,270,000
$6,864,560
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
Year
Day
Sample
Sample
Year
Location
Year
$26,900
$8,200
$1,000
$830
$1,400,000
$2,300
$105,000
1
9
37
365
1
17
1
M. Annual Maintenance Activities
Total Annual Maintenance Activities
$26,900
$73,800
$37,000
$302,950
$1,400,000
$39,100
$105,000
$1,984,750
$0
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
Percentage
Percentage
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
10%
25%
1,984,750
1,984,750
$1,984,750
$200,000
$500,000
$2,684,750
5 of 6
2014
Table 1-4 Cost Estimate: Alternative 2 with DMM Scenario C
Deep Dredging with Backfill, Local Decontamination and Beneficial Use
Component
N. Periodic Monitoring Activities
Community Outreach
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Location
Year
$95,000
$1,400,000
$2,400
$365,000
1
1
66
1
LF
$200
2,300
Percentage
Percentage
TOTAL PERIODIC O&M
10%
25%
2,478,400
2,478,400
Cost
$95,000
$1,400,000
$158,400
$365,000
$2,018,400
$460,000
$460,000
$2,478,400
$250,000
$620,000
$3,348,400
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-5 Cost Estimate: Alternative 3 with DMM Scenario A
Capping with Dredging for Flooding and Navigation, Confined Aquatic Disposal
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection RM0 to RM 2.2
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection RM2.2 to RM8.3
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Pore Water Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Cap Erosion Modeling for Armor Placement Design
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Capping Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$28,900
428,837,950
428,837,950
1
12
12
1
$25,730,000
$8,580,000
$355,000
$120,000
$576,000
$28,900
Core
$1,250
2,739
$3,423,750
Core
Boring
Sample
Sample
Sample
Sample
LS
Sample
Day
Day
LS
LS
LS
Sample
Sample
LS
$250
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$1,040
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
$18,000
2,739
77
30,129
7,755
7,106
231
1
274
9
9
1
1
1
300
354
1
$684,750
$750,750
$47,001,240
$9,926,400
$1,989,680
$286,440
$2,800,000
$284,960
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$927,480
$18,000
$105,220,950
EA
EA
LS
EA
EA
$237,000
$237,000
$13,800
$60,000
$237,000
2
2
1
1
1
$474,000
$474,000
$13,800
$60,000
$237,000
2014
Table 1-5 Cost Estimate: Alternative 3 with DMM Scenario A
Capping with Dredging for Flooding and Navigation, Confined Aquatic Disposal
Component
New Season Restart
Total Mobilization and Demobilization
C. Testing and Monitoring During Dredging and Capping
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling/Capping
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Barge Transport of Dredged Material
Shallow Water Sediments - Double Handling
Controls for Quality of Life Impacts
Total Dredging
E. Backfill and/or Engineered Cap
Backfill/Engineered Cap Material Purchase and Delivery
Backfill Material Placement
Engineered Cap Material Placement
Armor Material Purchase and Delivery
Armor Material Placement
Confirmation Coring
Sediment Recontamination Monitoring
Mudflat Engineered Cap
Mudflat Reconstruction
Riprapped Shoreline Repairs and Replacement
Total Backfill and/or Engineered Cap
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
$310,000
4
$1,240,000
$2,498,800
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$594,780
$1,350,000
$120,000
$355,000
5
5
5
5
5
5
$4,188,000
$7,273,000
$2,973,900
$6,750,000
$600,000
$1,775,000
$23,559,900
CY
Ton
CY
CY
Percentage
$25
$30
$10
$5
1%
4,304,000
6,000
6,676,000
203,500
424,587,950
$107,600,000
$180,000
$66,760,000
$1,017,500
$4,250,000
$179,807,500
CY
CY
CY
CY
CY
Core
Sample
CY
CY
SY
$30
$20
$30
$30
$30
$270
$1,560
$80
$150
$75
2,723,000
141,000
2,582,000
192,000
192,000
465
1,395
203,500
203,500
5,000
$81,690,000
$2,820,000
$77,460,000
$5,760,000
$5,760,000
$125,550
$2,176,200
$16,280,000
$30,525,000
$375,000
$222,971,750
Percentage
Percentage
10%
25%
428,837,950
534,058,900
$534,058,900
$42,880,000
$133,510,000
$710,448,900
2 of 6
2014
Table 1-5 Cost Estimate: Alternative 3 with DMM Scenario A
Capping with Dredging for Flooding and Navigation, Confined Aquatic Disposal
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F1. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Support Facility Site Investigation - Geotechnical
Upland Support Facility Site Investigation - Chemical
Topographic Survey - Upland Support Facility Site
Pre-Design Investigation of CAD Site - Chemical Sample Collection
Pre-Design Investigation of CAD Site - Geotechnical Sample Collection
Pre-Design Investigation of CAD Site - Chemical Analysis
Pre-Design Investigation of CAD Site - Geotechnical Analysis
Pre-Design Investigation of CAD Site - HARS Disposal Determination
Habitat Survey (upland support facility site)
Cultural Survey (upland support facility site)
Elutriate Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G1. CAD Excavation
Dredge Mobilization/Demobilization
Monitoring Equipment and Debris Removal Mobilization/Demobilization
Large Debris Removal
Contaminated Sediment Dredging and Disposal (First Cell)
Contaminated Sediment Testing for Disposal (First Cell)
Contaminated Sediment Dredge and Disposal (Subsequent Cells)
Clay Dredging/Transport/Disposal at HARS
Containment System Installation
Silt Curtain at CAD Entrance Channel
Air Monitoring During Construction
Testing and Monitoring
Total CAD Excavation
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
Core
Boring
Sample
Sample
LS
LS
LS
Sample
Day
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$1,330
$1,650
$9,700
$1,850
$1,240
$200,000
$5,000
$5,000
$1,040
$8,200
$76,000
357,533,120
357,533,120
5
1
2
10
5
5.5
111
15
111
45
1
1
1
11
1
1
$21,450,000
$7,150,000
$2,550,000
$119,000
$96,000
$32,200
$12,800
$7,315
$183,150
$145,500
$205,350
$55,800
$200,000
$5,000
$5,000
$11,440
$8,200
$76,000
$32,312,755
Vessel
Cell
Ton
CY
Sample
CY
CY
SF
SF
Month
Month
$237,000
$72,800
$300
$200
$1,090
$35
$25
$235
$100
$5,000
$294,020
8
2
500
278,000
56
278,000
5,062,000
220,000
7,500
24
24
$1,896,000
$145,600
$150,000
$55,600,000
$61,040
$9,730,000
$126,550,000
$51,700,000
$750,000
$120,000
$7,056,480
$253,759,120
2014
Table 1-5 Cost Estimate: Alternative 3 with DMM Scenario A
Capping with Dredging for Flooding and Navigation, Confined Aquatic Disposal
Component
H1. Upland Support Facility
Mobilization/Demobilization
Layout and Documentation Survey
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Wastewater Treatment System for Contact Water
Total Upland Support Facility
I1. CAD Closure
Cap Material Purchase and Delivery
Engineered Cap Material Placement
Confirmation Coring
Remove Containment System
Bathymetric Surveys
Additional Habitat Mitigation
Total CAD Closure
J1. Site Decommissioning/Restoration
Total Site Decommissioning/Restoration
Subtotal DMM Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Percentage
Day
LF
Acre
LS
SF
LS
CY
SF
SY
SF
Month
10%
$4,000
$60
$50,000
$20,000
$120
$125,000
$12
$18
$30
$160
$10,000
5,455,800
10
1,940
5
1
10,150
1
8,100
3,900
17,300
15,000
60
$550,000
$40,000
$116,400
$250,000
$20,000
$1,218,000
$125,000
$97,200
$70,200
$519,000
$2,400,000
$600,000
$6,005,800
CY
CY
Core
SF
Day
LS
$30
$30
$1,830
$36
$8,200
$63,770,000
420,000
420,000
380
220,000
4
1
$12,600,000
$12,600,000
$695,400
$7,920,000
$32,800
$63,770,000
$97,618,200
Acre
$30,000
5
Percentage
Percentage
10%
25%
357,533,120
389,845,875
$150,000
$150,000
$389,845,875
$35,750,000
$97,460,000
$523,055,875
4 of 6
2014
Table 1-5 Cost Estimate: Alternative 3 with DMM Scenario A
Capping with Dredging for Flooding and Navigation, Confined Aquatic Disposal
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Operational Testing
Upland Support Facility O&M
Operations Management/Coordination
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Month
Year
Year
Month
$6,820
$1,222,000
$939,000
$5,000
12
1
1
12
$81,840
$1,222,000
$939,000
$60,000
Percentage
Percentage
10%
25%
2,302,840
2,302,840
$2,302,840
$230,000
$580,000
$3,112,840
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Ice Scour Evaluation of Cap along Shoreline
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
Year
Year
Day
Sample
Sample
Year
Location
Year
$95,000
$26,900
$8,200
$1,000
$830
$1,540,000
$2,300
$105,000
1
1
10
54
1,870
1
25
1
$95,000
$26,900
$82,000
$54,000
$1,552,100
$1,540,000
$57,500
$105,000
$3,512,500
Year
LS
CY
$54,000
$21,000
$50
1
1
6,100
$54,000
$21,000
$305,000
$380,000
Percentage
Percentage
10%
25%
3,892,500
3,892,500
$3,892,500
$390,000
$970,000
$5,252,500
5 of 6
2014
Table 1-5 Cost Estimate: Alternative 3 with DMM Scenario A
Capping with Dredging for Flooding and Navigation, Confined Aquatic Disposal
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL PERIODIC O&M
Unit
Unit Cost
# of Units
Year
Location
Year
$1,400,000
$2,300
$365,000
1
78
1
$1,400,000
$179,400
$365,000
$1,944,400
CY
LF
$50
$200
151,000
2,300
$7,550,000
$460,000
$8,010,000
Percentage
Percentage
10%
25%
9,954,400
9,954,400
Cost
$9,954,400
$1,000,000
$2,490,000
$13,444,400
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-6 Cost Estimate: Alternative 3 with DMM Scenario B
Capping with Dredging for Flooding and Navigation, Off-site Disposal
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection RM0 to RM 2.2
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection RM2.2 to RM8.3
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Pore Water Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Cap Erosion Modeling for Armor Placement Design
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Capping Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$28,900
497,287,950
497,287,950
1
12
12
1
$29,840,000
$9,950,000
$355,000
$120,000
$576,000
$28,900
Core
$1,250
2,739
$3,423,750
Core
Boring
Sample
Sample
Sample
Sample
LS
Sample
Day
Day
LS
LS
LS
Sample
Sample
LS
$250
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$1,040
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
$18,000
2,739
77
30,129
7,755
7,106
231
1
274
9
9
1
1
1
300
354
1
$684,750
$750,750
$47,001,240
$9,926,400
$1,989,680
$286,440
$2,800,000
$284,960
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$927,480
$18,000
$110,700,950
EA
EA
LS
EA
EA
$237,000
$237,000
$13,800
$60,000
$237,000
2
2
1
1
1
$474,000
$474,000
$13,800
$60,000
$237,000
2014
Table 1-6 Cost Estimate: Alternative 3 with DMM Scenario B
Capping with Dredging for Flooding and Navigation, Off-site Disposal
Component
New Season Restart
Total Mobilization and Demobilization
C. Testing and Monitoring During Dredging and Capping
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling/Capping
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Barge Transport of Dredged Material
Shallow Water Sediments - Double Handling
Hydraulic Off-loading of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Backfill and/or Engineered Cap
Backfill/Engineered Cap Material Purchase and Delivery
Backfill Material Placement
Engineered Cap Material Placement
Armor Material Purchase and Delivery
Armor Material Placement
Confirmation Coring
Sediment Recontamination Monitoring
Mudflat Engineered Cap
Mudflat Reconstruction
Riprapped Shoreline Repairs and Replacement
Total Backfill and/or Engineered Cap
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
$310,000
4
$1,240,000
$2,498,800
EA
EA
EA
Year
Year
EA
$837,600
$1,454,600
$594,780
$1,350,000
$120,000
$355,000
5
5
5
5
5
5
$4,188,000
$7,273,000
$2,973,900
$6,750,000
$600,000
$1,775,000
$23,559,900
CY
Ton
CY
CY
CY
Percentage
$25
$200
$10
$5
$10
1%
4,304,000
6,000
6,676,000
203,500
6,676,000
492,367,950
$107,600,000
$1,200,000
$66,760,000
$1,017,500
$66,760,000
$4,920,000
$248,257,500
CY
CY
CY
CY
CY
Core
Sample
CY
CY
SY
$30
$20
$30
$30
$30
$270
$1,560
$80
$150
$75
2,723,000
141,000
2,582,000
192,000
192,000
465
1,395
203,500
203,500
5,000
$81,690,000
$2,820,000
$77,460,000
$5,760,000
$5,760,000
$125,550
$2,176,200
$16,280,000
$30,525,000
$375,000
$222,971,750
Percentage
Percentage
10%
25%
497,287,950
607,988,900
$607,988,900
$49,730,000
$152,000,000
$809,718,900
2 of 6
2014
Table 1-6 Cost Estimate: Alternative 3 with DMM Scenario B
Capping with Dredging for Flooding and Navigation, Off-site Disposal
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F2. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Sediment Processing Facility Site Investigation - Geotechnical
Upland Sediment Processing Facility Site Investigation - Chemical
Topographic Survey - Upland Sediment Processing Facility Site
Habitat Survey (upland sediment processing facility site)
Cultural Survey (upland sediment processing facility site)
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G2. Upland Sediment Processing Facility
Mobilization and Demobilization
Mechanical and Electrical
Layout and Documentation Surveys
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Prefabricated Building (Sprung Structure) for Dewatered Sediment Storage
Storage Area - Concrete Slab and Push Walls
Storage Area - Subgrade Material
Storage Area - Filter Fabric
Storage Area - Vapor Emissions Control
Piping
Upfront Storage and Recycle Water Tanks
Loadout Facility
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
LS
LS
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$870
$42,000
$42,000
$106,130
1,061,558,740
1,061,558,740
26
1
3
52
26
28.5
1
1
1
$63,690,000
$21,230,000
$13,260,000
$119,000
$144,000
$167,440
$66,560
$24,795
$42,000
$42,000
$106,130
$98,891,925
Percentage
Percentage
Day
LF
Acre
LS
LS
LS
CY
LS
SY
SF
SF
CY
CY
SY
Unit
LF
LS
LS
10%
10%
$4,000
$60
$50,000
$100,000
$25,650,000
$1,250,000
$12
$151,000
$30
$160
$40
$600
$40
$2
$5,000
$29
$707,000
$500,000
60,947,100
60,947,100
104
8,500
26
1
1
1
144,000
1
73,000
50,000
185,000
8,000
3,400
20,600
16
28,100
1
1
$6,090,000
$6,090,000
$416,000
$510,000
$1,300,000
$100,000
$25,650,000
$1,250,000
$1,728,000
$151,000
$2,190,000
$8,000,000
$7,400,000
$4,800,000
$136,000
$41,200
$80,000
$814,900
$707,000
$500,000
2014
Table 1-6 Cost Estimate: Alternative 3 with DMM Scenario B
Capping with Dredging for Flooding and Navigation, Off-site Disposal
Component
Rail Line Spur/Railcar Storage
Temporary Bunkers for Loadout Facility
Hazardous Material Storage Area
Air Monitoring During Construction
Total Upland Sediment Processing Facility
H2. Equipment Costs
Operating Equipment
Wastewater Treatment Plant
Total Equipment Costs
I2. Processing and Disposal
Mechanical Dewatering Using Filter Presses
Dredged Material Testing for Disposal
Transport Off-site Thermal Treatment
Thermal Treatment and Disposal (Off-site Facility)
Transport to Subtitle C Landfill (Off-site Facility)
Off-site Disposal in Subtitle C Landfill
Decontamination and Disposal of Medium-sized Debris
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill
Reclaimed Sand Processing, Transport, and Beneficial Use
Total Processing and Disposal
J2. Site Decommissioning/Restoration
Total Decommissioning/Restoration
Subtotal Dredged Material Management Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Mile
Unit
LS
Month
$1,000,000
$10,000
$93,000
$5,000
5
2
1
12
$5,000,000
$20,000
$93,000
$60,000
$73,127,100
LS
LS
$1,067,000
$6,688,000
1
1
$1,067,000
$6,688,000
$7,755,000
CY
5000 CY
Ton
Ton
Ton
Ton
CY
Ton
Ton
$50
$1,088
$240
$400
$130
$100
$200
$230
$50
4,304,000
530
180,000
180,000
2,460,000
2,460,000
238,000
24,000
600,000
Acre
$30,000
26
Percentage
Percentage
10%
25%
1,061,558,740
1,160,450,665
$215,200,000
$576,640
$43,200,000
$72,000,000
$319,800,000
$246,000,000
$47,600,000
$5,520,000
$30,000,000
$979,896,640
$780,000
$780,000
$1,160,450,665
$106,160,000
$290,110,000
$1,556,720,665
4 of 6
2014
Table 1-6 Cost Estimate: Alternative 3 with DMM Scenario B
Capping with Dredging for Flooding and Navigation, Off-site Disposal
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Wastewater Treatment Plant O&M
Sediment Processing Site O&M
Operations Management/Coordination
Wastewater Testing
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Year
Month
Month
$668,800
$2,737,000
$939,000
$5,430
$5,000
1
1
1
12
12
$668,800
$2,737,000
$939,000
$65,160
$60,000
Percentage
Percentage
10%
25%
4,469,960
4,469,960
$4,469,960
$450,000
$1,120,000
$6,039,960
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Ice Scour Evaluation of Cap along Shoreline
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
LS
EA
Day
Sample
Sample
LS
Location
EA
$95,000
$26,900
$8,200
$1,000
$830
$1,400,000
$2,300
$105,000
1
1
9
37
1,826
1
17
1
$95,000
$26,900
$73,800
$37,000
$1,515,580
$1,400,000
$39,100
$105,000
$3,292,380
EA
LS
CY
$54,000
$21,000
$50
1
1
5,200
$54,000
$21,000
$260,000
$335,000
Percentage
Percentage
10%
25%
3,627,380
3,627,380
$3,627,380
$360,000
$910,000
$4,897,380
5 of 6
2014
Table 1-6 Cost Estimate: Alternative 3 with DMM Scenario B
Capping with Dredging for Flooding and Navigation, Off-site Disposal
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL PERIODIC O&M
Unit
Unit Cost
# of Units
Cost
Year
Location
Year
$1,400,000
$2,400
$365,000
1
66
1
$1,400,000
$158,400
$365,000
$1,923,400
CY
LF
$50
$200
130,000
2,300
$6,500,000
$460,000
$6,960,000
Percentage
Percentage
10%
25%
8,883,400
8,883,400
$8,883,400
$890,000
$2,220,000
$11,993,400
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-7 Cost Estimate: Alternative 3 with DMM Scenario C
Capping with Dredging for Flooding and Navigation, Local Decontamination and Beneficial Use
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection RM0 to RM 2.2
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection RM2.2 to RM8.3
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Pore Water Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Cap Erosion Modeling for Armor Placement Design
Total Pre-Construction Activities
B. Mobilizationa nd Demobilization
Dredge Equipment Mobilization/Demobilization
Capping Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$28,900
497,047,950
497,047,950
1
12
12
1
$29,820,000
$9,940,000
$355,000
$120,000
$576,000
$28,900
Core
$1,250
2,739
$3,423,750
Core
Boring
Sample
Sample
Sample
Sample
LS
Sample
Day
Day
LS
LS
LS
Sample
Sample
LS
$250
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$1,040
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
$18,000
2,739
77
30,129
7,755
7,106
231
1
274
9
9
1
1
1
300
354
1
$684,750
$750,750
$47,001,240
$9,926,400
$1,989,680
$286,440
$2,800,000
$284,960
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$927,480
$18,000
$110,670,950
EA
EA
LS
EA
EA
$237,000
$237,000
$13,800
$60,000
$237,000
2
2
1
1
1
$474,000
$474,000
$13,800
$60,000
$237,000
2014
Table 1-7 Cost Estimate: Alternative 3 with DMM Scenario C
Capping with Dredging for Flooding and Navigation, Local Decontamination and Beneficial Use
Component
New Season Restart
Total Mobilization and Demobilization
C. Testing and Monitoring During Dredging and Capping
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling/Capping
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Barge Transport of Dredged Material
Shallow Water Sediments - Double Handling
Hydraulic Off-loading of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Backfill and/or Engineered Cap
Backfill/Engineered Cap Material Purchase and Delivery
Backfill Material Placement
Engineered Cap Material Placement
Armor Material Purchase and Delivery
Armor Material Placement
Confirmation Coring
Sediment Recontamination Monitoring
Mudflat Engineered Cap
Mudflat Reconstruction
Riprapped Shoreline Repairs and Replacement
Total Backfill and/or Engineered Cap
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
$310,000
4
$1,240,000
$2,498,800
EA
EA
EA
Year
Year
EA
$837,600
$1,454,600
$594,780
$1,350,000
$120,000
$355,000
5
5
5
5
3
5
$4,188,000
$7,273,000
$2,973,900
$6,750,000
$360,000
$1,775,000
$23,319,900
CY
Ton
CY
CY
CY
Percentage
$25
$200
$10
$5
$10
1%
4,304,000
6,000
6,676,000
203,500
6,676,000
492,127,950
$107,600,000
$1,200,000
$66,760,000
$1,017,500
$66,760,000
$4,920,000
$248,257,500
CY
CY
CY
CY
CY
Core
Sample
CY
CY
SY
$30
$20
$30
$30
$30
$270
$1,560
$80
$150
$75
2,723,000
141,000
2,582,000
192,000
192,000
465
1,395
203,500
203,500
5,000
$81,690,000
$2,820,000
$77,460,000
$5,760,000
$5,760,000
$125,550
$2,176,200
$16,280,000
$30,525,000
$375,000
$222,971,750
Percentage
Percentage
10%
25%
497,047,950
607,718,900
$607,718,900
$49,700,000
$151,930,000
$809,348,900
2 of 6
2014
Table 1-7 Cost Estimate: Alternative 3 with DMM Scenario C
Capping with Dredging for Flooding and Navigation, Local Decontamination and Beneficial Use
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F3. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Sediment Processing Facility Site Investigation - Geotechnical
Upland Sediment Processing Facility Site Investigation - Chemical
Topographic Survey - Upland Sediment Processing Facility Site
Habitat Survey (upland sediment processing facility site)
Cultural Survey (upland sediment processing facility site)
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G3. Upland Sediment Processing Facility
Mobilization and Demobilization
Mechanical and Electrical
Layout and Documentation Survey
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Prefabricated Building (Sprung Structure) for Dewatered Sediment Storage
Storage Area - Concrete Slab and Push Walls
Storage Area - Subgrade Material
Storage Area - Filter Fabric
Storage Area - Vapor Emissions Control
Piping
Upfront Storage and Recycle Water Tanks
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
LS
LS
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$870
$42,000
$42,000
$106,130
901,690,140
901,690,140
36
1
3
72
36
40
1
1
1
$54,100,000
$18,030,000
$18,360,000
$119,000
$144,000
$231,840
$92,160
$34,800
$42,000
$42,000
$106,130
$91,301,930
Percentage
Percentage
Day
LF
Acre
LS
LS
LS
CY
LS
SY
SF
SF
CY
CY
SY
Unit
LF
LS
10%
10%
$4,000
$60
$50,000
$100,000
$37,620,000
$1,250,000
$12
$168,000
$30
$160
$40
$600
$40
$2
$5,000
$29
$740,500
75,860,500
75,860,500
104
10,000
36
1
1
1
201,000
1
73,000
50,000
283,000
11,000
5,200
31,500
24
40,000
1
$7,590,000
$7,590,000
$416,000
$600,000
$1,800,000
$100,000
$37,620,000
$1,250,000
$2,412,000
$168,000
$2,190,000
$8,000,000
$11,320,000
$6,600,000
$208,000
$63,000
$120,000
$1,160,000
$740,500
2014
Table 1-7 Cost Estimate: Alternative 3 with DMM Scenario C
Capping with Dredging for Flooding and Navigation, Local Decontamination and Beneficial Use
Component
Loadout facility
Transfer Vehicle Storage
Temporary Bunkers for Loadout Facility
Hazardous Material Processing and Storage Area
Air Monitoring During Construction
Total Upland Sediment Processing Facility
H3. Equipment Costs
Operating Equipment
Wastewater Treatment Plant
Total Equipment Costs
I3. Local Decontamination
Mechanical Dewatering Using Filter Presses
Dredged Material Testing for Disposal
Thermal Treatment (On-Site/Local Facility)
Sediment Washing
Sediment Amendment
Decontamination and Disposal of Medium-sized Debris
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill
Reclaimed Sand Processing, Transport, and Beneficial Use
Total Local Decontamination
J3. Site Decommissioning/Restoration
Total Decommissioning/Restoration
Subtotal Dredged Material Management Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
LS
SY
Unit
LS
Month
$500,000
$30
$10,000
$93,000
$5,000
1
14,000
2
1
12
$500,000
$420,000
$20,000
$93,000
$60,000
$91,040,500
LS
LS
$1,067,000
$7,906,000
1
1
$1,067,000
$7,906,000
$8,973,000
CY
5000 CY
Tons
CY
Ton
CY
Ton
Ton
$50
$1,088
$370
$150
$80
$200
$230
$50
4,304,000
530
180,000
2,890,000
20,000
238,000
24,000
600,000
Acre
$30,000
36
Percentage
Percentage
10%
25%
901,690,140
992,992,070
$215,200,000
$576,640
$66,600,000
$433,500,000
$1,600,000
$47,600,000
$5,520,000
$30,000,000
$800,596,640
$1,080,000
$1,080,000
$992,992,070
$90,170,000
$248,250,000
$1,331,412,070
4 of 6
2014
Table 1-7 Cost Estimate: Alternative 3 with DMM Scenario C
Capping with Dredging for Flooding and Navigation, Local Decontamination and Beneficial Use
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Wastewater Treatment Plant O&M
Sediment Processing Site O&M
Operations Management/Coordination
Wastewater Testing
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Year
Month
Month
$790,600
$3,162,000
$939,000
$5,430
$5,000
1
1
1
12
12
$790,600
$3,162,000
$939,000
$65,160
$60,000
Percentage
Percentage
10%
25%
5,016,760
5,016,760
$5,016,760
$500,000
$1,250,000
$6,766,760
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Ice Scour Evaluation of Cap along Shoreline
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
LS
EA
Day
Sample
Sample
LS
Location
EA
$95,000
$26,900
$8,200
$1,000
$830
$1,400,000
$2,300
$105,000
1
1
9
37
1,826
1
17
1
$95,000
$26,900
$73,800
$37,000
$1,515,580
$1,400,000
$39,100
$105,000
$3,292,380
EA
EA
CY
$54,000
$21,000
$50
1
1
5,200
$54,000
$21,000
$260,000
$335,000
Percentage
Percentage
10%
25%
3,627,380
3,627,380
$3,627,380
$360,000
$910,000
$4,897,380
5 of 6
2014
Table 1-7 Cost Estimate: Alternative 3 with DMM Scenario C
Capping with Dredging for Flooding and Navigation, Local Decontamination and Beneficial Use
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL PERIODIC O&M
Unit
Unit Cost
# of Units
Cost
Year
Location
Year
$1,400,000
$2,400
$365,000
1
66
1
$1,400,000
$158,400
$365,000
$1,923,400
CY
LF
$50
$200
130,000
2,300
$6,500,000
$460,000
$6,960,000
Percentage
Percentage
10%
25%
8,883,400
8,883,400
$8,883,400
$890,000
$2,220,000
$11,993,400
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-8 Cost Estimate: Alternative 4 with DMM Scenario A
Focused Capping with Dredging for Flooding, Confined Aquatic Disposal
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Pore Water Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Cap Erosion Modeling for Armor Placement Design
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Capping Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
New Season Restart
Total Mobilization and Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$25,400
140,371,120
140,371,120
1
12
12
1
Core
Boring
Sample
Sample
Sample
Sample
LS
Sample
Day
Day
LS
LS
LS
Sample
Sample
LS
$250
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$1,040
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
$18,000
1,882
33
5,646
1,482
1,359
99
1
188
9
9
1
1
1
300
135
1
$470,500
$321,750
$8,807,760
$1,896,960
$380,520
$122,760
$2,800,000
$195,520
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$353,700
$18,000
$29,411,470
EA
EA
LS
EA
EA
Year
$237,000
$237,000
$13,800
$60,000
$237,000
$310,000
2
2
1
1
1
1
$474,000
$474,000
$13,800
$60,000
$237,000
$310,000
$1,568,800
$8,420,000
$2,810,000
$355,000
$120,000
$576,000
$25,400
2014
Table 1-8 Cost Estimate: Alternative 4 with DMM Scenario A
Focused Capping with Dredging for Flooding, Confined Aquatic Disposal
Component
C. Testing and Monitoring During Dredging and Backfilling/Capping
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling/Capping
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Barge Transport of Dredged Material
Shallow Water Sediments - Double Handling
Controls for Quality of Life Impacts
Total Dredging
E. Engineered Cap
Engineered Cap Material Purchase and Delivery
Engineered Cap Material Placement
Armor Material Purchase and Delivery
Armor Material Placement
Confirmation Coring
Sediment Recontamination Monitoring
Mudflat Engineered Cap
Mudflat Reconstruction
Riprapped Shoreline Repairs and Replacement
Total Engineered Cap
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$540,710
$1,350,000
$120,000
$355,000
2
2
2
2
2
2
$1,675,200
$2,909,200
$1,081,420
$2,700,000
$240,000
$710,000
$9,315,820
CY
Ton
CY
CY
Percentage
$25
$30
$10
$5
1%
1,021,000
2,000
1,584,000
103,500
138,981,120
$25,525,000
$60,000
$15,840,000
$517,500
$1,390,000
$43,332,500
CY
CY
CY
CY
Location
Sample
CY
CY
SY
$30
$30
$30
$30
$270
$1,560
$80
$150
$75
930,000
930,000
92,000
92,000
170
510
103,500
103,500
2,500
$27,900,000
$27,900,000
$2,760,000
$2,760,000
$45,900
$795,600
$8,280,000
$15,525,000
$187,500
$86,154,000
Percentage
Percentage
10%
25%
140,371,120
169,782,590
$169,782,590
$14,040,000
$42,450,000
$226,272,590
2 of 6
2014
Table 1-8 Cost Estimate: Alternative 4 with DMM Scenario A
Focused Capping with Dredging for Flooding, Confined Aquatic Disposal
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F1. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Support Facility Site Investigation - Geotechnical
Upland Support Facility Site Investigation - Chemical
Topographic Survey - Upland Support Facility Site
Pre-Design Investigation of CAD Site - Chemical Sample Collection
Pre-Design Investigation of CAD Site - Geotechnical Sample Collection
Pre-Design Investigation of CAD Site - Chemical Analysis
Pre-Design Investigation of CAD Site - Geotechnical Analysis
Pre-Design Investigation of CAD Site - HARS Disposal Determination
Habitat Survey (upland support facility site)
Cultural Survey (upland support facility site)
Elutriate Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G1. CAD Excavation
Dredge Mobilization/Demobilization
Monitoring Equipment and Debris Removal Mobilization/Demobilization
Large Debris Removal
Contaminated Sediment Dredging and Disposal
Contaminated Sediment Testing for Disposal
Clay Dredging/Transport/Disposal at HARS
Containment System Installation
Silt Curtain at CAD Entrance Channel
Air Monitoring During Construction
Testing and Monitoring
Total CAD Excavation
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
Core
Boring
Sample
Sample
LS
LS
LS
Sample
Day
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$1,330
$1,650
$9,700
$1,850
$1,240
$200,000
$5,000
$5,000
$1,040
$8,200
$76,000
116,012,940
116,012,940
5
1
2
10
5
5.5
30
5
30
15
1
1
1
5
1
1
$6,960,000
$2,320,000
$2,550,000
$119,000
$96,000
$32,200
$12,800
$7,315
$48,840
$48,500
$54,760
$18,600
$200,000
$5,000
$5,000
$5,200
$8,200
$76,000
$12,567,415
EA
EA
Ton
CY
Sample
CY
SF
LF
Month
Month
$237,000
$72,800
$300
$200
$1,090
$25
$235
$100
$5,000
$294,020
4
1
200
148,000
30
1,121,000
107,500
3,750
12
12
$948,000
$72,800
$60,000
$29,600,000
$32,700
$28,025,000
$25,262,500
$375,000
$60,000
$3,528,240
$87,964,240
2014
Table 1-8 Cost Estimate: Alternative 4 with DMM Scenario A
Focused Capping with Dredging for Flooding, Confined Aquatic Disposal
Component
H1. Upland Support Facility
Mobilization/Demobilization
Layout and Documentation Survey
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Wastewater Treatment System for Contact Water
Total Upland Support Facility
I1. CAD Closure
Cap Material Purchase and Delivery
Engineered Cap Material Placement
Confirmation Coring
Remove Containment System
Bathymetric Surveys
Additional Habitat Mitigation
Total CAD Closure
J1. Site Decommissioning/Restoration
Total Site Decommissioning/Restoration
Subtotal DMM Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Percentage
Day
LF
Acre
LS
SF
LS
CY
SF
SY
SF
Month
10%
$4,000
$60
$50,000
$20,000
$120
$125,000
$12
$18
$30
$160
$10,000
5,005,800
10
1,940
5
1
10,150
1
8,100
3,900
17,300
15,000
15
$500,000
$40,000
$116,400
$250,000
$20,000
$1,218,000
$125,000
$97,200
$70,200
$519,000
$2,400,000
$150,000
$5,505,800
CY
CY
Core
SF
Day
LS
$30
$30
$1,830
$36
$8,200
$12,950,000
90,000
90,000
90
107,500
1
1
$2,700,000
$2,700,000
$164,700
$3,870,000
$8,200
$12,950,000
$22,392,900
Acre
$30,000
5
Percentage
Percentage
10%
25%
116,012,940
128,580,355
$150,000
$150,000
$128,580,355
$11,600,000
$32,150,000
$172,330,355
4 of 6
2014
Table 1-8 Cost Estimate: Alternative 4 with DMM Scenario A
Focused Capping with Dredging for Flooding, Confined Aquatic Disposal
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Operational Testing
Upland Support Facility O&M
Operations Management/Coordination
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Month
Year
Year
Month
$6,820
$1,222,000
$939,000
$5,000
12
1
1
12
$81,840
$1,222,000
$939,000
$60,000
Percentage
Percentage
10%
25%
2,302,840
2,302,840
$2,302,840
$230,000
$580,000
$3,112,840
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Ice Scour Evaluation of Cap along Shoreline
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
Year
Year
Day
Sample
Sample
Year
Location
Year
$95,000
$26,900
$8,200
$1,000
$830
$1,440,000
$2,300
$105,000
1
1
8
45
1,584
1
18
1
$95,000
$26,900
$65,600
$45,000
$1,314,720
$1,440,000
$41,400
$105,000
$3,133,620
Year
LS
CY
$54,000
$21,000
$50
1
1
2,100
$54,000
$21,000
$105,000
$180,000
Percentage
Percentage
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
10%
25%
3,313,620
3,313,620
$3,313,620
$330,000
$830,000
$4,473,620
5 of 6
2014
Table 1-8 Cost Estimate: Alternative 4 with DMM Scenario A
Focused Capping with Dredging for Flooding, Confined Aquatic Disposal
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL PERIODIC O&M
Unit
Unit Cost
# of Units
Cost
Year
Location
Year
$1,400,000
$2,300
$365,000
1
63
1
$1,400,000
$144,900
$365,000
$1,909,900
CY
LF
$50
$200
51,000
2,300
$2,550,000
$460,000
$3,010,000
Percentage
Percentage
10%
25%
4,919,900
4,919,900
$4,919,900
$490,000
$1,230,000
$6,639,900
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-9 Cost Estimate: Alternative 4 with DMM Scenario B
Focused Capping with Dredging for Flooding, Off-site Disposal
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Pore Water Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Cap Erosion Modeling for Armor Placement Design
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Capping Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
New Season Restart
Total Mobilization and Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$25,400
156,711,120
156,711,120
1
12
12
1
Core
Boring
Sample
Sample
Sample
Sample
LS
Sample
Day
Day
LS
LS
LS
Sample
Sample
LS
$250
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$1,040
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
$18,000
1,882
33
5,646
1,482
1,359
99
1
188
9
9
1
1
1
300
135
1
$470,500
$321,750
$8,807,760
$1,896,960
$380,520
$122,760
$2,800,000
$195,520
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$353,700
$18,000
$30,711,470
EA
EA
LS
EA
EA
Year
$237,000
$237,000
$13,800
$60,000
$237,000
$310,000
2
2
1
1
1
1
$474,000
$474,000
$13,800
$60,000
$237,000
$310,000
$1,568,800
$9,400,000
$3,130,000
$355,000
$120,000
$576,000
$25,400
2014
Table 1-9 Cost Estimate: Alternative 4 with DMM Scenario B
Focused Capping with Dredging for Flooding, Off-site Disposal
Component
C. Testing and Monitoring During Dredging and Backfilling/Capping
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling/Capping
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Barge Transport of Dredged Material
Shallow Water Sediments - Double Handling
Hydraulic Off-loading of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Engineered Cap
Engineered Cap Material Purchase and Delivery
Engineered Cap Material Placement
Armor Material Purchase and Delivery
Armor Material Placement
Confirmation Coring
Sediment Recontamination Monitoring
Mudflat Engineered Cap
Mudflat Reconstruction
Riprapped Shoreline Repairs and Replacement
Total Engineered Cap
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$540,710
$1,350,000
$120,000
$355,000
2
2
2
2
2
2
$1,675,200
$2,909,200
$1,081,420
$2,700,000
$240,000
$710,000
$9,315,820
CY
Ton
CY
CY
CY
Percentage
$25
$200
$10
$5
$10
1%
1,021,000
2,000
1,584,000
103,500
1,584,000
155,161,120
$25,525,000
$400,000
$15,840,000
$517,500
$15,840,000
$1,550,000
$59,672,500
CY
CY
CY
CY
Core
Sample
CY
CY
SY
$30
$30
$30
$30
$270
$1,560
$80
$150
$75
930,000
930,000
92,000
92,000
170
510
103,500
103,500
2,500
$27,900,000
$27,900,000
$2,760,000
$2,760,000
$45,900
$795,600
$8,280,000
$15,525,000
$187,500
$86,154,000
Percentage
Percentage
10%
25%
156,711,120
187,422,590
$187,422,590
$15,670,000
$46,860,000
$249,952,590
2 of 6
2014
Table 1-9 Cost Estimate: Alternative 4 with DMM Scenario B
Focused Capping with Dredging for Flooding, Off-site Disposal
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F2. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Sediment Processing Facility Site Investigation - Geotechnical
Upland Sediment Processing Facility Site Investigation - Chemical
Topographic Survey - Upland Sediment Processing Facility Site
Habitat Survey (upland sediment processing facility site)
Cultural Survey (upland sediment processing facility site)
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G2. Upland Sediment Processing Facility
Mobilization and Demobilization
Mechanical and Electrical
Layout and Documentation Surveys
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Prefabricated Building (Sprung Structure) for Dewatered Sediment Storage
Storage Area - Concrete Slab and Push Walls
Storage Area - Subgrade Material
Storage Area - Filter Fabric
Storage Area - Vapor Emissions Control
Piping
Upfront Storage and Recycle Water Tanks
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
LS
LS
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$870
$42,000
$42,000
$106,130
307,587,540
307,587,540
26
1
3
52
26
28.5
1
1
1
$18,460,000
$6,150,000
$13,260,000
$119,000
$144,000
$167,440
$66,560
$24,795
$42,000
$42,000
$106,130
$38,581,925
Percentage
Percentage
Day
LF
Acre
LS
LS
LS
CY
LS
SY
SF
SF
CY
CY
SY
Unit
LF
LS
10%
10%
$4,000
$60
$50,000
$100,000
$25,660,000
$1,250,000
$12
$151,000
$30
$160
$40
$600
$40
$2
$5,000
$29
$707,000
60,901,100
60,901,100
104
8,500
26
1
1
1
144,000
1
73,000
50,000
185,000
8,000
3,500
20,600
16
28,100
1
$6,090,000
$6,090,000
$416,000
$510,000
$1,300,000
$100,000
$25,660,000
$1,250,000
$1,728,000
$151,000
$2,190,000
$8,000,000
$7,400,000
$4,800,000
$140,000
$41,200
$80,000
$814,900
$707,000
2014
Table 1-9 Cost Estimate: Alternative 4 with DMM Scenario B
Focused Capping with Dredging for Flooding, Off-site Disposal
Component
Loadout Facility
Rail Line Spur/Railcar Storage
Temporary Bunkers for Loadout Facility
Hazardous Material Storage Area
Air Monitoring During Construction
Total Upland Sediment Processing Facility
H2. Equipment Costs
Operating Equipment
Wastewater Treatment Plant
Total Equipment Costs
I2. Processing and Disposal
Mechanical Dewatering Using Filter Presses
Dredged Material Testing for Disposal
Transport Off-site Thermal Treatment
Thermal Treatment and Disposal (Off-site Facility)
Transport to Subtitle C Landfill (Off-site Facility)
Off-site Disposal in Subtitle C Landfill
Decontamination and Disposal of Medium-sized Debris
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill
Reclaimed Sand Processing, Transport, and Beneficial Use
Total Processing and Disposal
J2. Site Decommissioning/Restoration
Total Decommissioning/Restoration
Subtotal Dredged Material Management Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
LS
Mile
Unit
LS
Month
$500,000
$1,000,000
$10,000
$33,000
$5,000
1
5
2
1
12
$500,000
$5,000,000
$20,000
$33,000
$60,000
$73,081,100
EA
LS
$1,067,000
$6,688,000
1
1
$1,067,000
$6,688,000
$7,755,000
CY
5000 CY
Ton
Ton
Ton
Ton
CY
Ton
Ton
$50
$1,088
$240
$400
$130
$100
$200
$230
$50
1,021,000
130
30,000
30,000
600,000
600,000
56,000
6,000
100,000
Acre
$30,000
26
Percentage
Percentage
10%
25%
307,587,540
346,169,465
$51,050,000
$141,440
$7,200,000
$12,000,000
$78,000,000
$60,000,000
$11,200,000
$1,380,000
$5,000,000
$225,971,440
$780,000
$780,000
$346,169,465
$30,760,000
$86,540,000
$463,469,465
4 of 6
2014
Table 1-9 Cost Estimate: Alternative 4 with DMM Scenario B
Focused Capping with Dredging for Flooding, Off-site Disposal
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Wastewater Treatment Plant O&M
Sediment Processing Site O&M
Operations Management/Coordination
Wastewater Testing
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Year
Month
Month
$668,800
$2,838,000
$939,000
$5,430
$5,000
1
1
1
12
12
$668,800
$2,838,000
$939,000
$65,160
$60,000
Percentage
Percentage
10%
25%
4,570,960
4,570,960
$4,570,960
$460,000
$1,140,000
$6,170,960
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Ice Scour Evaluation of Cap along Shoreline
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
Year
Year
Day
Sample
Sample
Year
Location
Year
$95,000
$26,900
$8,200
$1,000
$830
$1,400,000
$2,300
$105,000
1
1
7
37
1,562
1
14
1
$95,000
$26,900
$57,400
$37,000
$1,296,460
$1,400,000
$32,200
$105,000
$3,049,960
Year
LS
CY
$54,000
$0
$50
1
1
1,900
$54,000
$0
$95,000
$149,000
Percentage
Percentage
10%
25%
3,198,960
3,198,960
$3,198,960
$320,000
$800,000
$4,318,960
5 of 6
2014
Table 1-9 Cost Estimate: Alternative 4 with DMM Scenario B
Focused Capping with Dredging for Flooding, Off-site Disposal
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL PERIODIC O&M
Unit
Unit Cost
# of Units
Year
Location
Year
$1,400,000
$2,400
$365,000
1
57
1
$1,400,000
$136,800
$365,000
$1,901,800
CY
LF
$50
$200
47,000
2,300
$2,350,000
$460,000
$2,810,000
Percentage
Percentage
10%
25%
4,711,800
4,711,800
Cost
$4,711,800
$470,000
$1,180,000
$6,361,800
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-10 Cost Estimate: Alternative 4 with DMM Scenario C
Focused Capping with Dredging for Flooding, Local Decontamination and Beneficial Use
Component
CAPITAL COSTS
A. Pre-Construction Activities
Design
Regulatory Requirements, Legal, and Community Outreach
Contractor Work Plans and Submittals
Pre-Construction Support Facility
Pre-Construction Oversight
General and Survey and Coring Vessels Mobilization
Pre-Design Investigation - Chemical, Waste Characterization, Geological Sample Collection
Pre-Design Investigation - Geotechnical Sample Collection
Pre-Design Investigation - Chemical Analysis
Pre-Design Investigation - Waste Characterization Analysis
Pre-Design Investigation - Geological Analysis
Pre-Design Investigation - Geotechnical Analysis
Biological Monitoring Baseline Studies
Pore Water Evaluation
Sub-bottom Geophysics and Bathymetric Survey
Video Survey for Debris Identification
Habitat Survey (in river)
Cultural Survey (in river)
Fish Spawning Study
Borrow Site Pre-Screening
Borrow Material Characterization
Cap Erosion Modeling for Armor Placement Design
Total Pre-Construction Activities
B. Mobilization and Demobilization
Dredge Equipment Mobilization/Demobilization
Capping Equipment Mobilization/Demobilization
Monitoring Equipment Mobilization/Demobilization
Debris Removal Equipment Mobilization/Demobilization
Shoreline Protection Equipment Mobilization/Demobilization
New Season Restart
Total Mobilization and Demobilization
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
LS
Month
Month
LS
6%
2%
$355,000
$10,000
$48,000
$25,400
156,711,120
156,711,120
1
12
12
1
Core
Boring
Sample
Sample
Sample
Sample
LS
Sample
Day
Day
LS
LS
LS
Sample
Sample
LS
$250
$9,750
$1,560
$1,280
$280
$1,240
$2,800,000
$1,040
$8,200
$8,200
$100,000
$540,000
$50,000
$3,000
$2,620
$18,000
1,882
33
5,646
1,482
1,359
99
1
188
9
9
1
1
1
300
135
1
$470,500
$321,750
$8,807,760
$1,896,960
$380,520
$122,760
$2,800,000
$195,520
$73,800
$73,800
$100,000
$540,000
$50,000
$900,000
$353,700
$18,000
$30,711,470
EA
EA
LS
EA
EA
Year
$237,000
$237,000
$13,800
$60,000
$237,000
$310,000
2
2
1
1
1
1
$474,000
$474,000
$13,800
$60,000
$237,000
$310,000
$1,568,800
$9,400,000
$3,130,000
$355,000
$120,000
$576,000
$25,400
2014
Table 1-10 Cost Estimate: Alternative 4 with DMM Scenario C
Focused Capping with Dredging for Flooding, Local Decontamination and Beneficial Use
Component
C. Testing and Monitoring During Dredging and Backfilling/Capping
Bathymetric Survey
Water Quality Monitoring
Sediment Monitoring
Biological Monitoring
Air Monitoring
Monitoring Reports (including Laboratory Reporting)
Total Testing and Monitoring During Dredging and Backfilling/Capping
D. Dredging
Mechanical Dredging
Large Debris Removal, Off-loading, Transport, and Disposal
Barge Transport of Dredged Material
Shallow Water Sediments - Double Handling
Hydraulic Off-loading of Dredged Material
Controls for Quality of Life Impacts
Total Dredging
E. Engineered Cap
Engineered Cap Material Purchase and Delivery
Engineered Cap Material Placement
Armor Material Purchase and Delivery
Armor Material Placement
Confirmation Coring
Sediment Recontamination Monitoring
Mudflat Engineered Cap
Mudflat Reconstruction
Riprapped Shoreline Repairs and Replacement
Total Engineered Cap
Subtotal Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
Year
Year
Year
Year
Year
Year
$837,600
$1,454,600
$540,710
$1,350,000
$120,000
$355,000
2
2
2
2
2
2
$1,675,200
$2,909,200
$1,081,420
$2,700,000
$240,000
$710,000
$9,315,820
CY
Ton
CY
CY
CY
Percentage
$25
$200
$10
$5
$10
1%
1,021,000
2,000
1,584,000
103,500
1,584,000
155,161,120
$25,525,000
$400,000
$15,840,000
$517,500
$15,840,000
$1,550,000
$59,672,500
CY
CY
CY
CY
Core
Sample
CY
CY
SY
$30
$30
$30
$30
$270
$1,560
$80
$150
$75
930,000
930,000
92,000
92,000
170
510
103,500
103,500
2,500
$27,900,000
$27,900,000
$2,760,000
$2,760,000
$45,900
$795,600
$8,280,000
$15,525,000
$187,500
$86,154,000
Percentage
Percentage
10%
25%
156,711,120
187,422,590
$187,422,590
$15,670,000
$46,860,000
$249,952,590
2 of 6
2014
Table 1-10 Cost Estimate: Alternative 4 with DMM Scenario C
Focused Capping with Dredging for Flooding, Local Decontamination and Beneficial Use
Component
DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
F3. Pre-Construction Activities for DMM
Design
Regulatory Requirements, Legal, and Community Outreach
Land Acquisition
Contractor Work Plans and Submittals
Pre-Construction Oversight
Upland Sediment Processing Facility Site Investigation - Geotechnical
Upland Sediment Processing Facility Site Investigation - Chemical
Topographic Survey - Upland Sediment Processing Facility Site
Habitat Survey (upland sediment processing facility site)
Cultural Survey (upland sediment processing facility site)
Miscellaneous Tests for DMM Design
Total Pre-Construction Activities for DMM
G3. Upland Sediment Processing Facility
Mobilization and Demobilization
Mechanical and Electrical
Layout and Documentation Survey
Fencing
Exterior Lighting
Security
Buildings
Utilities
Earthwork
Stormwater Management
Paving
Pier/Dock Structure
Prefabricated Building (Sprung Structure) for Dewatered Sediment Storage
Storage Area - Concrete Slab and Push Walls
Storage Area - Subgrade Material
Storage Area - Filter Fabric
Storage Area - Vapor Emissions Control
Piping
Upfront Storage and Recycle Water Tanks
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 6
Unit
Unit Cost
# of Units
Cost
Percentage
Percentage
Acre
LS
Month
Boring
Core
Acre
LS
LS
LS
6%
2%
$510,000
$119,000
$48,000
$3,220
$2,560
$870
$42,000
$42,000
$106,130
296,380,940
296,380,940
36
1
3
72
36
40
1
1
1
$17,780,000
$5,930,000
$18,360,000
$119,000
$144,000
$231,840
$92,160
$34,800
$42,000
$42,000
$106,130
$42,881,930
Percentage
Percentage
Day
LF
Acre
LS
LS
LS
CY
LS
SY
SF
SF
CY
CY
SY
Unit
LF
LS
10%
10%
$4,000
$60
$50,000
$100,000
$37,630,000
$1,250,000
$12
$168,000
$30
$160
$40
$600
$40
$2
$5,000
$29
$740,500
75,814,500
75,814,500
104
10,000
36
1
1
1
201,000
1
73,000
50,000
283,000
11,000
5,300
31,500
24
40,000
1
$7,581,000
$7,581,000
$416,000
$600,000
$1,800,000
$100,000
$37,630,000
$1,250,000
$2,412,000
$168,000
$2,190,000
$8,000,000
$11,320,000
$6,600,000
$212,000
$63,000
$120,000
$1,160,000
$740,500
2014
Table 1-10 Cost Estimate: Alternative 4 with DMM Scenario C
Focused Capping with Dredging for Flooding, Local Decontamination and Beneficial Use
Component
Loadout facility
Transfer Vehicle Storage
Temporary Bunkers for Loadout Facility
Hazardous Material Processing and Storage Area
Air Monitoring During Construction
Total Upland Sediment Processing Facility
H3. Equipment Costs
Operating Equipment
Wastewater Treatment Plant
Total Equipment Costs
I3. Local Decontamination
Mechanical Dewatering Using Filter Presses
Dredged Material Testing for Disposal
Thermal Treatment (On-Site/Local Facility)
Sediment Washing
Sediment Amendment
Decontamination and Disposal of Medium-sized Debris
Debris Transport and Disposal (Small Organic Fraction) in Subtitle C Landfill
Reclaimed Sand Processing, Transport, and Beneficial Use
Total Local Decontamination
J3. Site Decommissioning/Restoration
Total Decommissioning/Restoration
Subtotal Dredged Material Management Capital Costs
Construction and Program Management
Scope and Bid Contingency
TOTAL DREDGED MATERIAL MANAGEMENT CAPITAL COSTS
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Unit
Unit Cost
# of Units
Cost
LS
SY
Unit
LS
Month
$500,000
$30
$10,000
$33,000
$5,000
1
14,000
2
1
12
$500,000
$420,000
$20,000
$33,000
$60,000
$90,976,500
LS
LS
$1,067,000
$7,906,000
1
1
$1,067,000
$7,906,000
$8,973,000
CY
5000 CY
Tons
CY
Ton
CY
Ton
Ton
$50
$1,088
$640
$150
$80
$200
$230
$50
1,021,000
130
30,000
710,000
11,000
56,000
6,000
100,000
Acre
$30,000
36
Percentage
Percentage
10%
25%
296,380,940
339,262,870
$51,050,000
$141,440
$19,200,000
$106,500,000
$880,000
$11,200,000
$1,380,000
$5,000,000
$195,351,440
$1,080,000
$1,080,000
$339,262,870
$29,640,000
$84,820,000
$453,722,870
4 of 6
2014
Table 1-10 Cost Estimate: Alternative 4 with DMM Scenario C
Focused Capping with Dredging for Flooding, Local Decontamination and Beneficial Use
Component
DREDGED MATERIAL MANAGEMENT O&M COSTS
K. DMM Site O&M
Wastewater Treatment Plant O&M
Sediment Processing Site O&M
Operations Management/Coordination
Wastewater Testing
Air Monitoring
Subtotal DMM Site O&M
Construction and Program Management
Scope and Bid Contingency
Unit
Unit Cost
# of Units
Year
Year
Year
Month
Month
$790,600
$3,142,000
$939,000
$5,430
$5,000
1
1
1
12
12
$790,600
$3,142,000
$939,000
$65,160
$60,000
Percentage
Percentage
10%
25%
4,996,760
4,996,760
$4,996,760
$500,000
$1,250,000
$6,746,760
TOTAL DREDGED MATERIAL MANAGEMENT O&M COSTS
LONG-TERM O&M COSTS
L. Annual Monitoring Activities
Community Outreach
Mobilization and Demobilization of Monitoring Equipment
Bathymetric Survey
Water Column Sampling and Analysis
Sediment Sampling and Analysis
Biological Monitoring
Habitat Recolonization using SPI
Annual Monitoring Reports
Total Annual Monitoring Activities
M. Annual Maintenance Activities
Mobilization and Demobilization of Cap Maintenance Equipment
Ice Scour Evaluation of Cap along Shoreline
Annual Cap Maintenance
Total Annual Maintenance Activities
Subtotal Annual O&M
Construction and Program Management
Scope and Bid Contingency
Year
Year
Day
Sample
Sample
Year
Location
Year
$95,000
$26,900
$8,200
$1,000
$830
$1,400,000
$2,300
$105,000
1
1
7
37
1,562
1
14
1
$95,000
$26,900
$57,400
$37,000
$1,296,460
$1,400,000
$32,200
$105,000
$3,049,960
Year
LS
CY
$54,000
$21,000
$50
1
1
1,900
$54,000
$21,000
$95,000
$170,000
Percentage
Percentage
TOTAL ANNUAL O&M
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
Cost
10%
25%
3,219,960
3,219,960
$3,219,960
$320,000
$800,000
$4,339,960
5 of 6
2014
Table 1-10 Cost Estimate: Alternative 4 with DMM Scenario C
Focused Capping with Dredging for Flooding, Local Decontamination and Beneficial Use
Component
N. Periodic Monitoring Activities
Supplemental Biological Monitoring
Supplemental Habitat Recolonization using SPI
Performance Review Report
Total Periodical Monitoring Activities
O. Periodic Maintenance Activitites
Periodic Cap Maintenance
Natural Shoreline Maintenance
Total Periodic Maintenance Activitites
Subtotal Periodic O&M
Construction and Program Management
Scope and Bid Contingency
TOTAL PERIODIC O&M
Unit
Unit Cost
# of Units
Year
Location
Year
$1,400,000
$2,400
$365,000
1
14
1
$1,400,000
$33,600
$365,000
$1,798,600
CY
LF
$50
$200
47,000
2,300
$2,350,000
$460,000
$2,810,000
Percentage
Percentage
10%
25%
4,608,600
4,608,600
Cost
$4,608,600
$460,000
$1,150,000
$6,218,600
Notes: CAD = Confined Aquatic Disposal; CY = Cubic Yard; DMM = Dredged Material Management; EA = Each; HARS = Historic Area Remediation Site; LF = Linear Feet; LS = Lump Sum; O&M =
Operation and Maintenance; SPI = Sediment Profile Imaging; SF = Square Feet; SY = Square Yard.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
6 of 6
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 2 with DMM Scenario A: Deep Dredging with
Backfill, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario B: Deep Dredging with
Backfill, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario C: Deep Dredging with
Backfill, Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
TOTAL PV
CONTINGENCY
CM
COST PV
2014
2015
2016
2017
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,340,834,200
676,394,300
171,568,000
3,629,700
36,256,800
345,059,800
119,880,000
622,983,800
65,102,000
434,575,700
7,400,800
115,831,900
73,400
19,013,200
22,442,900
17,056,200
5,386,800
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
251,809,000
127,800,000
34,313,600
672,200
6,714,200
63,900,000
22,200,000
116,331,900
13,020,400
80,477,000
1,370,500
21,450,400
13,600
3,521,000
4,156,100
3,158,600
997,600
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
81,789,900
37,394,600
268,900
2,685,700
25,560,000
8,880,000
41,324,500
32,190,800
548,200
8,580,100
5,400
1,408,400
1,662,400
1,263,400
399,000
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,007,235,300
511,199,700
137,254,400
2,688,600
26,856,900
255,599,800
88,800,000
465,327,400
52,081,600
321,907,900
5,482,100
85,801,400
54,400
14,083,800
16,624,400
12,634,200
3,990,200
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
52,301,030
52,301,030
28,805,918
28,805,918
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
52,301,030
52,301,030
28,805,918
28,805,918
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
3,244,755,600
809,999,900
185,509,800
3,629,700
36,256,800
464,723,600
119,880,000
2,382,056,500
267,172,500
89,954,100
8,536,100
2,015,990,100
403,700
37,004,700
15,694,500
12,894,600
2,799,900
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
607,587,200
152,748,300
37,102,000
672,200
6,714,200
86,059,900
22,200,000
445,079,800
53,434,500
16,658,200
1,580,800
373,331,500
74,800
6,852,700
2,906,400
2,387,900
518,500
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
206,820,400
46,258,600
268,900
2,685,700
34,424,000
8,880,000
156,658,100
6,663,300
632,300
149,332,600
29,900
2,741,100
1,162,600
955,200
207,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
2,430,348,000
610,993,000
148,407,800
2,688,600
26,856,900
344,239,700
88,800,000
1,780,318,600
213,738,000
66,632,600
6,323,000
1,493,326,000
299,000
27,410,900
11,625,500
9,551,500
2,074,000
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
56,551,030
56,551,030
118,216,723
118,216,723
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
56,551,030
56,551,030
157,650,423
118,216,723
39,433,700
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
2,621,019,700
809,999,900
185,509,800
3,629,700
36,256,800
464,723,600
119,880,000
1,753,308,700
204,976,400
114,654,500
10,205,600
1,422,892,300
579,900
42,016,600
15,694,500
12,894,600
2,799,900
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
491,159,100
152,748,300
37,102,000
672,200
6,714,200
86,059,900
22,200,000
327,723,500
40,995,300
21,232,300
1,889,900
263,498,600
107,400
7,780,900
2,906,400
2,387,900
518,500
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
165,224,800
46,258,600
268,900
2,685,700
34,424,000
8,880,000
114,691,300
8,492,900
756,000
105,399,400
43,000
3,112,300
1,162,600
955,200
207,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,964,635,800
610,993,000
148,407,800
2,688,600
26,856,900
344,239,700
88,800,000
1,310,893,900
163,981,100
84,929,300
7,559,700
1,053,994,300
429,500
31,123,400
11,625,500
9,551,500
2,074,000
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
56,551,030
56,551,030
90,696,595
90,696,595
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
56,551,030
56,551,030
140,958,445
90,696,595
50,261,850
-
$
$
$
$
$
$
$
$ 53,559,830
$ 52,301,030
$
1,258,800
$
$
$
$ 168,398,180
$ 161,682,380
$
6,715,800
$
$
$
$
$
$
-
57,809,830
56,551,030
1,258,800
47,179,700
$ 39,433,700
$
7,746,000
$
$
$
$
$
$
-
2018
2019
2020
2021
$
60,651,455
$
60,961,455
$
60,961,455
$
60,961,455
$
$
$
$
$
4,387,560
41,756,818
14,507,077
-
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
-
$
310,000
$
4,387,560
$ 41,756,818
$ 14,507,077
$ 161,682,380
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
57,753,033
$ 161,682,380
$
$
-
$
-
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
57,753,033
2,300,840
-
$
75,132,365
$
75,442,365
$
75,442,365
$
75,442,365
$
$
$
$
$
4,387,560
56,237,727
14,507,077
28,805,918
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$
$
$
$
57,809,830
56,551,030
1,258,800
59,522,850
75,132,365
75,442,365
75,442,365
75,442,365
$
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$ 50,261,850
$
9,261,000
$
$
$
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
1 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 2 with DMM Scenario A: Deep Dredging with
Backfill, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario B: Deep Dredging with
Backfill, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario C: Deep Dredging with
Backfill, Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
2022
2023
2024
2025
2026
2027
2028
$
60,961,455
$
60,961,455
$
60,961,455
$
60,961,455
$
60,961,455
$
60,961,455
$
60,961,455
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
-
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
-
$
310,000
$
4,387,560
$ 41,756,818
$ 14,507,077
$ 161,682,380
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
57,753,033
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
-
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
-
$
$
$
$
$
310,000
4,387,560
41,756,818
14,507,077
57,753,033
$
-
$
-
2,300,840
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
57,753,033
2,300,840
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
2,300,840
-
$
$
$
$
$
$
57,753,033
2,300,840
-
$
75,442,365
$
75,442,365
$
75,442,365
$
75,442,365
$
75,442,365
$
75,442,365
$
75,442,365
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 243,961,600
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$ 243,961,600
$
$
4,478,060
$
$
$
-
$
$
$
$
$
$
$
75,442,365
2030
2031
2032
2033
2034
$ 161,682,380
$
$
$
$
$
$
75,442,365
2029
75,442,365
75,442,365
75,442,365
75,442,365
$
150,000
$
$
$
2,625,330
2,625,330
-
$
825,000
$
825,000
$
$
$
1,984,750
1,984,750
-
$
1,185,000
$
1,185,000
$
$
$
1,984,750
1,984,750
-
$
$
$
2,625,330
2,625,330
-
$
$
$
2,625,330
2,625,330
-
$
$
$
2,625,330
2,625,330
-
$
$
$
7,393,530
2,625,330
4,768,200
$ 2,625,330
$ 2,625,330
$
-
$
$
$
1,984,750
1,984,750
-
$
$
$
1,984,750
1,984,750
-
$
$
$
1,984,750
1,984,750
-
$
$
$
4,463,150
1,984,750
2,478,400
$ 1,984,750
$ 1,984,750
$
-
$
$
$
1,984,750
1,984,750
-
$
$
$
1,984,750
1,984,750
-
$
$
$
1,984,750
1,984,750
-
$
$
$
4,463,150
1,984,750
2,478,400
$ 1,984,750
$ 1,984,750
$
-
75,442,365
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$
310,000
$
4,387,560
$ 56,237,727
$ 14,507,077
$ 172,188,873
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
$ 172,188,873
$
$
5,084,560
$
$
$
-
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 2 with DMM Scenario A: Deep Dredging with
Backfill, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario B: Deep Dredging with
Backfill, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario C: Deep Dredging with
Backfill, Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
2046
2047
2048
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 7,393,530
$ 2,625,330
$ 4,768,200
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 7,393,530
$ 2,625,330
$ 4,768,200
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 7,393,530
$ 2,625,330
$ 4,768,200
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
3 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 2 with DMM Scenario A: Deep Dredging with
Backfill, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario B: Deep Dredging with
Backfill, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 2 with DMM Scenario C: Deep Dredging with
Backfill, Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Backfilling
Dredging
Backfill
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
2049
2050
2051
2052
2053
2054
2055
2056
2057
2058
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 7,393,530
$ 2,625,330
$ 4,768,200
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 2,625,330
$ 2,625,330
$
-
$ 7,393,530
$ 2,625,330
$ 4,768,200
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 1,984,750
$ 1,984,750
$
-
$ 4,463,150
$ 1,984,750
$ 2,478,400
2059
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
4 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 3 with DMM Scenario A: Capping with
Dredging for Flooding and Navigation, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario B: Capping with
Dredging for Flooding and Navigation, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario C: Capping with
Dredging for Flooding and Navigation, Local
Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
TOTAL PV
CONTINGENCY
CM
COST PV
2014
2015
2016
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
953,091,700
502,800,500
115,055,400
2,468,700
21,290,700
162,489,400
201,496,300
385,057,400
34,125,000
261,947,100
6,618,400
82,256,700
110,200
10,405,300
54,828,500
37,951,600
16,876,900
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
178,708,400
94,815,700
23,011,100
457,200
3,942,700
30,090,600
37,314,100
71,812,400
6,825,000
48,508,700
1,225,600
15,232,700
20,400
1,926,900
10,153,400
7,028,100
3,125,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
59,549,300
28,722,000
182,900
1,577,100
12,036,300
14,925,700
25,995,100
19,403,500
490,300
6,093,100
8,200
770,800
4,061,400
2,811,200
1,250,100
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
714,834,000
379,262,800
92,044,300
1,828,600
15,770,900
120,362,500
149,256,500
287,249,900
27,300,000
194,034,900
4,902,500
60,930,900
81,600
7,707,600
40,613,700
28,112,300
12,501,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
35,073,650
35,073,650
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
35,073,650
35,073,650
16,156,378
16,156,378
-
$ 36,332,450
$ 35,073,650
$
1,258,800
$
$
$
$ 149,041,738
$ 16,156,378
$ 126,879,560
$
6,005,800
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,731,067,900
570,650,000
121,047,600
2,468,700
21,290,700
224,346,700
201,496,300
1,089,792,800
111,749,000
83,406,800
8,546,000
885,518,200
572,800
20,197,200
50,427,900
35,366,800
15,061,100
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
324,017,000
107,469,200
24,209,500
457,200
3,942,700
41,545,700
37,314,100
203,469,100
22,349,800
15,445,700
1,582,600
163,984,900
106,100
3,740,200
9,338,500
6,549,400
2,789,100
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
110,983,100
33,304,000
182,900
1,577,100
16,618,300
14,925,700
72,447,600
6,178,300
633,000
65,593,900
42,400
1,496,100
3,735,400
2,619,800
1,115,600
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,296,067,800
429,876,800
96,838,100
1,828,600
15,770,900
166,182,700
149,256,500
813,876,100
89,399,200
61,782,800
6,330,400
655,939,400
424,300
14,960,900
37,354,000
26,197,600
11,156,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
36,900,317
36,900,317
49,445,963
49,445,963
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
36,900,317
36,900,317
86,009,513
49,445,963
36,563,550
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,584,675,300
570,400,400
121,014,800
2,468,700
21,073,900
224,346,700
201,496,300
941,179,100
103,172,300
103,838,200
9,888,300
723,487,500
793,000
22,667,900
50,427,900
35,366,800
15,061,100
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
296,779,800
107,422,600
24,203,000
457,200
3,902,600
41,545,700
37,314,100
175,820,900
20,634,500
19,229,300
1,831,200
133,979,200
146,900
4,197,800
9,338,500
6,549,400
2,789,100
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
100,777,000
33,287,900
182,900
1,561,000
16,618,300
14,925,700
62,074,600
7,691,700
732,500
53,591,700
58,700
1,679,100
3,735,400
2,619,800
1,115,600
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
1,187,118,500
429,689,900
96,811,800
1,828,600
15,610,300
166,182,700
149,256,500
703,283,600
82,537,800
76,917,200
7,324,600
535,916,600
587,400
16,791,000
37,354,000
26,197,600
11,156,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
36,890,317
36,890,317
45,650,965
45,650,965
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
36,890,317
36,890,317
91,171,215
45,650,965
45,520,250
-
$
$
$
$
$
$
$
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2017
5 of 12
2018
2019
2020
2021
$
85,267,830
$
85,577,830
$
85,577,830
$
85,577,830
$
$
$
$
$
4,711,980
35,961,500
44,594,350
-
$
310,000
$
4,711,980
$ 35,961,500
$ 44,594,350
$ 126,879,560
$
$
$
$
$
310,000
4,711,980
35,961,500
44,594,350
48,809,100
$
$
$
$
$
310,000
4,711,980
35,961,500
44,594,350
-
$
-
$ 126,879,560
$
$
$
$
$
$
2,302,840
-
$
$
$
$
$
$
2,302,840
-
$
$
$
$
$
$
48,809,100
2,302,840
-
$
$
$
$
$
$
2,302,840
-
$
98,957,830
$
99,267,830
$
99,267,830
$
99,267,830
38,159,117
36,900,317
1,258,800
44,318,550
$
$
4,711,980
$ 49,651,500
$ 44,594,350
$ 195,979,328
$
310,000
$
4,711,980
$ 49,651,500
$ 44,594,350
$ 195,979,328
$
310,000
$
4,711,980
$ 49,651,500
$ 44,594,350
$ 195,979,328
$
310,000
$
4,711,980
$ 49,651,500
$ 44,594,350
$ 195,979,328
$ 36,563,550
$
7,755,000
$
$
$
$
$
$
-
$ 195,979,328
$
$
4,469,960
$
$
$
-
$ 195,979,328
$
$
4,469,960
$
$
$
-
$ 195,979,328
$
$
4,469,960
$
$
$
-
$ 195,979,328
$
$
4,469,960
$
$
$
-
$
$
$
$
38,149,117
36,890,317
1,258,800
54,493,250
98,909,830
99,219,830
99,219,830
99,219,830
$
$
4,663,980
$ 49,651,500
$ 44,594,350
$ 160,119,328
$
310,000
$
4,663,980
$ 49,651,500
$ 44,594,350
$ 160,119,328
$
310,000
$
4,663,980
$ 49,651,500
$ 44,594,350
$ 160,119,328
$
310,000
$
4,663,980
$ 49,651,500
$ 44,594,350
$ 160,119,328
$ 45,520,250
$
8,973,000
$
$
$
$
$
$
-
$ 160,119,328
$
$
5,016,760
$
$
$
-
$ 160,119,328
$
$
5,016,760
$
$
$
-
$ 160,119,328
$
$
5,016,760
$
$
$
-
$ 160,119,328
$
$
5,016,760
$
$
$
-
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 3 with DMM Scenario A: Capping with
Dredging for Flooding and Navigation, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario B: Capping with
Dredging for Flooding and Navigation, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario C: Capping with
Dredging for Flooding and Navigation, Local
Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
2022
$
85,577,830
$
$
$
$
$
310,000
4,711,980
35,961,500
44,594,350
48,809,100
$
$
$
$
$
$
48,809,100
2,302,840
-
$
99,267,830
$
310,000
$
4,711,980
$ 49,651,500
$ 44,594,350
$ 195,979,328
$ 195,979,328
$
$
4,469,960
$
$
$
-
$
2023
$
150,000
$
$
$
3,892,500
3,892,500
-
$
780,000
$
780,000
$
$
$
3,627,380
3,627,380
-
$
1,080,000
$
1,080,000
$
$
$
3,627,380
3,627,380
-
2024
2025
2026
2027
2028
2029
2031
2032
2033
2034
$
$
$
3,892,500
3,892,500
-
$
$
$
3,892,500
3,892,500
-
$
$
$
3,892,500
3,892,500
-
$
$
$
13,846,900
3,892,500
9,954,400
$
$
$
3,892,500
3,892,500
-
$
$
$
3,892,500
3,892,500
-
$
$
$
3,892,500
3,892,500
-
$
$
$
3,892,500
3,892,500
-
$
$
$
13,846,900
3,892,500
9,954,400
$
$
$
3,892,500
3,892,500
-
$ 3,892,500
$ 3,892,500
$
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
12,510,780
3,627,380
8,883,400
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
12,510,780
3,627,380
8,883,400
$
$
$
3,627,380
3,627,380
-
$ 3,627,380
$ 3,627,380
$
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
12,510,780
3,627,380
8,883,400
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
3,627,380
3,627,380
-
$
$
$
12,510,780
3,627,380
8,883,400
$
$
$
3,627,380
3,627,380
-
$ 3,627,380
$ 3,627,380
$
-
99,219,830
$
310,000
$
4,663,980
$ 49,651,500
$ 44,594,350
$ 160,119,328
$ 160,119,328
$
$
5,016,760
$
$
$
-
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
2030
6 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 3 with DMM Scenario A: Capping with
Dredging for Flooding and Navigation, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario B: Capping with
Dredging for Flooding and Navigation, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario C: Capping with
Dredging for Flooding and Navigation, Local
Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
2046
2047
2048
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 13,846,900
$ 3,892,500
$ 9,954,400
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 13,846,900
$ 3,892,500
$ 9,954,400
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 13,846,900
$ 3,892,500
$ 9,954,400
$ 3,892,500
$ 3,892,500
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
7 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 3 with DMM Scenario A: Capping with
Dredging for Flooding and Navigation, CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario B: Capping with
Dredging for Flooding and Navigation, Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 3 with DMM Scenario C: Capping with
Dredging for Flooding and Navigation, Local
Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Backfilling and/or Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
2049
2050
2051
2052
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 3,892,500
$ 3,892,500
$
-
$ 13,846,900
$ 3,892,500
$ 9,954,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 3,627,380
$ 3,627,380
$
-
$ 12,510,780
$ 3,627,380
$ 8,883,400
2053
2054
2055
2056
2057
2058
2059
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
8 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 4 with DMM Scenario A: Focused Capping,
CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario B: Focused Capping,
Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario C: Focused Capping,
Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term O&M Costs
Annual O&M
Periodic O&M
TOTAL PV
CONTINGENCY
CM
COST PV
2014
2015
2016
2017
2018
2019
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
364,922,800
172,123,700
32,160,400
1,685,700
9,280,600
43,168,700
85,828,300
138,414,200
13,721,100
96,936,800
6,067,400
21,553,900
135,000
4,588,300
49,796,600
39,578,200
10,218,400
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
68,258,100
32,351,200
6,432,100
312,200
1,718,600
7,994,200
15,894,100
25,835,600
2,744,200
17,951,300
1,123,600
3,991,500
25,000
849,700
9,221,600
7,329,300
1,892,300
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
23,632,800
10,367,800
124,900
687,500
3,197,700
6,357,700
9,236,500
7,180,500
449,400
1,596,600
10,000
339,900
3,688,600
2,931,700
756,900
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
273,031,900
129,404,700
25,728,300
1,248,600
6,874,500
31,976,800
63,576,500
103,342,100
10,976,900
71,805,000
4,494,400
15,965,800
100,000
3,398,700
36,886,400
29,317,200
7,569,200
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
9,803,823
9,803,823
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
9,803,823
9,803,823
12,567,415
12,567,415
-
$
$
$
$
$
$
$
11,062,623
9,803,823
1,258,800
93,470,040
$
69,401,160
$
69,711,160
$
$
$
$
$
4,657,910
21,666,250
43,077,000
-
$
$
$
$
$
310,000
4,657,910
21,666,250
43,077,000
22,392,900
$
$
$
$
$
$
$
$
87,964,240
5,505,800
-
$
$
$
$
$
$
2,302,840
-
$
$
$
$
$
$
22,392,900
2,302,840
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
614,077,900
189,823,500
33,581,900
1,685,700
9,280,600
59,447,000
85,828,300
367,152,000
43,598,000
89,189,100
8,546,000
225,117,300
701,600
9,107,400
47,995,000
38,208,700
9,786,300
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
114,861,600
35,650,000
6,716,400
312,200
1,718,600
11,008,700
15,894,100
68,637,000
8,719,600
16,516,500
1,582,600
41,688,400
129,900
1,686,600
8,888,000
7,075,700
1,812,300
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
39,770,400
11,573,600
124,900
687,500
4,403,500
6,357,700
23,967,000
6,606,600
633,000
16,675,400
52,000
674,600
3,555,200
2,830,300
724,900
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
459,445,900
142,599,900
26,865,500
1,248,600
6,874,500
44,034,800
63,576,500
274,548,000
34,878,400
66,066,000
6,330,400
166,753,500
519,700
6,746,200
35,551,800
28,302,700
7,249,100
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
10,237,157
10,237,157
19,290,963
19,290,963
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
10,237,157
10,237,157
55,831,513
19,290,963
36,540,550
-
$
$
$
$
$
$
$
11,495,957
10,237,157
1,258,800
44,295,550
$
77,571,160
$
77,881,160
$
$
4,657,910
$ 29,836,250
$ 43,077,000
$ 112,985,720
$
310,000
$
4,657,910
$ 29,836,250
$ 43,077,000
$ 112,985,720
$ 36,540,550
$
7,755,000
$
$
$
$
$
$
-
$ 112,985,720
$
$
4,570,960
$
$
$
-
$ 112,985,720
$
$
4,570,960
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
605,505,900
189,823,500
33,581,900
1,685,700
9,280,600
59,447,000
85,828,300
357,695,200
48,457,100
103,765,300
9,888,300
194,613,100
971,500
9,955,800
48,031,400
38,459,500
9,571,900
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
113,346,100
35,650,000
6,716,400
312,200
1,718,600
11,008,700
15,894,100
66,957,700
9,691,400
19,215,800
1,831,200
36,039,500
179,900
1,843,700
8,894,700
7,122,100
1,772,600
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
38,775,600
11,573,600
124,900
687,500
4,403,500
6,357,700
22,906,600
7,686,300
732,500
14,415,800
72,000
737,500
3,557,900
2,848,900
709,000
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
453,384,200
142,599,900
26,865,500
1,248,600
6,874,500
44,034,800
63,576,500
267,830,900
38,765,700
76,863,200
7,324,600
144,157,800
719,600
7,374,600
35,578,800
28,488,500
7,090,300
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
-
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
$
10,237,157
10,237,157
66,929,215
21,440,965
45,488,250
-
$
$
$
$
$
$
$
$
77,571,160
$
77,881,160
$
$
$
$
$
4,657,910
29,836,250
43,077,000
97,675,720
$
$
$
$
$
310,000
4,657,910
29,836,250
43,077,000
97,675,720
$
$
$
$
$
$
$
-
10,237,157
10,237,157
21,440,965
21,440,965
-
11,495,957
10,237,157
1,258,800
54,461,250
$ 45,488,250
$
8,973,000
$
$
$
$
$
$
-
$ 97,675,720
$
$
4,996,760
$
$
$
-
$ 97,675,720
$
$
4,996,760
$
$
$
-
2020
$
150,000
$
150,000
$
$
$
3,313,620
3,313,620
-
$
780,000
$
780,000
$
$
$
3,198,960
3,198,960
-
$
1,080,000
$
1,080,000
$
$
$
3,219,960
3,219,960
-
2021
$
$
$
3,313,620
3,313,620
-
$
$
$
3,198,960
3,198,960
-
$
$
$
3,219,960
3,219,960
-
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
9 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 4 with DMM Scenario A: Focused Capping,
CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario B: Focused Capping,
Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario C: Focused Capping,
Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term O&M Costs
Annual O&M
Periodic O&M
2022
2023
2024
2025
2026
2027
2028
2029
2030
2031
2032
2033
2034
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$
$
$
8,233,520
3,313,620
4,919,900
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$
$
$
8,233,520
3,313,620
4,919,900
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$
$
$
3,313,620
3,313,620
-
$ 8,233,520
$ 3,313,620
$ 4,919,900
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$
$
$
7,910,760
3,198,960
4,711,800
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$
$
$
7,910,760
3,198,960
4,711,800
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$
$
$
3,198,960
3,198,960
-
$ 7,910,760
$ 3,198,960
$ 4,711,800
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$
$
$
7,828,560
3,219,960
4,608,600
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$
$
$
7,828,560
3,219,960
4,608,600
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$
$
$
3,219,960
3,219,960
-
$ 7,828,560
$ 3,219,960
$ 4,608,600
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
10 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 4 with DMM Scenario A: Focused Capping,
CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario B: Focused Capping,
Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario C: Focused Capping,
Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term O&M Costs
Annual O&M
Periodic O&M
2035
2036
2037
2038
2039
2040
2041
2042
2043
2044
2045
2046
2047
2048
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 8,233,520
$ 3,313,620
$ 4,919,900
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 8,233,520
$ 3,313,620
$ 4,919,900
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,313,620
$ 3,313,620
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 7,910,760
$ 3,198,960
$ 4,711,800
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 7,910,760
$ 3,198,960
$ 4,711,800
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,198,960
$ 3,198,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 7,828,560
$ 3,219,960
$ 4,608,600
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 7,828,560
$ 3,219,960
$ 4,608,600
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
$ 3,219,960
$ 3,219,960
$
-
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
11 of 12
2014
Table 1-11 Present Value Calculations
YEAR
Alternative 4 with DMM Scenario A: Focused Capping,
CAD
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
CAD Excavation
Upland Support Facility
CAD Closure
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario B: Focused Capping,
Off-Site Disposal
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Processing and Disposal
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term Operation and Maintenance Costs
Annual O&M
Periodic O&M
Alternative 4 with DMM Scenario C: Focused Capping,
Local Decontamination and Beneficial Use
TOTAL PRESENT VALUE
Capital Costs
Pre-construction Activities
Mobilization and Demobilization
Testing and Monitoring During Dredging and Capping
Dredging
Engineered Cap
Dredged Material Management Capital Costs
Pre-construction Activities for DMM
Upland Sediment Processing Facility
Equipment Costs
Local Decontamination
Site Decommissioning/Restoration
Dredged Material Management O&M Costs
Long-Term O&M Costs
Annual O&M
Periodic O&M
2049
2050
2051
2052
2053
2054
2055
2056
2057
2058
2059
$ 8,233,520
$ 3,313,620
$ 4,919,900
$ 7,910,760
$ 3,198,960
$ 4,711,800
$ 7,828,560
$ 3,219,960
$ 4,608,600
Notes: Present value costs calculated using a seven percent discount rate and project schedule shown in Figure 1-1. PV = Present Value; CM = Construction Management; O&M = Operation and Maintenance; CAD = Confined Aquatic Disposal.
Appendix H: Cost Estimates
Lower Eight Miles of the Lower Passaic River
12 of 12
2014
Figures
ALTERNATIVE & TASK DESCRIPTION
2A Deep Dredging with CAD Disposal
YEAR 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036 2037 2038 2039 2040 2041 2042 2043 2044 2045 2046 2047 2048 2049 2050 2051 2052 2053 2054 2055 2056 2057 2058 2059
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Facility Closure
Long-Term Maintenance
2017
2021
2025
2028
2028
2058
2B Deep Dredging with Off-Site Disposal
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Off-Site Treatment and Disposal
Facility Closure
Long-Term Maintenance
2017
2028
2028
2029
2058
2C Deep Dredging with Local Decontamination and Beneficial Use
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Full Decontamination Treatment Process
Facility Closure
Long-Term Maintenance
2017
2028
2028
2030
2058
3A Capping with Dredging for Flooding and Navigation with CAD Disposal
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Facility Closure
Long-Term Maintenance
2017
2020
2022
2022
2052
3B Capping with Dredging for Flooding and Navigation with Off-Site Disposal
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Off-Site Treatment and Disposal
Facility Closure
Long-Term Maintenance
2017
2022
2022
2023
2052
3C Capping with Dredging for Flooding and Navigation with Local Decontamination and Beneficial Use
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Full Decontamination Treatment Process
Facility Closure
Long-Term Maintenance
2017
2022
2022
2023
2052
4A Focused Capping with Dredging for Flooding with CAD Disposal
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Facility Closure
Long-Term Maintenance
2017
2019
2019
2049
4B Focused Capping with Dredging for Flooding with Off-Site Disposal
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Off-Site Treatment and Disposal
Facility Closure
Long-Term Maintenance
2017
2019
2019
2020
2049
4C Capping with Dredging for Flooding with Local Decontamination and Beneficial Use
Preconstruction Activities, Design, and Construction
Dredging, Backfilling, and Capping
Full Decontamination Treatment Process
Facility Closure
Long-Term Maintenance
2017
2019
2019
2020
2049
Note: Variations in estimated construction start and end dates associated with the modeling may deviate slightly from estimated dates used in the cost estimates. In general the differences were minor and
resulted in completion dates for the model and cost estimates that were within six months of each other. This difference should have no impact on the relative Present Value costs of the different alternatives
Anticipated Project Schedule
Figure 1-1
Lower Eight Miles of the Lower Passaic River
2014
DMM Scenario A: CAD Disposal (A)
Step Description
Sediment Process Flow
1S
In-Situ Sediment
2S
Scow
4S
Bottom-Dump Placement
5S
CAD
Debris Process Flow
1D
Off-Site Disposal of Large Debris
Units
Cubic Yards
Cubic Yards
Cubic Yards
Cubic Yards
Tons
Alternative 2
Alternative 3
Alternative 4
9,700,000
15,600,000
15,600,000
9,700,000
4,300,000
6,700,000
6,700,000
4,300,000
1,000,000
1,600,000
1,600,000
1,000,000
8,000
6,000
2,000
Legend
Alternative 2: Deep Dredging With Backfill
Alternative 3: Capping With Dredging for Flooding and Navigation
Alternative 4: Focused Capping with Dredging for Flooding
CAD - Confined Aquatic Disposal
(A)
Totals may not add due to rounding.
(B)
Large debris collected during CAD construction (e.g., cars) will be cleaned and disposed under applicable regulations;
medium and small size debris will be disposed in CAD. During dredging operations, debris will be disposed in CAD
Process Flow Diagram
DMM Scenario A: CAD Disposal
Figure 1-2
NOT TO SCALE
Lower Eight Miles of the Lower Passaic River
2014
Legend
Alternative 2: Deep Dredging With Backfill
Alternative 3: Capping With Dredging for Flooding and Navigation
Alternative 4: Focused Capping with Dredging for Flood ing
Notes:
(A) Volume of runoff resulting from one 10-yr 24-hr storm event over the area of the site’s exclusion zone.
(B) Stormwater in the retention basin is bled into the water treatment system over a period of 3 weeks.
(C) Debris collected during dredging operations and material processing will be disposed under applicable
regulations.
(D) Totals may not add due to rounding.
(E) Non-contact stormwater will be routed to retention basins and discharged
to the river under an NPDES permit.
(A)(2W)
DMM Scenario B: Off-Site Disposal (D)
Step
Description
Units
Alternative 2
Alternative 3
Alternative 4
Sediment Process Flow
1S
In-Situ Sediment
Cubic Yards
9,700,000
4,300,000
1,000,000
2S
Scow
Cubic Yards
15,600,000
6,700,000
1,600,000
3S
Hydraulic Off-loading
4S
Dewatered Material
Cubic Yards
65,300,000
22,800,000
5,400,000
Cubic Yards
5,700,000
2,000,000
500,000
Tons
7,300,000
2,600,000
600,000
(B)
Debris Process Flow
1D
Large Debris
Tons
8,000
6,000
2,000
2D
Medium/Small Debris
Tons
690,000
310,000
70,000
3D
Off-Site Disposal of Debris
Tons
698,000
316,000
72,000
4D
Sand for Beneficial Use
Tons
1,600,000
600,000
100,000
Water Process Flow
1W
Dewatering Water**
Gallons
11,496,800,000
4,048,300,000
960,600,000
2W
Contact Stormwater Runoff
Gallons
2,800,000
2,500,000
2,500,000
3W
Recycle Water
Gallons
9,421,400,000
3,063,300,000
726,900,000
Process Flow Diagram
DMM Scenario B: Off-site Disposal
Figure 1-3
NOT TO SCALE
Lower Eight Miles of the Lower Passaic River
2014
Legend
Alternative 2: Deep Dredging With Backfill
Alternative 3: Capping With Dredging for Flooding and Navigation
Alternative 4: Focused Capping with Dredging for Flooding
Notes:
(A) Volume of runoff resulting from one 10-yr 24-hr storm event over the area of the site’s
exclusion zone (Excluding dewatering cell area).
(B) Stormwater in the retention basin is bled into the water treatment system over a period of 3
weeks.
(C) Debris collected during dredging operations and generated during dewatering operations
will be cleaned disposed under applicable regulations.
(D) SCR used only for the dredge alternative.
(E) Totals may not add due to rounding.
(F) Non-contact stormwater will be routed to retention basins and discharged to the river
under an NPDES permit.
DMM Scenario C: Local Treatment and Beneficial Use (E)
Step
Description
Units
Sediment Process Flow
1S
In-Situ Sediment
Cubic Yards
2S
Scow
Cubic Yards
3S
Hydraulic Off-loading
Cubic Yards
4S
Sediment Washing
Cubic Yards
5S
Mechanical Dewatering
Cubic Yards
6S
Thermal Treatment
Cubic Yards
7S
Sediment Amendment
Cubic Yards
8S
Thermal Treament Beneficial Use Product
Cubic Yards
9S
Sed. Washing/Amendment Beneficial Use
Cubic Yards
10S
Sed. Amendment Only Beneficial Use
Cubic Yards
Debris Process Flow
1D
Large Debris
Tons
2D
Medium/Small Debris
Tons
3D
Off-Site Disposal of Debris
Tons
4D
Sand for Beneficial Use
Tons
Water Process Flow
1W
Dewatering Water
Gallons
2W
Contact Stormwater Runoff
Gallons
3W
Recycle Water
Gallons
Alternative 2
Alternative 3
Alternative 4
9,700,000
15,600,000
65,300,000
57,464,000
65,300,000
570,000
5,130,000
285,000
6,270,000
142,500
4,300,000
6,700,000
22,800,000
20,976,000
22,800,000
140,000
1,860,000
70,000
2,300,000
25,000
1,000,000
1,600,000
5,400,000
4,968,000
5,400,000
35,000
465,000
17,500
575,000
6,250
8,000
690,000
698,000
1,600,000
6,000
310,000
316,000
600,000
2,000
70,000
72,000
100,000
11,496,800,000
4,000,000
9,421,400,000
4,048,300,000
3,600,000
3,063,300,000
960,600,000
3,600,000
726,900,000
(B)
Process Flow Diagram
DMM Scenario C: Local Decontamination and Beneficial Use
Figure 1-4
NOT TO SCALE
Lower Eight Miles of the Lower Passaic River
2014
Download