Route 79/Davol Street Corridor Study Fall River, MA Public Information Meeting #2 November 21, 2013 Fall River Heritage State Park Fall River, MA Agenda Welcome and Introductions Overview of Study Process Review of Study Goals and Objectives Summary of Existing and Future No-Build Conditions Review of Issues, Constraints and Opportunities Alternatives Development Alternatives Analysis Welcome and Introductions MassDOT - Ethan Britland – Project Manager Study Team Joe Cahill – Consultant Team Project Manager (TranSystems) Lenny Velichansky – Consultant Deputy Project Manager/Traffic (TranSystems) Teresa Sandell – Traffic and Roadway Design (TranSystems) Jill Barrett – Public Involvement (Fitzgerald & Halliday) Margaret Collins – Land Use/Economic Development (Cambridge Economics) Sudhir Murthy – Traffic (TrafInfo) Deanna Peabody – Traffic (TrafInfo) Study Process Task 1 Task 2 Develop Goals & Objectives, Evaluation Criteria and Public Involvement Plan Task 3 Identify Existing and Future No-Build Conditions and Evaluate Issues Task 4 Task 5 Analyze Alternatives Develop Final Recommendations Develop Transportation Alternatives Task 1 Task 1 Goals and Objectives Study Area Evaluation Criteria Public Involvement Process Goals and Objectives Goals and Objectives Objectives Provide better multimodal connectivity between Fall River neighborhoods and its waterfront Enhance multimodal access to the future South Coast Rail Balance local and regional mobility Improve and enhance safety conditions Increase opportunities for economic development and land use Minimize potential impacts to the environment and community Focus Area Braga Bridge Wilbur Avenue Regional Transportation Impact Area Veterans Memorial Bridge I-195/Route 79 Interchange Design-Build Project N. Main Street Route 79 / Davol Street Corridor Eastern Avenue Watuppa Pond Highland Avenue Taunton River Evaluation Criteria Evaluation Criteria Categories Mobility Safety Health and Environmental Effects Land Use and Economic Development Community Effects Cost Public Involvement Plan Working Group Meetings Local officials & community members 7 meetings Provides input to the team on the study process Represents respective organizations with two-way communication Public Meetings 2 meetings Newsletters Study Website: www.mass.gov/massdot/route79 Task 2 Task 2 Existing Conditions Future No-Build Conditions Issues, Constraints and Opportunities 2035 Developments (No-Build Scenario) Restaurant on Remington Ave. 125 New Jobs Marina at City Pier 6 New Jobs Commonwealth Landing Mill Population – 112 525 New Jobs Regata Club 70 New Jobs South Coast Rail Focus Area Total Population – 112 726 New Jobs Existing and Future No-Build Conditions Traffic Level of Service Criteria 2012 Existing Traffic Operation – Regional Level Legend Braga Bridge Wilbur Ave AM PM Veterans Memorial Bridge Taunton River President Avenue Eastern Avenue Watuppa Pond 2035 No-Build Traffic Operation – Regional Level Legend Braga Bridge Wilbur Ave AM PM Veterans Memorial Bridge Taunton River President Avenue Eastern Avenue Watuppa Pond 2012 Existing Traffic Operation – Focus Area Level Legend AM PM 2035 No-Build Traffic Operation – Focus Area Level Legend AM PM Existing and Future No-Build Conditions Safety Three-Year Crash History (2008-2010) 10 Crashes Rate = 1.00 3 Crashes Rate = 0.28 14 Crashes Rate = 1.21 9 Crashes Rate = 0.54 2 Crashes Rate = 0.18 48 Crashes Rate = 1.75 16 Crashes Rate = 0.84 6 Crashes Rate = 0.48 45 Crashes Rate = 2.00 7 Crashes Rate = 2.09 Existing and Future No-Build Conditions Pedestrian and Bicycle Access Pedestrian and Bicycle Circulation Routes Pedestrian and Bicycle Circulation Routes Pedestrian and Bicycle Circulation Routes Pedestrian and Bicycle Circulation Routes Pedestrian and Bicycle Circulation Routes Pedestrian and Bicycle Circulation Routes Quequechan River Bike Trail and Regional Connections Existing Path Wilbur Avenue Planned Path Future Connector Braga Bridge Proposed Quequechan River Bike Trail Veterans Memorial Bridge N. Main Street Future Connector Existing Quequechan River Bike Trail President Avenue Watuppa Pond Taunton River Existing and Future No-Build Conditions Transit Future Transit – South Coast Rail Existing and Future No-Build Conditions Issues, Constraints and Opportunities Issues & Constraints - Transportation High crash rates on President Avenue and Davol Street A number of crashes involving pedestrians Lack of continuity in pedestrian paths of travel Lack of designated provisions for bicycles Limited connectivity between areas east and west of Rte. 79 Opportunities - Transportation Excess capacity on Route 79 allows some flexibility in development of alternatives Reconfiguration of Route 79/Davol Street Corridor will facilitate safety and circulation improvements for all modes Issues & Constraints – Economic Development and Land Use Economic: Low income/high unemployment/poverty Low Real Estate prices indicate weak demand Land Use: Underutilized sites on the west side of Davol Street Shallow sites on east side of Davol St. Rail barrier on east side of study area from Central to Pearce Street Opportunities – Economic Development and Land Use • South Coast Rail – Transit Oriented Development potential • Good supply of redevelopment sites along the river • Riverfront becoming a regional draw Task 3 Task 3 Transportation Alternatives Development Transportation Alternatives Development Short-Term Improvements Mid-Term Improvements Long-Term Alternatives Transportation Alternatives Development Short-Term and Mid-Term Improvements Short-Term Safety Improvements 45 Crashes Rate = 2.00 Short-Term Safety Improvements Short-Term Safety Improvements Short-Term Safety Improvements Short-Term Safety Improvements 48 Crashes Rate = 1.75 16 Crashes Rate = 0.84 Short-Term Safety Improvements Short-Term Safety Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Short-Term Bicycle Circulation Improvements Mid-Term Bicycle Circulation Improvements Transportation Alternatives Development Long-Term Alternatives Long-Term Alternatives Alternative 1: Elevated Limited Access Route 79 Alternative 2: Urban Boulevard Alternative 3: Boulevard with Frontage Roads Alternative 1: Elevated Limited Access Rte. 79 Alternative 1: Elevated Limited Access Rte. 79 Alternative 1: Elevated Limited Access Rte. 79 Alternative 1: Elevated Limited Access Rte. 79 Alternative 1: Elevated Limited Access Rte. 79 Alternative 1: Elevated Limited Access Rte. 79 Alternative 2: Urban Boulevard Alternative 2: Urban Boulevard Alternative 2: Urban Boulevard Alternative 2: Urban Boulevard Alternative 2: Urban Boulevard Alternative 2: Urban Boulevard Alternative 3: Boulevard with Frontage Roads Alternative 3: Boulevard with Frontage Roads Alternative 3: Boulevard with Frontage Roads Alternative 3: Boulevard with Frontage Roads Alternative 3: Boulevard with Frontage Roads Alternative 3: Boulevard with Frontage Roads Task 4 Task 4 Alternatives Analysis Assumed Development Mix Based on Commonwealth Landing Mill Consistent with 2002 Harbor Plan 5-Story Buildings Retail: One Floor Office: One Floor Residential: 3 Floors Maximum Development Potential Maximum Physical Build-Out Land Use Alternative 1 Elevated Route 79 Alternative 2 Urban Boulevard Alternative 3 Boulevard with Frontage Roads Parcel Size 10.1 ac Parcel Size: 10.6 ac Parcel Size: 15.0 ac Retail 265,912 sf 280,041 sf 398,209 sf Residential 797,737 sf 840,122 sf 1,194,626 sf Office 265,912 sf 280,041 sf 398,209 sf 1,329,561 sf 1,400,204 sf 1,991,044 sf Total Developable Area Supported Development Potential Maximum Build-Out Supported by Proposed Roadway Infrastructure Alternative Component Development Area Parking Requirements* Open Space within Parcels Construction Cost * Assumes structured parking Alternative 1 Elevated Rte. 79 Alternative 2 Urban Boulevard 1.3m sf (100% of max) 1.2m sf (85% of max) Alternative 3 Frontage Roads 0.3m sf (15% of max) 960 spaces 877 spaces 296 spaces 2.45 ac (24%) 3.73 ac (35%) 13.37 ac (89%) $100m $55m $55m Braga Bridge Wilbur Ave Alternative 1 - Traffic Operation: Regional Level Veterans Memorial Bridge Taunton River Highland Avenue President Avenue Eastern Avenue Watuppa Pond Alternative 1 - Traffic Operation: Focus Area Level Legend AM PM Alternative 2 – PM Peak Hour Traffic Diversions Braga Bridge Wilbur Ave Westbound diversion 200 vehicles per hour Veterans Memorial Bridge Eastbound diversion 300 vehicles per hour Taunton River Highland Avenue President Avenue Eastern Avenue Watuppa Pond Braga Bridge Wilbur Ave Alternative 2 - Traffic Operation: Regional Level Veterans Memorial Bridge Taunton River Highland Avenue President Avenue Eastern Avenue Watuppa Pond Alternative 2 - Traffic Operation: Focus Area Level Legend AM PM Alternative 3 – PM Peak Hour Traffic Diversions Braga Bridge Wilbur Ave Westbound diversion 100 vehicles per hour Veterans Memorial Bridge Eastbound diversion 200 vehicles per hour Taunton River Highland Avenue President Avenue Eastern Avenue Watuppa Pond Braga Bridge Wilbur Ave Alternative 3 - Traffic Operation: Regional Level Veterans Memorial Bridge Taunton River Highland Avenue President Avenue Eastern Avenue Watuppa Pond Alternative 3 – Traffic Operation: Focus Area Level Legend AM PM Alternative 1: Elevated Limited Access Rte. 79 Alternative 1: Elevated Limited Access Rte. 79 Alternative 2: Urban Boulevard Alternative 2: Urban Boulevard Alternative 3: Boulevard with Frontage Roads Alternative 3: Boulevard with Frontage Roads Evaluation Matrix – Mobility Alternatives MOBILITY No Build Rating Diversions Number of Traffic Signals Operation Discussion 1 – Elevated Route 79 with Cross Connections Rating Discussion 2 – At Grade Route 79 Boulevard Rating Discussion 3 – At Grade Route 79 with Frontage Roads Rating Discussion No Diversions No Diversions 500 Vehicles Diverted 300 Vehicles Diverted 2 Traffic Signals On Davol Street 7 Traffic Signals On Davol Street 4 Traffic Signals On Route 79 6 Traffic Signals On Route 79 and Davol Street 1 Intersection Operates at Level of Service D 1 Intersection Operates at Level of Service F 1 Intersection Operates at Level of Service D 2 Intersections Operate at Level of Service D All Intersections Operate at Level of Service C or better Legend Benefits Impacts Neutral 1 Intersection Operates at Level of Service E Some Moderate Substantial Evaluation Matrix – Mobility Alternatives MOBILITY Rating Travel Time Route 79 * (minutes) Travel Time Davol Street * (minutes) Pedestrian Delay (along President Ave from Lindsey St to Bicentennial Park) Pedestrian Time Savings (Turner St to City Pier) (Existing travel time is 17 min 34 sec) 1 – Elevated Route 79 with Cross Connections No Build Discussion AM Northbound 1.3 Southbound 1.3 AM Northbound 2.7 Southbound Rating PM 1.3 1.3 PM 2.7 1.8 2.6 Discussion AM Northbound 1.3 Southbound 1.3 AM Northbound 2.8 Southbound 2 – At Grade Route 79 Boulevard Rating PM 1.3 1.3 PM 3.7 2.0 2.3 Discussion AM Northbound 2.4 Southbound 2.7 AM Northbound 2.4 Southbound 3 – At Grade Route 79 with Frontage Roads Rating PM 2.9 2.9 PM 2.4 1.4 1.4 Discussion AM Northbound 3.4 Southbound 3.3 AM Northbound 3.9 Southbound 1.6 1.7 Distance: 450 feet PM Peak Hour: 1 min 24 sec Distance: 450 feet PM Peak Hour: 1 min 24 sec Distance: 450 feet PM Peak Hour: 1 min 46 sec Distance: 450 feet PM Peak Hour: 2 min 55 sec Distance: 3,400 feet 0 min 0 sec Distance: 560 feet PM Peak Hour: 13 min 30 sec Distance: 560 feet PM Peak Hour: 13 min 8 sec Distance: 560 feet PM Peak Hour: 11 min 59 sec * Travel Time along Route 79 and Davol Street is measured between Cedar Street and the Route 6 Overpass (approximately 1 mile) Legend Benefits Impacts Neutral Some Moderate PM 3.5 4.5 PM 4.7 Substantial Evaluation Matrix – Safety Considerations Alternatives SAFETY No Build Rating Pedestrian and Bicycle Safety Discussion • Existing wheelchair ramps and sidewalks do not meet current design standards and ADA requirements • No designated bicycle facilities are provided within the corridor • Sidewalks provided along one side of NB and SB Davol Streets 1 – Elevated Route 79 with Cross Connections Rating Discussion • ADA compliant crossings at all intersections and driveways. • Designated sidewalks and bike facilities provided throughout project limits. • East-west access provided for bicycles and pedestrians along 4 cross streets without conflict from vehicular traffic 2 – At Grade Route 79 Boulevard Rating Discussion 3 – At Grade Route 79 with Frontage Roads Rating • ADA compliant crossings at all intersections and driveways. • Designated sidewalks and bike facilities are provided throughout project limits. • Pedestrians and bicyclists have long crossing distances and conflicts at Route 79 intersections. Legend Benefits Impacts Neutral Discussion • ADA compliant crossings at all intersections and driveways. • Designated sidewalks and bike facilities are provided throughout project limits. • Pedestrians and bicyclists have long crossing distances and conflicts at Route 79 intersections. Some Moderate Substantial Evaluation Matrix – Safety Considerations Alternatives SAFETY No Build Rating Vehicular Safety Discussion • High crash locations at President Avenue at Lindsey Street, President Avenue at North Main Street, UTurn near Cedar Street, and Lindsey Street at Brownell Street • One east-west crossing limits emergency response 1 – Elevated Route 79 with Cross Connections Rating Discussion • Eliminated approach at high crash location of President Avenue and Lindsey Street • North Main Street intersection improved by adding protected left turn phase (short term) • U-Turn visibility and signage improved (short term) • Additional crossings provide improved emergency response times 2 – At Grade Route 79 Boulevard Rating Discussion • Eliminated approach at high crash location of President Avenue and Lindsey Street • North Main Street intersection improved by adding protected left turn phase (short term) • Unsafe access to Brownell is eliminated • U-Turn near Cedar Street is eliminated • Additional crossings provide improved emergency response times Legend Benefits Impacts Neutral 3 – At Grade Route 79 with Frontage Roads Rating Discussion • Eliminated approach at high crash location of President Avenue and Lindsey Street • North Main Street intersection improved by adding protected left turn phase (short term) • Lindsey & Brownell Intersection reconfigured • U-Turn near Cedar Street is eliminated • Additional crossings provide improved emergency response times Some Moderate Substantial Evaluation Matrix – Health and Environmental Effects Alternatives HEALTH AND ENVIRONMENTAL EFFECTS No Build Rating Discussion • Sustainable Design Emissions * * PM Peak Hour values provided • Existing corridor has 35.0 acres of impervious area (57% impervious) No treatment or Best Management Practices are in place for existing stormwater prior to discharge into the impaired, wild & scenic Taunton River Total Corridor Emissions: • CO – 6.55 kg • NOx – 1.27 kg • VOC – 1.52 kg Total Regional Emissions: • CO – 454,600 kg • NOx – 8,318 kg • VOC – 10,026 kg 1 – Elevated Route 79 with Cross Connections Rating Discussion • • • Alternative is 72% impervious area, increased over existing impervious area by 9.1 acres. Shifted roadway allows for more effective area for implementation of best management practices. Stormwater treated through BMPs prior to discharge will help improving the Taunton River’s condition Total Corridor Emissions: • CO – 11.91 kg • NOx – 2.31 kg • VOC – 2.77 kg Total Regional Emissions: • CO – 454,700 kg • NOx – 8,319 kg • VOC – 10,027 kg 2 – At Grade Route 79 Boulevard Rating Discussion • • • 3 – At Grade Route 79 with Frontage Roads Rating Alternative is 64% impervious area, increased from existing impervious area by 4.3 acres. Shifted roadway and wide median creates more area for landscaping and best management practices. Stormwater treated through BMPs prior to discharge will help improving the Taunton River’s condition • • • Total Corridor Emissions: • CO – 21.19 kg • NOx – 4.13 kg • VOC – 4.91 kg Total Regional Emissions: • CO – 454,800 kg • NOx – 8,321 kg • VOC – 10,030 kg Legend Benefits Impacts Neutral Discussion Alternative is 51% impervious area, decreased from existing impervious area by 3.9 acres. Shifted roadway and wide median creates most area for landscaping and best management practices. Stormwater treated through BMPs prior to discharge will help improving the Taunton River’s condition Total Corridor Emissions: • CO – 24.70 kg • NOx – 4.79 kg • VOC – 5.72 kg Total Regional Emissions: • CO – 454,700 kg • NOx – 8,319 kg • VOC – 10,029 kg Some Moderate Substantial Evaluation Matrix – Land Use and Economic Development Alternatives LAND USE AND ECONOMIC DEVELOPMENT No Build Rating Discussion 1 – Elevated Route 79 with Cross Connections Rating Discussion 2 – At Grade Route 79 Boulevard Rating Discussion 3 – At Grade Route 79 with Frontage Roads Rating Discussion Economic Development Potential • Development potential is limited to existing parcels along Davol Street • Perpetuates riverfront barrier • Only east-west connection is at President Avenue • Highest development potential • Complicated access to businesses for regional traffic • 3 new east-west connections improve access to businesses • High development potential • Better local business access • 3 new east-west connections improve access to businesses • Low development potential • Creates the most open space, including parcel near Old Brightman Street Bridge • Parcels can be used for Riverfront parking • 3 new east-west connections improve access to businesses Socio-Economic and Fiscal Impacts * • Limited to developments on existing parcels along Davol Street • 1,730 Jobs • 1,450 Housing Units • $54 Million Disposable Income • $3.5 Million Property Taxes • 1,550 Jobs • 1,300 Housing Units • $48 Million Disposable Income • $3.1 Million Property Taxes • 330 Jobs • 275 Housing Units • $10.3 million Disposable Income • $665,000 Property Taxes * All estimates for Alternatives 1, 2, and 3 are in addition to the No-Build Alternative Legend Benefits Impacts Neutral Some Moderate Substantial Evaluation Matrix – Community Effects Alternatives COMMUNITY EFFECTS No Build Rating Discussion 1 – Elevated Route 79 with Cross Connections Rating Discussion • • • Pedestrian and Bicycle Accommodations • • No provisions for bicyclists Only east-west connection for pedestrians is at President Avenue 4,900’ of sidewalk Pedestrian travel time from Lindsey Street to Bicentennial Park along President Avenue: 3.5 min • • • • • Sidewalk or shared use path is provided along Davol Streets and 4 eastwest connecting roads providing access to the waterfront and South Coast Rail. Bicycle accommodations provided throughout the project limits Extends shared use path from Veterans Memorial Bridge to the waterfront and South Coast Rail 5,300’ of sidewalk 8,100’ of shared use path. Pedestrian travel time from Lindsey Street to Bicentennial Park along President Avenue: 3.5 min 3 – At Grade Route 79 with Frontage Roads 2 – At Grade Route 79 Boulevard Rating Discussion • • • • • • • Rating Sidewalk or shared use path is provided along 4 east-west connecting roads, Route 79 and Davol Street to provide access to waterfront and South Coast Rail. Waiting to cross large Route 79 intersections increases pedestrian and bike delay. Bicycle accommodations provided throughout the project limits Extends shared use path from Veterans Memorial Bridge to the waterfront and South Coast Rail 6,800’ of sidewalk 8,000’ of shared use path. Pedestrian travel time from Lindsey Street to Bicentennial Park along President Avenue: 4 min Legend Benefits Impacts Neutral Discussion • • • • • • • Some Sidewalk or shared use path is provided along 4 east-west connecting roads and frontage roads to provide access to South Coast Rail and waterfront Waiting to cross large Route 79 intersections increases pedestrian and bike delay. Bicycle accommodations provided throughout the project limits Extends shared use path from Veterans Memorial Bridge to the waterfront and South Coast Rail 5,800’ of sidewalk 8,200’ of shared use path. Pedestrian travel time from Lindsey Street to Bicentennial Park along President Avenue: 5 min Moderate Substantial Evaluation Matrix – Community Effects Alternatives COMMUNITY EFFECTS No Build Rating Local Connectivity Discussion • No access provided from Brightman Street to Route 79 • Only east-west connection is at President Avenue 1 – Elevated Route 79 with Cross Connections Rating Discussion • 3 new two-way cross streets are constructed providing access to the waterfront, including direct access to South Coast Rail. • Converts Brightman Street to two-way road with access to NB Route 79. • Access from Brightman Street to SB Route 79 on-ramp via Lindsey Street and NB Davol Street 2 – At Grade Route 79 Boulevard Rating Discussion 3 – At Grade Route 79 with Frontage Roads Rating • 3 new two-way cross streets constructed for access to the waterfront, NB and SB Route 79 and direct access to South Coast Rail. • Converts Brightman Street to two-way road with direct access to and from NB Route 79 and access to SB Davol Street and SB Route 79. Legend Benefits Impacts Neutral Discussion • 3 new cross streets are constructed for access to the waterfront, NB and SB Route 79 and direct access to South Coast Rail. • Converts Brightman Street to a two-way road with direct access to and from NB Route 79 and access to SB Davol Street and Route 79. Some Moderate Substantial Evaluation Matrix – Community Effects Alternatives COMMUNITY EFFECTS No Build Rating Visual Impacts Discussion • “Visual barrier” of Route 79 remains • No open land available for green space, landscaping, or redevelopment 1 – Elevated Route 79 with Cross Connections Rating Discussion • “Visual barrier” created by Route 79 is worsened by raised elevations • Roadway shift creates 10.1 acres for green space and redevelopment. 2 – At Grade Route 79 Boulevard Rating Discussion 3 – At Grade Route 79 with Frontage Roads Rating • At-grade Route 79 removes “visual barrier” between Fall River and the waterfront. • Roadway shift creates 15.0 acres for green space and minor redevelopment. • Median between NB and SB Route 79 allows for landscaping. • At-grade Route 79 removes “visual barrier” between Fall River and the waterfront. • Roadway shift creates 10.6 acres for green space and redevelopment. • Large median allows for boulevard type landscaping. Legend Benefits Impacts Neutral Discussion Some Moderate Substantial Evaluation Matrix – Community Effects Alternatives COMMUNITY EFFECTS No Build Rating Construction Impacts Discussion • No construction impacts 1 – Elevated Route 79 with Cross Connections Rating Discussion • Construction will likely require 3 major construction stages (Davol Street Construction, NB Route 79 Construction, and SB Route 79 Construction) and 4 construction seasons due to construction of 10 bridges 3 – At Grade Route 79 with Frontage Roads 2 – At Grade Route 79 Boulevard Rating Discussion Rating • Construction will likely require 3 construction stages and 3 seasons (Davol Street Construction, NB Route 79 Construction, and SB Route 79 Construction). • Proposed Route 79 NB construction must occur under traffic and while maintaining all existing access to businesses, intersections and roadways. Legend Benefits Impacts Neutral Discussion • Construction will likely require 4 construction stages (Davol Street Construction, NB Route 79 Construction, SB Route 79 Construction, Ramp Construction) over 3 construction seasons • NB Route 79 must be constructed prior to NB Davol Street construction to maintain access to all roadways. • Reconstruction of the southbound ramps along Route 79 and Route 6 will require complicated staging and potential detours. Some Moderate Substantial Evaluation Matrix – Cost Alternatives COST No Build Rating Construction Cost * Discussion $0 1 – Elevated Route 79 with Cross Connections Rating Discussion $100 Million 2 – At Grade Route 79 Boulevard Rating Discussion 3 – At Grade Route 79 with Frontage Roads Rating $55 Million Discussion $55 Million * All costs are in 2013 dollars Legend Benefits Impacts Neutral Some Moderate Substantial Alternatives vs. Study Objectives Study Objective Provide better multimodal connectivity between Fall River neighborhoods and its waterfront Enhance multimodal access to the future South Coast Rail Balance local and regional mobility Improve and enhance safety conditions Increase opportunities for economic development and land use Minimize potential impacts to the environment and community NoBuild Alt. 1 Alt. 2 Alt. 3 Existing and Future No-Build Conditions Next Steps Next Steps and Study Schedule Aug Task 1 Task 2 Task 3 Task 4 Task 5 Task 6 Define Study Area Goals and Objectives Data Collection, Future Year Conditions, Issues Definition, Constraints Identification Alternatives Development Alternatives Analysis Draft and Final Recommendations Final Report Sep W 2012 Oct Nov Dec W Jan Feb Mar Apr May 2013 Jun Jul Aug Sep Oct Nov Dec W PP W W = Working Group Meeting P = Public Informational Meeting (P) = Public Informational Meeting if Necessary W W PP W (P) Questions Questions or Comments? www.mass.gov/massdot/route79