Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs 25% Design Public Hearing ● January 9, 2013 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Purpose of Tonight’s Hearing • Overview of 25% design plans • Update on new features and elements • Discuss design and construction schedule • Answer questions and hear comments Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Where are we in the project? Getting ready for construction STEP 1 Value Engineering Study This study – required by FHWA – suggested investigating removing Rte. 79 Viaduct at the I-195 Interchange. April 2009 STEP 2 Feasibility Study Detailed review of Value Engineering Study to assess feasibility of removing Rte 79 Viaduct at the I-195 Interchange. July 2009 STEP 3 Planning – Alternatives Study The level of design at the end of this stage is “conceptual.” December 2009 – July 2010 STEP 4 State (MEPA) & Federal (NEPA) Environmental Review This more detailed engineering and environmental analysis will lead to plans about 15% to 20% complete. STEP 5 Preliminary Engineering First intensive design stage. This step will take about 12-14 months and the design at the end will be 25% complete. May 2011 – Oct. 2012 August 2010 – September 2012 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs STEP 6 Hire DesignBuild Team to Finish Design & Build Project This stage will take about 44 months. Construction of Rte. 79 Project complete fall of 2016 Modified Design-Build Procurement Process • Phase 1 Qualifications Stage Complete • Phase 2 underway – Request for Proposals (RFP) released 12/28/12 – Confidential Contractor meetings with MassDOT – Technical/Price Proposals due 3/25/13 – Bid Opening on 5/1/13 – Contractor Notice to Proceed June 2013 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Project Background • Interchange has many structurally deficient bridges and is in disrepair • Original plan was rehabilitation • Commonwealth’s Accelerated Bridge Program provided funds for comprehensive solution • In-depth alternatives study aided by local Task Force determined removing elevated roadway was preferred alternative Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs What Has Happened So Far? • Alternatives study • State & federal environmental review • Task Force and public review • Key environmental permits received • 25% design engineering PERMITS SUMMARY Permit or Approval Rec’d National Environ. Policy Act Finding of No Significant Impact (FONSI) Mass. Environ. Policy Act Certificate Army Corps of Engineers Sect. 404 Category 2 General Permit Wetlands Protection Act Order of Conditions DEP Waterways Chapter 91 License pending • Preliminary right-of-way plans Coastal Zone Management Concurrence on Federal Consistency • Braga Bridge Phase I Sect.106 of National Historic Preservation Act Finding of No Adverse Effect DEP Section 401 Water Quality Certificate Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Project Purpose and Goals • Address structural deficiencies • Reduce life-cycle costs • Address substandard roadway geometry • Improve connections with I-195 and Rte. 79 • Meet Legislative funding requirements • Improve project-area aesthetics • Minimize impacts to historic and cultural resources • Remain consistent with area planning Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Proposed Project Rte. 79 New Connection to Anawan Street Repair and paint Braga Bridge Elevated Roadway removed; replaced at grade. Rte. 79 New Connection to Central Street New Water Street Connector at Rte. 79 4 lanes between Central and Anawan Milliken Connector Eastbound and Westbound Ramp from Central Street to I-195 eliminated Connector Street (Pocasset to Milliken) will become two-way Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Project Start: Columbia St. - Water Street Connector Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs I-195 On-ramp – Heritage State Park Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Community Boating Parking – Project End at Turnaround Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs I-195 Connections Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs MassDOT Right-of-Way Process • MassDOT Highway Division Right-of-Way Bureau is responsible for acquiring all the “right(s) of way” for road projects • Comply with the Uniform Relocation Assistance and Real Property Acquisition Act • Representatives from MassDOT ROW Bureau will contact property owners directly as the design progresses Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Property Impacts • Project is mostly within the existing public layout roadway right-of-way • No residential or business relocations anticipated • Two full commercial takings (small vacant or undeveloped parcels at 21 Broadway and gas co.) • Partial takings throughout project area for corner rounding, retaining walls and utility adjustments • Temporary easements for construction Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stormwater Improvements • Replace deficient and non-compliant drainage systems • Separate combined storm and sewer infrastructure in compliance with City’s CSO program • Address stormwater runoff treatment for controlled discharge • Improve the water quality condition of the Taunton River Watershed Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Pedestrian Improvements Pedestrian Improvements • Elevated roadway removed New & improved sidewalks throughout Shared-use path connects Milliken Blvd. & Rte. 79 • Three new signalized intersections • New and improved sidewalks • New crosswalks • Improved lighting Milliken Blvd. Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs • Shared-use path connecting Milliken Blvd. & Rte. 79. Environmental Mitigation • Erosion controls and Best Management Practices will protect wetlands, Crab Pond and the Quequechan and Taunton Rivers • Air quality: A variety of dust-control measures will be implemented • Noise control: Some overnight work (after 10 pm) will be necessary. Noise limits will be set to minimize noise impacts. Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Project Refinements Since Environmental Review • Braga Bridge steel repairs and painting project added to the Rte. 79 project • Landscaping and streetscape design • Heritage Park passive recreation improvements • Traffic management plans for combined work zones • Preliminary wall and bridge designs completed • Preliminary right-of-way plans • RFP issued to 3 short-listed Design-Build teams Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Braga Bridge Phase II Painting and Structural Repairs Ongoing Project Added to the Rte. 79 Interchange Project • Phase II of the project will complete the Braga Bridge work • Repairs to: – Structural elements – Concrete repairs – Expansion joints • Complete cleaning and painting underside of bridge Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Significant Advantages to Combining Rte. 79 and Braga Bridge Projects • Single contractor • Coordinated traffic management plans • Incentive and disincentive clauses are allowed • Communications with drivers, abutters, and residents will be coordinated • Shorter duration for Braga Bridge work Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Construction Overview • Construction summer 2013 though fall 2016 • Local and regional access provided by Rte. 79 will be provided at all times via alternate routes or Rte. 79 • Regional through traffic will be diverted to Rte. 24, I-195 and Veterans Memorial Bridge • Detours for local traffic will direct motorists to alternate roadways for local access Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Construction Overview, cont. • Detailed work plans will be developed with Fall River and Somerset input • Access and signage for Battleship Cove area will be provided throughout project • Emergency services will briefed by D-B Team at each major construction stage • Communications via website, changeable message signs, and public information campaign Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stage 1 Focus is on Rte. 79 corridor • Close Rte. 79 • Demolish Rte. 79 elevated road • Demolish ramps connecting I-195 and Rte. 79 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stage 1 Rebuild Rte. 79 At-Grade • Open Water Street Connector • Build new at-grade roadway from Central Street to new Water Street Connector Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stage 1 Rebuild Rte. 79 At-Grade • Open Water Street Connector • Complete work on Rte. 79 north of Central Street • Begin reconnecting Rte. 79 to I-195 at northern end of project Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stage 2 Focus is Spaghetti Ramps • Close Rte. 79 • Demolish Rte. 79 elevated road • Demolish ramps connecting I-195 and Rte. 79 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stage 2 Focus is on the Spaghetti Ramps • Rte. 79 is open • Demolish I-195 on- and offramps in interchange • Access to the Central Business District is via Plymouth Avenue interchange Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Stage 2 Focus is on Reconnecting Spaghetti Ramps • Access to/from Rte. 79 to I-195 restored • Access to CBD restored with Milliken Connector • Build I-195 ramp to Rte. 79 north Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Landscape & Streetscape South Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Landscape & Streetscape North • Landscaped buffers • Street trees Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Gates of the City Restoration New benches & bollards New pedestrian-only plaza Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Landscape & Streetscape • Street trees • Improvements to views, paths, nodes, continuity and image will be designed by DesignBuild contractor • Concept for streetscape improvements • 4 interpretive signs throughout project area Water St. Connector Proposed Waterfront District Entry Area Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Project-wide Improvements • Community Boating parking reconstructed • Utility improvements • Benches, picnic tables and bike racks Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Construction Stages: Detours Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Construction Staging • Early construction activities focus on upgrades and temporary improvements to facilitate construction and access • Vehicular, pedestrian, cyclist, large truck access to Battleship Cove area will be maintained at all times • Traffic signal monitoring required at 22 locations Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Construction Management Traffic Mitigation: – Staged construction – Alternate routes for traffic NOT headed to the CBD will be identified – Early and ongoing public information, variable message signs, media releases, e-alerts for drivers Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Next Steps • MassDOT will review 25% design hearing comments • MassDOT will secure its final permit (Ch. 91) • MassDOT will select Design-Build team spring 2013 and give contractor Notice to Proceed early summer • Selected contractor will hold kickoff public meeting summer 2013 • Rte. 79 Project construction: mid-2013 through 2016 • Braga Bridge Project construction ends spring 2017 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs How to Comment on the 25% design plans • Speak at this hearing—the verbatim transcript will be reviewed • Use the self-mailer in the handout or use your own stationery or paper (address in handout and below) • Fax or e-mail Thomas F. Broderick, P.E., Chief Engineer MassDOT Highway Division 10 Park Plaza Boston, MA 02116 Attention: Michael O’Dowd, Project File No. 605223 E-mail Stephanie.Boundy@state.ma.us Fax Chief Engineer fax 857-368-0618 Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs Questions & Answers www.mass.gov/massdot/route79project Route 79/I-195 Interchange Reconstruction & Braga Bridge Phase II Painting and Structural Repairs