White Cart Water Flood Prevention Scheme The problem… The White Cart Water has caused significant flood damage to homes and businesses in the south side of Glasgow. This normally shallow river can rise very quickly. More than twenty large floods have occurred since the early twentieth century. In 1984 over five hundred homes were flooded and personal possessions destroyed. The solution… Wh i te The implementation… Ca rt GLASGOW BARRHEAD A se ou h d ul B n ur Kittoch Bridge Kitt Flooding on Millbrae Crescent Flood storage area E 1,710 residential properties at risk of flooding 40 businesses at risk of flooding 20 significant floods in last 100 years Last significant flood in 1990 Flood events in January 2005 and October 2008 were very close to flooding property Cost of flood damage greater than £100m if nothing done Blackhouse Main rivers r Wetlands Kirkland Bridge Re-meandered channel Glasgow Location of principal components of project The catchment scale solution comprises three online flood storage areas and flood defence walls. The storage areas reduce river flows by up to 45% and result in 15% less flood defences and a reduction in wall height of over one metre in places thereby reducing the environmental and visual impact. Actual flood defence height at Spean Street Predicted Flood Outline – 0.5% Annual Probability Flood Event hW a te EAST KILBRIDE Flood defences oc rt Ca Key issues er at W n ar Dam i te Wh KEY Page 1 The implementation of the scheme was carried out over two phases. Contracts were completed by Carillion and VolkerStevin and result in those properties currently at risk being protected from the current 0.5% annual probability event. Kirkland Bridge flood storage area The provision of flood storage is an environmentally sustainable method of flood risk management for Glasgow whilst providing much wider benefits. A significantly higher wall would have been required if no flood storage was provided The largest vortex flow controls in the world were installed at each of the flood storage areas to reduce flows in the flood risk areas. They have no moving parts and are passable by fish and mammals. The provision of ledges through the culverts ensure that mammals can safely pass through the dams. In addition the vortex flow controls minimise the frequency of inundation and allow the land upstream to remain in agricultural use. Spean Street flood defence wall and planting www.whitecartwaterproject.org White Cart Water Flood Prevention Scheme Contract 1: Flood Storage Areas Contractor: Carillion Contract 2: Flood Defences Contractor: VolkerStevin Contract 1 comprises the construction of the three flood storage areas. The contract started in February 2008 and was completed in 2011. Contract 2 comprises the construction of 4.5 kilometres of flood walls, six pumping stations and the raising of two bridges together with significant environmental works in a very densely developed urban environment. The contract commenced in October 2008 and was completed in 2011. The majority of materials required to construct the earth embankments were sourced from on site borrow pits rather than importing. Excavated rock was reused on site in gabions and roads to avoid off site disposal and the need to import materials. This phase presented a number of challenges including the management of invasive species, contaminated land, dealing with numerous utilities and minimising the impact on an important wildlife corridor as well as keeping the several hundred affected residents fully informed. As well as the major civil engineering works, extensive environmental works were carried out including the creation of new wetland habitat, re-meandering a straightened river channel and the creation of new habitats for birds, otters and badgers and ensuring fish and mammals could pass through the dams unharmed. The recycling and re-use of materials was important with haul road materials used to create mammal ledges and as scour protection to newly formed riverbanks. River banks seeded with native species Boulders and baffles in culvert to enable passage by fish Kirkland Bridge – artificial nesting wall used by over a dozen nesting Sandmartin pairs Invasive species were prevalent Millbrae Crescent garden reinstatement • 4.5km flood defence walls and embankments • Six underground pumping stations • Two raised footbridges • Redevelopment of existing park • Embellishment of gardens and allotments • 1,000 trees planted • Creation of artificial habitats for birds, bats and otters • 20% recycled materials • Consultation was essential Collecting seed from existing wetland Key KeyFacts facts • • • • • • Kirkland Bridge – wetlands and wet woodland tree planting Page 2 Key KeyFacts facts Catchment scale solution 2.6Mm3 flood storage 9 hectares species rich wetlands 180,000m3 locally won embankment fill 6,000 trees and scrub planted Post construction environmental surveys and monitoring Completed flood defences at Tantallon Road www.whitecartwaterproject.org