MEMORANDUM TO: FR: RE: DA: Richard A. Davey, Secretary & CEO Frank DePaola, Highway Division Administrator Ongoing Work in the MHS Tunnels April 20, 2012 To follow is a summary of maintenance and construction activities performed over the last week in the Metropolitan Highway System tunnels. Please feel free to contact me if you need additional information. Overnight work: • • • • • • • • Contractors continue to make repairs to tunnel joints in the area of Ramp R-T, linking Essex Street to I-93 Northbound. The work is part of MassDOT’s ongoing efforts to repair water infiltration. Water infiltration repairs to nearby Ramp A-CN are ongoing. Work is also occurring in the Northbound side of the O’Neill Tunnel itself. Additional water infiltration repair work is occurring at Ramp CN-SA, near Exit 26 from I-93 Northbound, Ramp SA-CS (Surface Artery Southbound to I-93 Southbound), Ramp CS-P (I-93 Southbound to Purchase Street) in the area of Exit 23, Ramp S-N (Leverett Circle to I-93 Northbound), Ramp L-CS (Leverett Circle to I-93 Southbound) and Ramp SA-CT (Surface Artery Southbound to Callahan Tunnel). MassDOT replaced 8 cases of lamps and six ballasts in the HOV Tunnel. MassDOT also replaced 6 cases of lamps and three ballasts in the Ted Williams Tunnel Westbound. A contractor is continuing substructure repairs in the Storrow Tunnel Westbound under Leverett Circle. This work is scheduled to last through the end of the summer. MassDOT has an ongoing routine inspection underway throughout the tunnel system. That ongoing inspection will require periodic closures of various parts of the system to allow for better access by inspectors. Last week’s inspection work included inspections of the Connector Tunnel (both directions), I-93 Northbound near the exit portal, and the Prudential Tunnel Westbound. A contractor is also performing a routine ceiling inspection in the I-90 Connector Tunnel Eastbound and in the Prudential Tunnel Eastbound. A contractor continues to install conduit for fiber optic cables on the South wall of the Prudential Tunnel Eastbound. A contractor continued milling pavement in the Prudential Tunnel Westbound. Milling is grinding and removing pavement from the roadway so that repairs can be made below the wearing surface of the roadway. Repairs to the concrete slab have also begun. The contractor is also sounding concrete to determine where there may be weak concrete in need of repair. • • • • • • • • A contractor cleaned trench drains in the area of Tunnel ST-S (Sumner Tunnel to Storrow Drive). A contractor is inspecting the drain grates throughout the I-93 Tunnels (both directions). The contractor is in the process of replacing these grates. The contractor tightened bolts on grates on ramps SA-CN linking the Sumner Tunnel to I-93 Northbound, and ST-CN, Cross Street to I-93 Northbound. The contractor is also inspecting grates in Tunnel S-N (Storrow Drive Eastbound to Northbound Leverett Ramp) and the Dewey Square Tunnel. MassDOT repaired two cameras in the HOV Tunnel. MassDOT placed pavement striping at Ramp L-CS (Leverett Circle to I-93 Southbound) as part of spring maintenance. MassDOT and the Massachusetts State Police inspected the Prudential Tunnel Eastbound in the area of Exit 22. MSP was monitoring activity by homeless individuals, and clearing those individuals from the tunnel system. MassDOT performed a routine inspection of the jet fans in the Ted Williams Tunnel Westbound. MassDOT is in the process of installing a new carbon monoxide detection and monitoring system in the City Square (CANA) Tunnel Northbound. MassDOT recently installed a similar system in the Prudential Tunnel (both directions). A MassDOT maintenance crew removed handrail studs from the top of the safety catwalk in the I-93 Northbound Tunnel. This work is in conjunction with MassDOT’s efforts to remove certain handrails in the MHS tunnels. The studs that remained after removal of the rails posed a tripping hazard. Removal of those studs will continue as the handrails are removed in selected areas.