Route 2 / I-95 Bridge Replacement Project Public Information Meeting – February 24, 2015 Route 2 / I-95 Bridge Replacement Project Agenda • • • • • • • • Introductions Current Project Schedule Project Overview, Background and Objectives Key Project Elements / Construction Sequencing Environmental Protections Construction Progress / Upcoming Activities Communications Program Contact Information Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Design-Build Team SPS New England, Inc. (Prime Contractor) DW White Construction, Inc. (Subcontractor) TranSystems (Lead Designer) Specialty design subconsultants include: • Haley & Aldrich, Inc. – geotechnical engineering • Regina Villa Associates, Inc. – public outreach • Green International Affiliates, Inc. – landscape architecture Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Current Project Schedule • Construction Began – June 2014 • Design Complete – April 2015 • Route 2 EB Traffic Shifted to New Median Bridge – Summer 2015 • Bridge Construction Complete – Spring 2016 • Construction Substantially Complete – November 2016 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Project Overview • Route 2 carries 67,000 vehicles per day • Existing bridges are “structurally deficient” and “functionally obsolete” • I-95 in need of repaving, safety and drainage improvements Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Project Background and Objectives • Existing Bridge Conditions Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Key Project Elements • Route 2 WB will be reconfigured to include an auxiliary lane approaching the I-95 NB onramp Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Key Project Elements • Route 2 WB will be reconfigured approaching I-95 SB to improve the merge and accelerations lengths for the I-95 SB on and off ramps • All 8 on and off ramps will be improved geometrically I-95 Route 2 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Key Project Elements • Route 2 WB will be reconfigured approaching I-95 SB to improve the merge and accelerations lengths for the I-95 SB on and off ramps • All 8 on and off ramps will be improved geometrically I-95 Route 2 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – Route 2 • Stage 1A – Partial Demolition of Existing Bridges July 2014 – February 2015 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – Route 2 • Stage 1B – Westbound Bridge Construction February 2015 – Summer 2015 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – Route 2 • Stage 2A – Existing Eastbound Bridge Demolition August 2015 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – Route 2 • Stage 2B – New Eastbound Bridge Construction Summer 2015 – Spring 2016 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – Route 2 • Stage 3 – Remaining Bridge Demolition Spring 2016 – November 2016 Final Bridge Configuration Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – I-95 • Milling and Installing Intermediate Pavement Course July 2014 – October 2014 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – I-95 • Center Median Reconstruction April 2015 – May 2016 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Sequencing – I-95 • Shoulder and Drainage Construction Spring 2015 – May 2016 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Environmental Protections • Wetlands clearly marked • Erosion/Sedimentation control throughout site • Invasive species removed within areas of disturbance Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Environmental Protections • Wetlands clearly marked • Erosion/Sedimentation control throughout site • Invasive species removed within areas of disturbance • Stormwater management – Existing basins upgraded – New features added – Landscape plantings for softening & screening Public Information Meeting February 24, 2015 Landscape Buffer next to reservoir Route 2 / I-95 Bridge Replacement Project Construction Progress • Completed milling and installing intermediate pavement course on I-95 • Demolition of high-speed lane of existing bridges Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Construction Progress • Completed milling and installing intermediate pavement course on I-95 • Demolition of high-speed lane of existing bridges Upcoming Activities • Construction of new bridge • Median reconstruction on I-95 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Public Outreach • Project website • E-Blast updates • Social media Public Information Meeting February 24, 2015 • Press advisories • Business coordination • Public meeting Route 2 / I-95 Bridge Replacement Project Public Outreach Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Contact Information • Project website: www.mass.gov/massdot/rt2i95bridges • Donny Dailey, MassDOT Legislative Liaison (617) 945-4272, or donny.dailey@state.ma.us • Project Field Office Phone Number: (781) 790-5261 Public Information Meeting February 24, 2015 Route 2 / I-95 Bridge Replacement Project Thank you for attending! Public Information Meeting February 24, 2015