Route 18 Widening Project Abington – Weymouth | Project File No. 601630 Public Information Meeting October 17, 2012 | 7:00pm Weymouth High School Route 18 Widening Project Abington – W eymouth | Project File No. 601630 Route 18 Project Team • MassDOT • Prime Consultants – Tetra Tech – HNTB • Specialty Subconsultants – GZA GeoEnvironmental, Inc. (Soils/Geotechnical) – Survey and Mapping Consultants (Mapping/State Highway Alt) – HMMH (Noise) Route 18 Widening Project Abington – W eymouth | Project File No. 601630 2 Route 18 Project Limits Route 18 Widening Project Abington – W eymouth | Project File No. 601630 3 Route 18 Completed Projects Route 18 Widening Project Abington – W eymouth | Project File No. 601630 4 Route 18 Completed Projects Route 18 Widening Project Abington – W eymouth | Project File No. 601630 5 Route 18 Existing Issues • • • • • • • Route 18 Congestion Cut-Through Traffic on Local Streets Intersection Safety and Sub-Optimal Operation Deficient Pedestrian Accommodation Deficient Bicycle Accommodation Structurally Obsolete Bridge over Commuter Rail Drainage Route 18 Widening Project Abington – W eymouth | Project File No. 601630 6 Route 18 Existing Issues | Project Goals • Route 18 Congestion | Relieve Congestion • Cut-Through Traffic on Local Streets | Reduce Cut-Throughs • Intersection Safety and Sub-Optimal Operation | Improve Inter. Safety • Deficient Pedestrian Accommodation | Improve Ped. Accom. • Deficient Bicycle Accommodation | Improve Bike Accom. • Structurally Obsolete Bridge over Commuter Rail | Replace Bridge • Drainage | Reduce Flooding Route 18 Widening Project Abington – W eymouth | Project File No. 601630 7 Existing Average Week Day Daily Traffic (AWDT) Route 18 Widening Project Abington – W eymouth | Project File No. 601630 8 Existing AM Peak Hour Traffic Volumes Route 18 Widening Project Abington – W eymouth | Project File No. 601630 9 Existing PM Peak Hour Traffic Volumes Route 18 Widening Project Abington – W eymouth | Project File No. 601630 10 Future 2030 AM Peak Hour Traffic Volumes Route 18 Widening Project Abington – W eymouth | Project File No. 601630 11 Future 2030 PM Peak Hour Traffic Volumes Route 18 Widening Project Abington – W eymouth | Project File No. 601630 12 Existing AM Peak Hour Level of Service (LOS) Route 18 Widening Project Abington – W eymouth | Project File No. 601630 13 Future 2030 AM Peak Hour LOS With Completed Project Route 18 Widening Project Abington – W eymouth | Project File No. 601630 14 Existing PM Peak Hour Level of Service (LOS) Route 18 Widening Project Abington – W eymouth | Project File No. 601630 15 Future 2030 PM Peak Hour LOS With Completed Project Route 18 Widening Project Abington – W eymouth | Project File No. 601630 16 Proposed Project Construction • Widen Route 18 – (2) 11.5’ Travel Lanes Each Direction – (1) 5.0’ Shoulder Each Direction – (1) 5.5’ Sidewalk Each Direction • Reconstruct Signalized Intersections – Pond Street / Route 58 – Shea Drive • Replace Bridge over Commuter Rail Route 18 Widening Project Abington – W eymouth | Project File No. 601630 17 Proposed Project Construction (cont.) • Retrofit Completed Intersections for Optimal Operation and Safety – Randolph Street (Route 139) – Pond Street / Pleasant Street – West Street / Middle Street • Stormwater Mitigation • Wetland Mitigation Route 18 Widening Project Abington – W eymouth | Project File No. 601630 18 Route 18 Typical Section Route 18 Widening Project Abington – W eymouth | Project File No. 601630 19 Pond Street / Route 58 Intersection Trotter Rd Route 18 – Main St Route 18 Widening Project Abington – W eymouth | Project File No. 601630 20 Coordination with Proposed Parkway Route 18 – Main St Route 18 Widening Project Abington – W eymouth | Project File No. 601630 21 Route 18 Bridge Replacement Route 18 – Main St Route 18 Widening Project Abington – W eymouth | Project File No. 601630 22 Route 18 – Main St Shea Dr Shea Drive / Route 18 Intersection Route 18 Widening Project Abington – W eymouth | Project File No. 601630 23 Utility Work • • • • • Water Service Valves Reset – All Properties Hydrant Relocations Utility Poles Relocated to Back of Proposed Sidewalk Radio Operated Emergency Call Boxes Installed Gas Main Replaced – Specific Locations Route 18 Widening Project Abington – W eymouth | Project File No. 601630 24 Stormwater System • • • • New Catch Basins at the New Curb Lines Replacement of Drainage Trunk Lines Reconstruction of All Outlets Construction of Detention Basins (Recharge where feasible) Route 18 Widening Project Abington – W eymouth | Project File No. 601630 25 Wetland Impact • Total Permanent BVW Impact – Weymouth +/- 6,000 sf – Abington +/- 5,500 sf – SWNAS +/- 450 sf • Construct Low Retaining Walls to Reduce Impact Route 18 Widening Project Abington – W eymouth | Project File No. 601630 26 Wetland Mitigation • Permanent Wetland Impacts Mitigated at Southfield • 15,000 sf of Mitigation Proposed in Weymouth • 15,000 sf of Mitigation Proposed in Abington Route 18 Widening Project Abington – W eymouth | Project File No. 601630 27 Maintenance of Traffic Highway: Construction Stages 1 & 2 Route 18 Widening Project Abington – W eymouth | Project File No. 601630 28 Maintenance of Traffic Highway: Construction Stage 3 Route 18 Widening Project Abington – W eymouth | Project File No. 601630 29 Maintenance of Traffic Highway: Construction Stage 4 Route 18 Widening Project Abington – W eymouth | Project File No. 601630 30 Maintenance of Traffic at Bridge Construction Workzone Route 18 Widening Project Abington – W eymouth | Project File No. 601630 31 Maintenance of Traffic Temporary Bridge Plan: East Alignment Route 18 Widening Project Abington – W eymouth | Project File No. 601630 32 Maintenance of Traffic Temporary Bridge Profile: East Alignment Route 18 Widening Project Abington – W eymouth | Project File No. 601630 33 Maintenance of Traffic Temporary Bridge Plan: West Alignment Route 18 Widening Project Abington – W eymouth | Project File No. 601630 34 Maintenance of Traffic Temporary Bridge Profile: West Alignment Route 18 Widening Project Abington – W eymouth | Project File No. 601630 35 Goals of the Bridge Replacement • Accommodate the roadway widening • Implement all current standard safety features and code requirements • Increase live load capacity • Provide sidewalks on both sides • Provide adequate clearances over railroad • Provide durable, lowmaintenance structure Route 18 Widening Project Abington – W eymouth | Project File No. 601630 36 Existing Bridge • Through-girder config. – cannot be widened • No vehicular railings • Substandard horizontal clearance for railroad • Single span • Severe skew • Built in 1935 Route 18 Widening Project Abington – W eymouth | Project File No. 601630 37 Existing Bridge • Deteriorated, poor quality concrete – abutments can’t be salvaged Route 18 Widening Project Abington – W eymouth | Project File No. 601630 38 Features of the Proposed Bridge • • • • Four 11’-6” wide lanes with 5’ wide shoulders on each side Two 5’-6” wide sidewalks with protective screens Standard vehicular barriers with protective screens Maintains vertical under-clearance with improved horiz. clearance Route 18 Widening Project Abington – W eymouth | Project File No. 601630 39 Structural Details of the Proposed Bridge • • • • • • • • • • 364’ long 4-span continuous structure 4’-3” deep steel I-girders Precast concrete deck Low-maintenance weathering steel Semi-integral abutments No skew Steel integral cap beams Precast abutment components Drilled shaft foundations Precast MSE retaining walls on approaches Route 18 Widening Project Abington – W eymouth | Project File No. 601630 40 Proposed Bridge in Relation to Existing Route 18 Widening Project Abington – W eymouth | Project File No. 601630 41 Pier with Integral Cap Beams Route 18 Widening Project Abington – W eymouth | Project File No. 601630 42 Environmental Documentation & Permits Law or Regulation Permit Review or Approval Agency with Jurisdiction Status Federal NEPA Finding of No Significant Impact (FONSI) FHWA Issued September 15, 2009 NPDES NPDES Construction General Permit US EPA To be filed by contractor Section 404 of the Clean Water Act Massachusetts General Permit Category 2 US Army Corps of Engineers Section 106 of the National Historic Preservation Act Determination of No Effect FHWA and MHC MEPA SEIR Secretary’s Certificate Energy & Environmental Affairs MA Wetlands Protection Act Superseding Order of Conditions Weymouth & Abington MassDEP To be filed MA Wetlands Protection Act Variance (Combined) | Weymouth & Abington MassDEP To be filed Section 401 of the Clean Water Act 401 Water Quality Certificate MassDEP To be filed 2/3 Vote State Legislature To be filed Coordination under MESA MA NHESP To be filed Article 97 of the MA Constitution to approve the transfer of Conservation Land MA Endangered Species Act MA Wetlands Protection Act MA Wetlands Protection Act Article 97 of the MA Constitution to approve the transfer of Conservation Land Article 97 of the MA Constitution to approve the transfer of Conservation Land To be filed Issued April 10, 2008 and April 22, 2008 State Denial | Order of Conditions Weymouth & Abington Order of Conditions Unanimous Vote 2/3 Vote Local Issued September 28, 2012 Weymouth & Abington Conservation Commissions SWNAS Conservation Commission Weymouth Conservation Commission To be filed Weymouth Town Council To be filed Route 18 Widening Project Abington – W eymouth | Project File No. 601630 To be filed To be filed 43 Affected Environment Geology Business Access Topography Community Services Soils Noise Land Use Air Quality Zoning Stormwater Ground Water and Surface Water Cultural Resources Wetlands Visual and Aesthetics Flood Plains Hazardous Materials Listed Species Utilities Socioeconomics Traffic Route 18 Widening Project Abington – W eymouth | Project File No. 601630 44 Impact Assessment Noise • Noise Levels Increase • Noise Wall Feasibility – One Location is Feasible Stormwater • 401,387 SF Increase in Impervious Pavement Area • WPA Stormwater Management Variance Wetlands • 11,950 SF Impacted • WPA Variance Route 18 Widening Project Abington – W eymouth | Project File No. 601630 45 Right of Way • Identify & Measure Impacts from Construction – ROW Plans • Property Ownership / Title Examination • Appraisals • Interviews • Payments Awarded Route 18 Widening Project Abington – W eymouth | Project File No. 601630 46 Construction Cost & Schedule • • • • • $30 Million (2011 Dollars) Public Hearing – Fall 2012 75% Design Submission – Spring 2013 100% Design Submission – Fall 2013 2 ½ - 3 Year Construction Duration Route 18 Widening Project Abington – W eymouth | Project File No. 601630 47 Comments / Additional Information Donald Dailey, Office of Government Affairs Massachusetts Department of Transportation Email: Donald.Dailey@state.ma.us Phone: 617.945.4272 Project Website: http://www.massdot.state.ma.us/highway/HighlightedProjects/ Route18WideningProject.aspx Soon to be available: http://www.mass.gov/massdot/Route18WideningProject Route 18 Widening Project Abington – W eymouth | Project File No. 601630 48