ROAD SAFETY AUDIT Chief Justice Cushing Highway (Route 3A) at Kilby Street Town of Hingham May 27, 2010 Prepared For: MassDOT Highway Division Prepared By: BETA Group, Inc. Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Table of Contents Project Data ................................................................................................................................. 1 Background ................................................................................................................................. 2 Project Description ..................................................................................................................... 2 Audit Observations ..................................................................................................................... 5 Potential Safety Enhancements ................................................................................................. 6 Summary of Road Safety Audit ................................................................................................. 9 List of Appendices Appendix A. Appendix B. Appendix C. Appendix D. Appendix E. RSA Meeting Agenda RSA Audit Team Contact List Detailed Crash Data Speed Regulations Traffic Volume Data List of Figures Figure 1. Locus Map .............................................................................................................................. 3 List of Tables Table 1. Table 2. Table 3. Participating Audit Team Members ....................................................................................... 1 Estimated Time Frame and Costs Breakdown ....................................................................... 7 Potential Safety Enhancement Summary ............................................................................. 10 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Project Data A Road Safety Audit for the intersection of Chief Justice Cushing Highway (Route 3A) and Kilby Street in the Town of Hingham was held on May 10, 2010 at the Sons of Italy Lodge at 88 Chief Justice Cushing Highway, immediately adjacent to the intersection. As indicated in Table 1, the audit team consisted of representatives from State, Regional and Local agencies and included a cross-section of engineering, planning, emergency response and legislative expertise. Table 1. Participating Audit Team Members Audit Team Member Bonnie Polin Lisa Schletzbaum Jocelyn DeWire Robert Gregory Barbara LaChance Edward Feeney Stephen Burm Sgt. David Horte Efi Pagitsas Tony Keady David Killory Jeff Hanorahan Harry Sylvester Randy Sylvester Roger Fernandes Betty Foley Greg Lucas Christine Keches Tony Lionetta Agency/Affiliation MassDOT Highway Division – Safety Section MassDOT Highway Division – Safety Section MassDOT Highway Division – Project Management MassDOT Highway Division District 5 - Projects MassDOT Highway Division District 5 - Traffic MassDOT Highway Division District 5 - Traffic Rep. Bradley’s office Hingham Police Department Boston Region MPO Hingham School Dept – Principal, East Elementary Hingham School Dept – Dir. Of Business & Support Svc Hingham DPW Hingham DPW Hingham DPW Hingham DPW Hingham Asst. Town Administrator BETA Group, Inc. BETA Group, Inc. BETA Group, Inc. Page 1 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Background The Federal Highway Administration defines a Road Safety Audit (RSA) as the formal safety examination of an existing or future road or intersection by an independent, multidisciplinary team. The purpose of an RSA is to identify potential safety issues and possible opportunities for safety improvements considering all roadway users. A Road Safety Audit was scheduled for the intersection of Chief Justice Cushing Highway (Route 3A) and Kilby Street because of concerns from area residents about pedestrian safety, specifically for schoolchildren. Area children attend the East Elementary School which is a newly-constructed school approximately ½ mile from the intersection which opened in September 2009. Roadway and intersection improvements have also been made in the area as the result of the Greenbush MBTA commuter rail line, including signalization of the intersection of Route 3A and Summer Street, which is approximately 700 feet west of the Route 3A/Kilby Street intersection. The purpose of the RSA is to identify both short term and long term safety improvements that can be made at the subject intersection. Project Description The intersection of Chief Justice Cushing Highway (Route 3A) and Kilby Street, shown in Figure 1, is located in the eastern portion of Hingham. Chief Justice Cushing Highway (Route 3A) is a state-owned roadway functionally classified as an Urban Principal Arterial. Kilby Street is a town-owned roadway functionally classified as an Urban Minor Arterial. Chief Justice Cushing Highway (Route 3A) is a significant regional roadway, connecting Hingham with neighboring towns in the South Shore. Route 3A runs essentially parallel to Route 3 but provides more direct access to the town centers of Hingham and other neighboring South Shore towns. Route 3A is a north-south roadway, but has primarily an east-west alignment in Hingham. Kilby Street is an important local roadway, connecting Route 228 and Route 3A with Rockland Street, which provides access to the coastal areas of Hingham and Hull. Route 3A and Kilby Street form a 4-way intersection, with Kilby Street under STOP control. Route 3A provides a single travel lane and a shoulder in each direction. Kilby Street provides a single travel lane in each direction with no shoulder. A painted crosswalk is provided across Route 3A on the western leg of the intersection. Continuous sidewalks are provided along the west side of Kilby Street both north and south of Route 3A. There are no sidewalks along Route 3A, and no pedestrian signals or handicap access ramps at the intersection. The large corner radii at the intersection and the placement of the crosswalk make the Route 3A Southbound (looking eastbound) at Kilby Street Page 2 ³ KLA ROC S ND E TRE D IN W R SO LO CO NY A RO E IV DR E IV DR OR AN M OLD T D KIL B YS ET TR EE T E STR ER MM SU 3A CHIEF JUST ICE CUSHIN PROJECT LOCATION G HIGHWAY M M SU 3A ER E RE ST T 228 C O LL IN S R ST T EE ET STRE EAST EA ST G 228 AT E LA N E East Elementary 0 500 N LAI BER AM H C RU N 315 Norwood Park South Norwood, MA 02062 781.255.1982 BETA@BETA-inc.com 1,000 Feet Chief Justice Cushing Highway (Route 3A) at Kilby Street HINGHAM, MA Figure 1 Location Map Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. crosswalk very long, almost 100 feet in length. Audit participants attempting to cross Route 3A during the audit determined that a pedestrian would have to step a significant distance into the roadway to be visible to an approaching vehicle. There are post-mounted yellow and red flashers on the four corners of the intersection. Incandescent bulbs and overgrowth of brush reduce the visibility of the flashing signals. It was noted during the audit that the intersection was signalized many years ago, but that the signals were removed following a signal removal warrant study. Speed regulations maintained by MassDOT Highway Division establish a 45 MPH speed limit for Chief Justice Cushing Highway (Route 3A), which is not posted in the vicinity of the intersection. The land use of the surrounding area is primarily residential. The Sons of Italy Lodge is on the northeast corner of the intersection. The southeast corner of the intersection is a residence with driveway access to Kilby Street, while the southwest corner of the intersection is wooded. There is an empty lot on the northwest corner of the intersection, bordered by a chain link fence. Town of Hingham personnel could not recall a prior business on the site. There are multi-family apartment buildings on Route 3A to the west of Kilby Street. The MBTA commuter rail Greenbush Line crosses Kilby Street at an at-grade crossing 600 feet north of Route 3A, with a lighted pedestrian walkway providing access from Kilby Street to the Nantasket Junction Station, which has vehicle access from Summer Street. Crash data were provided by the Hingham Police Department and summarized by MassDOT for three years and are included in the Appendix. There were a total of 15 crashes at the intersection within the period from December 2006 to December 2009, which are mapped on the collision diagram included in the Appendix. Ten of the 15 mapped crashes were angle type crashes involving a vehicle traveling northbound on Kilby Street. Five of those ten crashes were between a northbound vehicle and a vehicle traveling eastbound (southbound) on Route 3A; four involved a northbound vehicle and a vehicle traveling westbound (northbound) on Route 3A; and one involved a vehicle turning left from Route 3A westbound (northbound) onto Kilby Street. Six of the 15 crashes involved a young driver, which is a driver under the age of 20. Four of those six crashes occurred during the summer months. Half of the overall crashes at the intersection occurred in the summer months of July and August. The crash rate for the intersection is 1.16 crashes per million entering vehicles (MEV), which is almost two times the statewide average for unsignalized intersections. Average Daily Traffic (ADT) information was obtained from MassDOT Highway Division records in advance of the audit. Data taken in 1999 show an ADT of 14,100 vehicles per day (vpd) on Route 3A both east and west of Kilby Street. Additional ATR data were provided by MassDOT following the audit. MassDOT collected ATR data for the four legs of the intersection from January 13 to 15, 2010. The data show an ADT of 11,500 vpd on Route 3A east of Kilby Street and 11,000 vpd on Route 3A west of Kilby Street. The ADT for Kilby Street is 1,800 vpd north of Route 3A and 1,900 vpd south of Route 3A. Manual Turning Movement Counts (TMC) were also provided by MassDOT. Data was collected on Thursday, January 14, 2010. The data show a clear commuter flow of traffic on Route 3A, with much heavier northbound traffic in the morning and heavier southbound traffic in the afternoon. The morning peak hour occurred from 7:15 AM to 8:15 AM, with the afternoon peak hour from 4:30 PM to 5:30 PM. Complete ATR and TMC data are included in the Appendix. Page 4 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Audit Observations Following a brief introduction to the RSA process and a summary of traffic volumes and crash information, the audit participants were asked to discuss safety issues at the intersection of Chief Justice Cushing Highway (Route 3A) and Kilby Street. Audit participants then conducted a site visit as a group, at which time they offered observations on safety concerns and deficiencies. A summary of those major safety considerations follows: • Pedestrian Accommodations – This audit was conducted because of concerns from area residents regarding pedestrian safety. As such, both existing pedestrian accommodations and potential improvements for pedestrians were a large part of the audit discussion. A summary of the issues raised by audit participants is as follows: o Length of crosswalk. The crosswalk crossing Route 3A at Kilby Street is almost 100 feet in length as a result of the large corner radii at the intersection. Large corner radii were likely provided to accommodate large trucks, several of which were observed navigating turns at the intersection during the audit. The length of the crosswalk requires pedestrians to enter the crosswalk by as much as 20 feet in order to be visible to approaching traffic. o Crosswalk visibility. The crosswalk is not clearly visible to approaching vehicles. Despite the presence of advance warning signs for both the intersection and the pedestrian crosswalk, neither the crosswalk nor the intersection with Kilby Street is noticeable for approaching vehicles. It was noted that although there are existing advance warning signs, they are not the highly visible fluorescent yellow-green color. It was also noted that the advance pedestrian warning sign for the northbound approach is missing, and that the pedestrian warning sign mounted at the crosswalk is in fact mounted beyond the crosswalk due to geometric limitations. Crosswalk sign on Route 3A Northbound (looking westbound) at Kilby Street Page 5 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. • Sign and Flashing Beacon Visibility – It was noted that existing signs and post-mounted beacons are not visible for all approaches at the intersection. Overgrowth of vegetation contributes to the visibility issues. It was also noted that the STOP sign for the Kilby Street southbound approach is mounted at a substandard height. Substandard height STOP sign Kilby Street Southbound at Route 3A STOP sign and Flashing Beacon hidden by overgrowth Kilby Street Northbound at Route 3A Page 6 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Potential Safety Enhancements After the site visit, audit participants returned to the meeting location to discuss the safety issues and consider improvements. Audit participants were encouraged to consider both short and long term improvements for each issue. Each improvement considered has been categorized as short-term, mid­ term, or long-term based on the definitions shown in Table 2. Additionally, a cost category has been assigned to each improvement based on the parameters set forth in Table 2. Table 2. Estimated Time Frame and Costs Breakdown Time Frame Short-term <1 year Mid-term 1–3 years Long-term >3 years Costs Low Medium High <$10,000 $10,001–$50,000 >$50,000 The following improvements were suggested by audit participants to improve safety issues associated with the intersection of Chief Justice Cushing Highway(Route 3A) and Kilby Street. • • • Conduct traffic counts during summer and revisit signal warrant analysis. Installation of a new traffic signal was raised as a potential solution by Town officials present at the audit. It was noted by MassDOT that traffic signal warrant analysis conducted based on data collected in 2010 show that the intersection does not meet any of the warrants identified in the Manual on Uniform Traffic Control Devices (MUTCD). It was suggested that counts may be higher during the summer months, and MassDOT agreed that the intersection should be counted again during that period. Unless a traffic signal is warranted, installation of a traffic signal is not recommended. Conducting additional traffic counts is a low cost, short-term improvement. Traffic signal construction would be a long-term, high cost improvement. Construct delta islands for corners. The length of the crosswalk and the large corner radii were both suggested as issues that compromise safety for pedestrians and vehicles. It was suggested that delta islands could be constructed on the northwest and southwest corners to shorten the crosswalk length for pedestrians while also providing a channelized turn lane for turning vehicles. This potential solution should be studied first to determine if it is feasible within existing geometric constraints while still providing required space for all turning movements. Construction of this recommended improvement is a medium cost, short-term improvement, including the initial study and design. Consider roundabout. This was raised as a potential solution but is not recommended at this time. Roundabouts are more effective where traffic on the four approaches is more closely balanced, and where there are heavy turning movements that can be more effectively accommodated with a roundabout than with a traffic signal. Traffic volumes at the audit intersection show that Route 3A is much more heavily traveled and that 92% of the traffic in the morning peak hour is comprised of through vehicles on Route 3A. In addition, a roundabout does not provide a protected pedestrian path without additional signalization on the approaches. A roundabout is not recommended by the audit team at this intersection. Page 7 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. • • • • Replace pedestrian warning signs. Crosswalk warning signs should be replaced with new fluorescent yellow-green W11-2 pedestrian warning signs with a supplemental arrow plaque. In addition, new fluorescent yellow-green W11-2 signs should be mounted in advance of the crosswalk on Route 3A with a supplemental “AHEAD” plaque. All existing or conflicting pedestrian warning signs should be removed. This is a shortterm, low cost improvement. Replace post mounted flashing beacons with overhead beacon. An overhead 4-way flashing beacon at the intersection would replace the four post mounted beacons and would increase visibility and awareness of the intersection for approaching vehicles. This is a mid-term, high cost improvement. Adjust mounting height of signs. The STOP sign on the Kilby Street southbound approach is mounted below standard height and should be placed on a new post. Other signs at the intersection should be measured to insure that they are at the proper height for roadside mounting. Current MassDOT standards require that the sign panel be mounted so that the bottom of the sign panel is 7 feet above the ground elevation at the edge of pavement. This is a short-term, low cost improvement. Trim brush and shrubs. Sign visibility is compromised by overgrowth on three of the four approaches. Brush and other growth should be cut back so that signs are visible from a distance by approaching vehicles. This is a short-term, low cost improvement. In addition to the improvements summarized above, the audit team considered whether it is feasible for students of the East Elementary School to walk to school, which requires them to cross Route 3A. Presently, students north of Route 3A are bussed to the East Elementary School, while students south of Route 3A (within a certain distance of the school) walk. Parents have complained that the school bus route for students north of the Route 3A/Kilby Street is approximately 40 minutes long, despite their homes being only ½ mile from the school. The most logical route for students north of Route 3A to utilize if they were to walk to school brings them across Route 3A at Kilby Street, south on Kilby Street to Summer Street, south on Summer Street to East Street (Route 228), then southwest on East Street to Collins Road and the East Elementary School. This route is approximately ½ mile in length from a starting point just north of the railroad tracks on Kilby Street. It was noted that there is a new traffic signal installation with pedestrian accommodations at Route 3A and Summer Street, and that pedestrians should be encouraged to use this crossing to safely cross Route 3A. This route would require pedestrians to walk along Route 3A, where no sidewalks are provided, or along the pedestrian path parallel to the railroad tracks which brings the pedestrians onto the train platform at the West Nantasket commuter rail station. This path is not practical for school children, and adds approximately ¼ mile to the trip for pedestrians bound to/from Kilby Street. It was suggested at the audit that no amount of improvements, including signalization, would prompt the Hingham school department to require students from north of Route 3A to walk to school. The town may wish to consider investigating bus routes to shorten the length of time that these students spend on the bus, and may also consider a bus stop on Kilby Street just north of Route 3A so that students can walk but not have to cross Route 3A. This potential short-term improvement should start with discussion between the school, the Town, parents, and the bus company. Page 8 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Summary of Road Safety Audit Table 3 summarizes potential recommendations discussed by the audit team. The recommendations are categorized based on the potential safety payoff, as well as by time frame and cost. The safety payoff is a qualitative judgment of the effectiveness of the potential safety improvements. Page 9 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Table 3. Potential Safety Enhancement Summary Safety Issue Safety Enhancement Design and construct delta islands on the Pedestrian Accommodation northwest and southwest corners to shorten crosswalk length. Replace pedestrian warning signs with fluorescent yellow-green signs. Include Pedestrian Accommodation, Visibility two signs per approach, one with an “AHEAD” plaque and one with an arrow plaque. Visibility Install overhead flashing beacon. Adjust mounting height of signs to meet Visibility minimum 7’ clearance. Visibility Trim brush and shrubs along approaches. Conduct traffic count in the summer and Pedestrian Accommodation revisit traffic signal warrant analysis. Study school bus route and discuss Pedestrian Accommodation potential changes between school, Town, parents and bus company. Install a traffic signal with pedestrian accommodation. (This improvement is only recommended if a traffic signal is Pedestrian Accommodation, Visibility warranted, and if construction of a traffic signal is supported by MassDOT and the Town of Hingham) Safety Payoff Time Frame Cost Medium Short-term $40,000 Medium Short-term $1,000 Medium Mid-term $100,000 Medium Short-term $1,000 Medium Short-term $500 Low Short-term $2,000 Low Short-term N/A High Long-term $300,000 Page 10 Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Appendix A. RSA Meeting Agenda Road Safety Audit Hingham – Chief Justice Cushing Highway (Route 3A) at Kilby Street Meeting Location: Sons of Italy Lodge 88 Chief Justice Cushing Highway, Hingham Monday, May 10th, 2010 10:00 AM – 12:00 noon Type of meeting: Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 10:00 AM Welcome and Introductions 10:15 AM Review of Site Specific Material • Crash, Speed & Volume Summaries • Existing Geometries and Conditions 10:45 AM Visit the Site • Walk to the intersection Route 3A / Kilby Street • As a group, identify areas for improvement 11:30 AM Completion of RSA • Finalize discussion on all areas for improvement • Discuss potential improvements with pros and cons and record possible countermeasures 12:00 noon Adjourn for the Day – but the RSA has not ended Instructions for Participants: • Before attending the RSA on May 10th, participants are encouraged to drive / walk through the intersection and complete/consider elements on the RSA Prompt List with a focus on safety. • All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. • After the RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Appendix B. RSA Audit Team Contact List )t Audli Team Members Phone Number. Name xxx-xxx-xxxx Road Safety Audit—Chief Justice Cushing Highway (Route 3A) at Kilby Street—Hingham, MA Prepared by BETA Group, Inc. Appendix C. Detailed Crash Data Permit Writers Workshop -4­ Collision Diagrams O.OLLISION DIAGRAM J lndicate· North by Arl"Oit .j9,1\,13,@ ~5 .... Ch\<( ( - f ~~ ® ..JJ Jv st•i' <; .,J -,., NIIM C.vs'n,~ ffi5hwr..// Rrc 3A ..\.. ~ ... ~ ·­ ..l. · -, ~ ,. lbfla, -+tH:Ji • t;·-·~1· 1klllfll ftftJc:J.­ .... uu *--- ....tri....atcJt rtttfd. 0 fiMd AJKt • f"«t•l Acct•t 0 lOrl'f Acd4dt lt.,.W • • 12h Iota .....Oo Sfelt $vt,.. ....,.r$.15.UG\ _.,- r lffnRSECTION ch-,e.+ ~,s+.,~ Cvs\...' j l-1-..~ / Rt& PERIOD FROM; ACtlOEIIT '' . + - - - .....IDIIOl'ltd· Yd.1d• ~ . SHOW ·FOR QCH TVPES OF COLliSIONS SYMBOLS I z Oi4 or cant,., t.tf't t.at)i Rtt"~lii 3A •nd .. Y:ctr~'leattn t. 'JJPt 411 .,.:Utstao .-. Wftkles: tldlftd~ J,. .. T1•., ·tar. ~itt ·~---wit ,......, lllfttl-.t .. • , ... ,...e;t u.... "._. of on·• .,....,td$'._ ~.) K, \b~ sn-,-:;t- to J-al ,) oq I Crash Data Summary Intersection of Chief Justice Cushing Highway at Kilby Street Dec 1, 2006-Dec 1, 2009 3 'uesdav IMondav 4 IFrtdav 6 I"""',, 2001 Auaust 7. 2007 JAugust 13,2007 IJanuarv 25. 2008 I 5 8 g · (2:5fPM · --­ · ·, "t f10:"i2AM I3:31PM h:oo PM - --\_.._·... • ~..~iiiit·~ -,r.._, ._.;:~ ; · IIJ~ight !CloudY IDark - roadway not lighted I Unknown IAngle Julv 30. 2008 'July 30, 2008 August 26. 2008 An ale Unknown I Rear-end I IADri12Q. 2009 J6:11AM IAnale loa\lliaht _... ---~:;_1 ; -,: - ..-:.;; ·­ WedlerCondltlaa < c.· RCMdlurface >· DftvwConlrlbutlnaCOcle ICloudv IDavti!lht IAnale ,~ ....~,; -..; ·.:·-_.;;,:,::': r~ · _ ~Clear IDaylight !Angle IAnale UnknO'Ml 17:41 PM !1 :45AM 3:14PM 2:30PM March 12, 2008 !TuesdaY -;.;;i....... ..-. : ~_:--~ , ~ •• ~ ~~~~l;~ii':·~· _ l2!v__ UnknO'Ml ro&­ Iclear Me I lory Dark -lighted roadway ~Clear Davtiaht UnknO'Ml :::Jflear !Daylight Daylight Clear , ... IFanad to vield riaht ofWav I 16. 311 !Failed to vield right of way ---.-----nt81 IFollowed too doselv I 39.31 --· -~· __d traffic signs, ~---,Operator thought it was a rour way s<op sianals. road marklnas I 18. 22 intersection Operator unlicensed & under influence of 43, 59 alcohol ' 29,62 39,41 !Failed to yield riaht of way 60.4 Followed too closely 'Failure to keep in proper lane or runnina off road 39.25 IDrv Jory lorv lorv OperaVng vehicle In erraflc, rec/dass, csre/ess, negligent, fll IThutsdav IAori130. 2009 !.5:54AM 'July 191 2( Auaust 14. 2009 .2009 >:19PM r:32AM J9:56AM I0:48AM 12:06-PM IOdober 12.2009 !9:51AM 1 12 13 Tlil.lrsdav Sunday 15 Thursdav 14 16 17 FiidaV' !MondaY IFttdav INovember 6. 2009 '.1J6AM Clear ::lear 'l&adon ~ 'ul_g Daylight Davtight D~ht Cloudy ~ 'ula Daylight Davliaht Da i ht Clear 1::e 3; t: lctear Out of Area 6 crashes of 151nvolved a young driver (driver between the ages of 16-20) 10 out of 15 crashes Involve a vehicle traveling In the NB dlracUon Summary Ana!e 12 80.0% Manner of Collision Rear-end I UnknO'Ml 1 2 6.7% 13.3% 6:00am-1O:OOam 4 26.7% 15 Total Crashes 10:00am-2:00om 4 26.7% Time of Day 2:00om.5:00om 5 33.3% !O:OOpm-2:00am 0 0.0% -· ~5-:" Drv 13 86.7% Mondav 2 13.3% , Road Surface , Wet Unknown 6.7% 6.7% Tuesdav 3 20.0% t Wednesdav 5 33.3% LICihtlna Dark- lighted Davtiaht 13 86.7% .. --­ , --­ ... . - 6.7% Dav of Weak Friday Thursdav I 2 2 13.3% 13.3% . . .- w., Summary basad on Crash Reports obtained from the Hingham Police Department ~- ·­ . .!. , Dark- not lighted 6.7% ~a -; 1._.:.· Saturday 0 0.0% .#--...,~~.~· Sunday 1 6.7% :+••. ·.-.~rJ'...!:jooo(:..:_ ~ 16:00om-1O:OOom 2 13.3% I I ~S... ... ~a.a.:.- ~ ~4: ~·23 !...§ I,M I .47 Jper.nor <ailed to stop at stop sign & 60. 41 I flashina red light IFolloW&d too ctoselv 48.52 sianats, road marldnas IDry LC/oudy ···"d not have a ,.,..__ ':.. manner •ilad to yield right of way •iled to vield right of way •ilad to yield right of way •ilad to yield right of way •fled to vield riaht of waY Disregarded traffic signs, ~ ~ ~ Davtiaht i.Qmight !Rear-and r aaaressive lory