1 Safety and Traffic Engineering MEMORANDUM TO: Eamon Kernan, Project Manager FROM: Corey O’Connor, Traffic Engineer DATE: July 10, 2015 RE: Project 606574: Andover, RSA at Route 28 and I-495 NB ramps The purpose of this Memorandum is to summarize the Road Safety Audit (RSA) that was held for the interchange of Interstate 495 northbound and Route 28 in the Town of Andover, MA. The intent of the RSA was to have an open ended discussion with attendees to highlight safety issues at the said location and develop possible mitigation measures, or countermeasures, to address the safety issues. Countermeasures should be incorporated in the short term by MassDOT District staff or in some future project. The RSA was held on June 24, 2015 in the Andover Public Safety Complex and a list of members who attended this RSA is below in Table 1. Table 1. Andover, I-495 and Route 28 RSA Attendees. Lisa Schwarz – Town of Andover Planning Buu Tran – MassDOT, Boston, Traffic Charles Edgerly – Town of Andover Police and Safety Corey O’Connor – MassDOT, Boston, Traffic Pat Keefe – Town of Andover Police Chief Adam Prichard – MassDOT, Boston, Intern John Gregg – MassDOT, D4, Traffic Operations Michelle Deng – MassDOT, Boston, Intern Keith Arnold – MassDOT, D4, Projects Shardly Romelus – MassDOT, Boston, Intern Eamon Kernan – MassDOT, Boston, Highway Design (Project Manager) The entire interchange of 495 and Route 28 is included in an Interstate 495 resurfacing project that is currently in design by District 4 staff (MassDOT Project 606574), referred to as “the resurfacing project” hereafter. The resurfacing project will begin in the Town of Andover just north of Exit 39 on I-495 and continue just north of Exit 43 in North Andover. Most on- and off-ramps will be included into the resurfacing project along with some of the secondary state highways immediately adjacent to the ramps, including the entire interchange of I-495 and Route 28. As Project 606574 is only a resurfacing project, all work being done will be within the existing highway crosssections. It is understood that all countermeasures to safety issues discussed at the RSA should be incorporated into the resurfacing project as long as the countermeasures are easily achievable within the current project’s scope. Countermeasures that fall too far outside of the resurfacing project’s scope may be considered in a future project. There is also an ongoing guide sign replacement contract within the area of the interchange of I-495 and Route 28 therefore any guide sign recommendations resulting from the RSA may be implemented through the ongoing contract. 2 Crash Data Background Crash data based from local and state police reports were collected for the entire I-495 and Route 28 interchange from 2011 to 2013. A very large majority of the crashes collected occurred in the southern portion of the interchange at the intersections of the I-495 NB ramps and Route 28 therefore discussion was mostly focused only on this portion of the interchange. From the collected reports, 33 crashes were found at the intersection of the I495NB ramps and Route 28. 11 of the 33 crashes resulted in injury and none resulted in any fatalities. An Equivalent Property Damage Only (EPDO) rating was calculated and found to have a rating of 77 which classifies the area of the I-495 NB ramps and Route 28 as a high crash location within the Merrimack Valley Planning Commission’s area. The detailed crash diagram and crash summaries can be found in the appendix of this document. Summary of Safety Issues and Possible Countermeasures 1. Interchange Geometry and Control In the vicinity of the interchange, Route 28 is a four lane divided secondary highway (two lanes in each direction) with a wide grass median. I-495 is a six lane Interstate (three lanes in each direction). The interchange between I-495 and Route 28 offers full access from and to every direction (eight maneuvers total). The geometry of the entire I-495 and Route 28 interchange is unique in that it has characteristics of a cloverleaf, diamond and fly-over interchange design. During the RSA two particular maneuvers within the interchange were understood to have been contributing to many of the crashes at the interchange: the I-495 south to Route 28 north maneuver and the Route 28 south to I-495 north maneuver. Vehicles on I-495 south wishing to go Route 28 north must get off of the Exit 41 loop ramp and merge onto Route 28 south. These vehicles must then weave to the left lane of Route 28 south within 700 feet and make a U-turn in the small roadway segment provided in the median connecting Route 28 north and south, referred to as “the U-turn segment” hereafter. Vehicles on Route 28 south wishing to go I-495 north must also use the U-turn segment however instead of making a complete U-turn onto Route 28 north they must cross two lanes of Route 28 north traffic onto the I-495 north on-ramp. The U-turn segment is under stop control while vehicles on Route 28 north have the right of way and flow freely. There is a single post mounted flashing red beacon provided for vehicles at the stop controlled U-turn segment and a four section post mounted flashing yellow “wig-wag” beacon for vehicles approaching on Route 28 north. The U-turn segment described above is a host to the majority of the 33 crashes analyzed at this location. The predominant crash type is angle collisions between a Route 28 northbound vehicle and a vehicle exiting the Uturn. 12 of the 33 crashes are of this manner and four of which resulted in injury. These angle crashes may occur due to the fact that two major interchange movements must utilize this U-turn segment which creates a large demand for the U-turn segment. With close to 15,000 vehicles per day traveling on Route 28 north, finding a gap in two lanes of conflicting traffic may be difficult as well. With such demand for the U-turn segment and large conflicting volume on Route 28 north, queues form at the stop line on the U-turn segment and spill back onto Route 28 south during the A.M. and P.M. peaks. Frustration and pressure from other vehicles in the queue may build for drivers in the queue which may lead the drivers at the stop line to accept an unsafe gap in traffic which may cause an angle crash. A few close calls between vehicles departing the stop line on the U-turn segment and Route 28 north were observed during the audit. As described above, the U-turn segment handles two movements: vehicles turning left onto Route 28 north and vehicles traveling straight to access I-495 north. It was observed during the audit that vehicles will stack side by side at the stop line on the U-turn segment. When this occurs, the vehicle waiting to travel straight onto I-495 north will block the view of the Route 28 north traffic from a vehicle waiting to turn left at the stop line on the U-turn segment. This may cause a vehicle waiting to turn left to inadvertently pull out into Route 28 north at an inappropriate time causing an angle crash. 3 Another contributing factor for angle collisions related to the geometry may be the separate but adjacent Uturn segment for Route 28 north to access Route 28 south. This north to south U-turn segment is located just south of the U-turn segment for south to north/I-495 north. Vehicles on Route 28 north accessing the U-turn segment to access Route 28 south may slow down in the inside lane and, especially if it is a large vehicle, block the view of a through vehicle in the outside lane from vehicles queuing at the stop line at the U-turn segment for south to north/I-495 north. A vehicle at the stop line on the south to north/I-495 north U-turn segment may incorrectly assume that it is safe to enter or cross Route 28 north and cause an angle crash. Rear-end crashes may also be contributed to the U-turn segment for south to north/I-495 north. The cross section of Route 28 south consists of two lanes throughout the interchange; however, for approximately 300 feet, Route 28 south widens prior to the U-turn segment to accommodate a non-marked de facto storage/deceleration lane for the U-turn segment. Due to poor pavement conditions, vehicles will often avoid this de facto storage/deceleration lane therefore slow down and queue in the inside through lane of Route 28 south. To exacerbate the issue, it was mentioned that the queue from the U-turn segment may spill back to the I-495 south off ramp located about 700 feet upstream from the U-turn segment. Vehicles on I-495 south wishing to access Route 28 north must then find a way to enter the queue and often will often block one or more lanes of Route 28 south through traffic while doing so. This queue spill back and vehicles decelerating may have contributed to the five rear-end crashes on Route 28 south in the vicinity north of the U-turn segment. Another geometrical feature that causes safety issues is the the proximity of the I-495 northbound/Route 28 southbound ramp to the U-turn segment. The I-495 north/Route 28 south ramp is located about 100 feet upstream from the U-turn segment. It was observed that vehicles will use the I-495 north/Route 28 south ramp and try to weave across Route 28 south to try to access the U-turn segment. This maneuver may have contributed to the two side-swipe/angle crashes between a vehicle on the off-ramp and a through vehicle on Route 28 south. This maneuver may also contribute to rear-end crashes as vehicles are focusing on weaving across Route 28 and not the queue that may have formed from the U-turn segment. Vehicles on the I-495 north/Route 28 south ramp should have no reason to access the U-turn segment because there is a separate loop ramp for I-495 north to Route 28 north. This move is also strongly discouraged by ways of a “NO TURNS” sign and a solid white lane line along the 100 foot weave section of roadway in between the I-495 north offramp and the U-turn segment. The geometry of the merge area from the I-495 north/Route 28 south ramp may have also contributed to other crashes not related to the U-turn segment. The ramp from I-495 north intersects Route 28 south at a very skewed angle such that vehicles merging onto Route 28 south from the ramp may feel that they may not have to yield to Route 28 south traffic despite the presence of yield signs. This scenario may have been the cause of the two side-swipe/angle crashes recorded at this location. Furthermore, drivers who do yield at the bottom of the ramp must look almost 180 degrees backwards to see the conflicting traffic on Route 28 south. This scenario may have contributed to some of the rear-end crashes in the area as drivers take their eyes off of the vehicle in front of them to look backwards towards the conflicting traffic. The geometry of the I-495 north/Route 28 south ramp may also contribute to the two single vehicle crashes near the end of the ramp in which the vehicles lost control and slid into the grassy gore area at the curve prior to the merge point. The downward grade of the ramp combined with the sharp corner prior to the merge point is most likely a factor into these two single vehicle crashes. Potential Enhancements: Reconstruct the interchange. Although this recommendation is a long term, high cost enhancement, well beyond the scope of the resurfacing project, reconstructing the interchange and eliminating the U-turn segment (by constructing a single point urban interchange (SPUI) or by providing separate ramps for I-495 south to 28 north and Route 28 4 south to I-495 north) are the most effective ways to eliminate most of the crashes at this location. Once the conflict between the U-turn segment and Route 28 north is eliminated all of the angle crashes at this location will be eliminated and rear-end crashes on Route 28 south will be mitigated by the removal of the queue spill back. - Signalize the U-turn segment and Route 28 north. Signalizing the U-turn segment and Route 28 is a long term, high cost enhancement that is outside of the scope of the resurfacing project. By signalizing these two approaches many of the angle crashes may be reduced between the U-turn segment and Route 28 north. This will remove the responsibility of the driver to determine whether a gap is acceptable or not. Also, as long as the signal processes traffic well, the queue spill back onto Route 28 south may be relieved hence reducing the rear-end crashes. Even though this enhancement is outside of the scope of this project, it is recommended that this enhancement is considered for a future project. Minor geometrical changes may also be required in order to make this enhancement most effective. - Mount flashing beacons overhead. Although mounting flashing beacons overhead may not be as effective in reducing crashes as the previous two safety enhancements, it may make the intersection more conspicuous and make more drivers more alert. This may mitigate the angle crashes between the U-turn segment and Route 28 north. Mounting beacons overhead is a high-cost, mid-term enhancement and is outside the scope of the resurfacing project. - Reduce Route 28 north to one lane at the U-turn segment. Reducing Route 28 north to one lane at the U-turn segment may reduce angle crashes due to the fact that vehicles departing the U-turn segment will only have to cross one lane of traffic. Reducing Route 28 north to one lane in this area may also calm traffic and reduce speeds. This enhancement may be accomplished by making the outside lane on Route 28 north exit only to the I-495 north on ramp. The second lane may then be re-added downstream of the U-turn segment; either by creating an add-a-lane for vehicles using the U-turn segment to access Route 28 north or by creating an add-a-lane for vehicles entering Route 28 north from the I-495 north off-ramp. This enhancement can be accomplished with pavement markings only therefore is a shortterm and low-cost enhancement that may be considered as part of the resurfacing project. The operational effects of Route 28 north shall be analyzed to determine if the elimination of a through lane will create other issues if this enhancement is considered. - Define lanes on the U-turn segment. It should be determined whether the U-turn segment should provide one lane for lefts and throughs to share or two lanes, one for each. Providing two lanes will provide more storage for vehicles queued at the stop line however the issue of the through vehicle blocking the view of the left turning vehicle will still exist at the stop line. Furthermore, if two lanes are provided, two lanes will most likely spill back into Route 28 south and may cause additional safety concerns. Providing one lane at the U-turn segment will eliminate the issue of a through vehicle blocking the view of a left turning vehicle and the spill back from one lane may be accommodated more safely given the current crosssection restrictions. This may reduce the number of angle crashes. Defining lanes on the U- 5 turn segment is a short-term and low-cost enhancement that can be done within the scope of the resurfacing project through striping. - Provide a formal storage/deceleration lane on Route 28 south for the U-turn segment. By providing a separate lane for storage and deceleration for vehicles accessing the U-turn segment rear-end crashes may be reduced by removing these queued vehicles from the through lanes and by providing a safe area to decelerate outside of the through lanes. This enhancement may be done with pavement markings provided that the cross section is wide enough. If so, this enhancement is a short-term and low-cost enhancement and should be done as part of the resurfacing project. Widening of the cross section may be needed to make this enhancement most effective. Widening of the cross section is a high-cost and long-term recommendation outside the scope of this project. - Provide a solid double white lane line on Route 28 south in the area of the I-495 north offramp. According to the MUTCD, crossing a solid double white line is prohibited. In attempt to further discourage vehicles from accessing the U-turn segment from the I-495 north/Route 28 south ramp a solid double white lane line can be applied on Route 28 south in the vicinity of the ramp. A R4-9 (STAY IN LANE) sign may also be provided to reinforce the solid double white line. Although all vehicles may not adhere to this treatment, these enhancements may reduce the amount of side-swipes and rear-end crashes in the area of the U-turn segment. Both the solid double white line and R4-9 sign are low-cost and shortterm enhancements that can be done within the scope of the project. - Extend the gore of the I-495 north/Route 28 south off-ramp downstream past the U-turn segment. Extending the gore of the I-495 north/Route 28 south off-ramp downstream past the U-turn segment by means of textured pavement and/or pavement markings will further discourage vehicles exiting the I-495 off-ramp from crossing Route 28 south to access the Uturn segment hence reducing the related crashes. This enhancement may require minor widening of Route 28 south therefore is a high-cost and long-term enhancement that may be outside of the scope of the resurfacing project. - Provide a smaller radius of entry on the I-495 north/Route 28 south off-ramp. Having the I495 north off-ramp intersect Route 28 south at a smaller radius, say 30 degrees, will allow drivers to easily view oncoming traffic on Route 28 south at the yield line on the off-ramp. This will eliminate the need for drivers look over their shoulder hence reducing the amount of rear-ends in the area. Additionally, with a lesser angle of entry, drivers will be required to come to more of a stop at the yield line hence increasing the conformance at the yield line and reducing the side-swipe/angle crashes caused by vehicles failing to yield. Finally, this enhancement may also reduce the amount of single vehicle crashes at the end of the offramp as the sharp curve to align the off-ramp parallel with Route 28 south will be eliminated. This is a long-term and high-cost enhancement that is outside of the scope of the resurfacing project. This enhancement may also be considered for all ramps throughout the interchange. 6 2. High Speeds High speeds on Route 28 within the area of the I-495 interchange were noted to possibly contribute to crashes. Route 28 has a regulated speed of 35 mph within the area of the interchange however speeds seemed to be higher from observations during the RSA, especially on Route 28 north. To confirm these field observations Andover police set up traffic data recorders on Route 28 north and south to record volumes and speeds. These th traffic data recorders confirmed the field observations: the 85 percentile speeds on Route 28 north and south were 42 and 37 mph, respectively. The traffic data recorders also found that it is not rare that vehicles travel at speeds greater than 50 mph and even 70 mph. The full data set from these traffic data recorders can be seen at the end of this document in the Appendix. High speeds can contribute to all crash types. Angle crashes were specifically called out as a consequence of high speeds because vehicles at the stop line on the U-turn segment may not expect vehicles on Route 28 north to approach the intersection as quickly as they do and accept an unsafe gap. th High speeds may also contribute to some of the rear-end crashes on Route 28 south. Even though the 85 percentile speed conforms closely to the posted speed on Route 28 south, there are still some outlying vehicles traveling at speeds greater than 50 or 70 mph. As vehicles merge onto Route 28 south from I-495, they may have to weave over to the left lane to access Route 28 north via the U-turn segment. This mix of slow, merging and weaving traffic with high speeds may cause some of the rear-end crashes. The fact that the U-turn segment’s queue can spill back onto Route 28 south further exacerbates the issue. Potential Enhancements: Continue speed enforcement. Andover police says that the interchange of Route 28 and I495 is already a regular spot for speed enforcement in Town. Andover police should continue to enforce the posted speed limit throughout the area and maintain a common police presence in order to discourage vehicles from speeding. This is a low-cost and shortterm improvement that can be implemented at any time. 3. Pavement conditions The pavement condition throughout the interchange of Route 28 and I-495 is in poor condition. With high volumes of traffic and large trucks using the interchange, rutting and wash boarding symptoms are prevalent. Of major concern are the pavement around the U-turn segment and the pavement toward the bottom of the I495 north/Route 28 south off-ramp. As described earlier on in this document, the pavement in the area of the non-marked de facto storage/deceleration lane for the U-turn segment is in poor condition. As vehicles decelerate along this segment and turn around the U-turn segment the pavement gets rutted and shoved creating an uneven and bumpy surface. Consequences include reduced friction and vehicles avoiding the uneven and bumpy surfaces. Both consequences contribute to rear-end crashes as vehicles may slide on the pavement or as vehicles decelerate in through lanes while avoiding the uneven and bumpy surface. Similar pavement conditions are present at the bottom of the I-495 north/Route 28 south off-ramp. As vehicles approach the horizontal curve at the bottom of the ramp prior to merging onto Route 28 south they are traveling on a downgrade and attempting to decelerate from highway speeds. Similar to the U-turn segment, as vehicles brake heavily and navigate the horizontal curve, the pavement becomes rutted and shoved creating a bumpy and uneven surface. As a consequence, friction is reduced and vehicles may lose control and run off the ramp. This may have contributed to the single vehicle crashes at the bottom of the ramp. 7 Potential Enhancements: Resurface the interchange. To eliminate the uneven, bumpy, rutted and shoved pavement the interchange should be resurfaced. Full depth reconstruction may be considered in some areas where extreme rutting and shoving are occurring. This may eliminate some of the rear-end crashes and single vehicle run-off-the-road crashes. Resurfacing the interchange is a long-term and high-cost improvement and it is understood that it will be included within the resurfacing project. 4. Vegetation Vegetation throughout the interchange was observed to be overgrown during the RSA. Two areas in particular were discussed: on the inside of the horizontal curve of the I-495 north/Route 28 south off-ramp and along the west side of Route 28 just south of the I-495 north/Route 28 south off-ramp. Vegetation on the inside of the horizontal curve on I-495 north/Route 28 south off-ramp obstructs the view of the yield line for vehicles traveling down the ramp. Although no crashes reported in this manner, a vehicle may not be able to see queued traffic at the yield line due to the brush obstructions and cause a rear-end crash. Furthermore, a pedestrian crosswalk is proposed at the bottom of the ramp as part of the resurfacing project. With the current conditions the view of pedestrians in the crosswalk will be obstructed by the brush on the inside of the ramp which may possibly lead to conflicts between vehicles and pedestrians. Vegetation just south of the I-495 north/Route 28 south off-ramp on the west side of Route 28 is overgrown to the point where it completely obstructs the sidewalk. During the RSA, attendees were forced to walk in the shoulder of Route 28 south due to the brush obstructions. Potential Enhancements: Trim vegetation throughout the interchange. Vegetation should be trimmed and cut back to allow adequate sight lines and clear pedestrian paths. This is a low-cost and short-term enhancement that should be done as part of regular District 4 maintenance before the resurfacing project. 5. Signage and Pavement Markings Guide signage throughout the interchange was discussed during the RSA however no major issues were brought up. A discussion of regulatory and warning signs on the I-495 north/Route 28 south off-ramp revealed that the yield sign at the merge point of the ramp and Route 28 south is inconspicuous and may contribute to the side-swipe/angle and rear-end crashes in the area. Pavement markings were also discussed throughout the interchange. As mentioned before, to prevent vehicles from accessing the U-turn segment from the I-495 north/Route 28 south off-ramp a solid single white lane line is provided in between the ramp and the U-turn segment. According to the MUTCD a solid single white lane line is intended for discouraging vehicles from changing lanes, it does not prohibit it. Also discussed above in the Interchange Geometry and Control section is the lack of lane definition in the U-turn segment at the stop line and the need for a deceleration/queue storage lane on Route 28 south. Other pavement markings were lacking throughout the interchange including a stop line on the U-turn segments, yield lines on all of the offramps and gore markings around the median islands defining the U-turn segments. Although it is difficult to relate any one crash to pavement markings, lacking pavement markings can add to confusion and may assist in noncompliance to the laws of the road. 8 At present, new ADA-compliant wheelchair ramps and sidewalk are being constructed across Route 28 between the Burke-Magliozzi Funeral Home and the Chinmaya Maruti Center, just south of the U-turn segments. Under the resurfacing project, MassDOT will need to ensure that pavement markings and signs associated with the crossing meet current MUTCD standards and are replicated under the resurfacing contract. Potential Enhancements: Provide W3-2 (yield ahead) signs in advance of the yield line on the I-495 north/Route 28 south off-ramp. Providing W3-2 signs will alert drivers of the upcoming yield and may increase the compliance of the yield sign which may reduce rear-end and side-swipe crashes at the yield line. Providing two signs, one on each side of the ramp, will increase conspicuousness. This is a low-cost and short-term enhancement that should be implemented into the resurfacing project. This enhancement can be implemented on all ramps throughout the interchange as well. - Provide two R1-2 (yield) signs at the yield line on the I-495 north/Route 28 south off-ramp. Currently there is one R1-2 sign at the yield line on the I-495 north/Route 28 south off-ramp. In order to make the need to yield more conspicuous for drivers a second R1-2 sign may be added across the ramp from the existing R1-2. This is a low-cost and short-term enhancement that should be implemented into the resurfacing project. This enhancement can be implemented on all ramps throughout the interchange as well. - Define lanes on the U-turn segment as discussed before. - Provide a formal storage/deceleration lane on Route 28 south for the U-turn segment as discussed before. - Provide a solid double white lane line on Route 28 south in the area of the I-495 north offramp as discussed before. - Provide wide gore lines around the U-turn segments. Providing wide gore lines around the U-Turn segments will better define the geometry and lanes of the roadway and may reduce confusion for drivers. This is a low-cost and short-term enhancement that should be implemented into the resurfacing project. - Provide stop lines and yield lines at stop signs and yield signs, respectively. Providing stop bars and yield lines, where appropriate, will highlight the point at which vehicles should stop and yield which may reduce the compliance of such control. This may reduce the amount of rear-end crashes and side-swipe angle crashes caused when vehicles fail to yield or stop. This is a low-cost and short-term enhancement that should be implemented into the resurfacing project. - Replace/provide proper signage and markings for the crosswalk under construction south of the U-turn segments. It is assumed that the crosswalk markings and signage will be up to date with current MUTCD standards as part of the ongoing project. If not, the resurfacing project should use the opportunity to implement any sign or marking improvements. This is a low-cost and short-term improvement. 9 6. Pedestrian and Bicycle Accommodations Pedestrian accommodations were lacking throughout the interchange. Continuous sidewalks run along Route 28 in both directions throughout the entire interchange however there are many obstructions, such as vegetation and utility poles, forcing pedestrians onto the shoulder of Route 28. Additionally, there are no wheel chair ramps at curb cuts and intersections. No marked cross walks or pedestrian warning signs are provided anywhere throughout the interchange. Even though there are no recorded pedestrian crashes within the interchange, pedestrian safety was discussed as an issue. The I-495 north/Route 28 south off-ramp was of particular concern in terms of pedestrian safety. Aside from the above mentioned safety issues, it is difficult for pedestrians to determine if it is safe to cross the ramp do to the fact that the horizontal curve and the thick vegetation inside the curve blocks the view of any approaching vehicles. Likewise, vehicles would not see if any pedestrians are crossing. To worsen the issue, vehicles usually travel at high speeds as they travel down the ramp. Although not discussed, this issue may exist on other ramps throughout the interchange. Bicycle accommodations were also lacking throughout the interchange. Shoulders vary in width from eight feet to one foot forcing bicyclists to ride in the outside travel lane with traffic at times. The layout of the intersecting ramps from I-495 also pose as a safety issue for bicyclists on Route 28. Bicyclists are forced to mix with high speed merging vehicles as they cross the merge and diverge points where the off-ramps intersect Route 28. Although no bicycle crashes were reported during the study period, bicyclists were observed during the RSA and these safety issues were discussed. Potential Enhancements: Trim and cut back vegetation. As discussed earlier, vegetation should be trimmed and cut back to allow adequate sight lines and clear pedestrian paths, especially in the area of the I495 north/Route 28 south off-ramp. This is a low-cost and short-term enhancement that should be done as part of regular District 4 maintenance before the resurfacing project. - Clear obstructions on sidewalks. Clearing obstructions in order to provide at least a 3 foot minimum clear width along the entirety of all sidewalks will allow safe and uninterrupted passage for all pedestrians including people with wheelchairs. Utility poles were the most common obstruction. Ideally, utility poles should be placed in back of the sidewalk. Relocating utility poles may be a mid-term and medium cost enhancement that will need coordination with the utility company. - Provide ADA compliant wheelchair ramps throughout. Currently there is a project in progress to update all wheelchair ramps in the area. If there is any area of sidewalk that is not included in the ramp project then it should be upgraded to meet ADA standards as part of the resurfacing project. This is a mid-term and medium cost enhancement that is assumed to be included in the resurfacing project. - Provide crosswalks and pedestrian warning signs where appropriate. Crosswalks should be placed across all off-ramps to alert drivers of the possible presence of pedestrians. Crosswalks should be placed at least 4 feet downstream from the stop or yield line. Advanced pedestrian warning signs should be considered for all crosswalks and pedestrian crossing signs with downward pointing arrows should be considered at crosswalks not located at a stop or yield line. As discussed earlier, signs and pavement markings should be replaced (or provided, if need be) at the crosswalk that is being constructed just south of the 10 U-turn segments. This is a short-term and low-cost enhancement that should be incorporated into the resurfacing project. - Provide a smaller radius of entry on the I-495 north/Route 28 south off-ramp. As discussed earlier, having the I-495 north off-ramp intersect Route 28 south at a smaller radius, say 30 degrees, will not only allow drivers to easily view oncoming traffic on Route 28 south at the yield line but it will also allow vehicles to better view pedestrians and bicyclists. Vehicles will be more likely to stop and yield to pedestrians and bicycles. Furthermore, crosswalks can more easily be placed at the point of yield and bicyclists will not need to mix with high speed merging traffic at the merge and diverge points. This is a long-term and high-cost enhancement that is outside of the scope of the resurfacing project. This enhancement may also be considered for all ramps throughout the interchange. - Provide consistent five foot shoulders for bicyclist. At least five foot shoulders should be provided throughout the interchange to provide bicycle accommodations. Special attention should be considered where I-495 ramps merge and diverge with Route 28 and bicyclists must cross merging and diverging traffic. Depending on the width of the cross section and the need for widening, this may be a short-term and low-cost enhancement that should be incorporated into the resurfacing project or it may be a long-term high-cost enhancement that is outside of the scope of the resurfacing project. 7. Highway Lighting Six out of the 33 crashes reported at the interchange of I-495 north and Route 28 occurred at night. Although these six crashes only account for about 18% of the total crashes, the lack of lighting throughout the interchange was discussed during the RSA. According to MassDOT District 4 staff there is a damaged and nonfunctioning highway lighting load center along Route 28 south just south of the I-495 off ramp. It is estimated that this load center powered about 10 highway lights throughout the interchange when it was functional. Currently there is no lighting anywhere within the interchange which may contribute to some of the night time crashes. Potential Enhancements: Provide highway lighting throughout the interchange. Providing lighting throughout the interchange will increase the visibility of any vulnerable road users (pedestrians and bicyclists) and will allow drivers to quickly assess roadway conditions at night. This will make the interchange safer and may possibly reduce the number of crashes occurring at night. It should be determined if the existing non-functioning highway lighting load center can be reused. This is a potentially long-term and high-cost enhancement that is outside the scope of the resurfacing project. A list of all safety issues discussed and all potential enhancements is provided below in Table 2. Safety payoff estimates are subjective and are based on the relative percent of crashes that may be reduced by the enhancement; for example, low (<30%), medium (31% to 70%), and high (>71%). The time frame is categorized as short-term (<1 year), mid-term (1 to 3 years), or long-term (>3 years). The costs are categorized as low (<$10,000), medium ($10,001 to $50,000), or high (>$50,001). Enhancements that are not to be included in this resurfacing project should be considered in a future project that may possibly occur. 11 Table 2. Summary of safety issues and enhancements. Safety Issue No Route 28 SB to I-495 NB or I-495 to Route 28NB Angle crashes between the U-turn segment and Route 28 north Queue spillback from Uturn segment Vehicles stacking side by side at U-turn segment’s stop line Vehicles accessing the U-turn segment from the I-495 north/Route 28 south ramp Rear-end crashes and vehicles failing to yield at the I-495 north/Route 28 south ramp Safety Enhancement Safety Payoff Time Frame Cost Reconstruct entire interchange to a single point urban interchange (SPUI) High Long High Construct new ramps for Route 28 SB to I­ 495 NB and I-495 to Route 28NB High Long High Signalize the intersection of Route 28 north and the U-turn segment High Long High Mount flashing beacons overhead Low Medium High Reduce Route 28 north to one lane at the Uturn segment. Medium Short Low Provide a formal storage/deceleration lane on Route 28 south for the U-turn segment Low Short Low Signalize the intersection of Route 28 north and the U-turn segment High Long High Define lanes on the U-turn segment Low Short Low Provide a solid double white lane line in the area of the I-495 north/Route 28 south ramp Low Short Low Provide a R4-9 (STAY IN LANE) sign to supplement the solid double white lane line Low Short Low Extend the gore of the I-495 north/Route 28 south off-ramp downstream past the U-turn segment Low Short/Long Low/High Lessen the angle of entry on the I-495 north ramp with Route 28 south High Long High Provide W 3-2 (yield ahead) signs on the I-495 north/Route 28 south ramp Low Short Low Provide a yield line Low Short Low Provide two R1-2 (yield) signs at the yield line Low Short Low 12 Safety Issue Safety Enhancement Safety Payoff Time Frame Cost Vehicles running off the road at the end of the Provide two R1-2 (yield) signs at the yield line Lessen the angle of entry on the I-495 north ramp with Route 28 south High Long High High speeds throughout the interchange Continue strict speed enforcement in the area Low Short Low Poor pavement conditions Resurface the interchange Medium Long High Vegetation overgrowth Trim vegetation throughout the interchange Medium Short Low Lacking pavement markings including stop lines, yield lines and gore lines Provide gore pavement markings around the islands of the U-turn segments and provide stop and yield lines where appropriate. Low Short Low Medium Short Low Move obstructions, such as utility poles, off of sidewalk or provide at least three feet of clear space Low Long High Provide ADA compliant wheelchair ramps at all curb cuts and intersections High Long High Provide marked crosswalks where appropriate Low Short Low Provide pedestrian warning signs where appropriate Low Short Low Clear vegetation from the inside of the curve on the I-495 north/Route 28 south ramp to open sight lines Medium Short Low Lessen the angle of entry on the I-495 north ramp with Route 28 south to provide more ideal crosswalk placement High Long High Provide a consistent shoulder throughout the interchange, five feet wide at least Medium Short/Long Low/High Lessen the angle of entry on the I-495 north ramp with Route 28 south so bicyclist will not have to mix with high speed merging traffic High Long High Medium Long High Obstructions in sidewalk forcing pedestrians to walk in roadway Lacking wheelchair ramps Pedestrians along Route 28 crossing I-495 offramps Lacking bicycle accommodations Lacking highway lighting Trim vegetation away from sidewalks Provide highway lighting throughout the interchange. Determine if the existing nonfunctioning load center can be reused. 13 APPENDIX I CRASH DIAGRAMS AND SUMMARIES Road Safety Audit Andover, MA Route 28 (Union St/N Main St) at Interstate 495 Meeting Location: Andover Public Safety Center 32 North Main Street, Andover, MA Wednesday, June 24th 2015 1:00 PM – 3:00 PM Type of meeting: High Crash Location – Road Safety Audit Attendees: Invited Participants to Comprise a Multidisciplinary Team Please bring: Thoughts and Enthusiasm!! 1:00 PM Welcome and Introductions 1:15 PM Discussion of Safety Issues Crash history, Speed Regulations – provided in advance Existing Geometries and Conditions 2:00 PM Site Visit Drive to the intersection As a group, identify areas for improvement 2:30 PM Discussion of Potential Improvements Discuss observations and finalize safety issue areas Discuss potential improvements and finalize recommendations 3:00 PM Adjourn for the Day – but the RSA has not ended Instructions for Participants: Before attending the RSA on June 24th, participants are encouraged to drive/walk through the intersection and complete/consider elements on the RSA Prompt List with a focus on safety. All participants will be actively involved in the process throughout. Participants are encouraged to come with thoughts and ideas, but are reminded that the synergy that develops and respect for others’ opinions are key elements to the success of the overall RSA process. After the RSA meeting, participants will be asked to comment and respond to the document materials to assure it is reflective of the RSA completed by the multidisciplinary team. Andover, MA •/}Jf.I!J.l!~-!!2QI I 1-495 NB Ramps at Rt 28 :ighway Division REGION: Merrimack Valley Planning Commission TIME PERIOD ANAL.YlED: 2011-2013 SOURCE OF CRASH REPORT'S: STAlE and LOCAL POLICE Report. COLLISION DIAGRAM DAlE PREPARED: 05/28/2015 PREPARED BY: William Ullom SYMBOLS TYPES OF CRASH 11+1 • Moving Vehicle ~ - Bicycle Head on ~ ((( • Backing Vehicle - - -+ Nan-Involved Vehicle ~ Pedntrlan SEVERITY • ___.../ Rear End Angle ~ Turning Injury Movement Animal ~Sideswipe ~ Parkecl Vehicle 0 D Fixed Object 0 • • 0 Out of Control Night Time Crash 0 Fatal N Crash Data Summary Table I-495 NB Ramps at Rt 28, Andover, MA January 1, 2011- December 31, 2013 Crash Date Crash Day m/d/y Time of Day 1 1/28/11 Friday 8:58 AM Angle Daylight Rain 2 2/4/11 Friday 3:07 PM Rear-end Daylight Rain 3 4 2/6/11 5/9/11 Sunday Monday 8:31 PM 7:13 AM Single Vehicle Crash Single Vehicle Crash Dark - lighted roadway Clear Daylight Clear Wet Dry 5 6 7 8 5/18/11 6/16/11 6/21/11 9/13/11 Wednesday Thursday Tuesday Tuesday 3:19 PM 6:52 PM 12:23 PM 11:54 AM Sideswipe, opposite direction Angle Angle Single Vehicle Crash Daylight Daylight Daylight Daylight Rain Clear Clear Clear 9 10 11 12 9/22/11 12/22/11 1/6/12 4/7/12 Thursday Thursday Friday Saturday 7:38 PM 3:03 PM 4:12 PM 9:15 AM Angle Angle Angle Angle Dark - lighted roadway Daylight Daylight Daylight 13 14 15 5/3/12 6/16/12 7/2/12 Thursday Saturday Monday 11:13 PM 2:05 PM 5:46 PM 16 17 18 19 20 7/3/12 7/18/12 8/2/12 9/23/12 12/1/12 Tuesday Wednesday Thursday Sunday Saturday 21 22 23 24 25 26 27 1/9/13 1/10/13 2/27/13 7/18/13 8/25/13 9/26/13 10/14/13 28 11/7/13 29 Crash Diagram Ref # Manner of Collision Type Light Condition Type Weather Condition Type Road Surface Driver Contributing Code Type Type Water (standing, moving) Other improper action Water (standing, moving) Inattention Ages D1 D2 48 84 52 55 Comments 32 50 Vehicle hit ice, lost control, and hit snowbank Vehicle hit utility pole. Wet Dry Dry Dry No Improper Driving Inattention Operating Vehicle in erratic, reckless, careless, negligent, or aggressive manner Failed to yield right of way Failed to yield right of way Over-correcting/over-steering 19 20 48 19 30 UNK 48 MV 2 ran stop sign and crashed into MV 1. MV 2, turning left, hit MV 1 after stopping at stop sign. MV 2 going straight to I-495N hit MV 1 and then fled. MV 1 swerved after she thought she saw another vehicle. Rain Clear Clear Clear Wet Dry Dry Dry Failed to yield right of way Failed to yield right of way Inattention Visibility Obstructed 27 16 MV 2 going straight to I-495N hit MV 1. 67 UNK MV 1 going straight to I-495N hit MV 2 and then fled. 25 19 MV 2 going straight to I-495N hit MV 1. 20 22 Single Vehicle Crash Single Vehicle Crash Rear-end Dark - lighted roadway Rain Daylight Clear Daylight Clear Wet Dry Dry 29 16 41 Slid on wet ramp, hit curb, and flipped. Collision with utility pole. 30 MV 1 rearended at stop sign, MV 2 thought MV 1 would enter traffic. 6:59 AM 3:42 PM 1:55 PM 4:34 PM 3:04 PM Rear-end Angle Angle Single Vehicle Crash Sideswipe, same direction Clear Clear Clear Clear Snow Dry Dry Dry Dry Wet 23 48 73 53 42 20 Road rage. 39 MV 2 going straight to I-495N hit MV 1. 19 MV 2 going straight to I-495N hit MV 1. Motorcycle lost ontol on off ramp. 68 MV 2 merged into MV 1. Wednesday Thursday Wednesday Thursday Sunday Thursday Monday 6:45 PM 10:35 AM 8:10 AM 9:04 AM 1:44 PM 5:05 PM 12:21 PM Rear-end Angle Rear-end Rear-end Rear-end Angle Angle Daylight Daylight Daylight Daylight Daylight Dark - roadway not lighted Daylight Daylight Daylight Daylight Daylight Daylight Inattention Inattention Inattention Operating Vehicle in erratic, reckless, careless, negligent, or aggressive manner Failed to yield right of way Failed to yield right of way Unknown Other improper action Cloudy Clear Rain Clear Clear Clear Clear Dry Dry Wet Dry Dry Dry Dry Followed too closely Other improper action Inattention Inattention Inattention Inattention Failed to yield right of way 41 20 33 49 26 23 54 47 59 27 28 57 20 74 Thursday 4:01 PM Angle Daylight Rain Wet 25 11/13/13 Wednesday 6:34 PM Single Vehicle Crash Daylight Clear Dry Inattention Swerving or avoiding due to wind, slippery surface, vehicle, object, nonmotorist in roadway, etc. 53 MV 1 swerved to avoid colliding with unknown MV from 495NB off-ramp, hits stop sign. 30 31 11/29/13 Friday 12/1/13 Sunday 6:04 PM 9:09 AM Angle Single Vehicle Crash Dark - lighted roadway Clear Daylight Cloudy Dry Ice Visibility Obstructed Driving too fast for conditions 36 26 21 MV 1 turned into U-turn section on N. Main St. from wrong lane, hit by MV 2. Veh lost control control on ice, hit utility box. 32 12/8/13 7:12 PM Rear-end Dark - lighted roadway Clear Dry Other improper action 45 25 MV 1 stopped to yeild and MV2 thought MV 1 had pulled into traffic. 33 12/18/13 Wednesday 6:16 PM Sideswipe, same direction Dark - lighted roadway Cloudy Dry Inattention 61 56 Sunday Summary based on Crash Reports obtained from the state and local police reports. Rear end on NB I-495 off-ramp. MV 2 merged into MV 1. MV 2 rear ended MV 1 while MV 1 was at yield line. MV 2 going straight to I-495N hit MV 1. MV 2 going straight to I-495N hit MV 1. MV 2 stopped at stop sign to turn left onto Rt 28 NB,alongside another vehicle. MV 2 does not see MV 1 coming up Rt 28 NB and pulls out and hits 57 MV 1. Crash Data Summary Tables and Charts I-495 NB Ramps at Rt 28, Andover, MA CRASH MONTH 16% 14% 12% 10% 8% 6% 4% 2% 0% 15% 12% 12% 9% 9% 12% 9% 9% 6% 3% 3% 0% J F M A M J J A S O N D CRASH DAY OF WEEK 27% 30% 25% 18% 20% 15% 15% 10% 12% 9% 9% Monday Tuesday 9% 5% 0% Wednesday Thursday Friday Saturday Sunday CRASH TIME OF DAY 25% 21% 18% 20% 15% 15% 15% 10% 12% 6% 6% 3% 5% 3% 0% 0% 0% 0% 6AM- 8AM 45% 40% 35% 30% 25% 20% 15% 10% 5% 0% 8AM­ 10AM 10AM­ 12PM 12PM­ 2PM 2PM- 4PM 4PM- 6PM 6PM- 8PM 8PM­ 10PM 10PM­ 12AM 12AM­ 2AM 2AM- 4AM 4AM- 6AM CRASH MANNER OF COLLISION 42% 24% 24% 6% Single Vehicle Crash Rear-end Angle Sideswipe, same direction Crash Data Spreadsheet_Rt 28 @ I-495_05_28_2015FINAL.xlsx2 of 3 3% Sideswipe, opposite direction 0% Head on 0% 0% Rear to Rear Unknown 5/28/2015 Crash Data Summary Tables and Charts I-495 NB Ramps at Rt 28, Andover, MA CRASH LIGHT CONDITION 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 79% 18% Daylight 0% 0% 3% Dawn Dusk Dark ­ Dark ­ Dark ­ Lighted Roadway not unknown Roadway lighted roadway lighting 0% 0% 0% Other Unknown CRASH WEATHER CONDITION 70% 60% 50% 40% 30% 20% 10% 0% 67% 21% 9% Clear Cloudy 3% Rain 0% 0% 0% 0% Severe Blowing Sleet, Hail, Fog, Smog, Smoke Crosswinds sand, snow Freezing Rain Snow 0% 0% Other Unknown CRASH ROAD SURFACE 80% 70% 60% 50% 40% 30% 20% 10% 0% 70% 21% Dry Wet 0% 3% Snow Ice 6% 0% Sand, mud, Water dirt, oil, (standing, gravel moving) 0% 0% 0% Slush Other Unknown CRASH DRIVER AGES 35% 30% 25% 20% 15% 10% 5% 0% 30% 18% 16% 16% 10% 5% 15-20 21-29 30-39 40-49 Crash Data Spreadsheet_Rt 28 @ I-495_05_28_2015FINAL.xlsx3 of 3 50-59 60-69 3% 70-79 2% 80+ 5/28/2015 14 APPENDIX II SPEED AND VOLUME DATA Page 1 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 Direction 1 Start Time 06/25/15 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12 PM 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Total Percent AM Peak Vol. PM Peak Vol. Grand Total Percent Statistics 1 29 30 15 13 8 10 28 54 99 90 117 146 156 149 175 138 167 179 183 181 140 133 176 96 31 2514 17.1% 11:00 156 17:00 183 30 32 5 5 4 2 5 17 24 61 83 55 86 56 73 59 65 79 71 97 92 71 63 54 31 8 1166 7.9% 10:00 86 17:00 97 2514 1166 17.1% 7.9% 33 35 9 13 7 6 6 14 34 46 84 50 69 41 56 34 58 51 69 46 52 54 46 51 53 22 971 6.6% 08:00 84 16:00 69 36 38 33 21 14 9 5 22 52 91 112 124 96 98 74 74 89 101 104 105 109 86 69 111 74 41 1714 11.6% 09:00 124 21:00 111 971 1714 6.6% 11.6% 15th Percentile : 50th Percentile : 85th Percentile : 95th Percentile : 10 MPH Pace Speed : Number in Pace : Percent in Pace : Number of Vehicles > 35 MPH : Percent of Vehicles > 35 MPH : Mean Speed(Average) : 39 41 34 19 25 10 8 32 57 116 147 167 120 125 132 128 163 146 174 189 177 163 114 192 107 49 2594 17.6% 09:00 167 21:00 192 2594 17.6% 11 MPH 25 MPH 42 MPH 46 MPH 37-46 MPH 4037 27.4% 10082 68.5% 27 MPH 42 44 29 25 17 6 10 35 82 128 144 135 111 114 154 140 131 178 181 206 251 177 176 195 111 54 2790 18.9% 08:00 144 18:00 251 45 47 19 17 10 2 10 25 64 52 78 76 75 66 108 86 85 93 129 135 151 115 106 121 45 25 1693 11.5% 08:00 78 18:00 151 48 50 5 5 10 1 7 12 28 29 17 40 28 42 51 47 38 52 59 56 67 53 49 54 27 12 789 5.4% 11:00 42 18:00 67 51 53 7 2 2 1 6 5 12 11 6 21 9 7 13 16 12 20 27 20 28 16 13 32 9 13 308 2.1% 09:00 21 21:00 32 Untitled S Site Code: 00000011 Station ID: Date Printed: 26-Jun-15 Untitled S Untitled S 54 56 1 0 2 0 0 5 6 3 1 3 3 4 6 8 3 10 10 6 5 2 5 9 11 6 109 0.7% 06:00 6 22:00 11 57 59 2 0 2 1 0 1 1 2 1 5 2 0 5 0 5 3 2 2 8 4 4 6 1 3 60 0.4% 09:00 5 18:00 8 60 62 0 0 0 0 0 0 1 0 1 1 0 0 0 1 0 1 2 2 0 0 1 0 3 0 13 0.1% 06:00 1 22:00 3 63 65 0 0 1 0 0 0 1 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3 0.0% 02:00 1 66 999 2 0 0 0 0 0 0 0 0 0 0 0 1 0 0 1 0 1 1 1 0 0 2 0 9 0.1% 00:00 2 22:00 2 2790 1693 789 308 109 60 13 3 9 18.9% 11.5% 5.4% 2.1% 0.7% 0.4% 0.1% 0.0% 0.1% Total 176 122 107 46 67 196 416 638 764 795 745 709 822 768 787 902 1007 1048 1122 882 779 1001 570 264 14733 09:00 795 18:00 1122 14733 85th Percent 42 43 44 40 45 43 44 42 42 42 40 41 42 42 42 42 43 42 43 43 43 43 42 44 95th Percent 47 46 49 45 50 48 48 46 45 47 45 46 47 46 46 47 47 46 47 47 47 47 47 50 Page 1 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 Start Time 12:00 AM 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 PM 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 Total Percentage AM Peak Vol. PM Peak Vol. Total 22-Jun-15 Mon 23-Jun-15 Tue 24-Jun-15 Wed * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - - 0 0 25-Jun-15 Thu 178 123 107 47 67 197 417 648 769 801 749 716 824 778 789 907 1012 1058 1125 888 781 1005 572 265 14823 100.6% 09:00 801 18:00 1125 Untitled Vo Site Code: 00000011 Station ID: Date Printed: 26-Jun-15 Untitled Vo Untitled Vo 26-Jun-15 Fri Weekday Average 27-Jun-15 Sat 4 * * * * * * * * * * * * * * * * * * * * * * * 4 0.0% 00:00 4 91 123 107 47 67 197 417 648 769 801 749 716 824 778 789 907 1012 1058 1125 888 781 1005 572 265 - 28-Jun-15 Sun - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - - - - Page 1 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 rte28nb june2015 Site Code: 00000011 Station ID: Date Printed: 26-Jun-15 rte28nb june2015 rte28nb june2015 Date\Speed (MPH) 6/25/2015 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Day Total 1-10 11-15 16-20 21-25 26-30 31-35 36-40 41-45 46-50 51-55 56-60 61-65 66-70 >70 0 0 0 0 0 0 0 0 0 2 0 1 0 0 0 0 0 0 0 0 0 0 0 0 3 0 0 0 0 0 1 0 2 1 0 3 0 0 0 0 0 0 0 1 1 0 0 0 0 9 2 0 0 0 0 0 0 1 6 10 2 1 3 2 0 1 0 0 0 0 0 3 5 2 38 7 6 3 1 5 6 6 15 19 28 38 38 43 43 38 34 45 44 38 44 40 67 30 13 651 12 10 9 7 7 25 56 95 88 95 129 138 120 137 109 146 155 160 156 110 106 114 57 16 2057 13 17 10 7 9 24 47 86 134 81 122 68 106 72 99 97 104 106 114 96 86 82 78 27 1685 52 35 30 15 11 43 82 168 207 232 179 177 161 154 211 185 216 226 234 179 139 236 154 63 3389 54 34 30 10 15 55 133 190 229 215 182 194 237 221 205 274 286 323 372 286 259 308 155 91 4358 14 18 16 3 14 28 68 58 62 95 69 74 121 100 90 111 145 142 149 129 116 129 55 27 1833 8 2 4 1 6 9 17 12 7 24 12 9 18 21 14 28 34 26 32 18 17 41 19 17 396 2 0 2 1 0 2 3 4 1 5 2 2 6 3 6 5 6 4 9 4 6 6 4 5 88 0 0 1 0 0 0 1 0 1 2 0 0 0 1 0 1 1 0 0 0 0 0 1 0 9 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 1 1 1 0 0 0 0 5 1 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 2 0 4 6/26/2015 Lane1 Total 0 3 1 10 0 38 2 653 16 2073 14 1699 41 3430 42 4400 19 1852 1 397 1 89 2 11 0 5 Lane1 Total 166 122 105 45 67 193 413 631 755 789 738 702 816 754 772 883 992 1032 1106 868 769 986 560 261 14525 0 139 4 14664 85 percentile = 45 Page 1 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 Direction 1 Start Time 06/25/15 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12 PM 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Total Percent AM Peak Vol. PM Peak Vol. Grand Total Percent Statistics 1 20 2 0 3 1 1 4 3 3 2 7 13 11 5 11 6 15 1 2 6 11 8 8 1 2 126 0.9% 10:00 13 15:00 15 21 22 0 2 0 1 2 2 7 13 10 8 4 11 11 13 7 7 7 1 3 10 8 6 2 5 140 1.0% 07:00 13 13:00 13 126 140 0.9% 1.0% 23 24 2 1 2 0 3 15 14 31 13 13 14 34 39 27 24 23 22 10 16 13 14 13 8 6 357 2.5% 11:00 34 12:00 39 25 26 8 3 1 4 12 31 41 59 27 36 49 47 50 49 65 53 41 26 38 37 35 35 15 15 777 5.4% 07:00 59 14:00 65 357 777 2.5% 5.4% 15th Percentile : 50th Percentile : 85th Percentile : 95th Percentile : 10 MPH Pace Speed : Number in Pace : Percent in Pace : Number of Vehicles > 35 MPH : Percent of Vehicles > 35 MPH : Mean Speed(Average) : 27 28 12 6 4 13 20 74 61 89 60 69 85 90 98 80 92 94 55 69 64 72 47 56 34 16 1360 9.4% 11:00 90 12:00 98 1360 9.4% 26 MPH 32 MPH 37 MPH 40 MPH 29-38 MPH 9209 64.4% 4449 31.1% 32 MPH 29 30 13 7 8 3 32 77 99 116 115 98 101 110 101 108 126 121 103 102 88 68 61 62 50 17 1786 12.4% 07:00 116 14:00 126 31 32 11 1 4 9 32 110 134 147 148 106 109 148 103 123 146 127 145 121 106 106 67 69 61 18 2151 14.9% 08:00 148 14:00 146 33 34 20 6 8 11 19 80 133 179 170 142 120 119 159 126 130 141 141 142 120 84 75 66 35 19 2245 15.5% 07:00 179 12:00 159 35 36 5 11 8 9 20 84 106 140 153 120 107 94 136 105 124 137 156 144 101 72 71 61 32 18 2014 13.9% 08:00 153 16:00 156 Untitled S Site Code: 00000090 Station ID: Date Printed: 26-Jun-15 Untitled S Untitled S 37 38 10 6 2 5 18 56 105 128 118 95 73 85 95 76 92 82 127 130 97 86 66 49 26 18 1645 11.4% 07:00 128 17:00 130 39 40 13 3 3 2 7 50 73 80 68 55 47 51 59 58 58 57 65 73 70 49 35 27 7 8 1018 7.0% 07:00 80 17:00 73 41 42 6 1 4 3 6 26 36 31 49 25 18 22 21 30 24 27 23 39 36 28 15 13 6 6 495 3.4% 08:00 49 17:00 39 43 44 2 1 2 1 2 9 21 13 13 10 2 5 9 5 9 11 7 13 11 13 9 10 4 3 185 1.3% 06:00 21 17:00 13 45 999 3 3 1 0 6 13 11 10 9 9 3 3 5 7 6 9 8 18 10 8 7 3 3 2 157 1.1% 05:00 13 17:00 18 1786 2151 2245 2014 1645 1018 495 185 157 12.4% 14.9% 15.5% 13.9% 11.4% 7.0% 3.4% 1.3% 1.1% Total 107 51 50 62 180 631 844 1039 955 793 745 830 891 818 909 904 901 890 766 657 518 478 284 153 14456 07:00 1039 14:00 909 14456 85th Percent 39 37 37 36 37 38 38 37 38 37 36 37 37 37 37 37 37 38 38 38 37 37 36 37 95th Percent 41 39 41 40 40 40 40 40 40 40 39 39 39 40 39 40 39 40 40 40 40 40 38 40 Page 1 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 Rte28SB June2015 Site Code: 00000090 Station ID: Date Printed: 26-Jun-15 Rte28SB June2015 Rte28SB June2015 Date\Speed (MPH) 6/25/2015 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 13:00 14:00 15:00 16:00 17:00 18:00 19:00 20:00 21:00 22:00 23:00 Day Total 1-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 41-45 46-50 51-55 56-60 61-65 >65 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 2 0 0 0 0 0 0 0 0 3 0 0 1 0 1 1 0 1 0 2 1 1 2 0 0 7 1 1 2 0 0 1 0 0 22 2 0 0 1 0 1 3 1 1 5 11 8 3 8 5 4 0 1 2 11 5 5 1 2 80 4 3 2 3 9 23 36 69 35 36 35 69 73 71 55 55 44 21 35 39 36 37 17 19 826 31 16 13 18 60 176 186 239 190 188 218 223 226 206 259 243 184 187 174 161 129 135 92 40 3594 35 11 18 22 66 231 314 402 393 310 284 316 339 302 344 338 353 340 270 224 183 164 116 50 5425 24 16 7 14 30 149 237 272 264 208 172 181 213 186 206 206 281 270 224 173 131 108 45 31 3648 9 2 6 4 10 39 58 48 66 37 22 29 32 39 37 43 33 60 49 44 28 23 12 9 739 1 3 0 0 4 7 10 6 5 7 0 1 3 3 2 2 4 9 8 4 3 3 1 1 87 0 0 1 0 0 2 0 0 0 0 1 0 0 0 0 2 1 1 0 1 0 0 0 1 10 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 6/26/2015 Lane1 Total 0 0 0 3 1 23 3 83 4 830 23 3617 29 5454 21 3669 9 748 1 88 1 11 1 2 0 0 Lane1 Total 107 51 48 62 180 629 844 1038 955 793 744 828 891 815 908 902 901 890 764 657 515 476 284 153 14435 0 93 0 14528 85 percentile = 37 Page 1 Rte28SB June2015 Site Code: 00000090 Station ID: Date Printed: 26-Jun-15 Rte28SB June2015 Rte28SB June2015 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 Direction 1 Report for 6/25/2015 12:01:00 AM to 6/25/2015 11:59:00 PM SPEED STATISTICS - 15 to 70+ by 5 MPH Speed in 1 - 15 MPH Count 25 Percent 0.2 15 Over Speed Count 14406 Percent 99.8 Percentile Speed 5% 25 Average 33 (Mean) Pace 28-37 Speed Number in 9874 Pace Percent in 68.4 Pace 16 - 20 21 - 25 26 - 30 31 - 35 36 - 40 41 - 45 46 - 50 51 - 55 56 - 60 61 - 65 66 - 70 71 - 75 80 0.6 825 5.7 3594 24.9 5422 37.6 3648 25.3 739 5.1 87 0.6 10 0.1 1 0.0 0 0.0 0 0.0 0 0.0 76 ­ 999 0 0.0 20 14326 99.3 25 13501 93.6 30 9907 68.7 35 4485 31.1 40 837 5.8 45 98 0.7 50 11 0.1 55 1 0.0 60 0 0.0 65 0 0.0 70 0 0.0 75 0 0.0 999 0 0.0 10% 27 15% 28 45% 32 50% 33 55% 34 85% 38 90% 39 95% 41 Page 2 Rte28SB June2015 Site Code: 00000090 Station ID: Date Printed: 26-Jun-15 Rte28SB June2015 Rte28SB June2015 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 COMBINED - Direction 1 Report for 6/25/2015 12:01:00 AM to 6/25/2015 11:59:00 PM SPEED STATISTICS - 15 to 70+ by 5 MPH Speed in 1 - 15 MPH Count 25 Percent 0.2 15 Over Speed Count 14406 Percent 99.8 Percentile Speed 5% 25 Average 33 (Mean) Pace 28-37 Speed Number in 9874 Pace Percent in 68.4 Pace 16 - 20 21 - 25 26 - 30 31 - 35 36 - 40 41 - 45 46 - 50 51 - 55 56 - 60 61 - 65 66 - 70 71 - 75 80 0.6 825 5.7 3594 24.9 5422 37.6 3648 25.3 739 5.1 87 0.6 10 0.1 1 0.0 0 0.0 0 0.0 0 0.0 76 ­ 999 0 0.0 20 14326 99.3 25 13501 93.6 30 9907 68.7 35 4485 31.1 40 837 5.8 45 98 0.7 50 11 0.1 55 1 0.0 60 0 0.0 65 0 0.0 70 0 0.0 75 0 0.0 999 0 0.0 10% 27 15% 28 45% 32 50% 33 55% 34 85% 38 90% 39 95% 41 Page 1 Andover Police Department 32 North Main St Andover, MA 01810 (978)475-0411 Start Time 12:00 AM 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 12:00 PM 01:00 02:00 03:00 04:00 05:00 06:00 07:00 08:00 09:00 10:00 11:00 Total Percentage AM Peak Vol. PM Peak Vol. Total 22-Jun-15 Mon 23-Jun-15 Tue 24-Jun-15 Wed * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - - 0 0 25-Jun-15 Thu 107 51 50 62 180 631 844 1040 955 793 746 830 891 819 910 904 901 890 766 657 519 478 284 153 14461 100.0% 07:00 1040 14:00 910 Untitled Vo Site Code: 00000090 Station ID: Date Printed: 26-Jun-15 Untitled Vo Untitled Vo 26-Jun-15 Fri * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - Weekday Average 107 51 50 62 180 631 844 1040 955 793 746 830 891 819 910 904 901 890 766 657 519 478 284 153 27-Jun-15 Sat 28-Jun-15 Sun - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - * * * * * * * * * * * * * * * * * * * * * * * * 0 0.0% - - - -