THIS DRAFT WAS NOT APPROVED, SIGNED OR SENT [shc 05-13-05] TO: FROM: DATE: RE: Lina Swan, Director of Fiscal Operations Stephen H. Clark, Administrative Law Judge May 13, 2005 Request for Direct Payment Under G.L. c.30, S.39F Claimant: Contractor: Contract # City/Town: Amount: Don Martin Corporation Co. (Don Martin) Roads Corporation (Roads) Contract #31285 Raynham $47,734.99 1. Don Martin filed this direct payment demand (Demand) for $47,734.99 on April 12, 2005. I found the Demand colorable and requested that District 5 report on the status of the subcontract work. 2. District 5 reported to Fiscal Operations on April 25, 2005 (received May 5, 2005) that Don Martin was an approved subcontractor, that the subcontract work was completed on August 27, 2003, and that the Department does not intend to make a claim for defective or incomplete work. 3. Roads replied to the Demand by a statement made under pains and penalties of perjury and copied by certified mail to Don Martin on April 20, 2005. Roads provided a detailed breakdown of the balance due under the subcontract in its sworn reply. Among other things, Roads’ reply purports to “exercise[] our right to off-set payment” to Don Martin for subcontract work Don Martin performed under MHD#32082. The amount of the “off-sets” claimed are $30,043.91. 4. Don Martin and Road agree that $384,438.99 is the value of the original subcontract work performed; and they also agree that a Department-approved change order for work of $2,181.30 should be added to that value, for a total of approved subcontract work of $386,620.29 ($384,438.99 + $2,181.30). To this amount I specifically refuse to add the sum of $4,340.00 that Don Martin claims as “change order work” for “Premium Cost Pave Nights” in its Demand. The District reported that it refused Roads’ request for extra work of $4,340.00 to the general contract. Accordingly, the $4,340.00 in Don Martin’s Demand is rejected on the grounds that it is not subject to Section 39F at all, as it is outside the general contract. Accordingly, I find that the total value of all subcontract work performed including approved extra work, before downward adjustments are made for claimed backcharges, credits, retainage or “off-sets,” is $386,620.29. 5. A downward adjustment to the total subcontract value is required for two agreed back charges. Roads and Don Martin agree that the sums of $69.60 (village street point lines) and $3,353.65 (village street parking lot) totaling $3,423.25 should be accounted for. Roads does so by subtracting $3,423.25 from the value of the subcontract as back charges while Don Martin “credits” as value received the same sum. In order to account for the agreed upon adjustment of $3,423.25 consistently, I treat the $3,423.25 as a backcharge to be subtracted from the subcontract value, which I then find to be $383,197.04 ($386,620.29 - $3,423.25). (I do not include $3,423.25 as a “credit” in calculating payments made to Don Martin. See paragraph 9 below.) 6. A final backcharge adjustment to the value of the subcontract should be made. Roads states under oath that a back charge of $2,625.13 (Raynham sidewalks) should be taken. Don Martin does not include that sum as a “credit” (or otherwise) in its accounting. Based on Roads’ sworn statement, I find that an additional back charge of $2,625.13 should be taken. After subtracting that backcharge the ultimate subcontract value of Department-approved work performed is $380,571.91 ($383,197.04 - $2,625.13). The sum of $380,571.91 agrees with the “revised contract” value submitted by Roads in its sworn reply. 7. I reject Roads’ contention that the sum of $13,616.40 should be subtracted from the total subcontract value because it is “retainage” held. Generally, retainage is due the subcontractor sixty-five days after completion of the work unless a dispute exists as the to quality of the work. See Bayer & Mingolla Indus. v. Orlando Contracting Co., 6 Mass. App. Ct. 1, 3 (1978). G.L. c.30, s. 39F(1)(b) requires that sixty-five days after the subcontractor has completed the work the “entire balance due under the subcontract,” less certain amounts, is “due” to the subcontractor.1 The amounts that may be subtracted from the “entire balance” are the costs of completing incomplete and unsatisfactory subcontract work. Here, there is no dispute concerning incomplete or unsatisfactory work. Accordingly, the retainage withheld from Don Martin in the amount of $13,616.40 is due.2 8. I also reject Roads’ contention that the payment of a direct payment demand by the awarding authority under Section 39F is subject to the mere assertion of Roads that Don Martin owes Roads $30,043.91 in “off-sets” as a result of 1 The pertinent part of G.L. c.30, s.39F(1)(b) provides: “Not later than the sixty-fifth day after each subcontractor substantially completes his work in accordance with the plans and specifications, the entire balance due under the subcontract less amounts retained by the awarding authority as the estimated cost of completing the incomplete and unsatisfactory items of work, shall be due the subcontractor; and the awarding authority shall pay that amount to the general contractor.” 2 See also Sullivan & Sons, Inc., v. Kay-Lock, Inc., 17 Mass. App. Ct. 997, 998 (1984) and cases cited. A contrary provision in the subcontract between Don Martin and Roads would not affect the outcome here. In Massachusetts a subcontract provision purported to make the release of a subcontractor’s retainage contingent upon prior final payment by the owner to the general contractor would be “contrary to G.L. c.30, s.39F” and “therefore void” as contradicting the requirements of G.L. c.30, s. 39F(1)(b). Bayer & Mingolla Indus., supra, 6 Mass. App. Ct. at 3. purported damage suffered by Roads under MHD contract #32082. Section 39F does not authorize such an “off-set” and Roads cites no authority in support. I note that a set off may be permitted if a court bars direct payment. See Section 39F(1)(e)(ii). 9. Don Martin and Roads do not agree on the amount of payments Roads has made to Don Martin exclusive of credits, backcharges and the like. Don Martin states that it has received $339,802.05, while Roads states that it has paid Don Martin $336,911.60. There is no evidence to suggest the source of the resulting $2,890.45 discrepancy. For the sole purpose of deciding this Demand I find that Roads has paid Don Martin $339,802.05 since I infer that Don Martin is unlikely to have overstated the amount it received from Roads. 10. In sum, I conclude that Don Martin has proved that the Department should pay it $40,769.86 as a direct payment ($380,571.91 - $339,802.05), summarized as Total original subcontract work Add MHD-approved extra work $384,438.99 2,181.30 $386,620.29 Subtract agreed backcharges) 3,423.25 Subtract backcharge (Raynham sidewalks) 2,625.13 $380,571.91 Subtract total payments to Don Martin $339,802.05 Amount of direct payment by MHD 40,769.86 11. Kindly pay $40,769.86 to the claimant out of the next periodic, semi-final or final estimate on the project if funds are available and deduct from payments due to Roads in accordance with G.L. c. 30, s. 39F(1)(h). 12. Take no action on the balance of Don Martin’s Demand. cc: Don Martin Corporation 475 School Street, Unit #6 Marshfield, MA 02050 The Roads Corporation 241 Treble Cove Road North Billerica, MA 01852 District Highway Director, District 5 Deputy Chief Engineer, Construction