,, COMMONWEALTH OF MASSACHUSEITS MASSACHUSEITS IllGHWAY DEPARTMENT BOARD OF CONTRACT APPEALS DATE: April 28, 2004, Item #2' CLAIM: Bardon Trimaunt, Inc .., aggrieved by the Massachusetts Highway Department's denial of its claim opposing the deduction of quantities taken during the finals review and failure to pay interest on 5 alleged late periodic payments appealed to Board of Contract Appeals. RECOMMENDATION: The claim of Bardon Trimaunt, Inc.'s under Contract No. 93174 for deduction in quantities should be approved in the amount of $1,449.00 and the claim for late periodic payments in the amount afS4,713.32 should be dertied. FOR DEPARTMENT SECRETARY Item # -3..---------------------------------------------------­ ___~ilJU_9A_______________________________________ ' Date The Board accepted the ~ecomrnendations Claim for deduction in quantities Approved. Claim for late periodic payments Denied. r---------::~~~~~ ATRUE copy _ATTEST ('... I .­ }l " ' '.'.~,. ­ uti" , '.. ,.~. .... J f.' , ""u. ~,""-­ .J\~ l..Jta.-­ SECRETARY, MASS. HIGHWP.Y COMM. 'MASS HIGHWAYDEPARn~ENT c omn';or.wealth ofMassachu setts In Contract # 93174 Bardon Trimount, Inc. (Bardon)1, disputes the deduction by the finals engineer of the Massachusetts Highway Department (MHD or Department) of 63 tons of pavement from Item #460.1 with a value of $1,449.00 in the final estimate and further disputes the refusal of the Department to pay interest of $4,713.32 on five (5) alleged late periodic payments. I find that Bardon’s appeal from the Department’s determination of the quantity dispute of 63 tons has merit and that the Department should not deduct $1,449.00 from the Department’s final estimate. I also find that the Department does not owe interest for late payment on any of the 5 periodic estimates at issue. Under the Contract no payments were “due” from the Department until Bardon submitted equal employment opportunity forms required by law. Where the Department paid periodic estimates within 35 days of the date on which the Department certified that Bardon had belatedly submitted the required forms, no interest was due. STATEMENT OF THE CASE Bardon appeals to the Board directly from the determinations of the finals engineer and filed this appeal on April 15, 2002. The appeal was heard on September 11,2003. There is a tape recording of the hearing. Present were John McDonnell Isaac Machado Paul Sullivan Mary Bearse Greg MacKenzie Acting Chief Administrative Law Judge Deputy Chief Counsel, MHD Final Engineer, MHD Fiscal Management, MHD Bardon The following exhibits were entered in evidence: Ex#1 Ex#2 Ex#3 1 Bardon’s Statement of Claim Notice of Hearing MHD Contract No. 93174 Bardon is now doing business as Aggregate Industries, Inc. Ex#4 Ex#5 Ex#6 Quantity Control Sheet for Item No. 460.1 Final Engineer’s Tally Sheet for Item No. 460.1 Contract Quantity Estimate Sheets Nos. 4, 5, 6, 24, and 27. The hearing officer requested additional documentation for the record at the conclusion of the hearing. The Department supplemented Ex. #6 by supplying Bardon and the hearing officer with Quantity Estimate Sheets Nos. 5, 6, 24 and 27. The Department also supplemented the record by submitting a six page Standard Operating Procedure titled “Contract Quantity Estimate.” Bardon did not make a post hearing submission. The report and recommendation was written by the undersigned with the participation of Mr. McDonnell, who heard the appeal. FINDINGS OF FACT Substantial evidence on the record, consisting of tape recorded testimony and documents, supports the following findings of fact, which I recommend the Board adopt. 1. Bardon is the contractor on MHD contract No. 93174 for work to resurface a section of Interstate Route 395, interchange ramps, and associated work, in Oxford and Auburn (Contract). 2. The Contract was entered into on September 17, 1992 with an original completion date of October 15, 1994. The Contract bid price was $3,551,018.00. The Notice to Proceed issued September 21, 1992. 3. The Contract work was completed on or before November 11, 1994, the date approved by the Department for extended completion. 4. The Contract included by reference, among other things, the Plans, the Special Provisions; the Standard Specifications for Highways and Bridges (1988 ed.) (Standard Specifications), the Supplemental Specifications 2 (August 7, 1991); the Required Contract Provisions, Federal-Aid Construction Contracts; 41 Code Of Federal Regulations 60-1 et seq. (41 CFR 60); the Standard Federal Equal Opportunity Contract Specifications; and the Commonwealth of Massachusetts Supplemental Equal Employment Opportunity Anti-Discrimination and Affirmative Action Program. 5. Subsection 9.05 of the Standard Specifications, entitled “Final Acceptance and Final Payment,” provides in pertinent part All prior partial estimates and payments shall be subject to correction in the final estimate and payment. 6. The Department’s finals review engineer checked the quantities of materials associated with the pay items and reviewed all prior partial estimates and payments in the Contract. 7. The Department prepared the Final Estimate on February 24, 1999. 8. On December 5, 2000 the Department sent Bardon the First Final Estimate Notice. 9. On January 8, 2002 the Department sent to Bardon The Fourth and Final Estimate Notice, which indicated, among other things, that the department deducted payment for 63 tons of concrete with a Contract value of $1,449.00. 10. On May 1, 2002 Bardon filed its Statement of Claim. 3 The Quantity Dispute 11. Item 460.1 of the Special Provisions provides that a certain estimated quantity of class I bituminous concrete pavement type I-1 be used on the project. 12. Bardon calculated that it had supplied 37,593 tons of Item 460.1 bituminous concrete. 13. The Department’s finals engineer calculated that Bardon had supplied 37,530 tons of Item 460.1 concrete. 14. The amount in dispute between the Department’s finals engineer and Bardon was 63 tons. 15. The Department’s resident engineer erroneously wrote the number “1,218” tons when attempting to transcribe the number 1,281 from one column to another for Item 460.1 on the final estimate work sheet submitted to the finals engineer. Ex. #4 line 9. 16. The quantity dispute of 63 tons for Item 460.1 is wholly explained by the transcription error by the Department’s resident engineer. 17. The transcription error of 63 tons resulted in a proposed reduction in payment under Item 460.1 of $1,449.00 (63 tons times $23/ton). The Interest Dispute 18. The Department refused to pay five periodic payment estimates submitted by Bardon because forms showing Bardon’s compliance with nondiscrimination provisions of federal and state law were not timely submitted. 4 19. G.L. c. 30, s.39G requires that the Contract contain Subsection 7.15 in the Standard Specifications. 20. Subsection 7.15 of the Standard Specifications provides, in pertinent part The awarding authority shall pay the amount due pursuant to any periodic, substantial completion or final estimate within thirty-five days after receipt of written acceptance of such estimate from the contractor and shall pay interest on the amount due pursuant to such estimate at the rate hereinabove provided from that thirty-fifth day to the date of payment. [Retainage may be withheld from such payments.] 21. Subsection 9.04 of the Standard Specifications provides, in pertinent part The [Department] shall pay biweekly to the Contractor while carrying on the work the balance not retained as hereinbefore provided. No such estimates or payment shall be required to be made when, in the Engineer’s judgment, the work is not proceeding in accordance with the provisions of the Contract…. 21. Subsection 1.44 defines the term “work” used in the Standard Specifications and provides in pertinent part Work shall mean the furnishing of all labor, materials, equipment and other incidentals necessary for or convenient to the successful completion of the project and the carrying out of all the duties and obligations imposed by the Contract. Work shall include in addition to work to be performed on the project location in the actual construction process, necessary shop plans, computations, ordering of materials and equipment, fabrication of material, parts and components, etc.” 22. The Contract contains eight pages of “Required Contract Provisions FederalAid Construction Contracts,” of which Section II, “Nondiscrimination,” incorporates by reference the Equal Employment Opportunity Affirmative Action Construction Contract Specifications set forth in 41 CFR 60-4.3 (EEO Specifications). 5 23. The EEO Specifications require Bardon to “not discriminate on the grounds of race, color, sex or national origin in the selection and retention of subcontractors, including procurement of material and leases of equipment.” Section II (4). 24. The EEO Specifications require Bardon to comply with 41 CFR Part 60, Section II (3)(d), to “furnish all information and reports required by Executive Order 11246, Section II (3)(e).” 25. EEO Specifications Section II (4)(b) provides in pertinent part (emphasis added) In the event of the contractor’s noncompliance with nondiscrimination provision of this Section II, paragraph 4, this contract may be subject to sanctions, including but not limited to the withholding of payment to the contractor under the contract until the contractor complies and/or cancellation, termination or suspension of the contract in whole or in part. 26. The Standard Operating Procedure (SOP) of the Department with respect to the preparation of Contract Quantity Estimates provides, in pertinent part If any document required under the contract has not been received within the time limit for each document …. The Resident Engineer shall enter the following statement in the bottom margin of the first part of the Contract Quantity Estimate prior to submission to the Contractor’s authorized representative: Approval withheld until [blank space for date] when the Contractor submitted the [list missing documentation]. 27. Contract Quantity Estimate No. 4 (CQE 4) was signed by Bardon and submitted to the Department’s resident engineer for approval on 5/20/93. CQE 4 has on its face this notation: “Approval withheld until 6-21-93 when contractor and subcontractor submit required EEO Forms. See Attached List.” Said attached list is contained on a form dated 5-19-93 which says: 6 “The following reports are due immediately”: [1] “Bardon Trimount” and [subcontractor] “Swank” “Projected manning tables April-June”; [2] Monthly Utilization 257 “Bardon Oct, Nov. Dec. April” and “Swank Oct. Nov.”; [3] “Bardon Biweekly training Rpt.”; and [4] “Bardon trainee reports 1409 semi annual.” [Original emphasis.] 28. Contract Quantity Estimates (CQE’s) numbered 5, 6, 24 and 27 have on their face notations made by the resident engineer showing that the Department [1] has withheld approval of the CQE until a date certain [2] after “contractor and subcontractor submit required EEO Forms. See Attached List.” 29. Late payment interest, in the amount of $8,675.39 for CQE #26 was paid on CQE #27. CQE #27 shows that Bardon signed the same on 2/17/95 but the resident engineer annotated that he “received back from contractor on 7/26/95.” 32. Following MHD’s receipt of required EEO Forms, CQE’s 4, 5, 6, 24 and 27 were approved and paid by the Department on the following dates, within the number of days shown after the CQE had been approved by the Department: Estimate No. 4 5 6 24 26 27 Day MHD Approved Date of Check 6/21/93 7/16/93 7/6/93 7/23/93 7/6/93 7/30/93 10/12/94 10/28/94 Interest paid on CQE #27 in amount of $8,675.39 8/4/95 8/24/95 Number Days 27 17 24 16 20 32. With respect to CQE’s 4, 5, 6, 24 and 27, in each instance the Department paid the full amount due within 35 days after it approved the CEQ. 7 DISCUSSION A. The Quantity Dispute Bardon appeals the Department’s deduction of 63 tons from Item 460.1 by the finals engineer. The record shows without doubt that the origin of the Department’s 63-ton quantity deduction was in a simple transcription error in the resident engineer’s worksheet, which error was carried forward throughout the final estimate process. Where clear and convincing evidence shows that clerical error is the genesis of the dispute, the error should be corrected and appeal resolved. I find that Bardon’s appeal has merit. The Department should not deduct from retainage $1,449.00 (63 tones at $23.00/ton) in the final estimate, which sum should be released. B. The Claim For Interest For Late Payment The Contract specifies that biweekly payments to the contractor carrying on the work “shall [not] be required to be made when, in the Engineer’s judgment, the work is not proceeding in accordance with the provisions of the Contract.” See Standard Specifications, Subsection 9.04. The word “work” is defined in the Contract to include “the carrying out of all the duties and obligations imposed by the Contract as well as the “furnishing of all labor, materials and equipment.” Id., Subsection 1.44. Bardon has the burden to show it was in compliance with all its duties and obligations under the Contract. One such contractual duty was the timely submission of forms to show that it and its subcontractor were in compliance with 8 express federal and state equal employment opportunity (EEO) regulations. It is undisputed that Bardon failed to submit certain federally mandated forms at various times in 1993, 1994 and 1995, as shown on the face of CQE’s numbered 4, 5, 6, 24 & 27. Each of those CQE’s is plainly marked that “required EEO forms” are missing. Each CQE states a date certain when the periodic payment will be approved for payment if the missing forms are supplied. The EEO forms that Bardon failed to timely supply were required by law and by the Contract. See Equal Employment Opportunity Affirmative Action Construction Contract Specifications (Federal Specifications) and 41 CFR 60-4.3. The Federal Specifications themselves provide for the withholding of payment to a contractor not in compliance in certain circumstances. The resident engineer followed the Department’s Standard Operating Procedure (SOP) governing the completion and payment of Contract Quantity Estimates. The relevant SOP provides: “If any document required under the contract has not been received … the Resident Engineer shall enter the following statement: …. Approval withheld until [blank space for date] when the Contractor submitted the [list missing documentation].” The Department is expressly permitted to withhold periodic payments under the Contract. Because Bardon was not in compliance with the Contract, as expressly noted on the face of the each periodic estimate at issue, the sums otherwise approved by the Department and Bardon never became an “amount due … pursuant to such [periodic] estimate” under Subsection 7.15. 9 Payment under CQE’s 4, 5, 6, 24 and 27 became due when Bardon cured its non-compliance. Bardon did in fact eventually submit the required EEO forms to the Department, as evidenced by the date the district highway director approved each CQE. The Department then paid the amount of the periodic payment estimate due Bardon within 35 days of that approval. Because payment was made within 35 days of the date of such approval, the Department owes no interest. Bardon’s contention that interest runs from the day Bardon itself approved the CQE’s without qualification is not correct. The Contract does not require periodic payments be made to Bardon while it was admittedly in non-compliance with federal and state law. To the contrary, the Contract expressly gives the engineer the authority to suspend payments in circumstances where B&E fails to meet its duties and obligations. The Department’s obligation to pay Bardon only arises after the engineer confirmed that Bardon had brought itself into compliance. Hence, the date when the Department “received” Bardon’s CQE’s could not commence the 35 day period for the Department to make the periodic payments. Rather, the time period begins on the date on which the engineer certified compliance. FINDINGS I find that a transcription error was the cause of the Department’s erroneous deduction of $1,449.00 from the final payment estimate. I further find that the Department owes no statutory interest in the circumstances presented. 10 RECOMMENDATION The Board should adopt the findings of fact set forth. The Board should order $1,449.00 be restored to the final payment owed Bardon. The Board should deny Bardon’s claim for interest. Respectfully submitted, Stephen H. Clark Chief Administrative Law Judge 11