THE COMMONWEALTH OF MASSACHUSETTS EXECUTIVE OFFICE OF TRANSPORTATION ( \ Min ROMNEY GOVERNOR KE-RRY·HEALE¥ LIEUTENANT GOVERNOR JOHN COGLIANO SECRETARY f\ To: Through: From: Secretary John Cogliano, EOT 1 Ii ;f Commissioner Luisa Paiewonsky, MHD Stephen H. Clark, Administrative Law JUdgev~ Date: May 25, 2006 Re: Report and Recommendation I~) I am pleased to submit for your consideration and approval the attached report and recommendation. The three pending appeals of the Todesca Equipment Co., Inc. (Todesca) arising from Department contracts #89123, #91078 and #92056 should be dismissed for the same reason: Todesca failed to timely state "valid written reasons" why the Department's f"mal estimate was not correct within six months of receipt of the respective f"mal estimates. Subsection 9.05 of the Standard Provisions of the Department's contract provides that, unless a contractor me within six months after receipt of a f"mal estimate "valid written reasons" why the f"mal estimate is not correct, the f"mal estimate is deemed "acceptable to the contractor...." Todesca did not me a "valid written reason" for not accepting the f"mal estimate in any of the three above contracts. Accordingly, Todesca's appeals to this office should be dismissed. TELEPHONE: TEN PARK PLAZA, BOSTON, MA 02116-3969 (617) 973-7000 • TELEFAX: (617) 523-6454 • TOO: (617) 973-7306 • WNIN.MASS.GOv/EOT '-­ o INTRODUCTION The Todesca Equipment Co., Inc. (Todesca) filed appeals challenging the Department’s final estimates in three separate contracts (MHD Nos. 89123, 91078 and 92056) on January 8, 2001. Each final estimate showed that Todesca owed the Department money. Two final estimates were sent to Todesca in 1995; one in 1997. At the pre-hearing conference held on February 23, 2006 the Department moved to dismiss all the appeals on the ground that Todesca had not properly challenged the final estimates within the time permitted by Subsection 9.05 of the Standard Specifications. I asked that both the Department and Todesca file written argument on whether the appeals should be dismissed, which the parties did. I conclude that all three appeals should be dismissed. Subsection 9.05 of the Standard Provisions sets forth the procedure that contractor’s must follow in order to challenge a final estimate. That subsection required that Todesca “file a valid … written reason(s) for not accepting the final estimate” “within six months from the date the final estimate is forwarded to the Contractor.” Todesca failed to make any such written statement setting forth any valid reason to disturb the final estimate within the time permitted for any of the three contracts listed above. Under Subsection 9.05 the Department’s final estimate is “considered acceptable to the contractor” should it fail to file such timely written reasons. In addition, Todesca’s failure to pursue the administrative remedy the contract gave it constituted a waiver of its rights to challenge the final estimates. Accordingly, Todesca’s three instant appeals seeking adjudication of purported final estimate disputes should be dismissed. BACKGROUND Contract #89123 Todesca completed work on contract #89123 in 1989. On March 3, 1995 the Department sent Todesca a final estimate which showed that Todesca owed the Department $14,230. On March 22, 1995 Todesca wrote the Department that it “did not agree” with the final estimate. It stated no reason for its disagreement; however, it asked for a meeting “to discuss and review” the project. Two years then passed. On February 24, 1997 the Department forwarded a copy of the final estimate to Todesca; again Todesca wrote on February 26, 1997 that “[w]e are not in agreement with the amounts of these final estimates,” but provided no statement to explain to the Department why it did not accept the final estimate. Two more years passed. On March 8, 1999 the Department’s general counsel wrote Todesca that “failure to respond and reimburse” the Department the money it owed “may affect your firm’s pre-qualification status.” Todesca did not respond. On December 14, 1999 the Department sent another copy of the original final estimate. Todesca failed to respond. On January 2, 2001 the Department sent a fifth notice again supplying a copy of the final estimate. On January 8, 2001 Todesca responded by filing an appeal in the office of the administrative law judge, stating “after reviewing this final estimate we are disputing the figures….” On February 28, 2001 Todesca filed a statement of claim stating “Final quantities agreed with Res. Engr.” A hearing on the appeal was scheduled for June 8, 2004. On the day of the hearing Todesca’s representative appeared and stated that he was not prepared to proceed. The hearing was suspended and Todesca was 2 ordered to file by July 15, 2004 a statement of claim that detailed the dispute. Todesca then filed an amended statement of claim five months later, on December 9, 2004. Contract #91078 Todesca completed work on contract #91078 in 1992. On May 18, 1994 the Department sent Todesca a final estimate which showed that Todesca owed the Department $19,612.77. On July 12, 1994 Todesca wrote the Department that it “did not agree” with the final estimate. No reason for its disagreement was stated but Todesca asked for a meeting. On September 1, 1994 the Department issued a memorandum to the finals engineer and wrote a letter to Todesca asking it to meet with the Department’s representative to resolve any disputed quantities. The record does not disclose whether a meeting was ever scheduled or held. On March 3, 1995 the Department sent a duplicate of the original final estimate, to which Todesca responded by on March 22, 1995 “we do not agree with the final quantities.” Two years then passed. On February 24, 1997 the Department again forwarded a copy of the original final estimate to Todesca. Todesca responded on February 26, 1997, stating “[w]e are not in agreement with the amounts of these final estimates.” The letter stated no reason why Todesca did not accept the final estimate. Two more years passed. On March 8, 1999 the Department’s general counsel wrote Todesca that “failure to respond and reimburse” the Department the money it owed “may affect your firm’s pre-qualification status.” Todesca did not respond. On December 14, 1999 the Department sent another copy of the final estimate. Todesca did nothing. On January 2, 2001 the Department sent a fifth notice with a copy of the final estimate. On January 8, 2001 Todesca filed an appeal in the office of the administrative 3 law judge, stating “after reviewing this final estimate we are disputing the figures….” On February 28, 2001 Todesca filed a statement of claim stating “Final quantities agreed with Res. Engr.” A hearing was duly scheduled for June 8, 2004. On the day of the hearing Todesca’s representative appeared and stated that he was not prepared to proceed. The hearing was suspended and Todesca was ordered to file by July 15, 2004 a statement of claim that set forth in detail its reasons for challenging the final estimate. Five months later, on December 9, 2004, Todesca filed an amended statement of claim. Contract #92056 Todesca completed its work on the contract in 1995. On February 24, 1997 the Department sent a final estimate to Todesca showing that it owed the Department $6,759.55. On February 26, 1997 Todesca wrote the Department that “[w]e are not in agreement with the amounts of these final estimates.” Todesca provided no explanation or basis for its disagreement. On March 8, 1999 the Department’s general counsel wrote Todesca that “failure to respond and reimburse” the Department the money it owed “may affect your firm’s pre-qualification status.” On March 16, 1999 the Department forwarded a duplicate of the final estimate. Todesca did not respond to either the general counsel’s letter or the notice of the final estimate. On January 2, 2001 the Department sent a third copy of the original final estimate. On January 8, 2001 Todesca responded by filing an appeal in the office of the administrative law judge, stating “after reviewing this final estimate we are disputing the figures….” On February 28, 2001 Todesca filed a statement of claim stating “Final quantities agreed with Res. Engr.” The matter was set down for a hearing on June 8, 4 2004. At the hearing Todesca’s representative stated that he was not prepared to proceed. The hearing was suspended and Todesca was ordered to file by July 15, 2004 a statement of claim that detailed the dispute. An amended statement of claim was filed five months later, on December 9, 2004. DISCUSSION Subsection 9.05 of the Standard Specifications provides All prior partial estimates and payments shall be subject to correction in the final estimate and payment. If within six months from the date of the final estimate is forwarded to the contractor, the Contractor has not filed a valid (as determined by the Engineer) written reason(s) for not accepting the final estimate, the final estimate will be considered acceptable to the contractor and payment of the final estimate made. Subsection 9.05 permitted Todesca to “file a valid … written reason(s) for not accepting the final estimate” “within six months from the date the final estimate is forwarded to the Contractor.” The record shows that with respect to each of the above contracts Todesca never timely provided the Department with any “written reason for not accepting the final estimate” when it first received the final estimate. With respect to #89123 and #91078 Todesca responded to the final estimate dated March 3, 1995 by a letter dated March 22, 1995 in which it stated “after review we do not agree with the final quantities.” With respect to #92056 Todesca responded to the final estimate dated February 24, 1997 by a letter dated February 26, 1997 in which it stated “[w]e are not in agreement with the amounts of these final estimates.” In none of the letters did Todesca offer any statement of the reasons it “was not in agreement” with the final estimates. Even when Todesca filed its appeals in this office in 2001 it failed to explicate the nature of its final estimate disputes with the Department. To describe the nature of its 5 appeals on the statements of claim required by this office, Todesca replied in each case: “Final quantities agreed with Res. Engr.” The first time Todesca explained the substance of its disagreement with the final estimates was on December 2, 2004, when it filed amended statements of claim for each of the three appeals. The Contract provides a mechanism for a contractor to bring to the Department’s attention the substance of its dispute with the Department’s final estimate. To activate the mechanism set forth in Subsection 9.05 requires an affirmative act by the contractor, that is, a statement made within six months that specifies a “valid … written reason” for not accepting the final estimate. At a minimum a written reason would inform the Department of what it disputes within the Department’s final estimate. Only a statement with some particularity would provide a meaningful opportunity for the Department to address the contractor’s complaint and address it through administrative action. Failure to supply a valid written reason within the time permitted has a specific consequence under Subsection 9.05: the acceptance of the Department’s estimate. Here, Todesca affirmatively refused to avail itself of the administrative remedy the contracts provided. Such failures had the contractual consequence in each case that Todesca was deemed to have accepted the Department’s final estimate. In addition, the failures to follow the contracts’ administrative procedure that gave Todesca a remedy to correct an erroneous final estimate result in a clear waiver of all Todesca’s rights to challenge the Department’s final estimates. See Glynn v. Gloucester, 9 Mass. App. Ct. 454, 461 (1980) (contractor’s failure to follow the remedies set forth in the contract precludes all relief). Todesca’s statement that “it did not agree” with the Department’s final estimate was not a “written reason” to challenge the substance of a final estimate. Even if filing a 6 statement of disagreement were considered a “reason” in the most general sense, it was not a “valid … written reason” to challenge any adjustment the Department was by contract permitted to make on the final estimate. See J.F. White Contracting Co. v. Massachusetts Bay Transportation Authority, 40 Mass. App. Ct. 937, 938-39 (1996) (rescript) (contractor not permitted to merely assert that it relied on earlier estimates where government had authority under the contract to adjust final quantities). By the time the Department prepares the final estimate and sends it to the contractor, it is obvious that the last chance to notify the Department of matters in dispute has come. See G.L. c.30, s.39G (legislative time limits for final payments). Todesca raises four arguments why the appeal to this office should be allowed to proceed, although none mentions the applicability of Subsection 9.05. (1) Anticipated Department Non-Cooperation: Todesca states that it “reasonably expected” that the Department engineers would refuse to meet to discuss the final estimate. That contention does not relieve Todesca of its contractual obligations to provide the Department with the underlying reasons for refusing to accept a final estimate in the first instance. There is no evidence that the Department refused to meet with Todesca. (2) Superseding Notices: Todesca contends that each of the multiple notices it received effectively “restarted” the six month time within which it could respond. Since the last notice was received on January 2, 2001, Todesca claims it provided a written “reason” “within six months” by filing a statement of claim in this office on February 28, 2001. The fact that the Department sent duplicate notices does not excuse Todesca’s failure to file its reasons of disagreement. Todesca did not do so either after receipt of the initial notice or at any time until 2001. Then it stated its reasons for disagreement was “Final quantities agreed with Res. Engr.” That statement is not a valid reason to dispute the final estimate. See J.F. White Contracting Co. v. Massachusetts Bay Transportation Authority, 40 Mass. App. Ct. at 937. (3) Statute of Limitations: Todesca states that the Department contends the appeals should be dismissed because Todesca “failed to prosecute its claim in a reasonable amount of time.” It asserts that the Department, not Todesca, “had control of the time of the proceedings in this matter” and therefore can not “cite the passage of time as a reason for dismissal.” Under Subsection 9.05 Todesca, 7 not the Department, was obligated to set forth valid reasons for not accepting the final estimate. The Department did nothing to prevent Todesca from making the required statement. It was Todesca’s failures and not any action of the Department that rendered it impossible for the Department to learn the substance of Todesca’s dispute until 2004. 1 (4) Prejudice: Todesca claims that it is prejudiced by the unavailability of MHD personnel due to “the simple existence of delays in the adjudication of its appeal, attributable at least in part to MHD itself….” It is not the adjudication of Todesca’s appeal that is the source of delay here—it is the failure of Todesca to set forth any “valid … written reasons” within the time permitted. Todesca’s failure meant that witnesses that could have explained Department actions taken in 1995 or 1997 are unavailable due to retirement or death. It is the Department that is prejudiced, not Todesca. CONCLUSION I conclude that Todesca’s failure to do what the contract required in Subsection 9.05 requires dismissal of each of the above captioned appeals. Under the Contract Todesca’s failure to act requires it to accept the Department’s final estimate. Because Todesca did not avail itself of the remedy the contract provided to dispute a final estimate, it is now precluded from pursuing an appeal to this office. See Glynn v. Gloucester, 9 Mass. App. Ct. 454 (1980). Respectfully submitted, Stephen H. Clark Administrative Law Judge Dated: May 25, 2006 1 It is not necessary to decide whether the Department’s argument that the three year statute of limitations had run is correct. See Campanella & Cardi Construction Co. v. Commonwealth, 351 Mass. 184, 187 (1966) (cause of action for contractor to bring a petition to dispute a final estimate accrues not later than the dates of the disputed semi-final or final estimate). 8