Longfellow Bridge Project
2
Longfellow Bridge Project DB Entity
WSC Attendees:
Bill Shea, Project Executive
Peter Rapp, Project Manager
Rob Collari, Project Design Coordinator
Jamie Sparks, Superintendent
Patricia Palmiere, Project Manager
STV Attendees:
Mark Ennis, Design Project Manager
Tetra Tech Attendees:
Erik Maki, Senior Project Manager
Regina Villa Associates Attendees:
Nancy Farrell, Project Principal
Kate Barrett, Vice President for Public Involvement
Amanda Agueda, Public Participation Assistant
3
Design Considerations
 Restore Structural Integrity
– Arch Ribs
– Spandrel Columns
– Roadway Deck
– Substructure
– Seismic Restraints
4
Design Considerations
5
Design Considerations
6
Design Considerations
7
Design Considerations
 Restore Historic
Elements
– Towers
– Railings/Fascia
– Arches/Columns
8
Structure Design/Modeling
 Structure Analysis
9
Structure Design/Modeling
 Pedestrian Bridge
10
Structure Design/Modeling
 Pedestrian Bridge
11
Structure Design/Modeling
 Pedestrian Bridge
12
Design Considerations
 Protect and
Enhance
Environment
13
Improve Bike/Pedestrian/ADA Accessibility
14
WSC Approach to Construction
Construction Staging
ADA, Bicycle and Pedestrian Accessibility
Maintain Navigable Channel
Noise Baseline Monitoring and Mitigation Plan
Work Hours
15
WSC Schedule
Begin Bridge Reconstruction
July 2013
Substantial Completion
September 30, 2016
Complete Track Reconstruction
October 2015
16
WSC Proposed Weekend Diversions
25 Total
25
17
Longfellow Bridge Construction Video
18
WSC Proposed Sequencing
General Overview
 Construction of the bridge is in 4 construction phases, but it
takes 6 traffic stages to perform the 4 construction phases
19
WSC Traffic Detour Routes
Construction Activities – June 2013 to September 2016
20
WSC Advanced Signage Plan
Construction Activities – April 2013 to June 2013
21
WSC Charles River Navigation Plan
22
WSC Proposed Traffic Stage 1
Construction Activities – April 2013 to August 2014
23
WSC Proposed Traffic Stage 1
Construction Activities – April 2013 to August 2014
24
WSC Proposed Traffic Stage 2
Construction Activities – August 2014 to September 2014
25
WSC Proposed Traffic Stage 3
Construction Activities – October 2014 to March 2015
26
WSC Proposed Traffic Stage 4
Construction Activities – April 2015 to August 2015
27
WSC Proposed Traffic Stage 5
Construction Activities – September 2015 to October 2015
28
WSC Proposed Traffic Stage 6
Construction Activities – November 2015 to September 2016
29
Bridge Complete/Final Traffic Pattern
30
WSC Communications
Objectives
 Seek stakeholder input/support to finalize design
elements, as feasible
 Provide frequent and timely construction updates
• Meetings and briefings
• E-blast updates/advisories
• Website
• Social media
• Press advisories
• Dedicated hotline and email
• Business coordination
31
WSC Next Steps
• Meet again in early
summer for update and
75% design
• Dedicated hotline and
email announced prior to
start of major construction
32
WSC Contact
For more information, questions or comments
contact:
Stephanie Boundy, MassDOT Accelerated Bridge
Program Public Outreach Coordinator
stephanie.boundy@state.ma.us
857-368-8904
www.massdot.state.ma.us/charlesriverbridges/LongfellowBridge
33
34
Pinch Points
Construction Activities – April 2013 to June 2013
35