Public Meeting July 10, 2013 1 WSC Design Build Team Construction Team J.F. White Contracting Company Skanska USA Civil Northeast, Inc Consigli Construction Co. Design Team STV – Lead Designer Tetra Tech – Environmental Lead, Traffic Management Gill Engineering Associates – Structural Design Support McGinley-Kalsow & Associates – Project Architect Regina Villa Associates – Public Outreach Copley-Wolff Design – Landscape Architecture Lin Associates – Substructure Design Support TRC Environmental Corp – Hazmat/Demolition Fortress – Emergency Preparedness Bryant Associates – Survey/ ROW UTRS – Corrosion & Stray Current Control 2 Introduction of DB Entity Personnel Bill Shea Leo Ryan Peter Rapp Robert Collari Mike Keville Mark Ennis Erik Maki Kate Barrett 3 Project Executive Area Manager Project Manager Design Coordinator General Superintendent Design Manager Traffic Mgmt & Signal Design Public Outreach (J.F. White) (J.F. White) (J.F. White) (J.F. White) (J.F. White) (STV) (Tetra Tech) (Regina Villa) Meeting Agenda – July 10 • Construction Staging Overview • • • Overall Scope of Project Schedule MBTA Diversion Weekends • Status Updates • • Current Activities Public Involvement & Outreach • Traffic Management Plan – Stage 1 4 Longfellow Bridge Project 5 Project Purpose and Goals • Improve structural integrity and capacity • Meet modern codes (including ADA accessibility) • Improve multi-modal access and bridge to city street connections • Create safer configuration for all bridge users • Restore historic elements • Protect and enhance environment 6 Design Considerations Restore Structural Integrity – Arch Ribs – Spandrel Columns – Roadway Deck – Substructure – Seismic Restraints 7 Design Considerations 8 Design Considerations 9 Design Considerations Restore Historic Elements – Towers – Railings/Fascia – Arches/Columns 10 Structure Design/Modeling Structure Analysis 11 Structure Design/Modeling Pedestrian Bridge 12 Structure Design/Modeling Pedestrian Bridge 13 Design Considerations Protect and Enhance Environment 14 Improve Bike/Pedestrian/ADA Accessibility 15 WSC Proposed Staging General Overview Construction of the bridge is in 4 construction phases, but it takes 6 traffic stages to perform the 4 construction phases 16 WSC Proposed Traffic Stage 1 Construction Activities – July 2013 to August 2014 17 Stage 1 - Outbound Detour Route Primary Route Revised Graphic to be inserted 18 WSC Project Schedule Begin Bridge Reconstruction July 2013 Substantial Completion September 30, 2016 Complete Track Reconstruction October 2015 19 WSC Proposed Weekend Diversions 25 Total vs. 82 Allowed by massDOT 25 20 Proposed Weekend Diversions 2013, 5 Weekends 19OCT13 20OCT13 Red Line Diversion Weekends for 2013: August 10 – 11, 2013 August 24 – 25, 2013 October 19 – 20, 2013 October 26 – 27, 2013 November 2 – 3, 2013 21 Red Line Weekend Service Diversions Boston Bound Vehicle Detour (Approximately 5 – 10 weekends per year) Revised Graphic to be inserted 22 Red Line Weekend Service Diversions MBTA Bus Route 23 Status Updates Construction • Charles Circle • Curb Realignment / Signal Work – Work continues this week • Charles River Dam Road • Restriping – Saturday • Kendall Portal Crossover • Curb Realignment – Starts this week • Trees / Borings • • • Transplants – 5 remaining in Cambridge – Continues this week Tree Removal – Next week Borings – Continues this week into next week • Pan-Tilt-Zoom (PTZ) Cameras • 19 of 23 cameras connected from cabinet to head end 24 Charles Circle Curb Modifications 25 New Signal Mast Arm at Charles Circle 26 Land Blvd at Charles River Dam Road 27 Charles River Dam Road to Land Blvd 28 Kendall Portal Crossover 29 Public Involvement & Outreach Updates • Public Involvement & Outreach - RVA • Public Meeting July 10 • • Traffic Stage 1 advisory & public meeting reminder • • Sent Monday by e-blast with Graphic MBTA posted weekend diversion advisories • 30 7 to 9 PM at MIT, Building E 25, Room 111 (E25-111), 45 Carleton Street, Cambridge listing the August through November weekends • • email – longfellowbridge@state.ma.us website: www.mass.gov/massdot/longfellowbridge • Dedicated Hot Line – 617-519-9892 Public Involvement & Outreach Hotline Protocol Hotline Protocol – Day/Night Shift Cell Phone is Answered by Field Office If Busy Voicemail lets them know they will get a call back in 2 hours. Message/Complaint Intake Form is Completed Record Copy of Completed Form Filed by WSC and Transmitted to RVA Hotline Protocol – Off Shift Voice Mail is Set Up to Receive all Off-Shift Calls Field Office Returns all Off-Shift Calls Received at Beginning of Next Shift Message/Complaint Intake Form is Completed Record Copy of Completed Form Filed by WSC and Transmitted to RVA 31 Public Involvement & Outreach Updates Initial Public Meetings/Stakeholder Briefings • • • • • • • • • • • • 32 Boston Transportation Department – numerous coordination meetings Cambridge TP&T/Public Works – numerous coordination meetings A Better City – numerous coordination meetings Public Information Meeting for Kick Off (Shriners) – April 9 Beacon Hill Civic Association – April 18 Cambridge DPW Open House – April 23 Kendall Square Association – May 16 Mass General Hospital – May 20 MassDOT Stakeholder Traffic Meeting – June 6 West End Civic Association – June 13 East Cambridge Neighborhood Briefing – July 1 Public Meeting for Traffic Stage 1 (MIT) – July 10 WSC - Stage 1 Traffic Plan Tetra Tech Major Components: • Traffic Management Plan • Initial Traffic Monitoring Period • Adjacent Project Coordination • Ongoing Assessment & Mitigation • Contingency Management Plans & Incident Action Plan • Fortress Inc. 33 Traffic Management Plan Portable Changeable Message Signs (PCMS) and Static Traffic Signs 34 Traffic Management Plan MassDOT Overhead Variable Message Signs (VMS) 35 Traffic Management Plan Public Outreach- MassDOT Overhead VMS Signs 36 Traffic Management Plan Lower Basin Area PCMS Locations 37 Traffic Management Plan Typical Static Traffic Sign 38 Traffic Management Plan Pre-Detour Alterations 39 Traffic Management Plan Pan-Tilt-Zoom (PTZ) Cameras for Traffic Monitoring 40 Stage 1 - Outbound Detour Route Primary Route Revised Graphic to be inserted 41 Stage 1 - Inbound Detour Route MBTA Bus Weekends Revised Graphic to be inserted 42 Stage 1 – Charles Circle Traffic Signal Modification Plan 43 Stage 1 – Charles Circle Traffic Signal Phasing 44 Stage 1 – Crossover at Kendall Portal 45 Stage 1 - Main Street at Memorial Drive Ramp Circulation 46 Stage 1 - Broadway at Third Street Median Crossover 47 Bicycle and Pedestrian Wayfinding Memorial Drive Cambridge 48 Traffic Monitoring Period- Overview • Initial Two Week Period • Starts Saturday July 20 • Non-destructive Activities on Bridge • Intense Traffic Monitoring • Daily Coordination Meetings 49 Traffic Monitoring Program • Anticipated Diversion Routes • Hot Spots • BTD – Traffic Management Center • WSC Staffing Plan • Police Deployment Plan 50 Traffic Monitoring Program Anticipated Diversion Routes 51 Traffic Monitoring Program Hot Spots - Level of Service (am/pm) 52 Traffic Monitoring Program Initial Two Week Period • BTD – Traffic Management Center • TMC Staffing Plan (preliminary) • • • • • • TMC Hours of Operation • • Weekdays 6am-10pm; Saturday 9am-5pm All-hands Meeting • • • 53 State Police, BPD, CPD Fire/EMS Boston / Cambridge Traffic MassDOT / DCR / MBTA WSC / Tetra Tech Daily 10AM at TMC Issues/Challenges/Lessons Learned • Implementation/Correction - WSC Staff reduction/Increases Traffic Monitoring Program Initial Two Week Period • BTD – Traffic Management Center • Resource – Pan-Tilt-Zoom (PTZ) Cameras • • • • Real Time Traffic Changes from TMC • • • • 54 300 City-wide Cameras 23 new Cameras • Activated Prior to Stage 1 Detour Shared with HOC Police Deployment • Hot Spots BTD Signal Timing HOC – VMS messages Communications – Field Staff / Police Details Initial Two Week Period Police Deployment Plan 55 Initial Two Week Period Police Deployment – Traffic Detail Locations 56 Initial Two Week Period Field Staff Locations – Tetra Tech 57 CMP and Incident Action Plans Fortress, Inc. 58 Police Detail Deployment Plan Police Detail Location Plans 59 Coordination with Adjacent Projects Cambridge Website 60 61