Silver Line Gateway Extension of Silver Line Bus Rapid Transit (BRT) to Chelsea and East Boston Design Public Hearing Chelsea, MA April 1, 2014 Introduction / Design Process Design Team – Joe Pavao, PE, MassDOT Project Manager – John McCormack, MBTA Project Manager – Frank Astone, PE, AECOM Municipal and Agency Partners – – – – – 2 City of Chelsea EEA MBTA MassDOT Massport Project Phasing • Phase I – MassDOT – Busway and BRT stations at Mystic Mall, Box District, and Eastern Avenue; – Washington Avenue bridge replacement; – Shared-use path • Phase II – MBTA – – – – 3 Commuter rail station at Mystic Mall; Decommissioning of existing commuter rail station BRT station at Downtown Chelsea Evaluation of Busway traffic signal systems Project Goal • Enhance transit access, mobility, and economic development potential in Chelsea and East Boston • Replace a functionally obsolete bridge 4 Public Outreach Project Development Phase Alternatives Analysis Event/Meeting Location Agenda • • March 13, May Chelsea City Hall, • Public Meetings 01, June 19, and Council Chambers Sept 18, 2013 • • Stakeholder Briefings 5 Date(s) Various Various • • • Chelsea City Hall, • Council Chambers • Expanded Environmental Notification Form (EENF) EENF Public Meeting and Site Visit 25% Design Design Public Hearing April 1, 2014 • Chelsea City Hall, • Council Chambers • Single Environmental Impact Report (SEIR) SEIR Public Comment Period Following SEIR filing in Spring 2014 Written comments • submitted to MEPA December 9, 2013 Civic Engagement Plan Project Background/Alternatives Route and station location options and impacts Analysis results Recommended alternative Chelsea Collaborative Neighborhood associations Permits required Recommended alternative update Potential environmental impacts and benefits Project update Progress / details from 25% design Questions and answers Public comment period established by MEPA Planning Study Overview • About 5 miles long • Diverse mix of land uses • Many recent state investments • • • • • • 6 Silver Line Transitway Williams Tunnel Airport Station Coughlin Bypass Road Chelsea Street Bridge Grand Junction purchase T T Proposed Project Elements 7 Project Schedule Phase I • • • • July 2014 November 2014 Spring 2015 Dec 2016 Advertise for construction Anticipated notice to proceed Start construction Substantial Completion of Construction Phase II • • • • 2014 - 2015 Spring 2015 Fall 2015 Dec 2017 8 Design development Finalize bid documents & advertise Bidding & award construction contract Substantial Completion of Construction Performance – Seaport Access No Build Performance Measures 111 Bus Commuter Rail Silver Line Gateway Blue Line Busway Downtown Chelsea to World Trade Center, Boston Travel Time 39 min 36 min 37 min 15-19 min Transfers 3 1 2 0 Reliability Low High Medium High Airport Blue Line Station to World Trade Center, Boston Travel Time NA NA 20-26 min 7-11 min Transfers NA NA 1 0 Reliability NA NA High High Notes: No-Build travel times are based on MBTA Trip Planner tool. Range of travel times for Silver Line Gateway are for surface and underground WTC stations, respectively. 9 Busway Alternative - Ridership • CTPS Travel Demand Forecasting Results – Year 2035 • Results as compared to No-Build Alternative 10 Busway – Everett Avenue BRTPlatform Platform BRT BRT Platform BRT Platform 11 Busway – Spruce Street 12 Busway – Arlington Street/Sixth Street BRT Platform 13 Busway – Downtown Chelsea Station BRT Platform BRT Platform 14 Busway – Washington Avenue 15 Busway – Broadway 16 Busway – Box District Station BRT Platforms 17 Busway – Library and Marlboro Streets 18 Busway – Cottage & Bellingham Street 19 Busway – Eastern Avenue Station BRT Platform BRT Platform 20 BRT Station Example – Eastern Avenue 21 BRT Station Example – Box District 22 Busway / Shared Use Path – Typical Section Busway Adjacent to Active Railroad – Typical Section Washington Avenue Bridge • Rated as functionally obsolete • Silver Line Gateway has resulted in new design concept for the bridge replacement 25 Two Lane Busway Beneath Bridge 26 Washington Avenue Bridge - Stage 1 Stage 1 Total Duration 17 months including utility relocations (Bridge Closure 8 to 10 months) 27 Washington Avenue Bridge - Stage 2 Stage 2 Total Duration 7 months Stage 2 Total Duration 7 months 28 Washington Avenue Bridge – Key Issues • Heard Street wall/barrier needs to be crash tested. May require temporary road closure • Underpinning of 63 Washington Avenue due to close proximity of south abutment. Needed to accommodate 2way busway beneath. • Utility work involved. Temporary support of existing utilities on east side and vaults at Heard St. intersection. 29 Cross Section of Completed Bridge 30 Chelsea Commuter Rail Station • MassDOT/MBTA’s Commitment: - Modern station - Accessible to all users - Convenient connections with Silver Line Gateway • Accessibility Regulations and MBTA Design Standards • Significant physical constraints to meeting these regulations and standards at existing Chelsea Commuter Rail Station 31 Relocated Chelsea Commuter Rail Station 32 Shared-Use Path • Ongoing coordination with EOEEA, City of Chelsea and consultants to incorporate design of proposed shared use path • Proposed from Eastern Avenue Station to Chestnut Street • Approximately ¾ mile long • Separated from the busway in some sections via vegetated swales • Innovative design approaches to coordinate the path and the busway alignments and crossing points 33 Potential Environmental Impacts • Impacts have been reviewed consistent with the EENF Certificate, including: – – – – – – – – 34 Hazardous Materials Utilities Parking At-Grade crossings Air Quality Wetlands/Water Resources Stormwater Coastal Zone Key MEPA Dates • Expanded Environmental Notification Form – Filed with MEPA – November 15, 2013 – Secretary’s Certificate Issued – December 27, 2013 • Single Environmental Impact Report (SEIR) – Addresses items identified in the EENF Certificate – SEIR filed with MEPA on March 31, 2014 – Public comment period ends May 2, 2014 – Final design to address items in SEIR Certificate 35 Questions 36