Silver Line Gateway Design Public Hearing Chelsea, MA

advertisement
Silver Line Gateway
Extension of Silver Line Bus Rapid Transit (BRT)
to Chelsea and East Boston
Design Public Hearing
Chelsea, MA
April 1, 2014
Introduction / Design Process
Design Team
– Joe Pavao, PE, MassDOT Project Manager
– John McCormack, MBTA Project Manager
– Frank Astone, PE, AECOM
Municipal and Agency Partners
–
–
–
–
–
2
City of Chelsea
EEA
MBTA
MassDOT
Massport
Project Phasing
• Phase I – MassDOT
– Busway and BRT stations at Mystic Mall, Box District,
and Eastern Avenue;
– Washington Avenue bridge replacement;
– Shared-use path
• Phase II – MBTA
–
–
–
–
3
Commuter rail station at Mystic Mall;
Decommissioning of existing commuter rail station
BRT station at Downtown Chelsea
Evaluation of Busway traffic signal systems
Project Goal
• Enhance transit access, mobility, and
economic development potential in
Chelsea and East Boston
• Replace a functionally obsolete
bridge
4
Public Outreach
Project
Development
Phase
Alternatives
Analysis
Event/Meeting
Location
Agenda
•
•
March 13, May
Chelsea City Hall, •
Public Meetings 01, June 19, and
Council Chambers
Sept 18, 2013
•
•
Stakeholder
Briefings
5
Date(s)
Various
Various
•
•
•
Chelsea City Hall,
•
Council Chambers
•
Expanded
Environmental
Notification
Form (EENF)
EENF Public
Meeting and
Site Visit
25% Design
Design Public
Hearing
April 1, 2014
•
Chelsea City Hall,
•
Council Chambers
•
Single
Environmental
Impact Report
(SEIR)
SEIR Public
Comment
Period
Following SEIR
filing in Spring
2014
Written comments
•
submitted to
MEPA
December 9,
2013
Civic Engagement Plan
Project Background/Alternatives
Route and station location options and
impacts
Analysis results
Recommended alternative
Chelsea Collaborative
Neighborhood associations
Permits required
Recommended alternative update
Potential environmental impacts and
benefits
Project update
Progress / details from 25% design
Questions and answers
Public comment period established by
MEPA
Planning Study Overview
• About 5 miles long
• Diverse mix of land
uses
• Many recent state
investments
•
•
•
•
•
•
6
Silver Line Transitway
Williams Tunnel
Airport Station
Coughlin Bypass Road
Chelsea Street Bridge
Grand Junction purchase
T
T
Proposed Project Elements
7
Project Schedule
Phase I
•
•
•
•
July 2014
November 2014
Spring 2015
Dec 2016
Advertise for construction
Anticipated notice to proceed
Start construction
Substantial Completion of Construction
Phase II
•
•
•
•
2014 - 2015
Spring 2015
Fall 2015
Dec 2017
8
Design development
Finalize bid documents & advertise
Bidding & award construction contract
Substantial Completion of Construction
Performance – Seaport Access
No Build
Performance
Measures
111
Bus
Commuter
Rail
Silver Line
Gateway
Blue Line
Busway
Downtown Chelsea to World Trade Center, Boston
Travel Time
39 min
36 min
37 min
15-19 min
Transfers
3
1
2
0
Reliability
Low
High
Medium
High
Airport Blue Line Station to World Trade Center, Boston
Travel Time
NA
NA
20-26 min
7-11 min
Transfers
NA
NA
1
0
Reliability
NA
NA
High
High
Notes:
No-Build travel times are based on MBTA Trip Planner tool.
Range of travel times for Silver Line Gateway are for surface and underground WTC stations, respectively.
9
Busway Alternative - Ridership
• CTPS Travel Demand Forecasting Results –
Year 2035
• Results as compared to No-Build Alternative
10
Busway – Everett Avenue
BRTPlatform
Platform
BRT
BRT Platform
BRT Platform
11
Busway – Spruce Street
12
Busway – Arlington Street/Sixth Street
BRT Platform
13
Busway – Downtown Chelsea Station
BRT Platform
BRT Platform
14
Busway – Washington Avenue
15
Busway – Broadway
16
Busway – Box District Station
BRT Platforms
17
Busway – Library and Marlboro Streets
18
Busway – Cottage & Bellingham Street
19
Busway – Eastern Avenue Station
BRT Platform
BRT Platform
20
BRT Station Example – Eastern Avenue
21
BRT Station Example – Box District
22
Busway / Shared Use Path – Typical
Section
Busway Adjacent to Active Railroad –
Typical Section
Washington Avenue Bridge
• Rated as functionally obsolete
• Silver Line Gateway has resulted in new
design concept for the bridge replacement
25
Two Lane Busway Beneath Bridge
26
Washington Avenue Bridge - Stage 1
Stage 1 Total Duration
17 months including utility relocations
(Bridge Closure 8 to 10 months)
27
Washington Avenue Bridge - Stage 2
Stage 2
Total Duration
7 months
Stage 2 Total Duration
7 months
28
Washington Avenue Bridge – Key Issues
• Heard Street wall/barrier needs to be crash tested. May
require temporary road closure
• Underpinning of 63 Washington Avenue due to close
proximity of south abutment. Needed to accommodate 2way busway beneath.
• Utility work involved. Temporary support of existing
utilities on east side and vaults at Heard St. intersection.
29
Cross Section of Completed Bridge
30
Chelsea Commuter Rail Station
• MassDOT/MBTA’s Commitment:
- Modern station
- Accessible to all users
- Convenient connections with Silver Line Gateway
• Accessibility Regulations and MBTA Design
Standards
• Significant physical constraints to meeting
these regulations and standards at existing
Chelsea Commuter Rail Station
31
Relocated Chelsea Commuter Rail Station
32
Shared-Use Path
• Ongoing coordination with
EOEEA, City of Chelsea and
consultants to incorporate
design of proposed shared
use path
• Proposed from Eastern
Avenue Station to Chestnut
Street
• Approximately ¾ mile long
• Separated from the busway
in some sections via
vegetated swales
• Innovative design approaches to coordinate the path
and the busway alignments and crossing points
33
Potential Environmental Impacts
• Impacts have been reviewed consistent
with the EENF Certificate, including:
–
–
–
–
–
–
–
–
34
Hazardous Materials
Utilities
Parking
At-Grade crossings
Air Quality
Wetlands/Water Resources
Stormwater
Coastal Zone
Key MEPA Dates
• Expanded Environmental Notification Form
– Filed with MEPA – November 15, 2013
– Secretary’s Certificate Issued – December 27, 2013
• Single Environmental Impact Report (SEIR)
– Addresses items identified in the EENF Certificate
– SEIR filed with MEPA on March 31, 2014
– Public comment period ends May 2, 2014
– Final design to address items in SEIR Certificate
35
Questions
36
Download