Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2015-2018 PROJECT INFORMATION # .14 MPO Project Location ID CENTRAL MA 605588 MULTIPLE Description WORCESTER, WEST BOYLSTON - INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I-190 OVER ROUTE 12 & RAMP B CURRENT Source Total NHPP $1,521,624 REVISED Federal Non Federal $1,217,299 $304,325 Year 2015 Source NHPP Total Federal $3,501,980 $2,801,584 FINANCIAL CONSTRAINT NonFederal Year Amendment Description $700,396 2015 ADJUSTMENT:Move Project Date 02/11/15 ADJUSTMENT:Increase Cost Construction / Design Status = Pre 25% / Bridge Maintenance + Interstate Maintenance + Stormwater Total Project Cost = $19,053,780 / FY 16 bridge funding was moved to FY 15 and consolidated, total project cost has increased .15 CENTRAL MA 605588 MULTIPLE WORCESTER, WEST BOYLSTON - INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I-190 OVER ROUTE 12 & RAMP B NHPP $14,910,480 $13,419,432 $1,491,048 2015 NHPP $14,317,162 $12,885,446 $1,431,716 2015 ADJUSTMENT:Decrease Cost 02/11/15 2015 STP-TE $1,234,637 02/11/15 Construction / Design Status = Pre 25% / Bridge Maintenance + Interstate Maintenance + Stormwater Total Project Cost = $19,053,780 / Decreased IM cost by $593,318, but total project cost has increased .16 CENTRAL MA 605588 MULTIPLE WORCESTER, WEST BOYLSTON - INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I-190 OVER ROUTE 12 & RAMP B $987,710 $246,927 2015 ADJUSTMENT:Add Funding Source Construction / Design Status = Pre 25% / Bridge Maintenance + Interstate Maintenance + Stormwater Total Project Cost = $19,053,780 / Added $1,234,637 in Stormwater funding to this project .17 CENTRAL MA 605588 WORCESTER WORCESTER, WEST BOYLSTON - INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I-190 OVER ROUTE 12 & RAMP B NHPP $1,519,992 $1,215,994 $303,998 2016 ADJUSTMENT:Remove Project HSIP $7,252,087 $6,526,878 $725,209 2015 HSIP $4,941,604 $4,447,444 $494,160 2015 ADJUSTMENT:Decrease Cost 02/12/15 NHPP $8,365,728 $7,529,155 $836,573 2015 NHPP $11,643,083 $10,478,775 $1,164,308 2015 AMENDMENT:Increase Cost 02/11/15 02/11/15 Construction / Design Status = Pre 25% / Bridge Maintenance (FY15&16) + Interstate Maintenance Total Project Cost = $17,952,096 / This project was moved from "On System" to "Bridge Maintenance" / Project #607518 & #607519 being combined into project #605588 .18 STATEWIDE SHSP STATEWIDE- VARIOUS SAFETY STRATEGIES TO BE DETERMINED BASED ON 2013 SHSP AND UPDATES Decrease to accommodate 608152-D4 High Friction Surface Treatment 8.01 CENTRAL MA 607181 NORTHBOROUGH NORTHBOROUGH - MARLBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $12,055,380 / Increased IM amount by $3,277,355, total project cost has also increased Date: 2/19/2015 Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2015-2018 PROJECT INFORMATION # MPO 8.02 CENTRAL MA Project Location ID Description 607181 NORTHBOROUGH NORTHBOROUGH - MARLBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 CURRENT Source Total Federal REVISED Non Federal Year Source Total 2015 STP-TE $412,297 2015 HSIP Federal $329,838 FINANCIAL CONSTRAINT NonFederal $82,459 Year Amendment Description 2015 AMENDMENT:Add Funding Source Date 02/11/15 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $12,055,380 / Added $412,297 in Stormwater funding to this project 9.01 STATEWIDE 608152 DISTRICT 4- HIGH FRICTION SURFACE TREATMENT AND RELATED WORK $2,280,000 $2,052,000 $228,000 2015 AMENDMENT:Add Project Add to 2015 HSIP list as part of 2013 SHSP. Date: 2/19/2015 02/12/15 2015 Central Mass MPO Transportation Improvement Program Amendment/Adjustment Type▼ MassDOT Project ID ▼ MPO ▼ 05/14/2014 Draft Released 06/25/2014 Endorsed Municipality Name ▼ MassDOT Project Description▼ MassDOT District ▼ MILLBURY - SUTTON - MEDIAN BARRIER REPLACEMENT ON ROUTE 146, FROM ROUTE 122A TO BOSTON ROAD Non-Federal Funds Additional ▼ Information ▼ Funding Source ▼ Total Programmed Funds ▼ 3 HSIP $ 1,000,000 $ 900,000 $ 100,000 3 HSIP $ 1,000,000 $ 900,000 $ 100,000 HSIP Subtotal ► $ 2,000,000 $ 1,800,000 $ 200,000 ◄ 90% Federal + 10% Non-Federal CMAQ 1,300,000 $ 1,040,000 $ 260,000 Federal Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 606485 Central Mass Multiple 606347 Central Mass Sturbridge STURBRIDGE - RESURFACING AND RELATED WORK ON ROUTE 20, FROM ROUTE 49 TO I-84 Construction / Design Status = 25% / TEC Score = 2.3 / STP + HSIP+ SW HSIP Total Project Cost = $5,350,000 Construction / Design Status = Book Job / TEC Score = 3.3 / STP + HSIP Total Project Cost = $2,700,000 ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 607484 605964 Central Mass Central Mass Multiple Millbury DISTRICT 3 - INSTALLATION OF CCTV CAMERAS AND VMS ON I-290 BETWEEN I295 AND I-90 MILLBURY - BRIDGE REPLACEMENT, M-22020, ROUTE 146 (NB & SB) OVER WEST MAIN STREET AND IMPROVEMENTS ON ROUTE 146 @ ELM STREET, ELMWOOD STREET & WEST MAIN STREET (ROTARY) 3 3 $ Construction / Design Status = TBD / Total Project Cost = $1,300,000 $ 2,317,000 $ 1,853,600 $ Construction / Design Status = 25% / TEC Score = 6.90 / Total Project Cost w/NFA Funding = $13,647,354 / See also NFA Bridge Project under 463,400 Section 2B CMAQ Subtotal ► $ 3,617,000 $ 2,893,600 $ 723,400 ◄ 80% Federal + 20% Non-Federal CMAQ ►TAP - Transportation Alternatives Program TAP01 Central Mass Multiple CMRPC REGION - BIKE RACKS INTALLATION 3 TAP $ 100,000 $ 80,000 $ 20,000 Construction / TEC Score = 1.03 / Total Project Cost = $100,000 TAP02 Central Mass Worcester WORCESTER - INSTALLION OF INFORMATIONAL KIOSK AT UNION STATION 3 TAP $ 100,000 $ 80,000 $ 20,000 Construction / TEC Score = 1.23 / Design Status = Pre 25% / Total Project Cost = $100,000 606629 Central Mass Worcester 3 TAP $ 226,039 $ 180,831 $ 45,208 TAP Subtotal ► $ 426,039 $ 340,831 $ 85,208 ◄ 80% Federal + 20% Non-Federal WORCESTER - BLACKSTONE VISITOR CENTER Construction / TEC Score = 2.43 / Design Status = Pre 25% / Total Project Cost = $226,039 ►Non-CMAQ/HSIP/TAP (Other) 606485 Central Mass Multiple 605559 Central Mass Warren 606686 Central Mass Warren 606347 Central Mass Sturbridge MILLBURY - SUTTON - MEDIAN BARRIER REPLACEMENT ON ROUTE 146, FROM ROUTE 122A TO BOSTON ROAD 3 STP $ 3,100,000 $ 2,480,000 $ 620,000 2 STP $ 1,398,000 $ 1,118,400 $ 279,600 2 STP $ 1,530,000 $ 1,224,000 $ 306,000 3 STP $ 1,700,000 $ 1,360,000 $ 340,000 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 7,728,000 $ 6,182,400 $ Total Federal Aid Target Funds Programmed ► $ 13,771,039 $ WARREN - RESURFACING & INTERSECTION IMPROVEMENTS AT ROUTE 67 & ROUTE 19 (WARREN TOWN CENTER) WARREN - RESURFACING AND RELATED WORK ON ROUTE 67 @ WEST WARREN AND WARREN TOWN CENTERS STURBRIDGE - RESURFACING AND RELATED WORK ON ROUTE 20, FROM ROUTE 49 TO I-84 Construction / Design Status = 25% / TEC Score = 2.3 / STP + HSIP+ SW HSIP Total Project Cost = $5,350,000 Construction / Design Status = 75% / TEC Score = 4.57 / Total Project Cost = $1,398,000 Construction / Design Status = 25% / TEC Score = 1.7 / Total Project Cost = $1,530,000 Construction / Design Status = Book Job / TEC Score = 3.3 / STP + HSIP Total Project Cost = $2,700,000 1,545,600 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis 13,797,888 ◄Total Target $ 26,849 Target Funds Available Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 7,728,000 $ 9,147,480 ◄ Max. NonCMAQ/HSIP/TAP $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 2,000,000 $ 3,617,000 $ 426,039 $ 965,570 ◄ Min. HSIP 3,258,799 ◄ Min. CMAQ 426,039 ◄ Min. TAP $ $ $ Construction / Design Status = Pre 25% / Bridge Maintenance + Interstate Maintenance + Stormwater Total Project Cost = $19,053,780 / FY 16 bridge funding was moved to FY 15 and consolidated, total project cost has increased 26,849 Non-CMAQ/HSIP/TAP (Other) A (1,034,430) HSIP Minimum Met (358,201) CMAQ Minimum Met - TAP Minimum Met HSIP, CMAQ, TAP Overprogrammed $ (1,392,631) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program ADJUSTMENT:Move Project (FROM 605588 2016),ADJUSTMENT:Increase Cost Central Mass Multiple WORCESTER, WEST BOYLSTON INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I190 OVER ROUTE 12 & RAMP B 3 NHPP $ 3,501,980 $ 2,801,584 $ 700,396 Statewide Bridge Maintenance Program Subtotal ► $ 3,501,980 $ 2,801,584 $ 700,396 ◄ 80% Federal + 20% Non-Federal $ 4,168,395 $ 3,334,716 $ 833,679 On System Subtotal ► $ 4,168,395 $ 3,334,716 $ 833,679 ◄ 80% Federal + 20% Non-Federal STP-BR-OFF $ 4,806,620 $ 3,845,296 $ 961,324 Off-System Subtotal ► $ 4,806,620 $ 3,845,296 $ 961,324 ◄ 80% Federal + 20% Non-Federal ►On System 605972 Central Mass Southbridge SOUTHBRIDGE - BRIDGE PRESERVATION, S-21-002, SR 131 (MAIN STREET) OVER QUINEBAUG RIVER 3 NHPP Construction / Design Status = TBD / Total Project Cost = $4,168,395 ►Off-System 604675 Central Mass Holden HOLDEN - BRIDGE REHABILITATION, H-18020, RIVER STREET OVER QUINAPOXET STREET 3 Construction / Design Status = 25% / Total Project Cost = $4,806,620 ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid 604892 608018 Central Mass Central Mass Worcester Worcester WORCESTER - BIKE PATH CONSTRUCTION, FROM TAINTER STREET TO KILBY STREET AND ROAD RESURFACING OF GARDNER AND KILBY STREET. WORCESTER - BLACKSTONE VISITOR CENTER AND BIKEWAY EARLY ACTION SITE WORK HPP $ 2,918,510 $ 2,334,808 $ 583,702 Construction / HPP#918 - MA136 & HPP#4288 MA207 / Design Status = 75-100% / Total Project Cost = $2,918,510 HPP $ 1,500,000 $ 1,200,000 $ 300,000 Construction / HPP#2351 - MA158, HPP#4283 MA202, HPP#2218 - MA157, HPP#2509 MA165 / Design Status = Pre 25% / Total Project Cost = $1,500,000 Other Federal Aid Subtotal ► $ 4,418,510 $ 3,534,808 $ 883,702 ◄ Funding Split Varies by Funding Source 3 3 ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program 606485 Central Mass Multiple MILLBURY - SUTTON - MEDIAN BARRIER REPLACEMENT ON ROUTE 146, FROM ROUTE 122A TO BOSTON ROAD 3 HSIP $ Statewide HSIP Program Subtotal ► $ Construction / Design Status = 25% / TEC Score = 2.3 / STP + HSIP+ SW HSIP Total Project Cost = $5,350,000 1,250,000 $ 1,125,000 $ 125,000 1,250,000 $ 1,125,000 $ 125,000 ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed $ - $ - $ - Funding Split Varies by Funding Source Statewide Safe Routes to Schools Program Subtotal ► $ - $ - $ $ - $ - $ $ - ◄ Funding Split Varies by Funding Source ► Statewide CMAQ No Projects Programmed $ Statewide CMAQ ► $ ►Statewide Transportation Enhancements 606434 Central Mass Worcester WORCESTER - CENTRAL BUSINESS DISTRICT STREETSCAPE IMPROVEMENT STP-TE $ - - - 1,652,015 Design & Construction / Design Status = Pre 25% / STP-TE+HPP Total Project Cost = $7,277,015 3 Statewide Transportation Enhancements Subtotal► $ ◄ 80% Federal + 20% Non-Federal 1,652,015 1,321,612.0 $ 1,321,612 $ 330,403.0 330,403 ◄ 80% Federal + 20% Non-Federal ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program 605588 ADJUSTMENT:Decrease Cost Central Mass $ Statewide ITS Subtotal ► $ Multiple NHPP WORCESTER, WEST BOYLSTON INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I190 OVER ROUTE 12 & RAMP B AMENDMENT:Increase Cost 607181 Central Mass Northborough NORTHBOROUGH - MARLBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 $ - $ - 12,885,445.8 $ - 14,317,162 3 NHPP $ Construction / Design Status = Pre 25% / Bridge Maintenance + Interstate Maintenance + Stormwater Total Project Cost = $19,053,780 / Decreased IM cost by $593,318, but total project cost has increased 1,431,716.2 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $12,055,380 / Increased IM amount by $3,277,355, total project cost has also increased 11,643,083 3 10,478,774.7 Statewide Interstate Maintenance Program Subtotal► $ 25,960,245 $ 1,164,308.3 23,364,221 $ ◄ 80% Federal + 20% Non-Federal 2,596,025 ◄ 90% Federal + 10% Non-Federal ►Statewide NHS Preservation Program+ No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ - $ Statewide RR Grade Crossings Subtotal ► $ - $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal ►Statewide RR Grade Crossings No Projects Programmed ►Statewide Stormwater Retrofits AMENDMENT:Add Funding Source 607181 Central Mass Northborough NORTHBOROUGH - MARLBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 STP-TE $ - 412,297 3 - - 329,837.6 ADJUSTMENT:Add Funding Source 605588 Central Mass Multiple WORCESTER, WEST BOYLSTON INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I190 OVER ROUTE 12 & RAMP B STP-TE $ Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $12,055,380 / Added $412,297 in Stormwater funding to this project 82,459.4 1,234,637 Construction / Design Status = Pre 25% / Bridge Maintenance + Interstate Maintenance + Stormwater Total Project Cost = $19,053,780 / Added $1,234,637 in Stormwater funding to this project 3 987,709.6 Statewide Stormwater Retrofits Subtotal ► $ 1,646,934 $ 246,927.4 1,317,547 $ 329,387 ◄ 80% Federal + 20% Non-Federal ►Statewide ADA Implementation Plan No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal - ◄ Funding Split Varies by Funding Source ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - $ - $ $ - $ Other Statewide Items Subtotal ► $ ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed NFA $ - - $ - - $ - - - - $ - - Non-Federal Aid Subtotal► $ - $ - ◄100% Non-Federal ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 605964 2015 Central Mass MPO TIP Summary Central Mass MILLBURY - BRIDGE REPLACEMENT, M-22020, ROUTE 146 (NB & SB) OVER WEST MAIN STREET NFA $ 11,330,354 $ 11,330,354 Construction / Design Status = 25% / TEC Score = 6.90 / Total Project Cost w/CMAQ Funding = $13,647,354 Section 2B / Non-Federal Bridge Projects Subtotal► $ 11,330,354 $ 11,330,354 ◄100% Non-Federal 3 TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ TIP Section 2: ▼ 61,175,738 $ 51,861,615 9,314,123 $ Total of All Projects ▼ 11,330,354 $ $ 11,330,354 $ 72,506,092 ◄ Total Spending in Region 51,861,615 ◄ Total Federal Spending in Region 20,644,477 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2016Central Mass M PO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ 05/14/2014 Draft Released 06/25/2014 Endorsed MassDOT Municipality Name ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Federal Funds ▼ Non-Federal Funds Additional ▼ Information ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 604864 Central Mass Westborough WESTBOROUGH - INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 9 & LYMAN STREET 3 HSIP $ 2,473,120 $ 2,225,808 $ 247,312 Construction / TEC Score = 7.9 / Design Status = 25% / HSIP+CMAQ Total Project Cost = $6,529,120 606207 Central Mass Spencer SPENCER - REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET 3 HSIP $ 904,800 $ 814,320 $ 90,480 Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ + TAP Total Project Cost = $3,192,800 HSIP Subtotal ► $ 3,377,920 $ 3,040,128 $ 337,792 ◄ 90% Federal + 10% Non-Federal ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 603251 Central Mass Worcester 604864 Central Mass Westborough 606207 Central Mass Spencer WORCESTER - SIGNAL & INTERSECTION IMPROVEMENTS @ HOLDEN STREET, DRUMMOND AVENUE & SHORE DRIVE Construction / Design Stage = Pre 25% / CMAQ + Statewide CMAQ Total Project Cost = $2,642,434 / Additional funding is provided by the Statewide CMAQ Program 3 CMAQ $ 900,640 $ 720,512 $ 180,128 WESTBOROUGH - INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 9 & LYMAN STREET 3 CMAQ $ 4,056,000 $ 3,244,800 $ 811,200 Construction / TEC Score = 7.9 / Design Status = 25% / HSIP+CMAQ Total Project Cost = $6,529,120 SPENCER - REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET 3 CMAQ $ 1,872,000 $ 1,497,600 $ 374,400 Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ + TAP Total Project Cost = $3,192,800 CMAQ Subtotal ► $ 6,828,640 $ 5,462,912 $ 1,365,728 ◄ 80% Federal + 20% Non-Federal ►TAP - Transportation Alternatives Program 606207 Central Mass Spencer TAP03 Central Mass Worcester SPENCER - REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET WORCESTER - WRTA STORMWATER MITIGATION 3 TAP $ 416,000 $ 332,800 $ 83,200 3 TAP $ 156,000 $ 124,800 $ 31,200 PROJECT TO BE DETERMINED $ TAP Subtotal ► $ - $ - Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ + TAP Total Project Cost = $3,192,800 Construction / TEC Score = .70 / Design Status = TBD / Total Project Cost = $156,000 - $ 572,000 $ 457,600 $ 114,400 ◄ 80% Federal + 20% Non-Federal ►Non-CMAQ/HSIP/TAP (Other) 603486 Central Mass Brookfield 604739 Central Mass West Brookfield BROOKFIELD - RECONSTRUCTION OF ROUTE 148 (FISKDALE ROAD) FROM MOLASSES HILL ROAD TO STURBRIDGE T.L. INCL. WEBBER ROAD WEST BROOKFIELD - RECONSTRUCTION ON ROUTE 9, ROUTE 67 & INTERSECTIONS AT SCHOOL STREET 3 STP $ 2,548,000 $ 2,038,400 $ 509,600 2 STP $ 1,664,000 $ 1,331,200 $ 332,800 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 4,212,000 $ 3,369,600 $ 842,400 Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 14,990,560 4,212,000 $ $ 15,170,796 10,858,343 Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 3,377,920 6,828,640 572,000 $ $ $ 869,013 2,715,666 727,774 Construction / Design Status = Pre 25% / TEC Score = 2.8 / Total Project Cost = $2,548,000 Construction / Design Status = 25% / TEC Score = 6.5 / Total Project Cost = $1,664,000 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis HSIP, CMAQ, TAP Overprogrammed $ (6,466,107) ►Section 1B / Federal Aid Bridge Projects ◄Total Target ◄ Max. NonCMAQ/HSIP/TAP $ $ ◄ Min. HSIP ◄ Min. CMAQ ◄ Min. TAP $ $ $ 180,236 Target Funds Available 180,236 Non-CMAQ/HSIP/TAP (Other) A (2,508,907) HSIP Minimum Met (4,112,974) CMAQ Minimum Met 155,774 TAP Minimum Not Met ►Statewide Bridge Maintenance Program ADJUSTMENT:Remove Project 605588 Central Mass Multiple $ 1,519,992 $ 1,215,994 $ 303,998 Construction / Design Status = Pre 25% / Bridge Maintenance (FY15&16) + Interstate Maintenance Total Project Cost = $17,952,096 / FY 2016 bridge funding will be moved to FY 2015 and consolidated with the current FY 2015 bridge funding with a new combined total of $3,501,980 Statewide Bridge Maintenance Program Subtotal ► $ 1,519,992 $ 1,215,994 $ 303,998 ◄ 80% Federal + 20% Non-Federal WORCESTER, WEST BOYLSTON INTERSTATE MAINTENANCE & RELATED WORK ON I-190, INCLUDING W-44-124, I-190 OVER ROUTE 12 & RAMP B 3 NHPP ►On System No Projects Programmed $ On System Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ►Off-System 607113 Central Mass Dudley DUDLEY - BRIDGE REPLACEMENT, D-12-009, CARPENTER ROAD OVER ABANDONED RR 3 STP-BR-OFF $ 2,305,800 $ 1,844,640 $ 461,160 Construction / Design Status = TBD / Total Project Cost = $2,305,800 606303 Central Mass Rutland RUTLAND - BRIDGE SUPERSTRUCTURE REPLACEMENT, R-14-004, INTERVALE ROAD OVER EAST BRANCH OF WARE RIVER 3 STP-BR-OFF $ 1,814,400 $ 1,451,520 $ 362,880 Construction / Design Status = TBD / Total Project Cost = $1,814,400 604468 Central Mass West Brookfield WEST BROOKFIELD - BRIDGE REPLACEMENT, W-19-008, WICKABOAG VALLEY ROAD OVER SUCKER BROOK 2 STP-BR-OFF $ 2,376,648 $ 1,901,318 $ 475,330 Construction / Design Status = Pre 25% / Total Project Cost = $2,376,648 Off-System Subtotal ► $ 6,496,848 $ 5,197,478 $ 1,299,370 ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid 604893 604893 605820 605820 606888 Central Mass Central Mass Central Mass Central Mass Central Mass Worcester Worcester Worcester Worcester Worcester WORCESTER - STREETSCAPE IMPROVEMENTS AT MAIN STREET & MAYWOOD STREET 3 WORCESTER - STREETSCAPE IMPROVEMENTS AT MAIN STREET & MAYWOOD STREET 3 WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W-44-041, MCGRATH BOULEVARD OVER MADISON STREET WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W-44-041, MCGRATH BOULEVARD OVER MADISON STREET WORCESTER - BLACKSTONE CANAL STREETSCAPE IMPROVEMENTS ON HARDING STREET 606434 Central Mass Worcester WORCESTER - CENTRAL BUSINESS DISTRICT STREETSCAPE IMPROVEMENTS 605674 Central Mass Sturbridge STURBRIDGE - GRAND TRUNK TRAIL 606629 Central Mass Worcester WORCESTER - BLACKSTONE VISITOR CENTER TI $ 2,285,798 $ 1,828,638 $ 457,160 Construction / TI#177 - MA213 / Design Status = Pre 25% / Total Project Cost = $2,297,798 TI $ 120,000 $ 96,000 $ 24,000 Design / TI#177 - MA213 / Design Status = 25%PSE / Total Project Cost = $2,297,798 HPP $ 4,411,942 $ 3,529,554 $ 882,388 Construction / HPP#4283 - MA202, HPP#2218 MA157, HPP#2509 - MA165 & MA006 / Design Status = 25% / Total Project Cost = $4,508,442 HPP $ 96,500 $ 77,200 $ 19,300 Design (25%-PSE) / HPP#2509 - MA165 / Design Status = 25% / Total Project Cost = $4,508,442 Sec 129 $ 735,000 $ 588,000 $ 147,000 Construction / MA238 / Design Status = 25% / Total Project Cost = $735,000 HPP $ 5,625,000 $ 4,500,000 $ 1,125,000 Construction / HPP#4266 - MA185 / Design Status = 25% / Total Project Cost = $7,277,015 HPP $ 507,500 $ 406,000 $ 101,500 HPP $ 6,449,200 $ 5,159,360 $ 1,289,840 3 3 3 3 3 3 Construction / HPP#2439 - MA162 / Design Status = 25% / Total Project Cost = $507,500 Construction / HPP#2351 - MA158 / Design Status = Pre 25% / Total Project Cost = $7 569 200 606629 Central Mass Worcester WORCESTER - BLACKSTONE VISITOR CENTER, BIKEWAY & BRIDGE HPP $ 1,120,000 $ 896,000 $ 224,000 Other Federal Aid Subtotal ► $ 21,350,940 $ 17,080,752 $ 4,270,188 - $ $ - $ $ - $ $ - $ $ - $ $ - $ $ - 3 Construction / HPP#4283 - MA202, HPP#2218 MA157, HPP#2509 - MA165 & MA006 / Design Status = Pre 25% / Total Project Cost = $7,569,200 ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ - Statewide Infrastructure Program Subtotal ► $ ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program No Projects Programmed $ - Statewide HSIP Program Subtotal ► $ - ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ - - - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source ► Statewide CMAQ 603251 Central Mass Worcester WORCESTER - SIGNAL & INTERSECTION IMPROVEMENTS @ HOLDEN STREET, DRUMMOND AVENUE & SHORE DRIVE 3 CMAQ $ Statewide CMAQ ► $ 1,741,794 $ 1,393,435 $ 348,359 Construction / Design Stage = Pre 25% / CMAQ + Statewide CMAQ Total Project Cost = $2,642,434 / 1,741,794 $ 1,393,435 $ 348,359 ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements No Projects Programmed $ Statewide Transportation Enhancements Subtotal ► $ - $ Statewide ITS Subtotal ► $ - $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program 605592 ►Statewide NHS Preservation Program+ 607176 607473 Central Mass Central Mass Central Mass Sturbridge Multiple Multiple STURBRIDGE - HOLLAND - INTERSTATE NHPP $ 3 MAINTENANCE & RELATED WORK ON I-84 Statewide Interstate Maintenance Program Subtotal ► $ 11,486,592 SHREWSBURY - WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 WEST BROOKFIELD - BROOKFIELD RESURFACING & RELATED WORK ON ROUTE 9, FROM SOUTH MAIN STREET WEST BROOKFIELD TO OLD WEST MAIN STREET BROOKFIELD (3.3 MILES) 11,486,592 NHPP $ 11,859,906 NHPP $ 3,504,883 - - $ 10,337,933 10,337,932.8 - $ 1,148,659 1,148,659.2 Construction / Design Status = TBD / Total Project Cost = $11,859,906 3 2/3 9,487,924.8 2,371,981.2 2,803,906.4 Statewide NHS Preservation Program Subtotal ► $ 15,364,789 Construction / Design Status = Pre 25% / Total Project Cost = $11,486,592 ◄ 90% Federal + 10% Non-Federal $ Construction / Design Status = TBD / Total Project Cost = $3,504,883 700,976.6 12,291,831 $ 3,072,958 ◄ 80% Federal + 20% Non-Federal ►Statewide RR Grade Crossings No Projects Programmed $ Statewide RR Grade Crossings Subtotal ► $ - $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal - ◄ 80% Federal + 20% Non-Federal ►Statewide Stormwater Retrofits No Projects Programmed - ►Statewide ADA Implementation Plan No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - ►Other Statewide Items ABP GANS Repayment $ $ - $ - - - - - - - Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ - $ - $ $ - $ Other Statewide Items Subtotal ► $ ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed $ - $ - - - - - ◄ Funding Split Varies by Funding Source - NFA $ Non-Federal Aid Subtotal► $ - $ $ - ◄100% Non-Federal NFA $ Section 2B / Non-Federal Bridge Projects Subtotal ► $ - $ $ - ◄100% Non-Federal ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects No Projects Programmed 2016 Central Mass MPO TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ 72,951,515 59,847,663 13,103,852 Total of All Projects ▼ TIP Section 2: ▼ $ - $ - $ $ $ 72,951,515 59,847,663 13,103,852 ◄ Total Spending in Region ◄ Total Federal Spending in Region ◄ Total Non-Federal Spending in Region Project costs have increased by 4% a year to account for inflation. 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2015 Statewide Categories Transportation Improvement Program Amendment/ MassDO T Adjustment Type ▼ Project MPO ▼ MassDOT Project Description▼ xx/xx/xxxx Draft Released xx/xx/xxxx Endorsed MassD OT Funding Source Total Programmed District ▼ Funds ▼ Additional Non-Federal Funds ▼ ▼ Federal Funds ▼ Information ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - $ - $ - $ - No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - ►On System ►Off-System ► Statewide Bridge Inspection Program ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid No Projects Programmed ►Section 1D / Federal Aid Major & State Category Projects ► Regional Major Infrastructure Program ► Statewide Infrastructure Program ► Statewide HSIP Program ADJUSTME NT:Decrease Cost AMENDME NT:Add Project SHSP Statewide 608152 Statewide STATEWIDE- VARIOUS SAFETY Statewid HSIP STRATEGIES TO BE e DETERMINED BASED ON 2013 SHSP AND UPDATES Statewid HSIP DISTRICT 4- HIGH FRICTION SURFACE TREATMENT AND e RELATED WORK $4,941,604 $4,447,444 $494,160 Decrease to accommodate 608152‐D4 High Friction Surface Treatment $2,280,000 $2,052,000 $228,000 Add to 2015 HSIP list as part of 2013 SHSP. ► Statewide Safe Routes to Schools Program No Projects Programmed ► Statewide CMAQ $ - $ - $ - ►Statewide Transportation Enhancements No Projects Programmed No Projects Programmed $ $ - $ - ►Statewide NHS Preservation Program+ No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ - - ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program No Projects Programmed $ - - $ - $ - $ - - ►Statewide RR Grade Crossings No Projects Programmed - ►Statewide Stormwater Retrofits No Projects Programmed ►Statewide ADA Implementation Plan No Projects Programmed $ - ►Other Statewide Items No Projects Programmed ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed NFA $ - $ - NFA $ - $ - ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects No Projects Programmed ◄ 80% Federal + 20% Non-Federal