Massachusetts Division April18,2016 U.S.Department of Transportation Federal Highway Administration 55 Broadway, 10hthFloor Cambridge, MA 02142 (617) 494-3657 (phone) (617) 494-3355 (fax) www.fhwa.dot.gov/madiv In Reply Refer To: HDA-MA David J. Mohler Executive Director Office of Transportation Planning Massachusetts Department of Transportation 10 Park Plaza, Room 4150 Boston, MA 02116-3969 Subject: Statewide Transportation Improvement Program Amendment Dear Mr. Mohler: Thank you for your letter received on March 16, 2016, and the revised fiscal constraint table submitted on April1, 2016. The Federal Highway Administration has reviewed the Fiscal Years 2016-2019 S t a t e w i d e Transportation Improvement Program (STIP) adjustments and amendments received from the Massachusetts Department of Transportation. Action 0.40-0.53 6.01-6.08 7.01-7.05 8.01-8.04 Organization Adjustments Central Massachusetts Amendments Montachusett Amendments Northern Middlesex Amendments In accordance with §93.104(c)(2), a Transportation Improvement Program (TIP) amendment requires a new conformity determination for the entire TIP before the amendment is approved by the MPO or accepted by DOT, unless the amendment merely adds or deletes exempt projects as defined in §93.126 or §93.127. Because these amendments affect exempt projects only, we are making the following determinations: • The projects in the STIP are based on a planning process that substantially meets the requirements of Title 23, U.S.C., the Federal Transit Act and Subparts A, B, and C of 23 CFR 450. The TIPs are based on a continuing, comprehensive transportation planning process carried out cooperatively b y the State, the MPOs, and the transit operators. The FY 2016-2019 ST IP highway actions identified above are hereby approved dated April8, 2016. Should you have any additional questions or concerns, please contact me at (617) 4943275 or Brandon Wilcox at (617) 494-3113. cc: Kristin Wood, FTA Region I Ariel Garcia, EPA Region I Sincerely, Michael Hong Planning & Environment Manager March 8, 2016 Pamela Stephenson Division Administrator Federal Highway Administration 55 Broadway – 10th floor Cambridge, Massachusetts 02142 Dear Ms. Stephenson: On behalf of Secretary Stephanie Pollack, I am writing to request your approval of the attached regional highway actions as endorsed by the Central Massachusetts Metropolitan Planning Organization, Montachusett Metropolitan Planning Organization, and Northern Middlesex Metropolitan Planning Organization pertaining to the Federal Fiscal Years 2016-2019 State Transportation Improvement Program: 0.40-0.53 6.01-6.08 7.01-7.05 8.01-8.04 Adjustments Central Mass Amendments Montachusett Amendments Northern Middlesex Amendments March 8, 2016 February 17, 2016 February 17, 2016 March 8, 2016 These actions do not require an air quality conformity determination. If you have any questions, please call me at (857) 368-8865. Sincerely, Executive Director Office of Transportation Planning cc: Steve Woelfel, Director of Strategic Planning Trey Wadsworth, Manager of MPO Activities Bryan K. Pounds, MPO Activities William Betts, FAPRO Federal Transit Administration Ten Park Plaza,Suite 4150, Boston, MA 02 116 Tel: 857-368-4636,TIY: 857-368-0655 www.mass.gov/massdot Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2016-2019 PROJECT INFORMATION # MPO Project Location ID .40 CAPECOD 607918 BOURNE Description SANDWICH TO ORLEANS- GUIDE & TRAFFIC SIGN REPLACEMENT ON A SECTION OF US ROUTE 6 (MID-CAPE HIGHWAY) CURRENT Source Total HSIP REVISED Year Source Total Federal FINANCIAL CONSTRAINT NonFederal Year Amendment Description Federal Non Federal $4,100,000 $3,690,000 $410,000 2016 NHPP $15,133,500 $13,620,150 $1,513,350 2016 NHPP $15,133,500 $13,620,150 $1,513,350 2016 ADJUSTMENT::Change Addl Info 02/17/16 STP-TE $900,000 $720,000 $180,000 2016 STP-TE $1,500,000 $1,200,000 02/17/16 ADJUSTMENT:Remove Funding Src Date 02/16/16 Total programmed = $4,100,000 .41 CENTRAL MA605592 STURBRIDGE STURBRIDGE-HOLLAND - INTERSTATE MAINTENANCE & RELATED WORK ON I-84 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $16,633,500 / Increase stormwater cost by $600,000 .42 CENTRAL MA605592 STURBRIDGE STURBRIDGE-HOLLAND - INTERSTATE MAINTENANCE & RELATED WORK ON I-84 $300,000 2016 ADJUSTMENT:Increase Cost ADJUSTMENT::Change Addl Info Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $16,633,500 / Increase stormwater cost by $600,000 .43 CENTRAL MA607176 MULTIPLE SHREWSBURY-WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 HSIP $350,000 $315,000 $35,000 2016 HSIP NHPP $12,949,320 $10,359,456 $2,589,864 2016 NHPP STP-TE $500,000 $400,000 $100,000 2016 STP-TE $350,000 $315,000 $35,000 2016 ADJUSTMENT::Change Addl Info 02/17/16 $12,949,320 $10,359,456 $2,589,864 2016 ADJUSTMENT::Change Addl Info 02/17/16 Construction / Design Status = TBD / NHS + HSIP + Stormwater Total Project Cost = $13,899,320 / Increased stormwater cost by $100K from $500K to $600K .44 CENTRAL MA607176 MULTIPLE SHREWSBURY-WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 Construction / Design Status = TBD / NHS + HSIP + Stormwater Total Project Cost = $13,899,320 / Increased stormwater cost by $100K from $500K to $600K .45 CENTRAL MA607176 MULTIPLE SHREWSBURY-WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 $600,000 $480,000 $120,000 2016 ADJUSTMENT:Increase Cost 02/17/16 ADJUSTMENT::Change Addl Info Construction / Design Status = TBD / NHS + HSIP + Stormwater Total Project Cost = $13,899,320 / Increased stormwater cost by $100K from $500K to $600K .46 CENTRAL MA607479 MULTIPLE SHREWSBURY-BOYLSTON-NORTHBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 NHPP $13,168,800 $11,851,920 $1,316,880 2016 NHPP $13,168,800 $11,851,920 $1,316,880 2016 ADJUSTMENT::Change Addl Info 02/17/16 STP-TE $800,000 $640,000 $160,000 2016 STP-TE $2,000,000 $1,600,000 02/17/16 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $15,168,800 / Increase stormwater cost by $1,200,000 .47 CENTRAL MA607479 MULTIPLE SHREWSBURY-BOYLSTON-NORTHBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 $400,000 2016 ADJUSTMENT:Increase Cost ADJUSTMENT::Change Addl Info Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $15,168,800 / Increase stormwater cost by $1,200,000 Date: 3/7/2016 Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2016-2019 PROJECT INFORMATION # .48 MPO Project Location ID CENTRAL MA608060 MULTIPLE CURRENT Federal REVISED Description Source Total Non Federal GARDNER-SHREWSBURY - STORMWATER IMPROVEMENTS ALONG ROUTE 68/ROUTE 70 STP-TE $415,000 $332,000 $83,000 HSIPR $1,750,000 $1,575,000 HPP $5,939,173 HPP NHPP Year Federal FINANCIAL CONSTRAINT Total 2016 STP-TE $561,800 $175,000 2016 HSIPR $4,751,338 $1,187,835 2017 HPP $5,798,073 $4,638,458 $1,159,615 2017 ADJUSTMENT:Decrease Cost 02/17/16 $5,625,000 $4,500,000 $1,125,000 2017 HPP $5,625,000 $4,500,000 $1,125,000 2017 ADJUSTMENT::Change Addl Info 02/17/16 $7,620,912 $6,858,821 $762,091 2017 NHPP $7,327,800 $6,595,020 $732,780 2017 ADJUSTMENT:Decrease Cost 02/17/16 $4,347,840 $3,478,272 $869,568 2019 STP-BR-OFF $4,347,840 $3,478,272 $869,568 2019 ADJUSTMENT:Change Project ID 02/17/16 $2,305,800 $1,844,640 $461,160 2016 STP-BR-OFF $100,000 2016 AMENDMENT:Decrease Cost 02/17/16 $449,440 NonFederal Year Amendment Description Source Date $112,360 2016 ADJUSTMENT:Increase Cost 02/17/16 $175,000 2016 ADJUSTMENT:Change Project Desc 02/17/16 Construction / Design Status = TBD / Total Project Cost = $561,800 / Increase cost by $146,800 .49 CENTRAL MA608168 DOUGLAS DOUGLAS - RESURFACING & RELATED WORK ON WEBSTER STREET (ROUTE 16), FROM T.L. (MM 2.8) TO MAIN STREET (MM 6.9) $1,750,000 $1,575,000 Construction / Design Status = TBD / Total Project Cost = $1,750,000 / Required under MAP-21 HRRRP rule .50 CENTRAL MA605820 WORCESTER WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W44-041, MCGRATH BOULEVARD OVER MADISON STREET Construction / HPP#4283 - MA202, HPP#2218 - MA157, HPP#2509 - MA165 & MA006 / Design Status = 25% / Total Project Cost = $6,058,072 / Decrease cost of construction portion of project by $141,100 and will add same amount to design .51 CENTRAL MA606434 WORCESTER WORCESTER - CENTRAL BUSINESS DISTRICT STREETSCAPE IMPROVEMENTS Construction / HPP#4266 - MA185 / Design Status = 25% / HPP + TE Total Project Cost = $6,977,015 / Added additional TE funding to this project .52 CENTRAL MA607562 MULTIPLE WEBSTER-OXFORD - INTERSTATE MAINTENANCE & RELATED WORK ON I-395 Construction / Design Status = TBD / Total Project Cost = $7,327,800 / Decrease cost by $293,112 .53 MONTACHU 608260 ATHOL SETT ATHOL - BRIDGE REPLACEMENT, A-15-5, STP-BRWASHINGTON AVE OVER SOUTH ATHOL POND OFF OUTLET Change Project ID from BR1903 to 608260; Cost Est as of 5/28/15; Total Cost = $4,347,840 Adjusted for YOE by 12%; Bridge Off System; Construction; 6.01 CENTRAL MA607113 DUDLEY DUDLEY - BRIDGE DEMOLITION, D-12-009, CARPENTER ROAD OVER QUINNEBAUG RAIL TRAIL Construction / Design Status = TBD / Total Project Cost = $500,000 / Reduced cost by $1,805,800 and changed description to Bridge Demolition STP-BROFF $500,000 $400,000 AMENDMENT:Change Project Desc AMENDMENT:Change Addl Info Date: 3/7/2016 Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2016-2019 PROJECT INFORMATION # MPO Project Location ID 6.02 CENTRAL MA605820 WORCESTER Description WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W44-041, MCGRATH BOULEVARD OVER MADISON STREET CURRENT Source Total HPP $118,900 Federal $95,120 REVISED Non Federal $23,780 Year 2017 Source HPP Total $260,000 Federal $208,000 FINANCIAL CONSTRAINT NonFederal $52,000 Year Amendment Description 2016 AMENDMENT:Move Project Date 02/17/16 AMENDMENT:Increase Cost Design / HPP#2509 - MA165 / Design Status = 25% / Total Project Cost = $6,058,072 / Add $141,100 to the design cost which came from the construction cost and move to FY 2016 6.03 CENTRAL MA608170 STURBRIDGE STURBRIDGE - SIGN AND PAVEMENT MARKING INSTALLATION AND UPGRADES, LIMITED ROADWAT IMPROVEMENTS AND RELATED WORK ON BROOKFIELD ROAD (ROUTE 148), FROM MAIN STREET (MM 0.0) TO TOWN LINE (MM 3.4) HSIPR $1,750,000 $1,575,000 $175,000 2016 HSIPR $1,000,000 $900,000 $100,000 2016 AMENDMENT:Decrease Cost 02/17/16 AMENDMENT:Change Project Desc Construction / Design Status = TBD / Total Project Cost = $1,000,000 / Required under MAP-21 HRRRP rule / Reduce cost of project by $750K 6.04 CENTRAL MA608169 DUDLEY DUDLEY - SIGN AND PAVEMENT MARKING INSTALLATION AND UPGRADES AND RELATED WORK ON DRESSER HILL ROAD (ROUTE 31), FROM STATE LINE (MM 0.0) TO TOWN LINE (MM 4.1) HSIPR $1,750,000 $1,575,000 $175,000 2016 HSIPR $1,000,000 $900,000 $100,000 2016 AMENDMENT:Decrease Cost 02/17/16 AMENDMENT:Change Project Desc Construction / Design Status = TBD / Total Project Cost = $1,000,000 / Required under MAP-21 HRRRP rule / Reduce cost of project by $750K 6.05 CENTRAL MA608133 MULTIPLE HOPEDALE-UXBRIDGE - STORMWATER IMPROVEMENTS ALONG ROUTE 140 AND ROUTE 146 STP-TE $401,300 $321,040 $80,260 2016 STP-TE $715,000 $572,000 $143,000 2016 AMENDMENT:Increase Cost 02/17/16 AMENDMENT:Change Project Desc Construction / Design Status = TBD / Total Project Cost = $715,000 / Increase cost of project by $313,700 and change project description from Grafton/Milford locations to Hopedale/Uxbridge Locations 6.06 CENTRAL MA606434 WORCESTER WORCESTER - CENTRAL BUSINESS DISTRICT STREETSCAPE IMPROVEMENTS 2017 STP-TE 2018 STP-TE $1,352,015 $1,081,612 $270,403 2017 AMENDMENT:Add Funding Source 02/17/16 $130,000 2018 AMENDMENT:Add Project 02/17/16 Construction / HPP#4266 - MA185 / Design Status = 25% / HPP + TE Total Project Cost = $6,977,015 / Added additional TE funding to this project 6.07 CENTRAL MA608394 STURBRIDGE STURBRIDGE - STORMWATER IMPROVEMENTS ALONG ROUTE 20 $650,000 $520,000 Construction / Design Status = TBD / Total Project Cost = $650,000 / Added this new project to the list Date: 3/7/2016 Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2016-2019 PROJECT INFORMATION # MPO Project Location ID 6.08 CENTRAL MA608237 MULTIPLE Description CURRENT Source Total Federal REVISED Non Federal WORCESTER - BOYLSTON - NORTHBOROUGH STRUCTURAL STEEL CLEANING AND PAINTING OF OVERHEAD BRIDGES ON I-290 Year 2019 Source NHPP Total Federal $1,450,848 $1,160,678 FINANCIAL CONSTRAINT NonFederal Year Amendment Description $290,170 2019 AMENDMENT:Add Project Date 02/17/16 Construction / Design Status = TBD / Total Project Cost = $1,450,843 / Added this new project to the list 7.01 MONTACHU 607960 ASHBURNHAM SETT ASHBURNHAM- ROUTE 101 AT WILLIAMS AND COREY HILL ROAD, INTERSECTION IMPROVEMENTS STP $624,000 $561,600 $62,400 2016 AMENDMENT:Remove Project 02/17/16 STP $624,000 $561,600 $62,400 2017 AMENDMENT:Remove Project 02/17/16 NHPP $17,612,774 $15,851,497 $1,761,277 2017 STP-TE $156,000 $124,800 $31,200 2017 AC Yr 1 of 2. Total Cost = $1,248,000 7.02 MONTACHU 607960 ASHBURNHAM SETT ASHBURNHAM- ROUTE 101 AT WILLIAMS AND COREY HILL ROAD, INTERSECTION IMPROVEMENTS AC Yr 2 of 2. Total Cost = $1,248,000 7.03 MONTACHU 606575 MULTIPLE SETT STERLING - LEOMINSTER - LANCASTER INTERSTATE MAINTENANCE & RELATED WORK ON I-190 NHPP $16,935,360 $15,241,824 $1,693,536 2017 AMENDMENT:Decrease Cost 02/17/16 Adjust Programmed Funds down from $17,768,774 and Remove Stormwater Component; Cost Est as of 12/29/15; Total Cost = $17,768,774; Cost = $17,612,774 IM + $156,000 Stormwater; Construction 7.04 MONTACHU 606575 MULTIPLE SETT STERLING - LEOMINSTER - LANCASTER INTERSTATE MAINTENANCE & RELATED WORK ON I-190 AMENDMENT:Remove Project 02/17/16 Cost Est as of 5/20/15; Total Cost = $17,768774; Cost = $17,612,774 IM + $156,000 Stormwater; Construction 7.05 MONTACHU 603513 GARDNER SETT GARDNER - SUPERSTRUCTURE REPLACEMENT, G-01-008, PLEASANT STREET OVER THE B&M RAILROAD 2018 NHPP $4,404,240 $3,523,392 $880,848 2018 AMENDMENT:Add Project 02/17/16 $58,311 2016 AMENDMENT:Add Project 03/08/16 2016 OTHER FA $16,737,188 $13,389,750 $3,347,438 2016 AMENDMENT:Add Project 03/08/16 2016 $1,100,000 03/08/16 Added Project to FFY 2018 2/17/2016; Prior Appendix Project. 8.01 N. FLAP01 LOWELL MIDDLESEX MERRIMACK RIVERWALK PHASE II FLAP PROJECT 2016 OTHER FA $293,311 $235,000 Reprogramming of FLAP award from FFY 2015 8.02 N. 608420 LOWELL MIDDLESEX LOWELL CANAL BRIDGES 8.03 N. 607752 LOWELL MIDDLESEX LOWELL-INTERSECTION & SIGNAL IMPROVEMENTS AT 2 LOCATIONS: SR 113 (VARNUM AVENUE & VFW HIGHWAY) AT MAMMOTH ROAD & VFW AT AIKEN STREET Tiger Grant award - non federal match includes $760,000 from Enel, $2,000,000 from Umass Lowell, and $587,438 from the City of Lowell. Design estimate: $1,162,500. Construction: $15,574,688 HSIP $990,000 $110,000 2016 AMENDMENT:Add Project Add Project Date: 3/7/2016 Massachusetts Department of Transportation - State Transportation Improvement Program Highway Actions Report 2016-2019 PROJECT INFORMATION # MPO Project Location ID 8.04 N. 607506 CHELMSFORD MIDDLESEX Description CHELMSFORD- BRIDGE DECK REPLACEMENT, C-08-037, ST 4 NORTH STREET OVER I-495 CURRENT Source Total Federal REVISED Non Federal Year 2017 Source NHPP Total Federal $2,400,000 $1,920,000 FINANCIAL CONSTRAINT NonFederal Year Amendment Description $480,000 2017 AMENDMENT:Add Project Add Project Date: 3/7/2016 Date 03/08/16 2016 Cape Cod MPO Transportation Improvement Program MassDOT Amendment/Adjustme Project ID nt Type ▼ ▼ Municipalit MassDOT MPO ▼ y Name ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ 06/15/2015 Draft Released 2/16/2016 Adjustment 07/20/2015 Endorsement Total Programmed Federal Non-Federal Additional Information ▼ Funds ▼ Funds ▼ Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 608033 Cape Cod Barnstable BARNSTABLE- LIGHTING & LANDSCAPING OF THE ROUNDABOUT AT THE MID-CAPE HIGHWAY (ROUTE 6) EASTBOUND EXIT RAMP & ROUTE 149 5 HSIP Total programmed = $600,000. Under desigm by MassDOT. $ 600,000 $ 540,000 $ 60,000 HSIP Subtotal ► $ 600,000 $ 540,000 $ 60,000 ◄ 90% Federal + 10% Non-Federa ►CMAQ - Congestion Mitigation and Air Quality Improvement Program Orleans ORLEANS- INTERSECTION IMPROVEMENTS AT 2 LOCATIONS: CRANBERRY HIGHWAY (ROUTE 6A) AND MAIN STREET; CHATHAM ROAD (ROUTE 28) AND MAIN STREET. 5 CMAQ $ 3,189,954 $ 2,551,963 $ Cape Cod Barnstable BARNSTABLE - HYANNIS VILLAGER DEMONSTATION 5 CMAQ $ 659,100 $ 527,280 $ Cape Cod Cape Cod CAPE COD BIKE RACK PROGRAM 5 CMAQ $ 50,000 $ 40,000 $ 606461 Cape Cod 201601 201602 CMAQ Subtotal ► $ 3,899,054 $ 3,119,243 $ Total programmed = $3,547,482 = $3,189,954 CMAQ + $357,528 TAP. 100% design 637,991 completed. CMAQ analysis completed. Project schedule adjusted due to right of way acquisition timing. Municipality is proponent. CMAQ -> FTA Transfer. Total programmed = $659,100. Year 1 of 3. Total programmed = $50,000. Funds to be 10,000 applied for by municipalities. Program specifics under development. 779,811 ◄ 80% Federal + 20% Non-Federa 131,820 ►TAP - Transportation Alternatives Program 606461 Cape Cod Orleans ►Non-CMAQ/HSIP/TAP (Other) ORLEANS- INTERSECTION IMPROVEMENTS AT 2 LOCATIONS: CRANBERRY HIGHWAY (ROUTE 6A) AND MAIN STREET; CHATHAM ROAD (ROUTE 28) AND MAIN STREET. 5 TAP $ 357,528 $ 286,022 $ TAP Subtotal ► $ 357,528 $ 286,022 $ 606596 Cape Cod Chatham CHATHAM- IMPROVEMENTS ON WEST MAIN STREET (ROUTE 28), FROM GEORGE RYDER ROAD TO BARN HILL ROAD 5 STP $ 2,735,090 $ 2,188,072 $ 607571 Cape Cod Dennis Yarmouth DENNIS- YARMOUTH- CONSTRUCTION OF A MULTIUSE PATH OVER THE BASS RIVER, INCLUDES NEW PEDESTRIAN BRIDGE D-07-007=Y-01-010 5 STP $ 307,026 $ 245,621 $ Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 3,042,116 $ 2,433,693 $ Total programmed = $3,547,482 = $3,189,954 CMAQ + $357,528 TAP. 100% design 71,506 completed. CMAQ analysis completed. Project schedule adjusted due to right of way acquisition timing. Municipality is proponent. 71,506 ◄ 80% Federal + 20% Non-Federa 547,018 61,405 Total programmed = $2,735,090. 25% design plans submitted. Total programmed = $2,403,106 =$2,096,080 from TI 173 MA 209 + $307,026 STP. Bass River Bridge portion of CCRT Dennis-Yarmouth extension. 608,423 ◄ 80% Federal + 20% Non-Federa ►Section 1A / Fiscal Constraint Analysis Total Federal Aid Target Funds Programmed ► Total Non-CMAQ/HSIP/TAP (Other) Programmed ► Total HSIP Programmed ► Total CMAQ Programmed ► Total TAP Programmed ► $ 7,898,698 $ 8,004,511 ◄Total $ 3,042,116 $ 5,755,612 ◄ Max. Non$ 600,000 $ 458,514 ◄ Min. HSIP $ 3,899,054 $ 1,432,857 ◄ Min. $ 357,528 $ 357,528 ◄ Min. TAP $ $ $ $ $ 105,813 105,813 (141,486) (2,466,197) - Target Funds Available Non-CMAQ/HSIP/TAP (Other) A HSIP Minimum Met CMAQ Minimum Met TAP Minimum Met HSIP, CMAQ, TAP Overprogrammed $ (2,607,683) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ Statewide Bridge Maintenance Program Subtotal► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federa $ On System Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federa $ - $ - $ - ►On System No Projects Programmed ►Off-System No Projects Programmed Off-System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federa $ Statewide Bridge Inspection Program Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federa $ 2,096,080 $ 2,096,080 $ - Total programmed = $2,403,106 =$2,096,080 from TI 173 MA 209 + $307,026 STP. Bass River Bridge portion of CCRT Dennis-Yarmouth extension. Other Federal Aid Subtotal ► $ 2,096,080 $ 2,096,080 $ - ◄ Funding Split Varies by Funding Source ► Statewide Bridge Inspection Program No Projects Programmed ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid 607571 Cape Cod Dennis Yarmouth DENNIS- YARMOUTH- CONSTRUCTION OF A MULTIUSE PATH OVER THE BASS RIVER, INCLUDES NEW PEDESTRIAN BRIDGE D-07-007=Y-01-010 5 TI 173 MA 209 ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed ► Statewide HSIP Program 607753 Cape Cod Barnstable Cape Cod Bourne Sandwich Barnstable Yarmouth Harwich Brewster Orleans ADJUSTMENT:Remove Funding Source 607918 $ Statewide Infrastructure Program Subtotal ► $ BARNSTABLE- INTERSECTION & SIGNAL IMPROVEMENTS AT SR 28 (FALMOUTH ROAD) AT STRAWBERRY HILL ROAD SANDWICH TO ORLEANS- GUIDE & TRAFFIC SIGN REPLACEMENT ON A SECTION OF US ROUTE 6 (MID-CAPE HIGHWAY) 5 5 HSIP HSIP $ - $ $ 550,000 $ - $ $ 495,000 $ $ 4,100,000 $ 3,690,000 $ Statewide HSIP Program Subtotal ► $ 550,000 $ 495,000 $ - 55,000 $ Statewide Safe Routes to Schools Program Subtotal ► $ - - $ $ - $ Statewide CMAQ ► $ - - $ $ $ Statewide Transportation Enhancements Subtotal► $ - $ Statewide ITS Subtotal ► $ Total programmed = $550,000. Preliminary design. RSA conducted. Adjust to remove project from CAPE COD TIP. Amend into Statewide Program as Statewide 410,000 Project with new Project Description and increased cost to accommodate I-195 components. 55,000 ◄ 90% Federal + 10% Non-Federa ► Statewide Safe Routes to Schools Program No Projects Programmed ◄ 80% Federal + 20% Non-Federa - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source $ $ - - $ $ - ◄ 80% Federal + 20% Non-Federa $ - $ - ◄ 80% Federal + 20% Non-Federa - $ - $ - ◄ 80% Federal + 20% Non-Federa $ Statewide Interstate Maintenance Program Subtotal► $ - $ - $ - ◄ 90% Federal + 10% Non-Federa $ Statewide NHS Preservation Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federa $ Statewide RR Grade Crossings Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federa $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federa $ Statewide ADA Implementation Plan Subtotal► $ - $ - $ - ◄ 80% Federal + 20% Non-Federa ► Statewide CMAQ No Projects Programmed - - - ►Statewide Transportation Enhancements No Projects Programmed ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program No Projects Programmed ►Statewide NHS Preservation Program+ No Projects Programmed ►Statewide RR Grade Crossings No Projects Programmed ►Statewide Stormwater Retrofits No Projects Programmed ►Statewide ADA Implementation Plan No Projects Programmed ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ $ Other Statewide Items Subtotal ► $ - - $ - ◄ Funding Split Varies by Funding Source $ Non-Federal Aid Subtota► $ - $ $ - ◄100% Non-Federal $ Section 2B / Non-Federal Bridge Projects Subtota► $ - $ $ - ◄100% Non-Federal $ ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects No Projects Programmed 2016 Cape Cod MPO TIP Summary TIP Section 1: ▼ TIP Section 2: ▼ Total ► $10,544,778 $ Federal Funds ► $ 8,970,038 Non-Federal Funds ► $ 1,574,740 $ - Total of All Projects ▼ $10,544,778 ◄ Total Spending in Region $ 8,970,038 ◄ Total Federal Spending in Region $ 1,574,740 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2016 Central Mass MPO Transportation Improvement Program Amendment/Adjustment Type▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ 06/10/2015 Draft Released 07/22/2015 Endorsed MassDOT Project Description▼ MassDOT District ▼ Non-Federal Funds Additional ▼ Information ▼ Funding Source ▼ Total Programmed Funds ▼ 3 HSIP $ 2,472,796 $ 2,225,516 $ 3 HSIP $ 900,000 $ 810,000 $ HSIP Subtotal ► $ 3,372,796 $ 3,035,516 $ 337,280 ◄ 90% Federal + 10% Non-Federal 3 CMAQ $ 3,805,000 $ 3,044,000 $ 761,000 3 CMAQ $ 1,610,000 $ 1,288,000 $ 322,000 CMAQ Subtotal ► $ 5,415,000 $ 4,332,000 $ Federal Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 604864 Central Mass Westborough 606207 Central Mass Spencer WESTBOROUGH - INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 9 & LYMAN STREET SPENCER - REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET 247,280 Construction / TEC Score = 7.9 / Design Status = PRE75% / HSIP+CMAQ Total Project Cost = $6,278,000 Construction / Design Status = 25% / TEC Score 90,000 = 5.1 / HSIP + CMAQ + TAP Total Project Cost = $3,207,000 ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 604864 Central Mass Westborough 606207 Central Mass Spencer WESTBOROUGH - INTERSECTION & SIGNAL IMPROVEMENTS AT ROUTE 9 & LYMAN STREET SPENCER - REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET Construction / TEC Score = 7.9 / Design Status = PRE75% / HSIP+CMAQ Total Project Cost = $6,278,000 Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ + TAP Total Project Cost = $3,207,000 1,083,000 ◄ 80% Federal + 20% Non-Federal ►TAP - Transportation Alternatives Program 606207 Central Mass Spencer TAP03 Central Mass Worcester SPENCER - REHABILITATION ON ROUTE 9 (MAIN STREET), FROM HIGH STREET TO GROVE STREET WORCESTER - WRTA STORMWATER MITIGATION 3 TAP $ 697,000 $ 557,600 $ 139,400 Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ + TAP Total Project Cost = $3,207,000 / Project Proponent is Town of Spencer 3 TAP $ 156,000 $ 124,800 $ 31,200 Construction / TEC Score = .70 / Design Status = 100% / Total Project Cost = $156,000 / Project Proponent is WRTA TAP Subtotal ► $ 853,000 $ 682,400 $ 170,600 ◄ 80% Federal + 20% Non-Federal ►Non-CMAQ/HSIP/TAP (Other) 604739 Central Mass West Brookfield 603486 Central Mass Brookfield 606686 Central Mass Warren WEST BROOKFIELD - RECONSTRUCTION ON ROUTE 9, ROUTE 67 & INTERSECTIONS AT SCHOOL STREET BROOKFIELD - RECONSTRUCTION OF ROUTE 148 (FISKDALE ROAD) FROM MOLASSES HILL ROAD TO STURBRIDGE T.L. INCL. WEBBER ROAD 2 STP $ 2,100,000 $ 1,680,000 $ 420,000 3 STP $ 2,230,000 $ 1,784,000 $ 446,000 2 STP $ 1,200,000 $ 960,000 $ 240,000 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 5,530,000 $ 4,424,000 $ Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 15,170,796 $ 5,530,000 $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 3,372,796 $ 5,415,000 $ 853,000 $ WARREN - RESURFACING AND RELATED WORK ON ROUTE 67 @ WEST WARREN AND WARREN TOWN CENTERS Construction / Design Status = 75% / TEC Score = 6.5 / Total Project Cost = $2,100,000 Construction / Design Status = 100% / TEC Score = 2.8 / Total Project Cost = $2,230,000 Construction / Design Status = 100% / TEC Score = 1.7 / Total Project Cost = $1,200,000 1,106,000 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis 15,170,796 ◄Total Target 10,734,039 ◄ Max. NonCMAQ/HSIP/TAP $ $ 869,013 ◄ Min. HSIP 2,715,666 ◄ Min. CMAQ 852,078 ◄ Min. TAP $ $ $ - Target Funds Available Non-CMAQ/HSIP/TAP (Other) A (2,503,783) HSIP Minimum Met (2,699,334) CMAQ Minimum Met (922) TAP Requirement Exceeded! HSIP, CMAQ, TAP Overprogrammed $ (5,204,039) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed $ - $ - $ - On System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Off-System AMENDMENT:Decrease Cost,AMENDMENT:Change Project 607113 Description,AMENDMENT:Change Additional Information Central Mass Dudley DUDLEY - BRIDGE DEMOLITION, D-12-009, CARPENTER ROAD OVER QUINNEBAUG RAIL TRAIL 3 STP-BR-OFF $ 500,000 $ 400,000 $ 100,000 Construction / Design Status = TBD / Total Project Cost = $500,000 / Reduced cost by $1,805,800 and changed description to Bridge Demolition 604468 Central Mass West Brookfield WEST BROOKFIELD - BRIDGE REPLACEMENT, W-19-008, WICKABOAG VALLEY ROAD OVER SUCKER BROOK 2 STP-BR-OFF $ 2,798,400 $ 2,238,720 $ 559,680 Construction / Design Status = 25% / Total Project Cost = $2,798,400 606303 Central Mass Rutland RUTLAND - BRIDGE SUPERSTRUCTURE REPLACEMENT, R-14-004, INTERVALE ROAD OVER EAST BRANCH OF WARE RIVER 3 STP-BR-OFF $ 3,435,600 $ 2,748,480 $ 687,120 Construction / Design Status = TBD / Total Project Cost = $3,435,600 Off-System Subtotal ► $ 6,734,000 $ 5,387,200 $ 1,346,800 ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid AMENDMENT:Move Project (FROM 2017),AMENDMENT:Increase Cost 605820 606629 Central Mass Central Mass Worcester Worcester WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W-44041, MCGRATH BOULEVARD OVER MADISON STREET HPP $ 260,000 $ 208,000 $ 52,000 HPP $ 5,014,925 $ 4,011,940 $ 1,002,985 HPP $ 442,675 $ 354,140 $ Other Federal Aid Subtotal ► $ 5,717,600 $ 4,574,080 $ 3 WORCESTER - BLACKSTONE VISITOR CENTER 3 606629 Central Mass Worcester WORCESTER - BLACKSTONE VISITOR CENTER, BIKEWAY & BRIDGE 3 Design / HPP#2509 - MA165 / Design Status = 25% / Total Project Cost = $6,058,072 / Add $141,100 to the design cost which came from the construction cost and move to FY 2016 Construction / HPP#4266 - MA 158 / Design Status = Pre 25% / HPP + NFA Total Project Cost = $8,908,667 88,535 Construction / HPP#4283 - MA 202, HPP#2218 MA 157, HPP#2509 - MA 165 & MA006 / Design Status = Pre 25% / HPP + NFA Total Project Cost = $8,908,667 1,143,520 ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program ADJUSTMENT:Change Additional Information AMENDMENT:Decrease Cost,AMENDMENT:Change Project Description 607176 Central Mass Multiple 607764 Central Mass Shrewsbury Sturbridge 608170 Central Mass SHREWSBURY-WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 3 HSIP $ 350,000 $ 315,000 $ 35,000 SHREWSBURY - INTERSECTION SIGNAL IMPROVEMENT AT US 20 (HARTFORD TURNPIKE) AT GRAFTON STREET 3 HSIP $ 550,000 $ 495,000 $ 55,000 STURBRIDGE - SIGN AND PAVEMENT MARKING INSTALLATION AND UPGRADES, LIMITED ROADWAT IMPROVEMENTS AND RELATED WORK ON BROOKFIELD ROAD (ROUTE 148), FROM MAIN STREET (MM 0.0) TO TOWN LINE (MM 3.4) 3 HSIPR $ 1,000,000 $ 900,000 $ 100,000 Construction / Design Status = TBD / NHS + HSIP + Stormwater Total Project Cost = $13,899,320 / Increased stormwater cost by $100K from $500K to $600K Construction / Design Status = TBD / Total Project Cost = $550,000 Construction / Design Status = TBD / Total Project Cost = $1,000,000 / Required under MAP21 HRRRP rule / Reduce cost of project by $750K AMENDMENT:Decrease Cost,AMENDMENT:Change Project Description 608169 ADJUSTMENT:Change Project Description 608168 Central Mass Dudley DUDLEY - SIGN AND PAVEMENT MARKING INSTALLATION AND UPGRADES AND RELATED WORK ON DRESSER HILL ROAD (ROUTE 31), FROM STATE LINE (MM 0.0) TO TOWN LINE (MM 4.1) Central Mass Douglas DOUGLAS - RESURFACING & RELATED WORK ON WEBSTER STREET (ROUTE 16), FROM T.L. (MM 2.8) TO MAIN STREET (MM 6.9) Construction / Design Status = TBD / Total Project Cost = $1,000,000 / Required under MAP21 HRRRP rule / Reduce cost of project by $750K 3 HSIPR $ 1,000,000 $ 900,000 $ 3 HSIPR $ 1,750,000 $ 1,575,000 $ Construction / Design Status = TBD / Total 175,000 Project Cost = $1,750,000 / Required under MAP21 HRRRP rule Statewide HSIP Program Subtotal ► $ 4,650,000 $ 4,185,000 $ 465,000 ◄ 90% Federal + 10% Non-Federal 100,000 ► Statewide Safe Routes to Schools Program No Projects Programmed - - - - $ $ - - $ - ◄ 80% Federal + 20% Non-Federal - - $ $ - $ - $ Statewide CMAQ ► $ - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source $ $ $ $ $ Statewide Safe Routes to Schools Program Subtotal ► $ ► Statewide CMAQ No Projects Programmed - - ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements No Projects Programmed $ Statewide Transportation Enhancements Subtotal ► $ ►Statewide ITS 607484 Central Mass Multiple DISTRICT 3 - INSTALLATION OF CCTV CAMERAS AND VMS ON I-290 BETWEEN I-495 AND I-90 STP $ Statewide ITS Subtotal ► $ ►Statewide Interstate Maintenance Program ADJUSTMENT:Change Additional 605592 Central Mass Sturbridge Information ADJUSTMENT:Change Additional Information 607479 Central Mass Multiple STURBRIDGE-HOLLAND - INTERSTATE MAINTENANCE & RELATED WORK ON I-84 SHREWSBURY-BOYLSTON-NORTHBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 Central Mass Multiple Information SHREWSBURY-WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 808,000.0 Consruction / Design Status = TBD / AC year 2 of 2 Total Project Cost = $6,540,000 4,040,000 $ 3,232,000 $ 808,000 ◄ 80% Federal + 20% Non-Federal NHPP $ 15,133,500 13,620,150.0 1,513,350.0 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $16,633,500 / Increase stormwater cost by $600,000 NHPP $ 13,168,800 11,851,920.0 1,316,880.0 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $15,168,800 / Increase stormwater cost by $1,200,000 3 3 Statewide Interstate Maintenance Program Subtotal ► $ ►Statewide NHS Preservation Program+ ADJUSTMENT:Change Additional 607176 3,232,000.0 4,040,000 3 NHPP $ 28,302,300 $ 12,949,320 25,472,070 $ 10,359,456.0 2,830,230 ◄ 90% Federal + 10% Non-Federal 2,589,864.0 3 Statewide NHS Preservation Program Subtotal ► $ 12,949,320 $ 10,359,456 $ Construction / Design Status = TBD / NHS + HSIP + Stormwater Total Project Cost = $13,899,320 / Increased stormwater cost by $100K from $500K to $600K 2,589,864 ◄ 80% Federal + 20% Non-Federal ►Statewide RR Grade Crossings No Projects Programmed ►Statewide Stormwater Retrofits 605592 ADJUSTMENT:Increase Cost,ADJUSTMENT:Change Additional Information ADJUSTMENT:Increase Cost,ADJUSTMENT:Change Additional Information 607479 ADJUSTMENT:Increase Cost,ADJUSTMENT:Change Additional Information 607176 ADJUSTMENT:Increase Cost 608060 Central Mass Central Mass Central Mass Central Mass Sturbridge Multiple Multiple Multiple $ Statewide RR Grade Crossings Subtotal ► $ STURBRIDGE-HOLLAND - INTERSTATE MAINTENANCE & RELATED WORK ON I-84 SHREWSBURY-BOYLSTON-NORTHBOROUGH INTERSTATE MAINTENANCE & RELATED WORK ON I-290 SHREWSBURY-WESTBOROUGH RESURFACING AND RELATED WORK ON ROUTE 9 GARDNER-SHREWSBURY - STORMWATER IMPROVEMENTS ALONG ROUTE 68/ROUTE 70 - $ - $ - ◄ 80% Federal + 20% Non-Federal STP-TE $ 1,500,000 1,200,000.0 300,000.0 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $16,633,500 / Increase stormwater cost by $600,000 STP-TE $ 2,000,000 1,600,000.0 400,000.0 Construction / Design Status = TBD / IM + Stormwater Total Project Cost = $15,168,800 / Increase stormwater cost by $1,200,000 STP-TE $ 600,000 480,000.0 120,000.0 Construction / Design Status = TBD / NHS + HSIP + Stormwater Total Project Cost = $13,899,320 / Increased stormwater cost by $100K from $500K to $600K STP-TE $ 561,800 449,440.0 112,360.0 Construction / Design Status = TBD / Total Project Cost = $561,800 / Increase cost by $146,800 3 3 3 3 AMENDMENT:Increase 608133 Cost,AMENDMENT:Change Project Description Central Mass Multiple HOPEDALE-UXBRIDGE - STORMWATER IMPROVEMENTS ALONG ROUTE 140 AND ROUTE 146 STP-TE $ 715,000 572,000.0 143,000.0 4,301,440 $ 1,075,360 ◄ 80% Federal + 20% Non-Federal 3 Statewide Stormwater Retrofits Subtotal ► $ 5,376,800 $ Construction / Design Status = TBD / Total Project Cost = $715,000 / Increase cost of project by $313,700 and change project description from Grafton/Milford locations to Hopedale/Uxbridge Locations ►Statewide ADA Implementation Plan No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - - $ $ - ◄ 80% Federal + 20% Non-Federal ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ $ Other Statewide Items Subtotal ► $ - - - ◄ Funding Split Varies by Funding Source $ $ ►Section 2A / Non-Federal Projects ►Non Federal Aid 606629 Central Mass Worcester WORCESTER - BLACKSTONE VISITOR CENTER $ 3,451,068 $ 3,451,068 Consruction / Design Status = Pre 25% / HPP + NFA Total Project Cost = $8,908,667 No Projects Programmed NFA $ Non-Federal Aid Subtotal► $ 3,451,068 $ $ 3,451,068 ◄100% Non-Federal No Projects Programmed NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ 3 NFA ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2016 Central Mass MPO TIP Summary - TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ $ $ TIP Section 2: ▼ 82,940,816 $ 69,985,162 12,955,654 $ - ◄100% Non-Federal Total of All Projects ▼ 3,451,068 $ $ 3,451,068 $ 86,391,884 ◄ Total Spending in Region 69,985,162 ◄ Total Federal Spending in Region 16,406,722 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation refe in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2017 Central Mass MPO Transportation Improvement Program Amendment/Adjustment Type▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ 06/10/2015 Draft Released 07/22/2015 Endorsed MassDOT Project Description▼ MassDOT District ▼ Non-Federal Funds Additional ▼ Information ▼ Funding Source ▼ Total Programmed Funds ▼ HSIP $ 1,768,000 $ 1,591,200 $ 176,800 HSIP Subtotal ► $ 1,768,000 $ 1,591,200 $ 176,800 ◄ 90% Federal + 10% Non-Federal Federal Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 605740 Central Mass Worcester WORCESTER - INTERSECTION IMPROVEMENTS AT WINTHROP STREET & PROVIDENCE STREET, VERNON STREET AND GRANITE STREET 3 Construction / TEC Score = 7.0 / Design Status = 25% / HSIP+CMAQ+TAP Total Project Cost = $5,026,320 ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 603251 Central Mass Worcester 605740 Central Mass Worcester WORCESTER - SIGNAL & INTERSECTION IMPROVEMENTS @ HOLDEN STREET, DRUMMOND AVENUE & SHORE DRIVE WORCESTER - INTERSECTION IMPROVEMENTS AT WINTHROP STREET & PROVIDENCE STREET, VERNON STREET AND GRANITE STREET Construction / TEC Score = 4.8 / Design Status = 195,936 TBD / CMAQ + Statewide CMAQ Total Project Cost = $2,791,146 3 CMAQ $ 979,680 $ 783,744 $ 3 CMAQ $ 2,704,000 $ 2,163,200 $ 540,800 CMAQ Subtotal ► $ 3,683,680 $ 2,946,944 $ 736,736 ◄ 80% Federal + 20% Non-Federal $ 554,320 $ 443,456 $ 110,864 TAP Subtotal ► $ 554,320 $ 443,456 $ 110,864 ◄ 80% Federal + 20% Non-Federal Construction / TEC Score = 7.0 / Design Status = 25% / HSIP+CMAQ+TAP Total Project Cost = $5,026,320 ►TAP - Transportation Alternatives Program 605740 Central Mass Worcester WORCESTER - INTERSECTION IMPROVEMENTS AT WINTHROP STREET & PROVIDENCE STREET, VERNON STREET AND GRANITE STREET 3 TAP Construction / TEC Score = 7.0 / Design Status = 25% / HSIP+CMAQ+TAP Total Project Cost = $5,026,320 / Project Proponent is City of Worcester ►Non-CMAQ/HSIP/TAP (Other) 602740 Central Mass Shrewsbury 606346 Central Mass Leicester 606206 Central Mass Oxford SHREWSBURY - RESURFACING AND RELATED WORK ON MAIN STREET, FROM I290 RAMPS EASTERLY TO MAPLE AVENUE Construction / Design Status = 25% / TEC Score = 4.6 / Total Project Cost = $5,55,680 3 STP $ 5,555,680 $ 4,444,544 $ 1,111,136 LEICESTER - RESURFACING & RELATED WORK ON ROUTE 56 (PAXTON STREET), FROM MAIN STREET TO HYLAND STREET 3 STP $ 2,392,000 $ 1,913,600 $ 478,400 Construction / TEC Score = 3.4 / Design Status = 75% / Total Project Cost = $2,392,000 OXFORD - RECONSTRUCTION ON CHARLTON STREET, BETWEEN MAIN STREET AND DUDLEY ROAD 3 STP $ 3,605,680 $ 2,884,544 $ 721,136 Construction / TEC Score = 3.6 / Design State = 25% / Total Project Cost = $3,605,680 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 11,553,360 $ 9,242,688 $ Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 17,559,360 $ 11,553,360 $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 1,768,000 $ 3,683,680 $ 554,320 $ 2,310,672 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis 17,951,638 ◄Total Target 13,813,317 ◄ Max. NonCMAQ/HSIP/TAP 869,013 ◄ Min. HSIP 2,715,666 ◄ Min. CMAQ 553,642 ◄ Min. TAP $ $ 392,278 Target Funds Available 392,278 Non-CMAQ/HSIP/TAP (Other) A $ $ $ (898,987) HSIP Minimum Met (968,014) CMAQ Minimum Met (678) TAP Requirement Exceeded! HSIP, CMAQ, TAP Overprogrammed $ (1,867,679) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program 606075 Central Mass Oxford OXFORD - STRUCTURAL STEEL CLEANING AND PAINTING AND OTHER RELATED WORK; BRIDGE NO. O-06-036 I-395 OVER DANA ROAD AND BRIDGE NO. O-06-037 I-395 SB OVER FEDERAL HILL ROAD 3 NHPP Construction / Design Status = TBD / Total Project Cost = $1,519,954 $ 1,519,954 $ 1,215,963 $ 303,991 Statewide Bridge Maintenance Program Subtotal ► $ 1,519,954 $ 1,215,963 $ 303,991 ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed ►Off-System $ - $ - $ - On System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ - $ - $ - Off-System Subtotal ► $ - $ - $ - $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid 604893 604893 ADJUSTMENT:Decrease Cost 605820 605820 606888 ADJUSTMENT:Change Additional Information 606434 605674 Central Mass Central Mass Central Mass Central Mass Central Mass Central Mass Central Mass Worcester Worcester Worcester Worcester Worcester Worcester Sturbridge WORCESTER - STREETSCAPE IMPROVEMENTS AT MAIN STREET & MAYWOOD STREET WORCESTER - STREETSCAPE IMPROVEMENTS AT MAIN STREET & MAYWOOD STREET WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W44-041, MCGRATH BOULEVARD OVER MADISON STREET WORCESTER - BLACKSTONE RIVER BIKEWAY (SEGMENT 7), INCLUDING BRIDGE REHAB, W44-041, MCGRATH BOULEVARD OVER MADISON STREET WORCESTER - BLACKSTONE CANAL STREETSCAPE IMPROVEMENTS ON HARDING STREET WORCESTER - CENTRAL BUSINESS DISTRICT STREETSCAPE IMPROVEMENTS TI $ 2,285,798 $ 1,828,638 $ TI $ 120,000 $ 96,000 $ HPP $ 5,798,073 $ 4,638,458 $ HPP $ 260,000 $ 208,000 $ Sec 129 $ 735,000 $ 735,000 $ HPP $ 5,625,000 $ 4,500,000 $ HPP $ 507,500 $ 406,000 $ Other Federal Aid Subtotal ► $ 15,331,371 $ 12,412,096 $ 3 457,160 Construction / TI#177 - MA213 / Design Status = Pre 25% / Total Project Cost = $2,405,798 24,000 3 3 1,159,615 Construction / HPP#4283 - MA202, HPP#2218 MA157, HPP#2509 - MA165 & MA006 / Design Status = 25% / Total Project Cost = $6,058,072 / Decrease cost of construction portion of project by $141,100 and will add same amount to design 52,000 3 - STURBRIDGE - GRAND TRUNK TRAIL 3 Design / HPP#2509 - MA165 / Design Status = 25% / Total Project Cost = $6,058,072 / Add $141,100 to the design cost which came from the construction cost and move to FY 2016 Construction / MA238 / Design Status = 25% / Total Project Cost = $735,000 / This project is 100% Federally funded 3 3 Design / TI#177 - MA213 / Design Status = Pre 25% / Total Project Cost = $2,405,798 1,125,000 Construction / HPP#4266 - MA185 / Design Status = 25% / HPP + TE Total Project Cost = $6,977,015 / Added additional TE funding to this project 101,500 Construction / HPP#2439 - MA162 / Design Status = 25% / Total Project Cost = $507,500 2,919,275 ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - - $ Statewide HSIP Program Subtotal ► $ - $ Statewide Safe Routes to Schools Program Subtotal ► $ - $ $ - - $ $ - $ $ - $ $ - - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program No Projects Programmed - - ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed - - - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source ► Statewide CMAQ 603251 ►Statewide Transportation Enhancements AMENDMENT:Add Funding Source 606434 Central Mass Central Mass Worcester Worcester WORCESTER - SIGNAL & INTERSECTION IMPROVEMENTS @ HOLDEN STREET, DRUMMOND AVENUE & SHORE DRIVE WORCESTER - CENTRAL BUSINESS DISTRICT STREETSCAPE IMPROVEMENTS 3 $ 1,811,466 $ 1,449,173 $ Construction / Design Status = TBD / CMAQ + 362,293 Statewide CMAQ Total Project Cost = $2,791,146 Statewide CMAQ ► $ 1,811,466 $ 1,449,173 $ 362,293 ◄ 80% Federal + 20% Non-Federal CMAQ STP-TE $ 1,352,015 1,081,612.0 270,403.0 3 Statewide Transportation Enhancements Subtotal ► $ 1,352,015 $ 1,081,612 $ Construction / HPP#4266 - MA185 / Design Status = 25% / HPP + TE Total Project Cost = $6,977,015 / Added additional TE funding to this project 270,403 ◄ 80% Federal + 20% Non-Federal ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program $ Statewide ITS Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ADJUSTMENT:Decrease Cost 607562 Central Mass Multiple WEBSTER-OXFORD - INTERSTATE MAINTENANCE & RELATED WORK ON I-395 3 NHPP $ Statewide Interstate Maintenance Program Subtotal ► $ 7,327,800 6,595,020.0 7,327,800 $ 732,780.0 6,595,020 $ Construction / Design Status = TBD / Total Project Cost = $7,327,800 / Decrease cost by $293,112 732,780 ◄ 90% Federal + 10% Non-Federal ►Statewide NHS Preservation Program+ No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide RR Grade Crossings Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide ADA Implementation Plan Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Statewide RR Grade Crossings No Projects Programmed ►Statewide Stormwater Retrofits No Projects Programmed ►Statewide ADA Implementation Plan No Projects Programmed ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ $ Other Statewide Items Subtotal ► $ - - $ - ◄ Funding Split Varies by Funding Source NFA $ Non-Federal Aid Subtotal► $ - $ $ - ◄100% Non-Federal NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ - $ $ - ◄100% Non-Federal $ ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects No Projects Programmed 2017 Central Mass MPO TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Total of All Projects ▼ TIP Section 2: ▼ 44,901,966 $ 36,978,152 7,923,814 $ - $ $ $ 44,901,966 ◄ Total Spending in Region 36,978,152 ◄ Total Federal Spending in Region 7,923,814 ◄ Total Non-Federal Spending in Region Project costs have increased by 4% a year to account for inflation. 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2018 Central Mass MPO Transportation Improvement Program Amendment/Adjustment Type▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ 06/10/2015 Draft Released 07/22/2015 Endorsed MassDOT Project Description▼ MassDOT District ▼ Non-Federal Funds Additional ▼ Information ▼ Funding Source ▼ Total Programmed Funds ▼ HSIP $ 3,401,632 $ 3,061,469 $ 340,163 HSIP Subtotal ► $ 3,401,632 $ 3,061,469 $ 340,163 ◄ 90% Federal + 10% Non-Federal CMAQ $ 2,924,646 $ 2,339,717 $ 584,929 CMAQ Subtotal ► $ 2,924,646 $ 2,339,717 $ 584,929 ◄ 80% Federal + 20% Non-Federal $ 553,779 $ 443,023 $ TAP Subtotal ► $ 553,779 $ 443,023 $ Federal Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 601368 Central Mass Worcester WORCESTER - RESURFACING & RELATED WORK ON ROUTE 122 (GRAFTON STREET), FROM WASHINGTON SQUARE TO RICE SQUARE (1.4 MILES) 3 Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ Total Project Cost = $6,326,278 ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 601368 Central Mass Worcester WORCESTER - RESURFACING & RELATED WORK ON ROUTE 122 (GRAFTON STREET), FROM WASHINGTON SQUARE TO RICE SQUARE (1.4 MILES) 3 ►TAP - Transportation Alternatives Program 606440 Central Mass Princeton PRINCETON - RECLAMATION ON ROUTE 140, FROM STERLING T.L. TO ROUTE 31 3 TAP Construction / Design Status = 25% / TEC Score = 5.1 / HSIP + CMAQ Total Project Cost = $6,326,278 Construction / TEC Score = 4.3 / Design Status = 25% / TAP + STP Total Project Cost = $7,165,600 / Project Proponent is Town of Princeton 110,756 ◄ 80% Federal + 20% Non-Federal 110,756 ►Non-CMAQ/HSIP/TAP (Other) 606440 Central Mass Princeton PRINCETON - RECLAMATION ON ROUTE 140, FROM STERLING T.L. TO ROUTE 31 3 STP $ 6,611,821 $ 5,289,457 $ 1,322,364 Construction / TEC Score = 4.3 / Design Status = 25% / TAP + STP Total Project Cost = $7,165,600 604948 Central Mass Uxbridge UXBRIDGE - RECONSTRUCTION OF ROUTE 122 (NORTH MAIN STREET), FROM HARTFORD AVENUE TO ROUTE 16 3 STP $ 4,611,942 $ 3,689,554 $ 922,388 Construction / TEC Score = 4.3 / Design Status = 75% / Total Project Cost = $4,611,942 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 11,223,763 $ 8,979,010 $ Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 18,103,820 $ 11,223,763 $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 3,401,632 $ 2,924,646 $ 553,779 $ 2,244,753 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis 18,733,750 ◄Total Target 14,595,428 ◄ Max. NonCMAQ/HSIP/TAP $ $ 869,013 ◄ Min. HSIP 2,715,666 ◄ Min. CMAQ 553,642 ◄ Min. TAP $ $ $ 629,930 Target Funds Available 629,929 Non-CMAQ/HSIP/TAP (Other) A (2,532,619) HSIP Minimum Met (208,980) CMAQ Minimum Met (137) TAP Requirement Exceeded! HSIP, CMAQ, TAP Overprogrammed $ (2,741,736) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - $ - $ - $ - On System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed ◄ 80% Federal + 20% Non-Federal ►Off-System 606638 ► Statewide Bridge Inspection Program Central Mass Sutton SUTTON - BRIDGE REPLACEMENT, S-33-005, BLACKSTONE STREET OVER BLACKSTONE RIVER 3 STP-BR-OFF Construction / Design Status = TBD / Total Project Cost = $5,435,448 $ 5,435,448 $ 4,348,358 $ 1,087,090 Off-System Subtotal ► $ 5,435,448 $ 4,348,358 $ 1,087,090 ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid Pending Central Mass Multiple Quinebaug Rail Trail $ 800,000 $ 640,000 $ 160,000 Other Federal Aid Subtotal ► $ 800,000 $ 640,000 $ 160,000 ◄ Funding Split Varies by Funding Source 3 HPP Construction / HPP#2173 - MA156 / Design Status = Pre 25% / Total Project Cost = $800,000 ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program 607917 Central Mass Multiple AUBURN TO WORCESTER - GUIDE & TRAFFIC SIGN REPLACEMENT ON A SECTION OF 3 HSIP $ INTERSTATE 290 Statewide HSIP Program Subtotal ► $ Construction / Design Status = TBD / Total Project Cost = $4,200,000 4,200,000 $ 3,780,000 $ 420,000 4,200,000 $ 3,780,000 $ 420,000 ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ - - $ $ - $ Statewide CMAQ ► $ - - $ $ $ Statewide Transportation Enhancements Subtotal ► $ - $ Statewide ITS Subtotal ► $ - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source $ $ - - $ $ - $ - $ - ◄ 80% Federal + 20% Non-Federal - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide Interstate Maintenance Program Subtotal ► $ - $ - $ - ◄ 90% Federal + 10% Non-Federal $ Statewide NHS Preservation Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide RR Grade Crossings Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ► Statewide CMAQ No Projects Programmed - - ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements No Projects Programmed ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program No Projects Programmed ►Statewide NHS Preservation Program+ No Projects Programmed ►Statewide RR Grade Crossings No Projects Programmed ►Statewide Stormwater Retrofits 608394 AMENDMENT:Add Project Franklin Sturbridge STURBRIDGE - STORMWATER IMPROVEMENTS ALONG ROUTE 20 3 STP-TE $ Statewide Stormwater Retrofits Subtotal ► $ 650,000 520,000.0 650,000 $ 130,000.0 520,000 $ Construction / Design Status = TBD / Total Project Cost = $650,000 / Added this new project to the list 130,000 ◄ 80% Federal + 20% Non-Federal ►Statewide ADA Implementation Plan No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning $ $ - - - $ - - - $ - - - Statewide Design and Right of Way Statewide Recreational Trails $ $ Other Statewide Items Subtotal ► $ - $ - ◄ Funding Split Varies by Funding Source NFA $ Non-Federal Aid Subtotal► $ - $ $ - ◄100% Non-Federal NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ - $ $ - ◄100% Non-Federal $ - ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects No Projects Programmed 2018 Central Mass MPO TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Total of All Projects ▼ TIP Section 2: ▼ 29,189,268 $ 24,111,578 5,077,690 $ - $ $ $ 29,189,268 ◄ Total Spending in Region 24,111,578 ◄ Total Federal Spending in Region 5,077,690 ◄ Total Non-Federal Spending in Region Project costs have increased by 4% a year to account for inflation. 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2019 Central Mass MPO Transportation Improvement Program Amendment/Adjustment Type▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ 06/10/2015 Draft Released 07/22/2015 Endorsed MassDOT Project Description▼ MassDOT District ▼ Non-Federal Funds Additional ▼ Information ▼ Funding Source ▼ Total Programmed Funds ▼ HSIP $ 2,812,160 $ 2,530,944 $ 281,216 HSIP Subtotal ► $ 2,812,160 $ 2,530,944 $ 281,216 ◄ 90% Federal + 10% Non-Federal CMAQ $ 3,937,024 $ 3,149,619 $ 787,405 CMAQ Subtotal ► $ 3,937,024 $ 3,149,619 $ 787,405 ◄ 80% Federal + 20% Non-Federal $ 426,324 $ 341,059 $ TAP Subtotal ► $ 426,324 $ 341,059 $ Federal Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 606125 Central Mass Upton UPTON - RECONSTRUCTION OF HARTFORD AVENUE NORTH, HIGH STREET AND HOPKINTON ROAD 3 Construction / TEC Score = 4.8 / Design Status = 25% / HSIP + CMAQ Total Project Cost = $6,749,184 ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 606125 Central Mass Upton UPTON - RECONSTRUCTION OF HARTFORD AVENUE NORTH, HIGH STREET AND HOPKINTON ROAD 3 Construction / TEC Score = 4.8 / Design Status = 25% / HSIP + CMAQ Total Project Cost = $6,749,184 ►TAP - Transportation Alternatives Program 607250 Central Mass Paxton PAXTON - RECLAMATION ON ROUTE 31 (HOLDEN ROAD) 3 TAP Construction / TEC Score = 3.6 / Design Status = 25% / TAP + STP Total Project Cost = $3,798,666 / Proejct Proponent is the Town of Paxton 85,265 ◄ 80% Federal + 20% Non-Federal 85,265 ►Non-CMAQ/HSIP/TAP (Other) 607250 Central Mass Paxton PAXTON - RECLAMATION ON ROUTE 31 (HOLDEN ROAD) 3 STP $ 3,372,342 $ 2,697,874 $ 674,468 Construction / TEC Score = 3.6 / Design Status = 25% / TAP + STP Total Project Cost = $3,798,666 605377 Central Mass Millbury MILLBURY - RECONSTRUCTION ON MCCRACKEN ROAD & GREENWOOD STREET, INCLUDES REHAB OF M-22-058, MCCRACKEN ROAD OVER ACCESS ROAD 3 STP $ 7,934,791 $ 6,347,833 $ 1,586,958 Construction / TEC Score = 5.4 / Design Status = 25% / Total Project Cost = $7,934,791 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 11,307,133 $ 9,045,706 $ 2,261,427 ◄ 80% Federal + 20% Non-Federal Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 18,482,641 $ 11,307,133 $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 2,812,160 $ 3,937,024 $ 426,324 $ ►Section 1A / Fiscal Constraint Analysis 18,733,750 ◄Total Target 14,723,032 ◄ Max. NonCMAQ/HSIP/TAP $ $ 869,013 ◄ Min. HSIP 2,715,666 ◄ Min. CMAQ 426,039 ◄ Min. TAP $ $ $ 251,109 Target Funds Available 251,109 Non-CMAQ/HSIP/TAP (Other) A (1,943,147) HSIP Minimum Met (1,221,358) CMAQ Minimum Met (285) TAP Requirement Exceeded! HSIP, CMAQ, TAP Overprogrammed $ (3,164,790) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program AMENDMENT:Add Project 608237 Central Mass Multiple WORCESTER - BOYLSTON NORTHBOROUGH - STRUCTURAL STEEL 3 NHPP $ CLEANING AND PAINTING OF OVERHEAD BRIDGES ON I-290 Statewide Bridge Maintenance Program Subtotal ► $ Construction / Design Status = TBD / Total Project Cost = $1,450,843 / Added this new project to the list 1,450,848 $ 1,160,678 $ 290,170 1,450,848 $ 1,160,678 $ 290,170 ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed $ - $ - $ - On System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Off-System 608190 Central Mass East Brookfield EAST BROOKFIELD - BRIDGE REPLACEMENT, E-2-1, SOUTH POND ROAD OVER SOUTH POND INLET 3 STP-BR-OFF Construction / Design Status = TBD / Total Project Cost = $2,873,024 $ 2,873,024 $ 2,298,419 $ 574,605 Off-System Subtotal ► $ 2,873,024 $ 2,298,419 $ 574,605 ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - $ - $ - $ - Other Federal Aid Subtotal ► $ - $ - $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid No Projects Programmed ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program 607757 Central Mass Worcester WORCESTER - SIGNAL & INTERSECTION IMPROVEMENTS ON ROUTE 122A (PROVIDENCE STREET) AT MILLBURY STREET & MCKEON ROAD 3 HSIP Construction / Design Status = TBD / Total Project Cost = $550,000 $ 550,000 $ 495,000 $ 55,000 Statewide HSIP Program Subtotal ► $ 550,000 $ 495,000 $ 55,000 ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ - - $ $ - $ Statewide CMAQ ► $ - - $ $ $ Statewide Transportation Enhancements Subtotal ► $ - $ Statewide ITS Subtotal ► $ - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source $ $ - - $ $ - $ - $ - ◄ 80% Federal + 20% Non-Federal - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide Interstate Maintenance Program Subtotal ► $ - $ - $ - ◄ 90% Federal + 10% Non-Federal $ Statewide NHS Preservation Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide RR Grade Crossings Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ Statewide ADA Implementation Plan Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ► Statewide CMAQ No Projects Programmed - - ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements No Projects Programmed ►Statewide ITS No Projects Programmed ►Statewide Interstate Maintenance Program No Projects Programmed ►Statewide NHS Preservation Program+ No Projects Programmed ►Statewide RR Grade Crossings No Projects Programmed ►Statewide Stormwater Retrofits No Projects Programmed ►Statewide ADA Implementation Plan No Projects Programmed ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning $ $ - - - $ - - - $ - - - Statewide Design and Right of Way Statewide Recreational Trails $ $ Other Statewide Items Subtotal ► $ - $ - ◄ Funding Split Varies by Funding Source NFA $ Non-Federal Aid Subtotal► $ - $ $ - ◄100% Non-Federal NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ - $ $ - ◄100% Non-Federal $ - ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects No Projects Programmed 2019 Central Mass MPO TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Total of All Projects ▼ TIP Section 2: ▼ 23,356,513 $ 19,021,426 4,335,087 $ - $ $ $ 23,356,513 ◄ Total Spending in Region 19,021,426 ◄ Total Federal Spending in Region 4,335,087 ◄ Total Non-Federal Spending in Region Project costs have increased by 4% a year to account for inflation. 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2016 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ MassDOT Project Description▼ Sterling STERLINGINTERSECTION IMPROVEMENTS AT ROUTE 12 AND CHOCKSETT ROAD MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ HSIP $ 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Federal Funds ▼ Non-Federal Funds ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 604699 Montachusett 3 $ HSIP Subtotal ► $ 445,955 $ - $ 401,360 - $ 44,596 $ 445,955 $ 401,360 $ 1,393,611 $ 1,114,889 $ STP/HSIP/CMAQ; Total Cost = $4,700,000 (as of 6/4/15); Construction; TEC 39 of 100; 25% Design Due 4/7/15; MassDOT Boston Design; HSIP & CMAQ Eligible; 44,596 ◄ 90% Federal + 10% Non-Federal ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 604699 Montachusett Sterling STERLINGINTERSECTION IMPROVEMENTS AT ROUTE 12 AND CHOCKSETT ROAD 3 CMAQ $ $ CMAQ Subtotal ► $ - $ - 278,722 $ 1,393,611 $ 1,114,889 $ 149,980 $ 119,984 $ STP/HSIP/CMAQ; Total Cost = $4,700,000 (as of 6/4/15); Construction; TEC 39 of 100; 25% Design Due 4/7/15; MassDOT Boston Design; HSIP & CMAQ Eligible; 278,722 ◄ 80% Federal + 20% Non-Federal ►TAP - Transportation Alternatives Program 604960 Montachusett Clinton CLINTONRESURFACING & RELATED WORK ON WATER STREET AND BOLTON ROAD (1.2 MILES) 3 TAP $ $ TAP Subtotal ► $ - $ - 29,996 $ 149,980 $ 119,984 $ STP/TAP; Non Adjusted Total Cost = $5,494,460 as of 3/25/15; Construction; TEC 43 of 100; Adv on 11/1/14; CMAQ eligible; AC Yr 2 of 2; Yr 2 Non Adjusted Cost = $2,659,241; 29,996 ◄ 80% Federal + 20% Non-Federal ►Non-CMAQ/HSIP/TAP (Other) 604699 Montachusett Sterling 604960 Montachusett Clinton STERLINGINTERSECTION IMPROVEMENTS AT ROUTE 12 AND CHOCKSETT ROAD CLINTONRESURFACING & RELATED WORK ON WATER STREET AND BOLTON ROAD (1.2 MILES) 3 STP $ 2,860,434 $ 2,288,347 $ 572,087 STP/HSIP/CMAQ; Total Cost = $4,700,000 (as of 6/4/15); Construction; TEC 39 of 100; 25% Design Due 4/7/15; MassDOT Boston Design; HSIP & CMAQ Eligible; 3 STP $ 2,509,261 $ 2,007,409 $ 501,852 STP/TAP; Non Adjusted Total Cost = $5,494,460 as of 3/25/15; Construction; TEC 43 of 100; Adv on 11/1/14; CMAQ eligible; AC Yr 2 of 2; Yr 2 Non Adjusted Cost = $2,659,241; Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ $ 5,369,695 $ 4,295,756 $ $ Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 7,359,241 $ 5,369,695 $ 7,785,267 ◄Total Target 5,795,721 ◄ Max. NonCMAQ/HSIP/TAP $ $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 445,955 $ 1,393,611 $ 149,980 $ 445,955 ◄ Min. HSIP 1,393,611 ◄ Min. CMAQ 149,980 ◄ Min. TAP $ $ $ 1,073,939 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis 426,026 Target Funds Available 426,026 Non-CMAQ/HSIP/TAP (Other) A - HSIP Minimum Met CMAQ Minimum Met TAP Minimum Met Remaining HSIP, CMAQ, and TAP Funds $ ‐ Montachusett MPO February 17, 2016 Page 1 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Total Programmed Funds ▼ Federal Funds ▼ Non-Federal Funds ▼ No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - - 2016 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ MassDOT Project Description▼ MassDOT District ▼ Funding Source ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - On System Subtotal ► $ - $ - $ - No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Off-System Subtotal ► $ - $ - $ - No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - - ◄ 80% Federal + 20% Non-Federal ►Off-System ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - Other Federal Aid Subtotal ► $ - $ - $ - ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ - $ $ $ - $ $ - - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program AMENDMENT:Remove Project 607960 Montachusett Ashburnham ASHBURNHAM- ROUTE 101 AT WILLIAMS AND COREY HILL ROAD, INTERSECTION IMPROVEMENTS 3 HSIPR No Projects Programmed $ $ Statewide HSIP Program Subtotal ► $ Montachusett MPO February 17, 2016 Page 2 of 4 624,000 $ - $ 624,000 $ 561,600 561,600 $ $ $ Adjust Funding Source from STP to HSIPR. Required under MAP-21 HRRRP rule. Total Cost = $1,248,000 (as of 5/20/15); Design funded through Regional HSIP in FFY 2014; 62,400 Construction to be funded under Statewide HSIP #607493 as a High Risk Rural Road Program (HRRRP) project; AC Yr 1 of 2; Yr 2 FFY 2017 Cost = $624,000; REMOVED 2/17/2016 62,400 ◄ 90% Federal + 10% Non-Federal FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2016 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ MassDOT Project Description▼ Fitchburg FITCHBURG - SOUTH STREET ELEMENTARY SAFE ROUTES TO SCHOOL Recommended improvements: Installation of sidewalks, wheelchair ramps, crosswalk striping and warning signs. MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Federal Funds ▼ Non-Federal Funds ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ► Statewide Safe Routes to Schools Program 607242 Montachusett 3 TAP $ No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ 884,000 $ 707,200 $ 176,800 80% Federal + 20% Non-Federal $ 884,000 $ 707,200 $ $ - Funding Split Varies by Funding Source 176,800 ◄ Funding Split Varies by Funding Source ► Statewide CMAQ - No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide CMAQ ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 90% Federal + 10% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal - - ►Statewide Transportation Enhancements No Projects Programmed $ $ No Projects Programmed Statewide Transportation Enhancements Subtotal ► $ - No Projects Programmed No Projects Programmed $ $ Statewide ITS Subtotal ► $ - $ No Projects Programmed No Projects Programmed $ Statewide Interstate Maintenance Program Subtotal ► $ - No Projects Programmed $ $ No Projects Programmed Statewide NHS Preservation Program Subtotal ► $ - No Projects Programmed $ $ No Projects Programmed Statewide RR Grade Crossings Subtotal ► $ - No Projects Programmed $ $ No Projects Programmed Statewide Stormwater Retrofits Subtotal ► $ - No Projects Programmed $ $ No Projects Programmed Statewide ADA Implementation Plan Subtotal ► $ - ►Statewide ITS ►Statewide Interstate Maintenance Program ►Statewide NHS Preservation Program+ ►Statewide RR Grade Crossings ►Statewide Stormwater Retrofits ►Statewide ADA Implementation Plan Montachusett MPO February 17, 2016 Page 3 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2016 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ MassDOT Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Federal Funds ▼ Non-Federal Funds ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ - - - $ - Other Statewide Items Subtotal ► $ - NFA $ NFA $ Non-Federal Aid Subtotal► $ No Projects Programmed NFA $ No Projects Programmed NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ $ - $ - ◄ Funding Split Varies by Funding Source - $ $ $ - ◄100% Non-Federal - $ $ $ - ◄100% Non-Federal ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2016 MONTACHUSETT MPO TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ TIP Section 2: ▼ 8,867,241 $ 7,200,788 1,666,453 $ Total of All Projects ▼ - $ $ $ 8,867,241 ◄ Total Spending in Region 7,200,788 ◄ Total Federal Spending in Region 1,666,453 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx Montachusett MPO February 17, 2016 Page 4 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2017 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ HSIP $ 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Federal Funds ▼ Non-Federal Funds ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 608188 Montachusett Multiple GARDNERLEOMINSTERSTERLING - SAFETY IMPROVEMENTS AT 3 LOCATIONS No Projects Programmed 3 $ HSIP Subtotal ► $ 552,500 $ - $ 552,500 $ 497,250 497,250 $ 55,250 $ HSIP; Total Cost =$552.500 Adjusted for YOE by 4%; Non Adjusted Total Cost = $531,250; MassDOT Design; Construction Funded HSIP; - $ 55,250 ◄ 90% Federal + 10% Non-Federal ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 606124 Montachusett Multiple FITCHBURGLUNENBURGLEOMINSTERRECONSTRUCTION OF SUMMER STREET AND NORTH STREET 3 CMAQ No Projects Programmed $ $ CMAQ Subtotal ► $ 1,393,611 $ - $ 1,393,611 $ 1,114,889 1,114,889 $ 278,722 $ $ STP/CMAQ/TAP; Total Cost = $8,003,595 Adjusted for YOE by 4%; Non Adjusted Total Cost = $7,695,764 as of 4/10/15; 25% received (1/21/14); Public Hearing May 2015; TEC 50 of 100; Not HSIP Eligibile; Construction; 278,722 ◄ 80% Federal + 20% Non-Federal ►TAP - Transportation Alternatives Program 606124 Montachusett Multiple FITCHBURGLUNENBURGLEOMINSTERRECONSTRUCTION OF SUMMER STREET AND NORTH STREET 3 TAP No Projects Programmed $ $ TAP Subtotal ► $ 97,450 $ - $ 97,450 $ 77,960 77,960 $ 19,490 $ STP/CMAQ/TAP; Total Cost = $8,003,595 Adjusted for YOE by 4%; Non Adjusted Total Cost = $7,695,764 as of 4/10/15; 25% received (1/21/14); Public Hearing May 2015; TEC 50 of 100; Not HSIP Eligibile; Construction; - $ 19,490 ◄ 80% Federal + 20% Non-Federal ►Non-CMAQ/HSIP/TAP (Other) 606124 Montachusett Multiple FITCHBURGLUNENBURGLEOMINSTERRECONSTRUCTION OF SUMMER STREET AND NORTH STREET 3 STP No Projects Programmed $ $ 6,512,534 $ - $ 5,210,027 - $ 1,302,507 $ $ STP/CMAQ/TAP; Total Cost = $8,003,595 Adjusted for YOE by 4%; Non Adjusted Total Cost = $7,695,764 as of 4/10/15; 25% received (1/21/14); Public Hearing May 2015; TEC 50 of 100; Not HSIP Eligibile; Construction; - Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 6,512,534 $ 5,210,027 1,302,507 ◄ 80% Federal + 20% Non-Federal Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 8,556,095 $ 6,512,534 $ 9,212,324 ◄Total Target 7,275,308 ◄ Max. NonCMAQ/HSIP/TAP $ $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 552,500 $ 1,393,611 $ 97,450 $ 445,955 ◄ Min. HSIP 1,393,611 ◄ Min. CMAQ 97,450 ◄ Min. TAP $ $ $ ►Section 1A / Fiscal Constraint Analysis 656,229 Target Funds Available 656,229 Non-CMAQ/HSIP/TAP (Other) A (106,545) HSIP Minimum Met - CMAQ Minimum Met - TAP Minimum Met HSIP, CMAQ, TAP Overprogrammed $ (106,545) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program Montachusett MPO February 17, 2016 Page 1 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Total Programmed Funds ▼ Federal Funds ▼ Non-Federal Funds ▼ No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - 2017 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ◄ 80% Federal + 20% Non-Federal ►On System 605094 Montachusett Fitchburg FITCHBURG - BRIDGE BETTERMENT, F-04-003, STATE ROUTE 31 OVER PHILLIPS BROOK 3 NHPP No Projects Programmed $ $ 5,439,420 $ - $ 4,351,536 - $ $ On System Subtotal ► $ 5,439,420 $ 4,351,536 $ 1,087,884 Cost Est as of 5/28/15; Total Cost = $5,439,420 Adjusted for YOE by 4%; Construction; 1,087,884 ◄ 80% Federal + 20% Non-Federal ►Off-System 608250 Montachusett Royalston ROYALSTON - BRIDGE REPLACEMENT, R-12001, STOCKWELL ROAD OVER LAWRENCE BROOK 607529 Montachusett Winchendon WINCHENDON - BRIDGE REPAIR, N. ROYALSTON ROAD OVER WEST BRANCH OF MILLERS RIVER, W-39-015, 2 STP-BR-OFF $ 1,075,360 $ 860,288 $ 215,072 Cost Est as of 5/28/15; Total Cost = $1,075,360 Adjusted for YOE by 4%; Bridge Off System; Construction; 2 STP-BR-OFF $ 2,624,440 $ 2,099,552 $ 524,888 Cost Est as of 5/28/15; Total Cost = $2,624,440 Adjusted for YOE by 4%; Bridge Off System; Construction; Off-System Subtotal ► $ 3,699,800 $ 2,959,840 $ 739,960 ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid 607347 Montachusett Gardner GARDNER- BIKE PATH CONSTRUCTION, NORTH CENTRAL PATHWAY (PHASE VI) 3 HPP No Projects Programmed $ $ Other Federal Aid Subtotal ► $ 1,040,000 $ - $ 1,040,000 $ 832,000 - $ $ 832,000 $ HPP #1798 MA 148 Earmark: YOE Cost = $1,040,000; Non Adjusted Total Cost = $1,000,000 (as of 4/9/14); Total Design = 208,000 $112,000 included in FFY 2013 TIP Amendment No. 2 MPO Endorsed 6/12/13; Total Estimated Design & Construction = $1,112,000 Non Adjusted; Construction; 208,000 ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed Montachusett MPO February 17, 2016 $ Page 2 of 4 - $ - $ - $ - $ - FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2017 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Statewide Infrastructure Program Subtotal ► $ - 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Federal Funds ▼ Non-Federal Funds ▼ Additional Information ▼ $ ◄ 80% Federal + 20% Non-Federal $ - 1/15/2016 Draft Released 2/17/2016 Endorsed - ► Statewide HSIP Program AMENDMENT:Remove Project 607960 Montachusett Ashburnham ASHBURNHAM- ROUTE 101 AT WILLIAMS AND COREY HILL ROAD, INTERSECTION IMPROVEMENTS 3 HSIPR $ No Projects Programmed $ Statewide HSIP Program Subtotal ► $ $ 555,360 $ Amend Funding Source from STP to HSIPR. Required under MAP-21 HRRRP rule. Total Cost = $1,248,000 (as of 5/20/15); Design funded through Regional HSIP in FFY 2014; 68,640 Construction to be funded under Statewide HSIP #607493 as a High Risk Rural Road Program (HRRRP) project; AC Yr 2 of 2; Yr 1 FFY 2016 Cost = $624,000; REMOVED 2/17/2016 $ 624,000 $ 555,360 $ $ 68,640 ◄ 90% Federal + 10% Non-Federal 624,000 ► Statewide Safe Routes to Schools Program $ - $ - $ No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ No Projects Programmed - $ $ - $ $ - - - Funding Split Varies by Funding Source - Funding Split Varies by Funding Source - ◄ Funding Split Varies by Funding Source ► Statewide CMAQ No Projects Programmed $ - $ - $ - No Projects Programmed $ Statewide CMAQ ► $ - $ $ - - - $ $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal - ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements No Projects Programmed No Projects Programmed $ Statewide Transportation Enhancements Subtotal ► $ - ►Statewide ITS No Projects Programmed No Projects Programmed $ $ Statewide ITS Subtotal ► $ - ►Statewide Interstate Maintenance Program AMENDMENT:Decrease Cost 606575 Montachusett Multiple STERLING LEOMINSTER LANCASTER INTERSTATE MAINTENANCE & RELATED WORK ON I190 3 NHPP $ No Projects Programmed $ Statewide Interstate Maintenance Program Subtotal ► $ 16,935,360 15,241,824 16,935,360 $ 15,241,824 Adjust Programmed Funds down from $17,768,774 and Remove Stormwater 1,693,536 Component; Cost Est as of 12/29/15; Total Cost = $17,768,774; Cost = $17,612,774 IM + $156,000 Stormwater; Construction $ 1,693,536 ◄ 90% Federal + 10% Non-Federal ►Statewide NHS Preservation Program+ 607475 Montachusett Winchendon WINCHENDON RESURFACING & RELATED WORK ON ROUTE 12, FROM MILL STREET/BEGINNING OF STATE HIGHWAY TO NEW HAMPSHIRE STATE LINE (2.5 MILES) 2 NHPP $ No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ Montachusett MPO February 17, 2016 Page 3 of 4 1,879,150 1,503,320 1,879,150 $ 1,503,320 375,830 $ Cost Est as of 5/20/15; Total Cost = $1,879,150 Adjusted for YOE; Construction 375,830 ◄ 80% Federal + 20% Non-Federal FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2017 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ 6/22/2015 Draft Released 7/30/2015 Endorsed AMEND/ADJUST No. 1 Federal Funds ▼ Non-Federal Funds ▼ 1/15/2016 Draft Released 2/17/2016 Endorsed Additional Information ▼ ►Statewide RR Grade Crossings No Projects Programmed $ No Projects Programmed $ Statewide RR Grade Crossings Subtotal ► $ ►Statewide Stormwater Retrofits AMENDMENT:Remove Project 606575 Montachusett Multiple - - $ $ - ◄ 80% Federal + 20% Non-Federal STERLING LEOMINSTER LANCASTER 3 STP-TE $ INTERSTATE MAINTENANCE & RELATED WORK ON I No Projects Programmed $ Statewide Stormwater Retrofits Subtotal ► $ 156,000 124,800 156,000 $ 124,800 No Projects Programmed $ No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ - - - $ - - - Other Statewide Items Subtotal ► $ - NFA $ NFA $ Non-Federal Aid Subtotal► $ No Projects Programmed NFA $ No Projects Programmed NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ 31,200 Cost Est as of 5/20/15; Total Cost = $17,768774; Cost = $17,612,774 IM + $156,000 Stormwater; Construction; REMOVED 2/17/2016 $ 31,200 ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal ►Statewide ADA Implementation Plan $ - ►Other Statewide Items $ - $ - ◄ Funding Split Varies by Funding Source - $ $ $ - ◄100% Non-Federal - $ $ $ - ◄100% Non-Federal ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2017 MONTACHUSETT MPO TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Montachusett MPO February 17, 2016 Page 4 of 4 TIP Section 2: ▼ 38,329,825 $ 32,468,806 5,861,019 $ Total of All Projects ▼ - $ $ $ 38,329,825 ◄ Total Spending in Region 32,468,806 ◄ Total Federal Spending in Region 5,861,019 ◄ Total Non-Federal Spending in Region FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2018 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Federal Funds ▼ Non-Federal Funds ▼ Additional Information ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 605651 Montachusett Leominster LEOMINSTERRECONSTRUCTION ON ROUTE 13, FROM HAWES STREET TO PROSPECT STREET 3 HSIP No Projects Programmed $ $ HSIP Subtotal ► $ 445,955 $ - $ 445,955 $ 401,360 $ - $ 401,360 $ ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 605651 Montachusett Leominster LEOMINSTERRECONSTRUCTION ON ROUTE 13, FROM HAWES STREET TO PROSPECT STREET 3 CMAQ No Projects Programmed $ $ CMAQ Subtotal ► $ 1,393,611 $ - $ 1,393,611 $ 1,114,889 $ - $ 1,114,889 $ ►TAP - Transportation Alternatives Program 605651 Montachusett Leominster LEOMINSTERRECONSTRUCTION ON ROUTE 13, FROM HAWES STREET TO PROSPECT STREET 3 TAP No Projects Programmed $ $ TAP Subtotal ► $ 97,450 $ - $ 97,450 $ 77,960 $ - $ 77,960 $ HSIP/CMAQ/TAP/STP; Total Cost = $3,741,288 Adjusted for YOE by 8%; Non Adjusted Total Cost = $3,459,031 (as of 6/17/15); 44,596 Construction; TEC 61 of 100; 25% Design; Cost includes utilites; AQ analysis shows positive impact 44,596 ◄ 90% Federal + 10% Non-Federal HSIP/CMAQ/TAP/STP; Total Cost = $3,741,288 Adjusted for YOE by 8%; Non Adjusted Total Cost = $3,459,031 (as of 6/17/15); 278,722 Construction; TEC 61 of 100; 25% Design; Cost includes utilites; AQ analysis shows positive impact 278,722 ◄ 80% Federal + 20% Non-Federal HSIP/CMAQ/TAP/STP; Total Cost = $3,741,288 Adjusted for YOE by 8%; Non Adjusted Total Cost = $3,459,031 (as of 6/17/15); 19,490 Construction; TEC 61 of 100; 25% Design; Cost includes utilites; AQ analysis shows positive impact 19,490 ◄ 80% Federal + 20% Non-Federal ►Non-CMAQ/HSIP/TAP (Other) 605651 607321 607252 Montachusett MPO February 17, 2016 Montachusett Montachusett Montachusett Leominster LEOMINSTERRECONSTRUCTION ON ROUTE 13, FROM HAWES STREET TO PROSPECT STREET Templeton TEMPLETON RESURFACING & RELATED WORK ON A SECTION OF ROUTE 68 FROM THE GARDNER CITY LINE TO THE END OF STATE HIGHWAY (2.0 MILES) Gardner GARDNER RESURFACING & RELATED WORK ON MATTHEW STREET 3 2 3 STP STP STP Page 1 of 4 $ $ $ 1,804,272 $ 2,087,488 $ 865,280 $ 1,443,418 $ HSIP/CMAQ/TAP/STP; Total Cost = $3,741,288 Adjusted for YOE by 8%; Non Adjusted Total Cost = $3,459,031 (as of 6/17/15); 360,854 Construction; TEC 61 of 100; 25% Design; Cost includes utilites; AQ analysis shows positive impact 1,669,990 $ 75% Received 3/5/15; Total Cost = $2,087,488 Adjusted for YOE by 8%; Non Adjusted Total Cost = $1,930,000 (as of 4/10/15); TEC 27 of 100; Construction; Originally FY 2019 - Moved Due to Fiscal Constraint Issues 692,224 $ 417,498 100% design due 4/30/15; city to design; Total Cost = $865,280 Adjusted for YOE by 8%; Non Adjusted Total Est Cost = $800,000 as of 173,056 6/17/15; TEC 11 of 100; Construction; Originally FY 2016 - Moved Due to Fiscal Constraint Issues FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2018 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ 607446 MPO ▼ Montachusett 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed Municipality Name MassDOT ▼ Project Description▼ Westminster MassDOT District ▼ WESTMINSTERINTERSECTION IMPROVEMENTS, ROUTE 2A AT ROUTE 140 3 Funding Source ▼ STP Total Programmed Funds ▼ Federal Funds ▼ Non-Federal Funds ▼ 440,640 Additional Information ▼ Total Cost = $2,203,200 Adjusted for YOE by 8%; Non Adjusted Total Cost = $2,036,982 (as of 6/3/15); Prelim Design; Est Const - Summer 2019; Consultant Design; Construction; TEC 43 of 100; $ 2,203,200 $ 1,762,560 $ Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 6,960,240 $ 5,568,192 $ Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 8,897,256 $ 6,960,240 $ 9,613,684 ◄Total Target 7,676,668 ◄ Max. NonCMAQ/HSIP/TAP $ $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 445,955 $ 1,393,611 $ 97,450 $ 445,955 ◄ Min. HSIP 1,393,611 ◄ Min. CMAQ 97,450 ◄ Min. TAP $ $ $ 1,392,048 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis 716,428 Target Funds Available 716,428 Non-CMAQ/HSIP/TAP (Other) A - HSIP Minimum Met CMAQ Minimum Met TAP Minimum Met Remaining HSIP, CMAQ, and TAP Funds $ ‐ ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - On System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Off-System 608179 Montachusett Royalston 607127 Montachusett Hubbardston ROYALSTON - BRIDGE REPLACEMENT, R-12-9, N. FITZWILLIAM ROAD OVER THE LAWRENCE BROOK HUBBARDSTON BRIDGE REPLACEMENT, H-24009, EVERGREEN ROAD OVER MASON BROOK 2 STP-BR-OFF $ 1,549,152 $ 1,239,322 $ 309,830 Cost Est as of 5/28/15; Total Cost = $1,549,152 Adjusted for YOE by 8%; Bridge Off System; Construction; 3 STP-BR-OFF $ 1,726,760 $ 1,381,408 $ 345,352 Cost Est as of 5/28/15; Total Cost = $1,726,760 Adjusted for YOE by 8%; Bridge Off System; Construction; Off-System Subtotal ► $ 3,275,912 $ 2,620,730 $ 655,182 ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid No Projects Programmed Montachusett MPO February 17, 2016 $ Page 2 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2018 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Federal Funds ▼ $ - $ - $ - Other Federal Aid Subtotal ► $ - $ - $ - No Projects Programmed Non-Federal Funds ▼ Additional Information ▼ ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - - - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program $ - $ - $ No Projects Programmed $ Statewide HSIP Program Subtotal ► $ No Projects Programmed - $ $ - $ $ - - - ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program $ - $ - $ No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ No Projects Programmed - $ $ - $ $ - - - Funding Split Varies by Funding Source - - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source ► Statewide CMAQ No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide CMAQ ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 80% Federal + 20% Non-Federal $ - $ - ◄ 90% Federal + 10% Non-Federal - - ►Statewide Transportation Enhancements No Projects Programmed $ No Projects Programmed $ Statewide Transportation Enhancements Subtotal ► $ - No Projects Programmed No Projects Programmed $ $ Statewide ITS Subtotal ► $ - No Projects Programmed $ No Projects Programmed $ Statewide Interstate Maintenance Program Subtotal ► $ - ►Statewide ITS ►Statewide Interstate Maintenance Program ►Statewide NHS Preservation Program+ AMENDMENT:Add Project 603513 Montachusett Gardner $ GARDNER SUPERSTRUCTURE REPLACEMENT, G-013 NHPP 008, PLEASANT STREET OVER THE B&M RAILROAD No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ 4,404,240 3,523,392 880,848 Added Project to FFY 2018 2/17/2016; Prior Appendix Project. 4,404,240 $ 3,523,392 $ 880,848 ◄ 80% Federal + 20% Non-Federal ►Statewide RR Grade Crossings No Projects Programmed $ No Projects Programmed $ Statewide RR Grade Crossings Subtotal ► $ Montachusett MPO February 17, 2016 Page 3 of 4 - $ - $ - ◄ 80% Federal + 20% Non-Federal FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2018 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Federal Funds ▼ Non-Federal Funds ▼ Additional Information ▼ ►Statewide Stormwater Retrofits No Projects Programmed $ No Projects Programmed $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - $ - ◄ 80% Federal + 20% Non-Federal ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ - - - $ - - - Other Statewide Items Subtotal ► $ - NFA $ NFA $ Non-Federal Aid Subtotal► $ No Projects Programmed NFA $ No Projects Programmed NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ ►Statewide ADA Implementation Plan ►Other Statewide Items $ - $ - ◄ Funding Split Varies by Funding Source - $ $ $ - ◄100% Non-Federal - $ $ $ - ◄100% Non-Federal ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2018 TIP Section 1: ▼ MONTACHUSETT MPO TIP Summary Total ► $ Federal Funds ► $ Non-Federal Funds ► $ TIP Section 2: ▼ 16,577,408 $ 13,306,522 3,270,886 $ Total of All Projects ▼ - $ $ $ 16,577,408 ◄ Total Spending in Region 13,306,522 ◄ Total Federal Spending in Region 3,270,886 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx Montachusett MPO February 17, 2016 Page 4 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2019 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed Municipality Name MassDOT ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Additional Non-Federal Funds ▼ Information ▼ Federal Funds ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 604499 Montachusett Leominster LEOMINSTERRECONSTRUCTION/RE HABILITATION ON ROUTE 12 (CENTRAL STREET), INCLUDING REHABILITATION OF L08-022 3 HSIP No Projects Programmed $ $ HSIP Subtotal ► $ 445,955 $ - $ 445,955 $ 401,360 401,360 $ 44,596 $ $ STP/HSIP/TAP/CMAQ Possible; Total Cost = $9,392,614 Adjusted for YOE by 12%; Non Adjusted Total Cost = $8,350,000 as of 6/3/15; Preliminary Design; Construction; If Widening Involved Likely CMAQ; HSIP within Limits; TEC 36 of 100. 44,596 ◄ 90% Federal + 10% Non-Federal ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 604499 Montachusett Leominster LEOMINSTERRECONSTRUCTION/RE HABILITATION ON ROUTE 12 (CENTRAL STREET), INCLUDING REHABILITATION OF L08-022 3 CMAQ No Projects Programmed $ $ CMAQ Subtotal ► $ 1,393,611 $ - $ 1,393,611 $ 1,114,889 1,114,889 $ 278,722 $ $ STP/HSIP/TAP/CMAQ Possible; Total Cost = $9,392,614 Adjusted for YOE by 12%; Non Adjusted Total Cost = $8,350,000 as of 6/3/15; Preliminary Design; Construction; If Widening Involved Likely CMAQ; HSIP within Limits; TEC 36 of 100. 278,722 ◄ 80% Federal + 20% Non-Federal ►TAP - Transportation Alternatives Program 604499 Montachusett Leominster LEOMINSTERRECONSTRUCTION/RE HABILITATION ON ROUTE 12 (CENTRAL STREET), INCLUDING REHABILITATION OF L08-022 3 TAP No Projects Programmed $ $ TAP Subtotal ► $ 74,990 $ - $ 74,990 $ 59,992 59,992 $ 14,998 $ $ STP/HSIP/TAP/CMAQ Possible; Total Cost = $9,392,614 Adjusted for YOE by 12%; Non Adjusted Total Cost = $8,350,000 as of 6/3/15; Preliminary Design; Construction; If Widening Involved Likely CMAQ; HSIP within Limits; TEC 36 of 100. 14,998 ◄ 80% Federal + 20% Non-Federal ►Non-CMAQ/HSIP/TAP (Other) 604499 Montachusett Leominster LEOMINSTERRECONSTRUCTION/RE HABILITATION ON ROUTE 12 (CENTRAL STREET), INCLUDING REHABILITATION OF L08-022 3 STP STP/HSIP/TAP/CMAQ Possible; Total Cost = $9,392,614 Adjusted for YOE by 12%; Non Adjusted Total Cost = $8,350,000 as of 6/3/15; Preliminary Design; Construction; If Widening Involved Likely CMAQ; HSIP within Limits; TEC 36 of 100. $ 7,478,058 $ 5,982,446 $ 1,495,612 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ $ $ 7,478,058 $ 5,982,446 $ $ $ 1,495,612 ◄ 80% Federal + 20% Non-Federal Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 9,392,614 $ 7,478,058 $ 9,613,684 ◄Total Target 7,699,128 ◄ Max. NonCMAQ/HSIP/TAP Total HSIP Programmed ► $ 445,955 $ ►Section 1A / Fiscal Constraint Analysis Montachusett MPO February 17, 2016 Page 1 of 4 445,955 ◄ Min. HSIP $ $ $ 221,070 Target Funds Available 221,070 Non-CMAQ/HSIP/TAP (Other) A - HSIP Minimum Met FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2019 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed Municipality Name MassDOT ▼ Project Description▼ MassDOT District ▼ Funding Source ▼ Total Programmed Funds ▼ Total CMAQ Programmed ► $ Total TAP Programmed ► $ Additional Non-Federal Funds ▼ Information ▼ Federal Funds ▼ 1,393,611 $ 74,990 $ 1,393,611 ◄ Min. CMAQ 74,990 ◄ Min. TAP $ $ - CMAQ Minimum Met TAP Minimum Met Remaining HSIP, CMAQ, and TAP Funds $ ‐ ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - - ◄ 80% Federal + 20% Non-Federal ►On System No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - On System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Off-System ADJUSTMENT:Change Project ID 608260 Montachusett Athol ATHOL - BRIDGE REPLACEMENT, A-15-5, WASHINGTON AVE OVER SOUTH ATHOL POND OUTLET 608259 Montachusett Townsend TOWNSEND - BRIDGE REPLACEMENT, T-7-13, WEST MEADOW ROAD OVER LOCKE BROOK 2 STP-BR-OFF $ 4,347,840 $ 3,478,272 $ 869,568 Change Project ID from BR1903 to 608260; Cost Est as of 5/28/15; Total Cost = $4,347,840 Adjusted for YOE by 12%; Bridge Off System; Construction; 3 STP-BR-OFF $ 3,100,138 $ 2,480,110 $ 620,028 Cost Est as of 5/28/15; Total Cost = $3,100,138 Adjusted for YOE by 12%; Bridge Off System; Construction; Off-System Subtotal ► $ 7,447,978 $ 5,958,382 $ 1,489,596 ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed $ - $ - $ No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - $ - $ - $ - $ - $ - $ - Other Federal Aid Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid No Projects Programmed No Projects Programmed ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - - - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program Montachusett MPO February 17, 2016 Page 2 of 4 FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2019 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed MassDOT District ▼ Funding Source ▼ No Projects Programmed Total Programmed Funds ▼ Additional Non-Federal Funds ▼ Information ▼ Federal Funds ▼ $ - $ - $ No Projects Programmed $ Statewide HSIP Program Subtotal ► $ - $ $ - $ $ - - - ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed ► Statewide CMAQ 608193 Montachusett Multiple $ - $ - $ No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ - $ $ - $ $ FITCHBURG LEOMINSTER - RAIL TRAIL CONSTRUCTION (TWIN CITIES RAIL TRAIL) No Projects Programmed 3 CMAQ $ $ Statewide CMAQ ► $ - - - Funding Split Varies by Funding Source - - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source $ 9,313,874 $ 2,328,468 Statewide CMAQ - New Listing as of 5/22/2015 $ 11,642,342 $ 9,313,874 $ $ 2,328,468 ◄ 80% Federal + 20% Non-Federal 11,642,342 ►Statewide Transportation Enhancements No Projects Programmed $ No Projects Programmed $ Statewide Transportation Enhancements Subtotal ► $ - No Projects Programmed No Projects Programmed $ $ Statewide ITS Subtotal ► $ - No Projects Programmed $ No Projects Programmed $ Statewide Interstate Maintenance Program Subtotal ► $ - No Projects Programmed $ No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ - No Projects Programmed $ No Projects Programmed $ Statewide RR Grade Crossings Subtotal ► $ - No Projects Programmed $ No Projects Programmed $ Statewide Stormwater Retrofits Subtotal ► $ - No Projects Programmed $ No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. - $ - $ - $ - $ - $ - $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 90% Federal + 10% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal $ - ◄ 80% Federal + 20% Non-Federal ►Statewide ITS ►Statewide Interstate Maintenance Program ►Statewide NHS Preservation Program+ ►Statewide RR Grade Crossings ►Statewide Stormwater Retrofits ►Statewide ADA Implementation Plan ►Other Statewide Items Montachusett MPO February 17, 2016 $ $ Page 3 of 4 - - FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2019 MONTACHUSETT MPO Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name MassDOT ▼ Project Description▼ 6/22/2015 Draft Released AMEND/ADJUST No. 1 1/15/2016 Draft Released 7/30/2015 Endorsed 2/17/2016 Endorsed MassDOT District ▼ Funding Source ▼ DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails Total Programmed Funds ▼ Additional Non-Federal Funds ▼ Information ▼ Federal Funds ▼ $ - - - $ $ - - - $ - - - Other Statewide Items Subtotal ► $ - NFA $ NFA $ Non-Federal Aid Subtotal► $ No Projects Programmed NFA $ No Projects Programmed NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ $ - $ - ◄ Funding Split Varies by Funding Source - $ $ $ - ◄100% Non-Federal - $ $ $ - ◄100% Non-Federal ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2019 TIP Section 1: ▼ MONTACHUSETT MPO TIP Summary Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Montachusett MPO February 17, 2016 Page 4 of 4 TIP Section 2: ▼ 28,482,934 $ 22,830,943 5,651,991 $ Total of All Projects ▼ - $ $ $ 28,482,934 ◄ Total Spending in Region 22,830,943 ◄ Total Federal Spending in Region 5,651,991 ◄ Total Non-Federal Spending in Region FFY 2016-2019 TIP MPO ENDORSED Amendment No. 1 2016 Northern Middlesex Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ 06/23/2015 Draft Released 07/23/2015 Endorsed MassDOT Project Description▼ MassDOT District ▼ Funding Source ▼ Non-Federal Funds Additional ▼ Information ▼ Total Programmed Funds ▼ Federal Funds ▼ $ - $ - $ - HSIP Subtotal ► $ - $ - $ - ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program No Projects Programmed ◄ 90% Federal + 10% Non-Federal ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 607251 Northern Middlesex Westford WESTFORDINTERSECTION & SIGNAL IMPROVEMENTS @ ROUTE 110 & TADMUCK RD 3 CMAQ Total Project Cost Estimate = $3,200,000; CMAQ, TAP; TEC = 6.50; Construction $ 2,781,640 $ 2,225,312 $ 556,328 CMAQ Subtotal ► $ 2,781,640 $ 2,225,312 $ 556,328 ◄ 80% Federal + 20% Non-Federal $ 418,360 $ 334,688 $ 83,672 TAP Subtotal ► $ 418,360 $ 334,688 $ 83,672 ◄ 80% Federal + 20% Non-Federal $ 2,976,437 $ 2,381,150 $ AC Year 2 of 2 Total Project Cost $6,688,616; 595,287 Funding Sources CMAQ, TAP, STP; TEC = 5.52; Construction Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 2,976,437 $ 2,381,150 $ 595,287 ◄ 80% Federal + 20% Non-Federal Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 6,176,437 $ 2,976,437 $ 6,825,200 ◄Total Target 6,496,651 ◄ Max. NonCMAQ/HSIP/TAP $ $ 648,763 Target Funds Available 2,251,703 Non-CMAQ/HSIP/TAP (Other) Available Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ $ 2,781,640 $ 418,360 $ 390,961 ◄ Min. HSIP 1,221,753 ◄ Min. CMAQ 318,775 ◄ Min. TAP $ $ $ 390,961 HSIP Minimum Not Met (1,559,887) CMAQ Minimum Met (99,585) TAP Requirement Exceeded! ►TAP - Transportation Alternatives Program 607251 Northern Middlesex Westford WESTFORDINTERSECTION & SIGNAL IMPROVEMENTS @ ROUTE 110 & TADMUCK RD 3 TAP Total Project Cost Estimate = $3,200,000; CMAQ, TAP; TEC = 6.50; Construction ►Non-CMAQ/HSIP/TAP (Other) 601426 Northern Middlesex Billerica BILLERICA RECONSTRUCTION OF ALLEN RD, FROM RTE 3A TO WEBB BROOK RD (5,400 FEET) 4 STP ►Section 1A / Fiscal Constraint Analysis HSIP, CMAQ, TAP Overprogrammed $ (1,268,511) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►On System 602932 Northern Middlesex Lowell LOWELL- BRIDGE REPLACEMENT, L-15-058, VFW HIGHWAY OVER BEAVER BROOK (BR-ON) 4 NHPP $ 6,917,805 $ 5,534,244 $ 1,383,561 AC Year 2 of 2. Total Cost $20,934,881 On System Subtotal ► $ 6,917,805 $ 5,534,244 $ 1,383,561 ◄ 80% Federal + 20% Non-Federal ►Off-System $ - $ - $ - Off-System Subtotal ► $ - $ - $ - $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - No Projects Programmed ◄ 80% Federal + 20% Non-Federal ► Statewide Bridge Inspection Program No Projects Programmed ◄ 80% Federal + 20% Non-Federal ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid AMENDMENT:Add Project AMENDMENT:Add Project FLAP01 608420 Northern Middlesex Northern Middlesex Lowell Lowell MERRIMACK RIVERWALK PHASE II FLAP PROJECT LOWELL CANAL BRIDGES Reprogramming of FLAP award from FFY 2015 4 4 Other FA Other FA $ 293,311 $ 235,000 $ $ 16,737,188 $ 13,389,750 $ Other Federal Aid Subtotal ► $ 17,030,499 $ 13,624,750 $ 58,311 Tiger Grant award - non federal match includes $760,000 from Enel, $2,000,000 from Umass Lowell, and $587,438 from the City of Lowell. 3,347,438 Design estimate: $1,162,500. Construction: $15,574,688 3,405,749 ◄ Funding Split Varies by Funding Source ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program AMENDMENT:Add Project 607752 Northern Middlesex Lowell LOWELL-INTERSECTION & SIGNAL IMPROVEMENTS AT 2 LOCATIONS: SR 113 (VARNUM AVENUE & VFW HIGHWAY) AT MAMMOTH ROAD & VFW AT AIKEN STREET $ 1,100,000 $ 990,000 $ 110,000 Add Project Statewide HSIP Program Subtotal ► $ 1,100,000 $ 990,000 $ 110,000 ◄ 90% Federal + 10% Non-Federal 4 HSIP ► Statewide Safe Routes to Schools Program - Funding Split Varies by Funding Source ◄ Funding Split Varies by Funding Source $ $ - - $ $ - $ - $ - ◄ 80% Federal + 20% Non-Federal - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ Statewide Interstate Maintenance Program Subtotal ► $ - $ - $ - ◄ 90% Federal + 10% Non-Federal No Projects Programmed $ Statewide NHS Preservation Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed - - - $ $ - - $ $ No Projects Programmed $ Statewide Transportation Enhancements Subtotal ► $ - No Projects Programmed $ Statewide ITS Subtotal ► $ No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ - ► Statewide CMAQ No Projects Programmed $ Statewide CMAQ ► $ - - ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements ►Statewide ITS ►Statewide Interstate Maintenance Program ►Statewide NHS Preservation Program+ ►Statewide RR Grade Crossings $ - - Statewide RR Grade Crossings Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ Statewide ADA Implementation Plan Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails - ►Statewide Stormwater Retrofits ►Statewide ADA Implementation Plan ►Other Statewide Items $ $ - - $ - - - $ $ - - - $ Other Statewide Items Subtotal ► $ - NFA $ NFA $ Non-Federal Aid Subtotal► $ No Projects Programmed NFA $ No Projects Programmed NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ $ - ◄ Funding Split Varies by Funding Source - $ $ $ - ◄100% Non-Federal - $ $ $ - ◄100% Non-Federal $ - ►Section 2A / Non-Federal Projects ►Non Federal Aid No Projects Programmed No Projects Programmed ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2016 Northern Middlesex TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Total of All Projects ▼ TIP Section 2: ▼ 31,224,741 $ 25,090,144 6,134,597 $ - $ $ $ 31,224,741 ◄ Total Spending in Region 25,090,144 ◄ Total Federal Spending in Region 6,134,597 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx 2017 Northern Middlesex Transportation Improvement Program Amendment/Adjustment Type ▼ MassDOT Project ID ▼ MPO ▼ Municipality Name ▼ 06/23/2015 Draft Released 07/23/2015 Endorsed MassDOT Project Description▼ MassDOT District ▼ Funding Source Total Programmed ▼ Funds ▼ Non-Federal Funds ▼ Federal Funds ▼ Additional Information ▼ ►Section 1A / Federal Aid Target Projects ►HSIP - Highway Safety Improvement Program 608036 Northern Middlesex Westford WESTFORD-TRAFFIC SIGNAL INSTALLATIONS AND INTERSECTION IMPROVEMENTS AT RTE 40 AND OAK HILL RD 3 HSIP $ 858,870 $ 772,983 $ 85,887 606189 Northern Middlesex Lowell LOWELL-IMPROVEMENTS ON ROUTE 38 AT FOUR INTERSECTIONS 4 HSIP $ 2,426,825 $ 2,184,143 $ 242,683 HSIP Subtotal ► $ 3,285,695 $ 2,957,126 $ 328,570 ◄ 90% Federal + 10% Non-Federal CMAQ $ 1,221,753 $ 977,402 $ 244,351 CMAQ Subtotal ► $ 1,221,753 $ 977,402 $ 244,351 ◄ 80% Federal + 20% Non-Federal $ 318,775 $ 255,020 $ TAP Subtotal ► $ 318,775 $ 255,020 $ Total Project Cost at 2017 YOE $2,080,623 ($2,000,599); Funding Sources - HSIP, CMAQ; TEC = 6.77 Total Project Cost at 2017 YOE $2,745,600 (2,640,000) Funding Sources HSIP, TAP; TEC = 6.25. ►CMAQ - Congestion Mitigation and Air Quality Improvement Program 608036 Northern Middlesex Westford WESTFORD-TRAFFIC SIGNAL INSTALLATIONS AND INTERSECTION IMPROVEMENTS AT RTE 40 AND OAK HILL RD 3 Total Project Cost at 2017 YOE $2,080,623 ($2,000,599); Funding Sources - HSIP, CMAQ; TEC = 6.77 ►TAP - Transportation Alternatives Program 606189 Northern Middlesex Lowell LOWELL-IMPROVEMENTS ON ROUTE 38 AT FOUR INTERSECTIONS 4 TAP Total Project Cost at 2017 YOE $2,745,600 (2,640,000) Funding Sources HSIP, TAP; TEC = 6.25. 63,755 ◄ 80% Federal + 20% Non-Federal 63,755 ►Non-CMAQ/HSIP/TAP (Other) 29492 Northern Middlesex Billerica BEDFORD-BILLERICA-BURLINGTONMIDDLESEX TURNPIKE IMPROVEMENTS FROM CROSBY DRIVE NORTH TO MANNING ROAD, INCLUDES RECONSTRUCTION OF B04-006 4 STP $ 1,000,000 $ 800,000 $ 200,000 The balance of the project is programmed in the Boston MPO TIP in 2016 and 2017. Total project cost estimate is $26,935,171. NMMPO is funding $1,000,000 in STP funds. Design is at 100%. TEC Score = 7.50. 604694 Northern Middlesex Lowell LOWELL-CONNECTOR RECONSTRUCTION FROM THORNDIKE ST TO GORHAM ST 4 STP $ 1,030,652 $ 824,522 $ 206,130 Total project cost at FFY 2017 YOE $1,030,652 ($991,011; Funding Source STP; TEC = 5.72. 607401 Northern Middlesex Chelmsford CHELMSFORD-TRAFFIC SIGNAL INSTALLATION AT ROUTE 110 & ROUTE 495 (2 LOCATIONS) 4 STP $ 1,219,400 $ 975,520 $ 243,880 Total Project Cost at 2016 YOE $1,219,400 ($1,172,500); Funding : STP; TEC = 5.82 Non-CMAQ/HSIP/TAP (Other) Subtotal ► $ 3,250,052 $ 2,600,042 $ Total Federal Aid Target Funds Programmed ► $ Total Non-CMAQ/HSIP/TAP (Other) Programmed ► $ 8,076,275 $ 3,250,052 $ 8,076,275 ◄Total Target 6,144,787 ◄ Max. NonCMAQ/HSIP/TAP $ $ Total HSIP Programmed ► $ Total CMAQ Programmed ► $ Total TAP Programmed ► $ 3,285,695 $ 1,221,753 $ 318,775 $ 390,961 ◄ Min. HSIP 1,221,753 ◄ Min. CMAQ 318,775 ◄ Min. TAP $ $ $ 650,010 ◄ 80% Federal + 20% Non-Federal ►Section 1A / Fiscal Constraint Analysis - Target Funds Available 1 Non-CMAQ/HSIP/TAP (Other) Available (2,894,734) HSIP Minimum Met - CMAQ Minimum Met - TAP Minimum Met HSIP, CMAQ, TAP Overprogrammed $ (2,894,734) ►Section 1B / Federal Aid Bridge Projects ►Statewide Bridge Maintenance Program No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Statewide Bridge Maintenance Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►On System AMENDMENT:Add Project 607506 Northern Middlesex Chelmsford CHELMSFORD- BRIDGE DECK REPLACEMENT, C-08-037, ST 4 NORTH STREET OVER I-495 No Projects Programmed 4 NHPP $ $ On System Subtotal ► $ 2,400,000 $ - $ 2,400,000 $ 1,920,000 $ - $ 1,920,000 $ 480,000 Add Project 480,000 ◄ 80% Federal + 20% Non-Federal ►Off-System No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Off-System Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Statewide Bridge Inspection Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal No Projects Programmed $ - $ - $ - No Projects Programmed $ - $ - $ - Other Federal Aid Subtotal ► $ - $ - $ - ◄ Funding Split Varies by Funding Source ► Statewide Bridge Inspection Program ►Section 1C / Federal Aid Non-Target Projects ►Other Federal Aid ►Section 1D / Federal Aid Major & State Category Projects ► Statewide Infrastructure Program No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide Infrastructure Program Subtotal ► $ - $ $ - $ $ - - - ◄ 80% Federal + 20% Non-Federal ► Statewide HSIP Program No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide HSIP Program Subtotal ► $ - $ $ - $ $ - - - ◄ 90% Federal + 10% Non-Federal ► Statewide Safe Routes to Schools Program No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide Safe Routes to Schools Program Subtotal ► $ - $ $ - $ $ - - - Funding Split Varies by Funding Source - Funding Split Varies by Funding Source - ◄ Funding Split Varies by Funding Source ► Statewide CMAQ No Projects Programmed $ - $ - $ No Projects Programmed $ Statewide CMAQ ► $ - - - $ $ - $ $ - $ $ Statewide Transportation Enhancements Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ $ Statewide ITS Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ $ Statewide Interstate Maintenance Program Subtotal ► $ - $ - $ - ◄ 90% Federal + 10% Non-Federal $ $ - - - - ◄ 80% Federal + 20% Non-Federal ►Statewide Transportation Enhancements No Projects Programmed No Projects Programmed ►Statewide ITS No Projects Programmed No Projects Programmed ►Statewide Interstate Maintenance Program No Projects Programmed No Projects Programmed ►Statewide NHS Preservation Program+ No Projects Programmed No Projects Programmed Statewide NHS Preservation Program Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ $ Statewide RR Grade Crossings Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ $ Statewide Stormwater Retrofits Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal $ $ Statewide ADA Implementation Plan Subtotal ► $ - $ - $ - ◄ 80% Federal + 20% Non-Federal ►Statewide RR Grade Crossings No Projects Programmed No Projects Programmed ►Statewide Stormwater Retrofits No Projects Programmed No Projects Programmed ►Statewide ADA Implementation Plan No Projects Programmed No Projects Programmed ►Other Statewide Items ABP GANS Repayment Award Adjustments, Change Orders, Project Value Changes, Etc. DBEs, FAPO, Pavement Lab Retrofits, and Misc. Programs Planning Statewide Design and Right of Way Statewide Recreational Trails $ $ - - - $ - - - $ $ $ Other Statewide Items Subtotal ► $ - - $ - ◄ Funding Split Varies by Funding Source No Projects Programmed No Projects Programmed NFA $ NFA $ Non-Federal Aid Subtotal► $ - $ $ $ - ◄100% Non-Federal No Projects Programmed No Projects Programmed NFA $ NFA $ Section 2B / Non-Federal Bridge Projects Subtotal► $ - $ $ $ - ◄100% Non-Federal $ ►Section 2A / Non-Federal Projects ►Non Federal Aid ►Section 2B / Non-Federal Bridge Projects ►Section 2B / Non-Federal Bridge Projects 2017 Northern Middlesex TIP Summary TIP Section 1: ▼ Total ► $ Federal Funds ► $ Non-Federal Funds ► $ Total of All Projects ▼ TIP Section 2: ▼ 10,476,275 $ 8,709,590 1,766,686 $ - $ $ $ 10,476,275 ◄ Total Spending in Region 8,709,590 ◄ Total Federal Spending in Region 1,766,686 ◄ Total Non-Federal Spending in Region 701 CMR 7.00 Use of Road Flaggers and Police Details on Public Works Projects / 701 CMR 7.00 (the Regulation) was promulgated and became law on October 3, 2008. Under this Regulation, the CMR is applicable to any Public works Project that is performed within the limits of, or that impact traffic on, any Public Road. The Municipal Limitation referenced in this Regulation is applicable only to projects where the Municipality is the Awarding Authority. For all projects contained in the TIP, the Commonwealth is the Awarding Authority. Therefore, all projects must be considered and implemented in accordance with 701 CMR 7.00, and the Road Flagger and Police Detail Guidelines. By placing a project on the TIP, the Municipality acknowledges that 701 CMR 7.00 is applicable to its project and design and construction will be fully compliant with this Regulation. This information, and additional information relative to guidance and implementation of the Regulation can be found at the following link on the MassDOT Highway Division website: http://www.massdot.state.ma.us/Highway/flaggers/main.aspx FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2016 I ANTICIPATED NET APPORTIONMENTS OF FEDERAL FUNDS FUNDING CATEGORY II ACTUAL CARRYOVER BALANCE III IV ANTICIPATED TRANSFER TOTAL FUNDS AVAILABLE OF FUNDS (10/1) SUBJECT TO OBLIGATION AUTHORITY V PROGRAMMED OBLIGATIONS STIP 2016-2019, Rev003 VI ESTIMATED BALANCE REMAINING NET CHANGE IN PROGRAMMED OBLIGATIONS CODE NATIONAL HIGHWAY PERFORMANCE NATIONAL HIGHWAY FREIGHT PROGRAM STP FLEX BRIDGE-OFF SYSTEM $310,658,805 $3,382,446 $20,000,000 $334,041,251 $301,471,935 $32,569,315 ($9,175,680) $17,218,352 $46,285,895 $0 $18,025,072 $0 ($25,000,000) $17,218,352 $39,310,967 $0 $26,447,901 $17,218,352 $12,863,066 $0 ($561,600) $28,456,838 $69,816,594 $98,273,432 $28,430,389 $69,843,043 ($1,444,640) $41,444,577 $117,239,654 $73,885,118 $43,354,536 ($561,600) $47,372,093 $9,870,574 $57,242,667 $44,749,423 $12,493,244 $0 -BARNSTABLE URBAN AREA $2,858,926 $8,956,415 $11,815,341 $2,433,693 $9,381,648 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $6,160,537 $4,524,073 $10,684,610 $8,928,129 $1,756,480 $0 -WORCESTER URBAN AREA $5,256,568 $9,147,566 $14,404,134 $7,527,756 $6,876,378 $0 -PROVIDENCE, PAWTUCKET $3,016,315 $8,859,586 $11,875,901 $0 $11,875,901 $0 STP NON-FLEX $75,795,077 -BOSTON URBAN AREA -OTHER AREAS (RURAL & SMALL URBAN) STP-ENHANCEMENT SAFE ROUTES TO SCHOOLS PGM. RECREATIONAL TRAILS $11,130,638 $86,363 $0 $31,015,281 $0 $11,217,001 $10,246,117 $970,884 $0 $31,015,281 $10,679,014 $20,336,267 $1,808,400 $0 $675,394 $675,394 $0 $675,394 $0 $1,186,729 $4,315,112 $5,501,841 $1,172,512 $4,329,329 $0 TAP FLEX $5,376,538 $14,905,289 $20,281,827 $1,354,300 $18,927,527 $0 TAP NON-FLEX $5,370,529 $5,043,312 $10,413,841 $8,438,946 $1,974,895 $0 $3,356,593 $1,717,569 $5,074,162 $5,005,831 $68,331 $0 -BARNSTABLE URBAN AREA $202,572 $449,639 $652,211 $647,929 $4,282 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $436,510 $907,928 $1,344,438 $758,302 $586,136 $0 -WORCESTER URBAN AREA $372,459 $856,851 $1,229,310 $802,384 $426,926 $0 -PROVIDENCE, PAWTUCKET $213,724 $624,718 $838,442 $0 $838,442 $0 -BOSTON URBAN AREA -OTHER AREAS (RURAL & SMALL URBAN) $0 $788,671 $486,607 $29,071,004 $2,677,777 HSIP - High Risk Rural $2,273,676 $5,304,843 RLWY/HWY CROSSINGS- HAZARD ELIMINATION $1,923,582 $7,602,143 $0 RLWY/HWY CROSSINGS- PROTECTIVE DEVICES $1,923,583 $4,396,236 CMAQ $61,911,071 $16,775,885 PLANNING HWY SAFETY IMPROVEMENT PGM. $1,275,278 $1,224,500 $50,778 $0 $36,748,781 $33,369,362 $3,379,418 ($2,700,000) $7,578,519 $3,375,000 $4,203,519 ($1,350,000) $9,525,725 $3,400,000 $6,125,725 $0 $0 $6,319,819 $3,400,000 $2,919,819 $0 $0 $78,686,956 $60,934,684 $17,752,272 $0 $0 $5,000,000 $21,017,168 $40,426,473 $61,443,641 $24,470,263 $36,973,378 -METROPOLITAN PLANNING PROGRAM $8,951,863 $13,752,849 $22,704,712 $7,860,021 $14,844,691 $0 -STATEWIDE PLANNING $9,048,979 $19,688,930 $28,737,909 $13,010,242 $15,727,667 $0 -STATEWIDE RESEARCH FEDERAL AID SUB-TOTAL: Federal Aid Programming and Reimbursement Office March 11, 2016 $3,016,326 $6,984,694 $608,468,847 $265,806,434 $0 $10,001,020 $3,600,000 $6,401,020 $0 $874,275,281 $580,829,425 $293,445,856 ($13,985,120) FEDERAL O/A GUIDANCE $600,000,000 Page 1 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2016 HIGH PRIORITY PROJECTS FERRY BOAT DESC SECTION 115 PROJECTS SECTION 117 PROJECTS SECTION 125 PROJECTS MISCELLANEOUS / OTHER / UNDETERMINED FEDERAL AID TOTAL > STIP 2016-2019, Rev003 $14,111,586 $123,599,708 $137,711,294 $137,711,294 $0 $778,520 $0 $778,520 $0 $0 $208,000 $0 $778,520 $0 $0 $0 $230,852 $230,852 $0 $230,852 $4,142,809 $4,142,809 $0 $4,142,809 $0 $22,097,595 $46,641,080 $68,738,675 $24,675,329 $44,063,346 $13,624,750 $630,566,442 $455,310,989 $1,085,877,431 $619,616,340 $466,261,091 ($152,370) $0 STATE MATCH FOR FEDERAL AID $129,998,639 NON-FEDERAL AID + FEDERAL AID TOTAL > $749,614,979 NOTES: MISCELLANEOUS / OTHER / UNDETERMINED Apportionment Includes estimated NHPP Exempt and Lowell Tiger Grant funds. Federal Aid Programming and Reimbursement Office March 11, 2016 Page 2 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2017 I ANTICIPATED NET APPORTIONMENTS OF FEDERAL FUNDS FUNDING CATEGORY NATIONAL HIGHWAY PERFORMANCE II ESTIMATED CARRYOVER BALANCE III ANTICIPATED TRANSFER OF FUNDS IV TOTAL FUNDS AVAILABLE (10/1) SUBJECT TO OBLIGATION AUTHORITY V PROGRAMMED OBLIGATIONS STIP 2016-2019, Rev003 VI ESTIMATED BALANCE REMAINING NET CHANGE IN PROGRAMMED OBLIGATIONS $324,867,908 $32,569,315 ($11,600,000) $345,837,223 $260,486,198 $85,351,024 $1,046,527 STP FLEX $16,805,845 $44,863,304 $17,218,352 $12,863,066 $0 $0 $34,024,197 $57,726,370 $0 $33,988,614 $34,024,197 $23,737,756 $0 ($561,600) BRIDGE-OFF SYSTEM $28,456,838 $69,843,043 $98,299,881 $28,833,230 $69,466,651 $0 STP NON-FLEX $79,245,428 $43,354,536 $122,599,964 $89,491,716 $33,108,248 ($561,600) NATIONAL HIGHWAY FREIGHT PROGRAM -BOSTON URBAN AREA $49,528,570 $12,493,244 $62,021,814 $50,063,118 $11,958,696 $0 -BARNSTABLE URBAN AREA $2,989,071 $9,381,648 $12,370,719 $11,970,170 $400,549 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $6,440,978 $1,756,480 $8,197,458 $8,172,661 $24,797 $0 -WORCESTER URBAN AREA $5,495,857 $6,876,378 $12,372,235 $9,242,688 $3,129,547 $0 $0 -PROVIDENCE, PAWTUCKET -OTHER AREAS (RURAL & SMALL URBAN) STP-ENHANCEMENT SAFE ROUTES TO SCHOOLS PGM. $3,153,624 $11,875,901 $15,029,525 $0 $15,029,525 $11,637,328 $970,884 $12,608,212 $10,043,079 $2,565,133 $0 $0 $20,336,267 $20,336,267 $11,301,402 $9,034,865 $956,812 $0 $0 $675,394 $675,394 $0 $675,394 $0 RECREATIONAL TRAILS $1,186,729 $4,329,329 $5,516,058 $800,000 $4,716,058 $0 TAP FLEX $5,376,538 $18,927,527 $24,304,065 $4,433,551 $19,870,514 $0 TAP NON-FLEX $5,370,529 $1,974,895 $7,345,424 $5,118,990 $2,226,434 $0 $3,356,593 $68,331 $3,424,924 $3,289,996 $134,928 $0 -BARNSTABLE URBAN AREA $202,572 $4,282 $206,854 $197,867 $8,987 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $436,510 $586,136 $1,022,646 $492,711 $529,935 $0 -WORCESTER URBAN AREA $372,459 $426,926 $799,385 $443,456 $355,929 $0 -PROVIDENCE, PAWTUCKET $213,724 $838,442 $1,052,166 $617,000 $435,166 $0 -OTHER AREAS (RURAL & SMALL URBAN) $788,671 $50,778 $839,449 $77,960 $761,489 $0 $44,159,545 $40,786,034 $3,373,511 $6,477,195 $0 $6,477,195 $0 $7,389,793 $4,000,000 $3,389,793 $0 -BOSTON URBAN AREA HWY SAFETY IMPROVEMENT PGM. $0 $29,780,127 $3,379,418 HSIP - High Risk Rural $2,273,676 $4,203,519 RLWY/HWY CROSSINGS- HAZARD ELIMINATION $1,264,069 $6,125,725 $0 RLWY/HWY CROSSINGS- PROTECTIVE DEVICES $11,000,000 $1,264,069 $2,919,819 $600,000 $4,783,888 $4,000,000 $783,888 $0 CMAQ $63,285,149 $17,752,272 $0 $81,037,421 $77,716,720 $3,320,701 $0 PLANNING $21,198,441 $36,973,378 $58,171,819 $24,870,263 $33,301,556 $0 $625,238,649 $293,445,856 $918,684,504 $585,826,718 $332,857,786 $880,139 FEDERAL O/A GUIDANCE $600,000,000 FEDERAL AID SUB-TOTAL: Federal Aid Programming and Reimbursement Office March 11, 2016 $0 Page 3 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2017 STIP 2016-2019, Rev003 HIGH PRIORITY PROJECTS $123,599,708 FERRY BOAT DESC SECTION 115 PROJECTS $778,520 $123,599,708 $17,316,816 $106,282,892 $0 $0 $0 ($208,000) $0 $778,520 $0 $778,520 $0 $0 SECTION 117 PROJECTS $230,852 $230,852 $0 $230,852 SECTION 125 PROJECTS $4,142,809 $4,142,809 $0 $4,142,809 $0 $8,911,921 $44,063,346 $52,975,268 $2,659,638 $50,315,630 $0 $634,150,570 $466,261,091 $1,100,411,661 $605,803,172 $494,608,488 $672,139 MISCELLANEOUS / OTHER / UNDETERMINED Lowell Tiger Grant FEDERAL AID TOTAL > $0 STATE MATCH FOR FEDERAL AID $121,415,476 NON-FEDERAL AID + FEDERAL AID TOTAL > $727,218,648 NOTES: MISCELLANEOUS / OTHER / UNDETERMINED Apportionment Includes estimated NHPP Exempt. Federal Aid Programming and Reimbursement Office March 11, 2016 Page 4 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2018 I ANTICIPATED NET APPORTIONMENTS OF FEDERAL FUNDS FUNDING CATEGORY NATIONAL HIGHWAY PERFORMANCE II ESTIMATED CARRYOVER BALANCE III ANTICIPATED TRANSFER OF FUNDS IV TOTAL FUNDS AVAILABLE (10/1) SUBJECT TO OBLIGATION AUTHORITY V PROGRAMMED OBLIGATIONS STIP 2016-2019, Rev003 VI ESTIMATED BALANCE REMAINING NET CHANGE IN PROGRAMMED OBLIGATIONS $324,867,908 $85,351,024 ($40,250,000) $369,968,932 $258,213,886 $111,755,046 $3,523,392 NATIONAL HIGHWAY FREIGHT PROGRAM STP FLEX $18,333,650 $45,021,017 $34,024,197 $23,737,756 $0 $5,000,000 $52,357,847 $73,758,773 $0 $57,552,914 $52,357,847 $16,205,859 $0 $0 BRIDGE-OFF SYSTEM $28,456,838 $69,466,651 $97,923,489 $28,844,573 $69,078,916 $0 STP NON-FLEX $82,398,579 $33,108,248 $115,506,827 $72,855,019 $42,651,808 $0 $51,576,544 $11,958,696 $63,535,240 $50,391,229 $13,144,011 $0 -BARNSTABLE URBAN AREA $2,989,071 $400,549 $3,389,620 $2,348,694 $1,040,926 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $6,707,308 $24,797 $6,732,105 $5,848,302 $883,803 $0 $0 -BOSTON URBAN AREA -WORCESTER URBAN AREA $5,723,108 $3,129,547 $8,852,655 $3,689,554 $5,163,101 -PROVIDENCE, PAWTUCKET $3,284,024 $15,029,525 $18,313,549 $0 $18,313,549 $0 $12,118,524 $2,565,133 $14,683,657 $10,577,240 $4,106,417 $0 STP-ENHANCEMENT $0 $9,034,865 $9,034,865 $4,829,600 $4,205,265 $520,000 SAFE ROUTES TO SCHOOLS PGM. RECREATIONAL TRAILS $0 $675,394 $675,394 $0 $675,394 $0 $1,186,729 $4,716,058 $5,902,787 $800,000 $5,102,787 $0 TAP FLEX $4,440,861 $19,870,514 $24,311,375 $4,769,421 $19,541,954 $0 $5,370,529 $2,226,434 $7,596,963 $4,866,773 $2,730,190 $0 $3,356,593 $134,928 $3,491,521 $3,222,212 $269,309 $0 -OTHER AREAS (RURAL & SMALL URBAN) TAP NON-FLEX -BOSTON URBAN AREA $0 $0 -BARNSTABLE URBAN AREA $202,572 $8,987 $211,559 $185,845 $25,714 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $436,510 $529,935 $966,445 $492,711 $473,734 $0 -WORCESTER URBAN AREA $372,459 $355,929 $728,388 $0 $728,388 $0 -PROVIDENCE, PAWTUCKET $213,724 $435,166 $648,890 $0 $648,890 $0 $0 -OTHER AREAS (RURAL & SMALL URBAN) $788,671 $761,489 $30,384,042 $3,373,511 HSIP - High Risk Rural $2,273,676 $6,477,195 RLWY/HWY CROSSINGS- HAZARD ELIMINATION $1,291,548 $3,389,793 HWY SAFETY IMPROVEMENT PGM. RLWY/HWY CROSSINGS- PROTECTIVE DEVICES $3,000,000 $0 $1,550,160 $966,005 $584,155 $36,757,553 $33,905,466 $2,852,087 $8,750,871 $0 $8,750,871 $0 $4,681,341 $3,400,000 $1,281,341 $0 $1,291,548 $783,888 $250,000 $2,325,436 $1,400,000 $925,436 $0 CMAQ $64,488,462 $3,320,701 $32,000,000 $99,809,163 $90,425,709 $9,383,454 $0 PLANNING $21,390,327 $33,301,556 $54,691,883 $24,870,263 $29,821,620 $0 -METROPOLITAN PLANNING PROGRAM $9,325,022 $16,117,806 $25,442,828 $7,860,021 $17,582,807 $0 -STATEWIDE PLANNING $9,048,979 $11,366,404 $20,415,383 $13,410,242 $7,005,141 $0 -STATEWIDE RESEARCH $3,016,326 $5,817,346 $8,833,672 $3,600,000 $5,233,672 $0 $631,195,713 $332,857,786 $964,053,499 $586,733,624 $377,319,875 $4,043,392 FEDERAL O/A GUIDANCE $600,000,000 FEDERAL AID SUB-TOTAL: Federal Aid Programming and Reimbursement Office March 11, 2016 $0 Page 5 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2018 STIP 2016-2019, Rev003 HIGH PRIORITY PROJECTS $0 FERRY BOAT DESC SECTION 115 PROJECTS $0 $0 $106,282,892 $106,282,892 $8,492,004 $97,790,888 $0 $778,520 $0 $778,520 $0 $0 $0 $778,520 $0 $0 SECTION 117 PROJECTS $0 $230,852 $230,852 $0 $230,852 $0 SECTION 125 PROJECTS $0 $4,142,809 $4,142,809 $0 $4,142,809 $0 $9,082,334 $50,315,630 $59,397,964 $0 $59,397,964 $0 $640,278,047 $494,608,488 $1,134,886,536 $595,225,628 $539,660,907 $4,043,392 MISCELLANEOUS / OTHER / UNDETERMINED Lowell Tiger Grant FEDERAL AID TOTAL > $0 STATE MATCH FOR FEDERAL AID $117,801,567 NON-FEDERAL AID + FEDERAL AID TOTAL > $713,027,196 NOTES: MISCELLANEOUS / OTHER / UNDETERMINED Apportionment Includes estimated NHPP Exempt. Federal Aid Programming and Reimbursement Office March 11, 2016 Page 6 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2019 I ANTICIPATED NET APPORTIONMENTS OF FEDERAL FUNDS FUNDING CATEGORY NATIONAL HIGHWAY PERFORMANCE II ESTIMATED CARRYOVER BALANCE III ANTICIPATED TRANSFER OF FUNDS IV TOTAL FUNDS AVAILABLE (10/1) SUBJECT TO OBLIGATION AUTHORITY V PROGRAMMED OBLIGATIONS STIP 2016-2019, Rev003 VI ESTIMATED BALANCE REMAINING NET CHANGE IN PROGRAMMED OBLIGATIONS $324,867,908 $111,755,046 ($52,550,000) $384,072,953 $248,342,856 $135,730,097 $1,160,678 NATIONAL HIGHWAY FREIGHT PROGRAM STP FLEX $20,625,356 $44,721,866 $52,357,847 $16,205,859 $0 $16,000,000 $72,983,203 $76,927,725 $0 $59,811,464 $72,983,203 $17,116,261 $0 $0 BRIDGE-OFF SYSTEM $28,456,838 $69,078,916 $97,535,754 $30,356,149 $67,179,605 $0 STP NON-FLEX $85,696,985 $42,651,808 $128,348,793 $69,635,735 $58,713,058 $0 $53,560,807 $13,144,011 $66,704,818 $44,441,129 $22,263,689 $0 -BARNSTABLE URBAN AREA $3,232,418 $1,040,926 $4,273,344 $0 $4,273,344 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $6,965,353 $883,803 $7,849,156 $5,860,308 $1,988,848 $0 -BOSTON URBAN AREA -WORCESTER URBAN AREA $5,943,288 $5,163,101 $11,106,389 $8,720,707 $2,385,682 $0 -PROVIDENCE, PAWTUCKET $3,410,368 $18,313,549 $21,723,917 $0 $21,723,917 $0 $16,691,168 $10,613,591 $6,077,577 $0 $4,205,265 $4,323,200 ($117,935) $0 -OTHER AREAS (RURAL & SMALL URBAN) $12,584,751 $4,106,417 STP-ENHANCEMENT $0 $4,205,265 SAFE ROUTES TO SCHOOLS PGM. RECREATIONAL TRAILS $0 $675,394 $675,394 $0 $675,394 $0 $0 $5,102,787 $5,102,787 $800,000 $4,302,787 $0 TAP FLEX $4,440,861 $19,541,954 $23,982,815 $4,755,665 $19,227,150 $0 TAP NON-FLEX $5,370,529 $2,730,190 $8,100,719 $3,500,884 $4,599,835 $0 $3,356,593 $269,309 $3,625,902 $2,235,217 $1,390,685 $0 -BOSTON URBAN AREA $0 $0 -BARNSTABLE URBAN AREA $202,572 $25,714 $228,286 $143,011 $85,275 $0 -SPRINGFIELD, CHICOPEE, HOLYOKE $436,510 $473,734 $910,244 $16,726 $893,518 $0 -WORCESTER URBAN AREA $372,459 $728,388 $1,100,847 $341,059 $759,788 $0 -PROVIDENCE, PAWTUCKET $213,724 $648,890 $862,614 $0 $862,614 $0 $0 -OTHER AREAS (RURAL & SMALL URBAN) HWY SAFETY IMPROVEMENT PGM. $788,671 $584,155 $30,975,534 $2,852,087 $9,500,000 $1,372,826 $764,871 $607,955 $43,327,621 $40,182,101 $3,145,520 HSIP - High Risk Rural $2,273,676 $8,750,871 $11,024,547 $0 $11,024,547 $0 RLWY/HWY CROSSINGS- HAZARD ELIMINATION $1,319,028 $1,281,341 $1,900,000 $4,500,369 $3,400,000 $1,100,369 $0 RLWY/HWY CROSSINGS- PROTECTIVE DEVICES $1,319,028 $925,436 $150,000 $2,394,464 $1,400,000 $994,464 $0 CMAQ $65,668,975 $9,383,454 $25,000,000 $100,052,429 $86,600,532 $13,451,897 $0 PLANNING $21,590,541 $29,821,620 $51,412,161 $24,870,263 $26,541,898 $0 -METROPOLITAN PLANNING PROGRAM $9,525,236 $17,582,807 $27,108,043 $7,860,021 $19,248,022 $0 -STATEWIDE PLANNING $9,048,979 $7,005,141 $16,054,120 $13,410,242 $2,643,878 $0 -STATEWIDE RESEARCH $3,016,326 $5,233,672 $8,249,998 $3,600,000 $4,649,998 $0 $637,327,124 $377,319,875 $1,014,647,000 $577,978,849 $436,668,151 $1,160,678 FEDERAL O/A GUIDANCE $600,000,000 FEDERAL AID SUB-TOTAL: Federal Aid Programming and Reimbursement Office March 11, 2016 $0 Page 7 of 8 FOR PLANNING AND POLICY DEVELOPMENT PURPOSES ONLY Federal Fiscal Year 2019 HIGH PRIORITY PROJECTS FERRY BOAT DESC SECTION 115 PROJECTS STIP 2016-2019, Rev003 $512,000 $97,278,888 $97,790,888 $97,790,888 $778,520 $0 $778,520 $0 $0 $0 $778,520 $0 $0 $0 SECTION 117 PROJECTS $230,852 $230,852 $0 $230,852 SECTION 125 PROJECTS $4,142,809 $4,142,809 $0 $4,142,809 $0 $8,912,881 $59,397,964 $68,310,845 $0 $68,310,845 $0 $646,240,006 $539,660,907 $1,185,900,913 $578,490,849 $607,410,064 $1,160,678 MISCELLANEOUS / OTHER / UNDETERMINED Lowell Tiger Grant FEDERAL AID TOTAL > $0 STATE MATCH FOR FEDERAL AID $110,317,880 NON-FEDERAL AID + FEDERAL AID TOTAL > $688,808,729 NOTES: MISCELLANEOUS / OTHER / UNDETERMINED Apportionment Includes estimated NHPP Exempt. Federal Aid Programming and Reimbursement Office March 11, 2016 Page 8 of 8