Capital Projects Update June 2, 2015 1

advertisement
Capital Projects Update
June 2, 2015
1
Capital Projects Update
Capital Projects
Work in Progress
2
Capital Projects Update
WCL - Tenley
Terrace/roof deck and Yuma Wing
3
Capital Projects Update
WCL - Tenley
Garage entrance and Nebraska Wing
4
Capital Projects Update
WCL - Tenley
5
Library Wing
Library Wing
Level 4 Classrooms
Capital Hall Atrium Entrance
Capital Projects Update
WCL - Tenley
Six Month Look-Ahead Schedule
Phase
June
July
Exterior Façade
Interior Fitout
Capital Hall Renovation
Utility, Site, & Landscape Work
Functioanal Testing & Turnover
Yuma/Nebraska Completion
Capital Hall Completion
Move-in
• Community update meeting May 15th
6
2015
August
September
October
November
Capital Projects Update
East Campus
Garage excavation looking south
Concrete batch plant
7
Garage excavation looking northwest
Capital Projects Update
AUEC
East Campus Project
Six Month Look-Ahead Schedule
Phase
June
July
Geo-Piers
Foundations & Garage Structure
Below slab utilities
Above grade structure
Offsite - Precast façade fabrication
• Community update meeting June 16th
8
2015
August
September
October
November
Capital Projects Update
Science Building
• Soliciting proposals for architectural and engineering services
• Feasibility study to validate scope, schedule and budget
• Further processing
9
Download