PROPERTY LEASE BACK PROJECT PROJECT INITIATION DOCUMENT North Norfolk Pathfinder Programme 2010 CONTENTS 1. Background 2. Introduction 3. Scope and overall approach 4. Project organisation 5. Project timescales 6. Project constraints 7. Project controls 8. Quality plan 9. Configuration 10. Reports to Defra 11. Appendices 1 1. Background In late 2004 North Norfolk District Council (NNDC) published the draft Kelling to Lowestoft Shoreline Management Plan. On much of the frontage it was proposed that there would be a change from a policy of defence to one of retreat or doing nothing. While in many respects this move reflected the reality that the North Norfolk coastline has been eroding for thousands of years, it was nevertheless not a change the Council and its communities found acceptable without there being some recognition of the consequences of such a policy change and the need for help in responding to the issues arising from coastal erosion. In the period since 2004 the Council has, with others, lobbied strongly for changes to the proposed arrangements. The outcome was the announcement by Government as part of the Comprehensive Spending Review 2007 of a Coastal Change (formerly Adaptation) Fund. This has been coupled with the publication in June 2009 of a draft Coastal Change Policy. At the same time as publishing this draft Coastal Change Policy the Government invited local authorities in whose areas coastal change and management was a significant issue to bid for funds to trial various approaches to coastal change. North Norfolk District Council submitted a bid under the Coastal Pathfinder Programme and was successful in securing £3 million to trial a number of projects. This project forms part of NNDC’s trial Pathfinder projects. 2 2. Introduction The eroding coast of North Norfolk has placed a number of communities at risk. Beyond the imminently at risk properties (examples and associated Pathfinder project for there acquisition, demolition and relocation) there are other properties which will be threatened in the next 20 to 100 years. The owners of these properties have difficulties in selling the property on the open market at prices that are considered reasonable. It is also anticipated that as the coastline erodes, there will be less incentive for property owners to continue maintaining the properties and therefore the properties would begin to further blight the community. Through purchasing these properties and leasing them back to either the existing occupier of finding an alternative use, the authority could through a suitable means, ensure the properties are maintained for the remainder of their useful life. This would prevent the gradual disinvestment and decline or the property and the associated blighting. There are potentially complex issues around the legal aspects of this project and the options which may be available will require carful investigation and consideration prior to any implementation of an acquisition and lease back scheme. Following the options being appraised the Council will be required to take a view as to which is the favoured approach and to what level they wish the initiative to be implemented. At the conclusion of the project a full report will be prepared detailing the methodologies, lessons learned and make recommendations as to the suitability of the approaches to enable the government to decide if the approach should be taken forward for future policy. 3 3. Scope and Overall approach 2.1 Project Aims • Evaluate the options for purchasing properties that are at risk in the period beyond the first SMP epoch and leasing them • Develop a method for evaluating the feasibility and the benefits of this approach • Identify a suitable organisation (e.g. a housing association) to work in partnership with in implementing this approach • Identify the properties that present the most suitable opportunities, within the available budget • Negotiate suitable terms for the purchase and lease of these properties and implement as appropriate 2.2 Scope The project will investigate the feasibility and delivery of a method of purchasing properties on Beach Road Happisburgh for leasing to residents or finding new uses between the 20-100 year erosion zones. 2.3 Approach The project will be lead by the NNDC Coastal Management Team with Peter Frew, Head of Coastal Management as Project Officer. The property advice and negotiations will be provided by Bruton Knowles who will act independently, but on behalf of NNDC. The local community will be involved through the Happisburgh Project Liaison Group. They will be updated on the projects approach and progress and are in a position to feedback information from the community to the project team. The initial stages of the project will focus around the internal policies and decision making structures required for purchasing properties and investigations around the setting up lease agreements or finding new uses. 2.4 Outcomes The project will have the following outcomes: • • • • Assist to enable the community of Happisburgh with its transition, from one which is under stress and has lost its confidence to one which is resilient and positive about its future. Improve the vitality and viability of the whole community through the removal of imminently at risk properties therefore reducing a blighting influence. Enable the residents included within this project to have the option to move on in their lives without the threat that coastal change imposes. Develop a methodology for valuing and negotiating purchase for properties at medium risk and finding new uses. 4 4. Project Organisation 4.1 Project Structure The Project will co-ordinated as part of the Pathfinder programme of projects and will be structured as in figure 1. Figure 1. Project structure PATHFINDER PROJECT BOARD (Programme management) PROJECT MANAGEMENT TEAM Peter Frew (Head of Coastal Management) Coastal Management Team Ian Coupe (Legal Executive) Karen Hill (Strategic Housing Manager) REFERENCE GROUP (Overseeing Project Development) HAPPISBURGH LIASON GROUP (Overseeing implementation of the project) PROPERTY ADVISOR Bruton Knowles 4.2 Roles and Responsibilities The programme Sponsor is Steve Blatch (Strategic Director, Community Services). The Project Board will be responsible for the overall management of the demolition and relocation of properties most imminently at risk project. It consists of officers and councillors, augmented by the Chair of the North Norfolk Business Forum. The Reference and Happisburgh Liaison Group will play key roles involving the community and will feedback to the Project Board through the pathfinder project team. For information regarding the Project Board and Reference Group please view the Programme Initiation Document. The Property Acquisition, Demolition and Relocation Project team will be formed consisting of Peter Frew (Head of Coastal Strategy) as Project Officer and will be supported by the Coastal Management Team. Legal support will be provided by Ian Coupe (Legal Executive) and Karen Hill (Strategic Housing Manager) will advise in re-housing issues. Bruton Knowles have been appointed to act as the Councils independent property advisor and will lead in the development of the valuation of properties, negotiations and advising and developing on other property matters. 5 The function of the Project Team is to: • oversee the delivery of the project and provide advice/ideas/input into the project and identify any challenges, issues, risks, lessons learned and costs; • ensure that the tasks identified within the project plan are carried out in accordance with the timetable of the project plan; • ensure the project communication is undertaken as identified in the Programme Communications Matrix and that any further methods are identified; • report progress to the Project Board. 4.3 Interfaces & Community Engagement All the North Norfolk pathfinder projects have been based on public engagement and this will be maintained throughout their implementation. The Communications and Community Engagement Strategy sets out how this will be achieved (see the Programme Initiation Document). Key engagement of the projects in Happisburgh will be public open days to be arranged at key points as the Happisburgh packages of projects are implemented. The Happisburgh Liaison Group will help to share information with residents to keep them updated. It will be essential to ensure the owners of the properties are kept informed as the project is developed and implemented and that a high degree of sensitivity, particularly when negotiating with those at greatest risk is maintained. The table below summarises the communications required for this project as identified in the Pathfinder Programme communications matrix. Who will be informed NNDC Staff Council Members Project Board Project Team (Internal) Parish Council Reference Group Liaison Group How The Briefing Newsletter Members Bulletin Coastal Management Board Coastal issues Forum Newsletter Meetings Meetings Via the Happisburgh Liaison Group and attending meeting where required. Meetings Documents and updates from the Project board Meetings 6 How Often Monthly Monthly At key stages During scheduled meetings Quarterly Monthly At scheduled meeting or if required Weekly Throughout the project. Minimum once per quarter Ongoing As often as required by the project and the group Who will be informed Property owners Public How Initial meeting introducing the project stating that should they have any queries or require updates to contact the team Open Day Letters One to one meetings Outlook Articles Pathfinder Newsletter Press articles Local newsletter articles Website Open days/Workshops Quarterly Reports Defra External government agencies, authorities, & professionals Final Report Conferences/Events Meetings Workshops Periodicals Website Final Report How Often At key stages At key stages During investigation and one-to-one meetings. Quarterly Monthly At key stages When key information is required to be disseminated Updated Weekly At key stages April, July, October 2010, January 2011 June 2011 As required Ongoing June 2011 4.4 Dependencies The success of this project is dependent on: • • • • the willingness of property owners to partake in the negotiations. the project is able to meet the needs of the residents. The levels of the valuation and the ability of the authority to enter into agreements. The ability for the Authority to enter into lease agreements or attract other parties to service those lease agreements. 7 5. Project Plan 5.1 Project Timetable The project will progress as outlined in the figure 2. Figure 2 – Project timescales 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12. 13. Task Develop project approach Advertise for an independent property advisor Publicise the project at Open Day. Appraise and select property advisor through tendering system Investigate initial legal issues and options for ‘buy and lease back’ Identify and appraise options available Present options to the Project Management Board Further circulation of options to Officers Preferred approach agreed by Project Board Seek relevant authority to proceed Promote scheme and seek interested property owners Property advisor to implement the agreed method (detail to follow) Report to Defra Predicted timescale January – March 2010 February – March 2010 April 2010 March – April 2010 May- July 2010 July – August 2010 September 2010 September 2010 October 2010 October - November 2010 December 2010 December – March 2010 April – June 2011 5.2 Project plan The project plan will be created and updated using MS Project. The plan will detail all the tasks required to complete the project and will be used to forecast estimated timescales of project completion and aid in the allocation of resources. 8 6. Project Constraints 6.1 Time This project has a defined timeframe and must be completed or have funds committed by April 2011. 6.2 Personnel/contracts Officer time is limited due to other commitments beyond the Pathfinder programme. Bruton Knowles, property advisor and negotiator for NNDC during the pathfinder projects will be available to provide property advice and complete the tasks outlined in the tender brief. Bruton Knowles will also be able to complete additional schemes of work should the need arise, they accept and the funds are available. It may be necessary to engage with external specialists to provide some of the skills required to fulfil the project, this may include for example a planning agent. It will be necessary for other internal departments to assist in the delivery in the programme, particularly, Planning (including Planning Policy), Finance/Procurement, and Communications. Additional internal assistance may be limited due to other commitments. 6.3 Finance The pathfinder projects have been allocated budgets to enable them to be planned and proceed. These allocations may be amended as projects progress. The Property Purchase for Lease Project has been allocated a project budget of £350,000 capital with an addition of £14, 845.47 for project management costs, totalling £364,845.47. 6.4 Legal Procurement must follow the NNDC Procurement Strategy. The project supports the corporate aims around coastal management as stated in Changing Gear, the corporate plan (page 31). Delegated authority has been granted by the cabinet of NNDC that the Chief Executive or Strategic Director (Communities) is able to procure works and services within the parameters set out in the Council’s Coastal Change Pathfinder applications. The Authority has the powers to acquire land for coastal protection works the under the Coast Protection Act 1949. However for this project these powers are not relevant. However under section 120 of the Local Government Act 1972 acquisition of land can be completed for the purposes of the benefit, improvement or development of their area. State aid rules are not relevant to private individuals. This would need to be reassessed should it be discovered that any of the properties also include business premises. 9 It is necessary that all due processes within the council are followed, and should the project deviate from existing policies or conventions it will be assessed and the relevant action taken to ensure that there are no constitutional issues. One element which has arisen is the need for a Corporate Acquisitions Policy. 6.5 Land Availability Some property owners have expressed and interest in this project and would be wish to be involved in any implementation of a scheme. There would be no compulsion for owners to accept an offer should they choose at a later date not to take part. 6.6 Assumptions It is assumed that Defra wish NNDC to complete the projects as we see fit as indicated by to the open nature of the funding offer. The Coastal Management Team also assume the general support of the Authority and its departments as a whole in the project delivery. It assumed that property owners involved in this project will wish to partake and that negotiations will be able to reach a mutually agreeable conclusion. It is assumed that the Council will have the appetite to take forward any favoured approach and the ownership/responsibility of the long term management of properties. 10 6.7 Risks The following risks have been identified with the pathfinder project programme. The risk matrix can be viewed in Appendix C of the Programme Initiation Document. Ref Date Logged Owner Title Likelihood Impact 1 03.03.10 PF Funds 2 4 Inherent Risk (Likelihood x Impact) 8 2 03.03.10 PF Availability 1 5 5 The property owners do not wish to sell their properties 3 16.04.10 PF Legal 4 3 12 Following initial investigations buying residential properties and leasing back has many potential problems and is likely to be a liability for the authority. 1 = Low → 5 = High 11 Description Summary of Actions/Mitigation Status Subsequent Likelihood Impact Residual Risk Following the property advisors valuations and scoping of options, the project may not have sufficient funds to purchase many properties The advisor knows the budget and will present options to the board, the board will need to decide which is the most equitable and achievable option with regard to the limitations and risks. If not enough funds are available a decision as to which properties or options to pursue will be required. open 1 3 3 No property owners will be made to sell a property and this project will be targeted at persons who wish to sell to enable them to move on/release funds. Continue investigations into head leases, and other methods of delivery. The board will need to assess the options when available. If the buy lease-back scheme as envisaged is not suitable, this is valid and useful to report back to Defra. open 1 5 5 open 3 2 6 7. Project Controls 7.1 Management The project will be documented with the following; project initiation document, project plan, ongoing issues log, quality log, lessons learned log and change log as required. The project initiation document will be agreed by the Project Board. The board will be updated during each stage of the project and will make decisions at key points and advise in the project direction. When ‘exceptions’ occur which require a decision to be made urgently by the project board, information will be circulated via email to members of the Board. The discussions and decision will be recorded in the emails and resolution must be met in a maximum of 5 working days. The minutes of the Liaison Group will be assessed by the Programme Manager and action taken as required. The minutes will be circulated prior to Board meetings and made available to the Reference Group. Bruton Knowles will meet with NNDC on a monthly basis whereby a monthly report will be submitted identifying progress, issues and any other relevant information. 7.2 Financial The project must not exceed the total budget of £364,845.47 unless further funds are assigned to the budget by the project board and the capital and revenue split must be maintained. The accounts will be monitored monthly following a report from the Accounts Team by the Programme Manager and reported back to the board. Should the project have an expected under spend of 10% or if there is any predicted overspend, it will be reported to the board. 12 8. Quality Plan The quality log will include the meetings for the Liaison Group and reports public open days and meetings with property owners. Where the quality check reveals the project is off specification or feedback suggest the scope of the project may need amending, the project team with the programme manager will investigate the options and present to the Project Board agree the most appropriate action. The monthly financial report/check and scheduled re assessment of risks and issues logs will be completed prior to Project board meetings. 9. Miscellaneous 9.1 Document Versions Project documents will be saved in the pathfinder folders M:\File System\Pathfinder Programme\Projects\Infrastructure Package\Trimingham village hall of the coastal management section and documents will carry in their title the creation/amendment date to enable current versions to be easily identified. 9.2 Meeting Minutes Meetings will be concisely recorded with Actions, Decisions and Issues highlighted where appropriate. 10. Defra Reports The project will be reported quarterly from April 2010 to Defra on the proforma provided. Report will be produced for the end of the month in: • • • • • April 2010 July 2010 October 2010 January 2011 April 2011 13