Planning Performance Update This is the quarterly planning performance report concerning the Planning Service for the October to December 2009 period and in particular covering the turn round of planning applications and appeal outcomes. Table 1A sets out performance for the third quarter of 2009/10. For the first time during the current financial year 2 major decisions were taken, both within the 13-week period. The number of minor decisions fell back by some 24 from the previous quarter and was the same as for the first quarter of the financial year. 8 fewer “other” decisions were made than in the previous quarter, i.e. slightly fewer than in the first two quarters. In terms of speed in all three categories both Government and Council targets were comfortably exceeded and cumulatively this remains the case, in respect of the year as a whole. Table 1B shows quarterly figures for some of the key components of workload for the service. 287 formal applications were received in the quarter, 6 less than in the previous quarter and pre-application enquiries and “Do I need planning permission?” queries were both substantially lower in the quarter, in part doubtless reflecting the normal seasonal adjustment for the Christmas period and the closure of the offices for a substantial period. Table 2 sets out the situation concerning planning appeals. During the quarter only 3 appeals were determined by the Planning Inspectorate, but all 3 were dismissed. This has had the impact of improving the cumulative performance figure for 2009/10, such that only 3 out of 19 appeals have been allowed, i.e. less than 16%, which is less than half of the national average and better than the Council target of 20%. In terms of staffing issues, significant time was spent during the quarter in completing the implementation of the PROBASS project, the new system going live in stages during November. An extension to the project, to provide increased use of electronic document management, the implementation of a measuring tool for plans on the Council’s Planning website and a review of processes and procedures following initial experience of using the new system, has been agreed and will be implemented in the period up to April 2010. Whilst requiring substantial staff input in the short term, this should substantially extend the ability of customers and consultees of the service to access information and should lead to greater efficiencies in terms of application processing. Steve Oxenham Head of Planning & Building Control, Extension 6135 TABLE 1A – PLANNING PERFORMANCE DECISIONS BY SPEED – 2008/09 MAJOR 0 – 13 WEEKS 13 + WEEKS MINOR 0 – 8 WEEKS TOTAL % 8+ WEEKS OTHERS 0 – 8 WEEKS 8+ WEEKS 15 9 363 190 782 130 62.50% 37.50% 65.64% 34.36% 85.75% 14.25% DECISIONS BY SPEED – QUARTER 2009/10 MAJOR 0 – 13 WEEKS 13 + WEEKS MINOR 0 – 8 WEEKS 8+ WEEKS OTHERS 0 – 8 WEEKS 8+ WEEKS TOTAL 2 0 70 18 160 17 % 100% 0% 79.55% 20.45% 90.40% 9.60% DECISIONS BY SPEED – CUMULATIVE 2009/10 MAJOR 0 – 13 WEEKS 13 + WEEKS MINOR 0 – 8 WEEKS 8+ WEEKS OTHERS 0 – 8 WEEKS 8+ WEEKS TOTAL 2 0 228 60 497 47 % 100% 0% 79.17% 20.83% 91.36% 8.64% TARGETS – COUNCIL GOVERNMENT 60% 60% 65% 72% 80% 85% TABLE 1B – WORKLOAD 2008/09 Applications submitted Pre-Application Inquiries Do I need Planning Permission? 1415 444 343 Applications submitted Pre-Application Inquiries Do I need Planning Permission? 287 91 47 Applications submitted Pre-Application Inquiries Do I need Planning Permission? 897 351 232 QUARTER 3 2009/10 CUMULATIVE 2009/10 TABLE 2 - PLANNING APPEAL DECISIONS Year ending 31 March 2005 Year ending 31 March 2006 Year ending 31 March 2007 Year ending 31 March 2008 Year ending 31 March 2009 Quarter 3 2009/10 Cumulative 2009/10 Allowed Dismissed Total 11 (28.2%) 28 39 8 (16.7%) 40 48 9 (20.9%) 34 43 8 (22.2%) 28 36 6 (11.8%) 45 51 0 (0%) 3 (100%) 3 3 (15.79%) 16 (84.21%) 19 Council target for 2009/10 = 20%