Cabinet 9 January 2012 Agenda Item No______7_______ COUNCIL OFFICES BUILDING Summary: The Council Offices are within the 20-25 year age when much of the original plant and equipment infrastructure will be beyond or close to design life-expectancy and the building structure elements will also require renewal. Various Capital projects were identified some years ago for the Council Offices totalling £275,000, but spend was deferred pending a full structural report. Consultants were engaged to completely review building and advise on defects and priorities to establish if the deferred capital items remained the most urgent issues to be addressed. Conclusions: Recommendations: The consultants have provided a schedule of both current defects (failed items) and those close to life expired where failure might be reasonably expected in the short to medium term. Amongst the current defects are some with potential significant impact on health and safety (legislation) and/or operation of services from the premises. It was also identified that part of the front section of the Annexe building was effectively life expired. 1. That immediate action is taken to remedy those issues identified as of major concern as listed in paragraph 5 of this report and that £200,000 from the consolidated capital fund for administration buildings is made available to address these specific items. 2. That a regular programme of improvement works as recommended by the consultants is scheduled for the next five years as part of the capital funding for Council officers to secure the functionality and value of the asset. Cabinet member(s): Contact Officer, telephone number, and e-mail: 1. All Tony Turner, Property Manager (01263) 516196 tony.turner@north-norfolk.gov.uk Background As a result of recommendations made to Council some years ago regarding improvements to the Council main administration offices a number of capital projects were proposed and amounts allotted although the individual projects were not instigated pending uncertainty relating to unification. It was agreed in October Cabinet to roll these into a single Capital fund for Administration buildings of £275,000 Cabinet 9 January 2012 As the original recommendations were made some years ago, it is appropriate to establish whether these recommendations were still relevant or whether funds should be reallocated to more urgent projects within the Council offices. Structural, mechanical and electrical engineers were asked to carry out an in-depth condition survey of the premises and produce a prioritised and costed planned maintenance programme for the premises 2. Consultants Reports The consultants were given a wide-ranging brief including confirming that the expected life-scan of the buildings; alternative uses and therefore sale potential; sustainability and energy reduction review; existing space utilisation and commenting on areas underutilised or requiring change; disability access issues as well as the core issues of identifying building and mechanical electrical defects. 3. Consultant’s Conclusions - The Council’s main building is structurally sound. - The Annexe has a part which is effectively life expired and is not economically viable to repair for the medium or long-term. - There are some defects which should be immediately addressed for both health and safety/legislation grounds and practical continued occupation of the building. - There are some medium-term measures which should be considered and planned for in order to ensure continued practical occupation of the buildings and prevent sudden failure of some systems. - The main building will remain fit-for-purpose as office accommodation even if many of the structural issues identified are not addressed. - The main building was specifically designed as Council offices with public access and information point via a large central reception and a Council Chamber and public meeting rooms as well as staff working areas. This requirement of the original design does potentially restrict alternative uses of the building compared to if the building had been a more utilitarian design and of standard construction. The Consultants have considered the alternative uses for the building other than as office accommodation, although the construction costs necessary for the conversions could make this uneconomic. - The use of space within the buildings is not consistent. Some areas appearing to be little used although furnished with a large number of workstations and the use of “hot-desking” or shared facilities appears little used. - There are Equality and Diversity issues with regards to access applicable to both the main building and the Annexe. The Annexe is not be accessible and the main building has a single access point for the upper floor for which there is no contingency in the event of a breakdown or emergency. - In terms of carbon-reduction or energy saving considerations, many of the options considered whilst possible, do not provide a realistic economically viable pay-back period. The exceptions to this are a Building Management System (BMS) to control heating, cooling, ventilation and lighting; possible wind turbine to supplement energy consumption and solar shading with or without a combination of window louvers to provide night time ventilation 4. Council Office Asset Value and Options The alternative uses of the building have been considered and evaluated and considered to be uneconomic as a conversion by any potential developer. The option of Cabinet 9 January 2012 sale and lease-back or disposal of the site for other uses to fund a new smaller building has also been considered and again found to be uneconomic beyond the short-term. There are no directly comparable figures and the estimates provided are only theoretical based on general historical office accommodation, land sales data etc. However, the data has not been tested and in the prevailing economic situation it is understood there is little activity in the speculative property market and it may not be possible to either find interested parties in either purchase; purchase and lease-back; purchase for redevelopment or an alternative site. The key figures are: Estimated market value of existing site including buildings as investment value (office use) £1,750,000 Gross Internal Area of main building (ex basement archive/plant room) 3,127m2 plus 258m2 Annexe Estimated rental cost to Council to lease back £60m2 (£6 per ft2) main building and £50m2 (£5 per ft2) annexe; annual rent payable £200,000. In addition to which service charges would apply including remedial work as identified by consultants. Estimated value of development land in Cromer (per acre) £250,000. Area of existing site being 0.9 acre Estimated cost of demolition of existing Council buildings including asbestos removal and waste management £130,000 Estimated cost of land acquisition out-of-town or similar and site ½ acre £100,000 Estimated construction cost offices/public buildings £2,000 m2 Estimated required size of replacement building including Council chamber, public rooms, reception etc GIA 2,500m2 As stated these figures are best estimates from data over the last few years and do not necessarily reflect current market conditions. The figures also do not take into account planning restrictions, availability, communication and utility supply costs, staff and management time in such a major disruptive project, all of which could significantly increase the costs. The current site has a number of restrictions on use plus the gipsy and traveler site might need to be relocated to maximize site value, this also has not been included. Overall the conclusion is that the expenditure in a new building is not viable and that sale and lease-back is uneconomic in the medium to long term. 5. Immediate Health & Safety Issues (Risk Implications) The consultants report details current defects in the building and its infrastructure i.e. those items no longer functioning as well as issues which could be reasonably expected to become issues in the future. Their report on issues provides the basis for a programme for building and plant/equipment renewal and they have provided costs for replacement/repairs. However, their proposed prioritisation does not necessarily reflect the Council’s own specific needs and their costs are to replace/repair to best available standard, which again may not be always required. Therefore a 10 year Pre-Planned Maintenance programme is being devised as an on-going Capital project. There are some items identified as failed, which do require immediate attention for health and safety/legislation compliance and these are: Emergency Lighting – sporadic throughout the building. A full redesign and replacement is recommended. Budget cost £93,000 including Annexe Fire Alarm system does not cover the whole building and is obsolete. Replacement recommended. Budget cost £50,500 including Annexe. Cabinet 9 January 2012 Fire exits in some instances end in flower beds, others have poor handrails, or trip hazards. All need review and improvement. Budget cost £20,000 The heating system pumps are in poor condition with signs of corrosion. Replacements required before failure of heating. Budget cost £13,000 Office flooring flood-wiring cable boxes are faulty in some cases and the panels protrude above the floor creating trip hazards. Budget cost £20,000 The roof terraces have cracked paving allowing water to penetrate and require resealing to prevent water damage to internal areas. Budget cost £1,500 All smoke seals and intumescent strips to be checked and replaced where necessary. Budget cost £1,000 A total of £199,000 although it is anticipated that some savings off this figure can be achieved. 6. Remedial Works Identified by Consultants In addition to those items listed above which must be considered to be of immediate concern, the consultants listed and rated a large number of items within both the main building and the Annexe and in summary their recommendations for remedial works is: Main Building Annexe Immediate to within the next 5 years £ 759,000 £ 74,100 Within 5 to 10 years £ 284,900 £ 18,500 Within 10 to 20 years £ 222,150 £ 15,000 Longer (i.e. anticipated but not expected to have to be incurred for at least 25 years). £ 324,500 £ Overall Total (from 2011 to 2036) £1,590,550 £108,350 750 This is currently being fully analysed item by item as a number of these may not be necessary or alternative measures found to maintain whilst reducing expenditure. Also their suggestions as to when these works need to be prioritised may need amending. Therefore a full 10 year plan is being developed for consideration. 5. Sustainability As commented in final point paragraph 3 above, the consultants identified areas for improvement and for consideration the majority of which are already included within the Carbon Management Plan. 6. Overall Implications for the Building (including Equalities) Whilst the consultants have concentrated their report on the structural, mechanical and electrical aspects of the Council offices, they have also made references to other aspects of the building that should be considered for improvement or change to maximise opportunities and occupation e.g. disabled access, re-design of main reception etc. These will be incorporated within the 10 year plan and whilst these issues are not within the conventional building standard condition ratings, there is a need to consider all changes within the building to ensure that opportunities for incorporating building maintenance items are included in other changes reducing disruption and potential duplication of cost. Cabinet 7. 9 January 2012 Conclusion/Recommendations The main building is fit-for-purpose and structurally sound, but as would be expected for a building 20+years old does now require regeneration and improvement to maintain the usability of the building and prevent further degeneration to a state where there are major defects in the premises affecting delivery of Council services, contravention of health and safety and other legislation and also expensive to remedy. It is therefore recommended that the most immediate health and safety issues are addressed utilising part of the Capital Funds held for the building with work being undertaken over the next 18 month period. However, in addition to these specifically identified issues, a regular programme of improvement works is scheduled for the next five years and beyond based on the consultant’s recommendations and priorities but also adapted to the Council’s own more specific needs where appropriate. In this way sudden breakdowns or failures can be avoided, best value achieved by not requiring emergency repairs and disruption mitigated by planning the work with those affected. It is recommended that this programme is part of on-going capital funding for the Council offices whereby the investment of capital provides safe, secure and functional Council building for the future and protects the asset value.