OFFICERS’ REPORTS TO DEVELOPMENT COMMITTEE – 12 JANUARY 2012 Each report for decision on this Agenda shows the Officer responsible, the recommendation of the Head of Planning and Building Control and in the case of private business the paragraph(s) of Schedule 12A to the Local Government Act 1972 under which it is considered exempt. None of the reports have financial, legal or policy implications save where indicated. PUBLIC BUSINESS – ITEM FOR DECISION 1. HEMPTON – PF/10/0329 – The erection of 5 two storey dwellings and 2 flats: site adjacent to 21 Dereham Road for Flagship Housing Group To give the application further consideration following the receipt of comments from English Heritage in relation to drainage and archaeological remains. Background This application has been subject to consideration by the former Development Control Committee on three previous occasions. On 10 June 2010 the Committee resolved to defer the application for design negotiations to take place and to await the response of the Environment Agency on the acceptability of soakaways in this location and land contamination. The application was referred back to Committee on 23 September 2010 for further consideration to be given to the above issues. No objections were received from the Environment Agency in relation to soakaways and contamination and no objections were received from the Conservation, Design and Landscape Manager or the Housing Enabling Officer regarding the amended design. Following objections being raised by local residents regarding the water-logged nature of the site and impact of the development on the water table the Building Control Manager was consulted. He confirmed that the water-logged nature of the site was not an insurmountable problem and would not prevent the construction of the proposed dwellings on the site. With regard to the impact on the water table, the Environment Agency had been consulted on this matter and advised that this was outside the limits of the advice it could provide. It was therefore resolved that the Head of Planning and Building Control be authorised to approve the application, subject to no further grounds of objection being received from the Parish Councils or following expiry of the readvertisement of the amended plans and the satisfactory resolution of the impact of the development on the water table and subject to the imposition of appropriate conditions. Following that decision further investigations were carried out by the applicants in relation to the impact of the development on the water table. It was agreed with the applicant’s engineer, the Environment Agency and the District Council’s Building Control Manager that a condition should be imposed on any approval requiring a scheme to be submitted and agreed to secure de-watering of the site prior to the commencement of the development. However, the application was again referred back to Committee on 14 April 2011 after it had become apparent through further investigation by the applicants that the use of soakaways on the site would not be an acceptable method for the disposal of surface water due to the height of the water table. An amended plan regarding an alternative drainage method of an attenuated surface water system was submitted. This would be via a pipe laid underground with an outfall to a ditch on adjoining land. Development Committee 1 12 January 2012 Members will note from the report to the meeting on 14 April 2011 in Appendix 1 that the amended drainage plan was re-advertised and re-consultations carried out. It will also be noted from the minutes of that meeting in Appendix 1 that Norfolk Landscape Archaeology (now known as the Historic Environment Service) objected to the route proposed for the drainage pipe as it was considered to be inappropriate. It was requested that an alternative route be sought which did not affect the archaeological remains on the site of the adjacent former priory. The resolution of the Committee was to give delegated authority to approve subject to a satisfactory resolution of the drainage and archaeological issues, no objection being received from outstanding consultees and imposition of appropriate conditions. Updates since previous report Following the meeting on 14 April 2011 a site meeting and discussions took place between the applicants, their engineers and the Historic Environment Service regarding the route of the drainage pipe. As a result of this, confirmation was received on 19 July 2011 from the Historic Environment Service that it had been concluded that there was no viable alternative to draining eastwards from the development across the northern part of the site of the Hempton Priory. It was confirmed that, having considered the feasibility study in detail, the Historic Environment Service accepted that conclusion, and recommended that a condition be imposed on any approval for a programme of archaeological work in accordance with PPS 5. A copy of this response is contained in Appendix 1. However, prior to this a letter had been received from MJC Associates acting for Hempton Parish Council (copy contained in Appendix 1). The letter asserted that, given that the priory site is a designated heritage asset and protected as a Scheduled Ancient Monument, the proposed development would significantly impact upon the setting of the designated heritage asset, and that such a material consideration had not been formally considered during the current planning process. The letter also expressed the opinion that the siting of the proposed development on an undesignated area of land containing earthworks associated with the designated heritage asset should only be undertaken subject to the requirements of PPS5. A copy of this letter was sent to the Historic Environment Service and the Conservation, Design and Landscape Manager for their comments. Both responses are contained in Appendix 1. They agree that the proposed development would have some impact on the setting of both the designated and undesignated parts of the site. However, neither considers that the impact on the setting would affect the significance of the asset. The Historic Environment Service have no objection in principle to the change in setting and the Conservation, Design and Landscape Manager did not at any stage during his two site visits conclude that the development would result in a level of harm sufficient to justify refusal. However, he agreed with the representation on a procedural matter and confirmed that as the development would be likely to affect the site of a scheduled monument that the Local Planning Authority was required to consult English Heritage. A finalised drainage plan was received from the agents, re-advertised on site and reconsultations have taken place, including with English Heritage. The application was also re-advertised as affecting the setting of a Scheduled Monument. In addition to the matters of drainage and archaeological impacts, the Environment Agency provided Officers with a copy of a letter received from Hempton Parish Council along with their response. The Parish Council wrote to the Environment Agency on matters which they considered to fall within their remit regarding Development Committee 2 12 January 2012 contamination, piling, surface water drainage, protected species, Scheduled Ancient Monuments, sewage and ‘Blackleg’. The Parish Council state that the site is contaminated with ‘Blackleg’ and that cattle grazing the land have to be vaccinated against the disease. They also state that the applicants have advised them that they can mitigate against this by washing any deposits of soil during the build phase into the main drain at the end of the road some 50 – 70 yards from the site entrance. The Environment Agency confirmed to the Parish Council that; (i) they have requested a condition in relation to further investigations into contaminants being carried out at the site; (ii) that the applicants have confirmed they will not be piling; (iii) they are satisfied with information submitted in relation to surface water drainage; (iv) protected species are not within their remit; and (v) that they are not the competent authority in relation to scheduled ancient monuments and sewage. However, the Environment Agency advised the Parish Council that they had concerns over the contamination of this site with Blackleg, and the alleged proposal of washing any deposits of soil into the main drain. This is an unacceptable method of disposal of any material, whether contaminated or uncontaminated, and would constitute an offence under the Environmental Permitting Regulations. The Environment Agency advised that they would wish to be consulted along with Animal Health, regarding the removal and correct disposal of any contaminated soil from the site, which would require the relevant authorisations. The Environment Agency were then asked to confirm what further information they would require in order to address their concerns in relation to the alleged contamination of the site with Blackleg. In response to this they confirmed that this matter was outside their expertise, and suggested that the advice of Environmental Health or Animal Health be sought. In view of this the District Council’s Contaminated Land Officer was consulted. He discussed the issue with the Environmental Protection Team and has clarified that Blackleg appears to be a Bacterial disease mainly affecting cattle and sheep. The bacteria responsible naturally reside in soils and causes infection after ingestion. In terms of contaminated land, pathogenic organisms lay outside of the legislation and are not something that we would normally consult on. However, the Contaminated Land Officer contacted Animal Health and established that they did not have any concerns over this matter on the basis that the condition was not a notifiable disease and suggested contacting the local farm veterinary surgeon for further information. The Contaminated Land Officer was advised that Blackleg is highly infectious to cattle, sheep and goats, grazing animals being particularly susceptible. The bacterium that causes infection once present in soils can remain for many years and cannot be removed or eradicated. There is little evidence to show that Blackleg is any threat to human health. The advice given suggested that if a site is infected by this disease it is advised to keep soil disturbance to a minimum, but this is in order to protect livestock if present. Effective vaccinations for the disease are available. In view of the above the Contaminated Land Officer is satisfied that a condition requiring a site investigation into possible contaminants is appropriate, as originally requested by the District Council and the Environment Agency. The Environment Agency has subsequently confirmed that the issue of Blackleg does not fall within their remit, and that Animal Health are best placed to advise and if they are satisfied that it does not pose a significant risk it is recommended their advice is followed as the competent authority. Development Committee 3 12 January 2012 On the matter of possible disposal of any contaminated soil, confirmation has been received from the applicants’ Project Manager that he can categorically state that the Parish Council has not been advised by the applicants or their agents that they can mitigate against this contamination by washing any deposits of soil into the main drain. The Project Manager states that he is not aware what they are referring to by ‘main drain’, and there is no public surface water sewer in the vicinity. He also states that they were advised that cattle on the wider field had been diagnosed as being infected with Blackleg back in 2004. They had subsequently consulted with the Health Protection Agency and East of England Animal Health Regional Office who both advised that there is no known risk to human health from clostridium chauvoei (the spore that causes Blackleg) and the preventative action for livestock is vaccine. The agencies advised that there is no good practice guide for not spreading spores because it is not needed for this clostridium spore, but he confirms they would of course ensure that groundworkers adhere to standard practices to avoid spreading soils from the site. Consultee responses following receipt of finalised drainage plan Hempton Parish Council – Object to the amended application on the basis that there has been no substantial amendment made to the application. Comments in relation to further amended plans: Object, for same reasons as above.. Environmental Health – No further comments, apart from request for condition regarding investigation into possible contaminants at the site as originally requested. Environment Agency – Blackleg does not fall within our remit. We feel that Animal Health are best placed to advise and if they are satisfied that it does not pose a significant risk, we would recommend that you follow their advice as competent authority. Please note that if contaminated soil is to be removed from site as part of the works, this will need to be removed by a licensed waste carrier and disposed of at a permitted premises. The applicant should refer to our website for further information on dealing with contaminated land and which regulations and permissions apply. Specific information relating to contaminated land can be found at: http://www.environmentagency.gov.uk/research/planning/121619.aspx and netregs provides advice on regulations applying to land contamination (www.netregs.gov.uk). Norfolk Wildlife Trust – No response Conservation, Design and Landscape Manager (Landscape) – This does not affect the previous comments of the Landscape Section, which were no objection, subject to measures to safeguard the adjacent County Wildlife Site. Building Control – No additional comments Norfolk Landscape Archaeology – The route of the surface water drain shown on the map is agreed by the Historic Environment Service, the developer and Oxbury & Company during a site meeting on 23 August 2011. If this route is followed the drain will cross the possible medieval wall at a point where none of the wall survives above ground. During the site meeting it was agreed a short stretch of the pipe trench centred on the middle of the wall line will be hand excavated (rather than machine dug) to ensure any impact on possible below ground remains associated with the wall is minimised during the installation of the pipe. This is confirmed by annotation Development Committee 4 12 January 2012 on the map. This area of hand excavation will form part of a scheme for monitoring groundworks under archaeological supervision and control, a programme covered by the condition requested by the Historic Environment Service on 19 July 2011, and a brief produced by the Historic Environment Service on 31 August 2011. The Historic Environment Service believes that this revised drainage scheme and associated archaeological works will ensure the impact on the significance of the heritage asset is the minimum possible. Strategic Housing – No objection to amendments proposed. The local housing need remains virtually unchanged since the previous analysis of applications on the Housing Register, and currently identifies 45 households from Hempton and the adjoining Civil parishes (namely Sculthorpe, Dunton and Pudding Norton) who have a housing need and a local connection with Hempton as required by the Rural Exceptions Scheme policy. There is a significant local need for affordable housing, which this proposal for 7 dwellings will go some way to meet. The proposed scheme meets with all the requirements of Policy H03 and contributes to meeting the Core Aims and objectives outlined in the Core Strategy and Corporate Plan. Housing Services therefore strongly supports this application to develop 7 much needed affordable homes in Hempton. English Heritage – Have commented on the different aspects of this scheme, which are summarised as follows: Impact of the character and appearance of the Hempton Conservation Area: 1. Clarification is required regarding which walls will be in facing bricks and which will rendered. 2. Raised brick quoins should only be used in association with facing brickwork 3. The facing brickwork should be Flemish bond 4. The treatment of window heads in facing brickwork needs to be clarified 5. Window heads should be formed either with segmental brick arches or with an expressed reconstituted stone lintel. 6. The decision to combine some ground floor windows and external doors is questioned. It is suggested they are separated. 7. Glazing in the doors should be reviewed to achieve an historically appropriate appearance. 8. The porch to Plot 1 has a wide gable which is visually overlarge and would be better replaced by a simple lean-to porch. If a gable required then should be narrower and centred on the door. 9. With regard to landscaping the hedge that will screen the close boarded fence to plot 1 should be maintained at 1.8m to fully screen the fence. 10. Consideration should be given to using bound gravel rather than tarmac to the hard paving areas for parking and turning. Impact on the setting of the Scheduled Monument: The development would create a degree of change to the setting, and although potentially harmful, this change is not considered to be substantial enough to warrant refusal on the grounds of impacts upon the setting of the monument. A design of sufficient quality is sought and the advice above in relation to Conservation Area would enable the delivery of a more appropriate scheme. Potential of the development on un-designated archaeology within the development area: Development Committee 5 12 January 2012 The proposed development has been evaluated and it is considered to be outside of the precinct of the St Stephen’s Priory, the remains of which lie to the south and possibly to the east. No features of medieval date have been revealed. Archaeological features of possible Romano –British were however identified on site. These are not considered to be of sufficient significance to require preservation in situ. Disturbance of these undesignated assets will need to be mitigated through the development control process. An archaeological condition is recommended. Potential of the development on un-designated archaeology with the development area in relation to external drainage: This land (area to east of proposed development) is outside the protected area of the monument. It has been assessed by English Heritage’s Designation Department to have sufficient archaeological potential to be considered for inclusion in the designated area, as it contains archaeological earth works and structural remains of possible medieval date and likely to contain buried archaeological remains. This requires a formal review of the designation, which has not yet taken place but must be considered in policy terms under PPS5 as significant but undesignated heritage assets. Although PPS5 favours the conservation of significant assets, as the area is undesignated English Heritage are deferring the advice to the County Council’s Historic Environment Service in regard to the drainage scheme. An archaeology condition is, however, required for the works that specifically cover the installation of the drain. To minimise future preservation the pipe should however, be non-porous to prevent contamination of the archaeological deposits. Comments following receipt of amended plans: In respect of the impact of the proposals on the character and appearance of the Hempton Conservation Area; I have now had the opportunity to examine the revised drawings, the comments from Richard Pike Associates and the comments from your Senior Conservation and Design Officer. I note Richard Pike Associates are concerned that our request for Flemish bond would have a spatial implication though this could be achieved using ‘snapped headers’ without spatial implications. You may therefore wish to consider requiring Flemish bond on at least the front elevations, but I am content for you to take the advice of your Senior Conservation and Design Officer on this matter and for the application to be determined by your members. In the light of this advice and, in the event that they are minded to approve the application, that the detailed aspects of the design are controlled by way of appropriate conditions. Conservation, Design and Landscape Manager (Conservation and Design) (summarised) – Comments do not differ from previous. Following the recent planning tour with Members, the value of good quality landscaping and surfacing was a recurring theme. Hence, in the event of an approval being issued, need to ensure perimeter planting sufficient to screen/soften the units and their associated close boarded boundary fences. Ideally there should also be some definition in the materials to be used in the rear parking court. Comments following English Heritage’s initial response: Firstly, in terms of the impact upon the Scheduled Monument, it is interesting to note that EH have independently arrived at the same conclusion; i.e. that the proposed development would involve some change to the setting of the designation but that the level of harm would not be sufficient to justify a recommendation of refusal. Development Committee 6 12 January 2012 In terms of the more specific comments made: The elevations are a little bit sketchy but do appear to provide sufficient detail on materials. Other details, such as windows/doors, arches and eaves/verges can be dealt with by condition. Raising the brickwork in Flemish Bond would definitely given the scheme a more refined and historically accurate appearance. What is less clear, however, is whether specifying this over a normal stretcher bond would be reasonable in this case. Combining some of the GF windows/doors is indeed unfortunate. However, as this only takes place only on the rear elevation, it is not considered to be sufficiently injurious to merit revision. It is agreed that the doors should not have dropped fanlights to be historically accurate. However, this can be part of any condition mentioned above. It is also agreed that the porch on Unit 1 could be much improved if it just covered the doorway. As shown, it does look overlarge and unbalanced. The importance of the boundary hedging can not be over-stated – it will be essential to bed the development into its setting. Certainly it will need to provide a meaningful screen of the potentially suburban boundary fencing. The comment about improving the surfacing is very much supported (as mentioned in my last consultation response of the 3rd November 2011. Comments following receipt of amended plans in respect of response from English Heritage: With reference to the latest amended plans received by the Local Planning Authority on the 30th November 2011, I can confirm that these satisfactorily address the previous design concerns expressed in my response of the 28th November 2011. Hence with the dropped fanlights removed from some of the front doors, the porch design improved on Unit 1 and the surfacing properly delineated, there are no further Conservation or Design objections to this scheme. As stated previously, whilst it would undeniably be preferable for the units to be raised in Flemish bond, it is questionable whether we can insist upon this, particularly as the new build next door has been built in stretcher bond. In the event of the application being approved, conditions are requested covering: • • • Brick, tile and paviour samples to be agreed prior to their use on site (NB: in respect of the paviours, two contrasting yet complementary samples would need to be specified for both the driveway and the parking bays). Door and window details to be agreed prior to their installation Architectural detailing; i.e. window arches, verge and eaves to be agreed prior to their formation With satisfactory compliance, the impact upon existing heritage assets would be minimised. Representations received Two letters of objection and one comment have been received, raising the following points: Development Committee 7 12 January 2012 1. Surely it is wrong to destroy Ancient Monuments and build on conservation land? 2. Alternative site available. 3. Impact on water table. 4. The land is contaminated and disturbance could lead to contaminating the River Wensum. 5. Building here is likely to inflict un-repairable damage to our future heritage. Key Policy Issues The key issues for consideration at this time are the matters of design raised by English Heritage, the acceptability of the drainage route and impacts upon archaeology in accordance with policies EN4, EN8 and EN13 of the adopted North Norfolk Core Strategy. Other material considerations include ministerial advice from the Rt Hon Greg Clark MP – Minister for Decentralisation concerning Planning for Growth dated 23 March 2011. The ministerial advice states, amongst other things, that: When deciding whether to grant planning permission, local planning authorities should support enterprise and facilitate housing, economic and other forms of sustainable development. Where relevant - and consistent with their statutory obligations - they should therefore: (i) consider fully the importance of national planning policies aimed at fostering economic growth and employment, given the need to ensure a return to robust growth after the recent recession (ii) take into account the need to maintain a flexible and responsive supply of land for key sectors, including housing (iii) consider the range of likely economic, environmental and social benefits of proposals; including long term or indirect benefits such as increased consumer choice, more viable communities and more robust local economies (which may, where relevant, include matters such as job creation and business productivity) (iv) be sensitive to the fact that local economies are subject to change and so take a positive approach to development where new economic data suggest that prior assessments of needs are no longer up-to-date (v) ensure that they do not impose unnecessary burdens on development. In determining planning applications, local planning authorities are obliged to have regard to all relevant considerations. They should ensure that they give appropriate weight to the need to support economic recovery, that applications that secure sustainable growth are treated favourably (consistent with policy in PPS4), and that they can give clear reasons for their decisions. The Committee is referred to the ministerial advice in full. It constitutes a material consideration to which appropriate weight should be afforded. It is a matter for the Committee to decide what weight to give this statement. In July 2011, the Department for Communities and Local Government issued Draft National Planning Policy Framework (NPPF) for consultation which, amongst other things, places greater emphasis towards securing sustainable economic growth. Whilst the NPPF is not yet adopted Government policy it does give a clear indication of the Government’s current intent. Again it is a matter for the Committee to decide what weight to afford this document as a material planning consideration given that it Development Committee 8 12 January 2012 is only in draft at this stage and, following the consultation process, it may be revised or altered in light of that consultation process. It is considered that the NPPF is a matter which does attract some weight at this stage given that it is consistent with the previous statements of Government policy. Appraisal The Committee will note that this application has been considered by the former Committee on three occasions, and apart from deferral at the first meeting to negotiate on matters of design the Committee has given delegated authority to approve subject to the resolution of matters of drainage, impacts on water table and archaeological impacts on two further occasions. The application is being referred back to Committee following the receipt of comments from English Heritage on design grounds, impacts on the setting of the designated and undesignated assets and the drainage route. The matter of the land being contaminated with ‘Blackleg’ also requires further consideration. All other matters have already been addressed at previous Committee meetings. With regard to the comments from English Heritage in relation to design, the applicants have given this matter further consideration. Following the advice of Officers, including the Conservation, Design and Landscape Manager, the applicants have provided further clarification on the plans of which walls are to rendered and brickwork, as well as the use of brick quoins and window head details. The views of English Heritage regarding the combining of ground floor windows with external doors have been considered, but this would be to the rear of the properties only and not in a prominent position in the Conservation Area. With the erection of the screen fencing proposed, these fenestration details would not be visible in the wider area. This is not therefore considered to be of sufficient detriment to warrant a further revision. The amended plans show a revision to the glazing in the doors, as well as a reduction in the size of the porch to dwelling 1 and change in design to a more simple lean-to roof, as suggested by English Heritage. The point raised by English Heritage regarding the height of the hedging to the site boundaries would be included as part of any landscaping conditions. With regard to the parking and turning areas, whilst bound gravel is not being proposed the applicants have revised the plans to include two different paviour colours to differentiate between parking and turning areas. The only other suggestion made by English Heritage that the applicants have not revised concerns the use of Flemish Bond brickwork. The Committee will note the comments of the Conservation, Design and Landscape Manager on this matter, who confirms that whilst this would be preferable it is a questionable as to whether this can be insisted upon, given that the new build dwelling adjacent is constructed using stretcher bond. The Committee will note that following the receipt of amended plans in relation to design and materials that English Heritage are not raising an objection; they are satisfied for the Committee to take the advice of the Conservation, Design and Landscape Manager, subject to appropriate conditions. In view of the comments already provided by the Conservation, Design and Landscape Manager it is not considered that this could be insisted upon on this case. Other matters in relation to materials can be addressed by way of conditions to ensure a satisfactory development in terms of its appearance. With regard to the drainage plans and the impact upon archaeology and designated and undesignated sites, the Committee will note that no objections have been received from the expert consultees. The Historic Environment Service, Development Committee 9 12 January 2012 Conservation, Design and Landscape Manager and English Heritage all have no objection subject to an archaeological condition being imposed on any approval. It is considered that the applicants have demonstrated through their investigations and discussions with the Historic Environment Service that the route proposed for the drain is the most appropriate and can be appropriately mitigated. The Committee will also note that English Heritage do not consider the change in the setting of the designated monument to be substantial enough to warrant refusal, nor do they consider the archaeological features on the un-designated area to be of sufficient significance to require preservation in situ. English Heritage have also deferred to the advice of the Historic Environment Service in relation to the drainage proposal. With regard to the concerns raised in relation to the alleged contamination of the site with Blackleg; the Contaminated Land Officer has consulted with Animal Health as suggested by the Environment Agency. No concerns have been raised by Animal Health and both the Contaminated Land Officer and Environment Agency are satisfied with this. A condition requiring a site investigation into possible contaminants is required on any approval to address contamination on the site. If contaminated soil is to be removed from site as part of the works, this will need to be removed by a licensed waste carrier and disposed of at a permitted premises. Further information on this matter is provided by the Environment Agency on their website and information on any permissions required. This information would be included as an advisory note to the applicants on any approval. In summary, taking these issues into account it is considered that the matters of design raised by English Heritage have now been satisfactorily addressed and can be conditioned appropriately. The alternative drainage method proposed is also acceptable, given that mitigation can be put in place to minimise the impact upon the archaeological remains. It has been established that Blackleg does not pose a significant risk to human health and contamination can be dealt with under an appropriate site investigation condition. Furthermore, English Heritage has confirmed that the change in the setting of the designated and undesignated assets as a result of the proposal would not be substantial enough to warrant a refusal. In relation to these matters the proposal is therefore considered to be acceptable and in accordance with Development Plan policies. RECOMMENDATION: Approve subject to the imposition of appropriate conditions. (Source: Jo Medler, Senior Planning Officer ext 6128) Development Committee 10 12 January 2012 PUBLIC BUSINESS – ITEM FOR DECISION 2. WEYBOURNE – PF/09/1270 – Installation of buried electrical cable system in connection with off-shore wind farm; Land from Weybourne to Great Ryburgh for Dudgeon Offshore Wind Ltd To give the application further consideration following the receipt of the appeal decision on the Little Dunham sub station, and to consider the applicants’ response to issues raised by the Committee on 14 July 2011. Background The Committee last considered this application at the meeting on 14 July 2011 when it was resolved to defer determination of the application for the following reasons: 1. To await the outcome of the inquiry in respect of the Little Dunham substation. 2. To seek the applicants’ views as to whether they are willing to delete stage 2 from the current application. 3. To request the applicants to reconsider the precise route at Westwood Farm, Great Ryburgh. 4. To seek further information on the short-term impact on tourism and agriculture. 5. To seek the applicants’ view as to the use of horizontal directional drilling across the Rivers Stiffkey and Wensum. 6. To seek further information in respect of soil heating. Copies of the report to that meeting and the minutes are attached as Appendix 2. Examination of Issues The following are updates on the issues raised by the Committee: Issue 1: Outcome of the inquiry in respect of the Little Dunham sub-station. A decision has now been issued by the Secretary of State for Communities and Local Government and the Secretary of State for Energy and Climate Change dismissing the appeal for the sub-station at Little Dunham. The Secretaries of State considered a report from the Planning Inspector who recommended that the appeal be dismissed. A full copy of the Planning Inspector’s report and the Secretaries of State’s decision is contained in Appendix 2. The overall conclusion arrived at by the Secretaries of State was as follows: “They consider that a substation is required and is vital to the utilisation and distribution of off-shore wind energy. In accordance with national policy set out in PPS22, the Secretaries of State have attached significant weight to the wider environmental and economic benefits of the proposals. However, they conclude that there would be visual impacts on the landscape adjacent to Little Dunham that would result in a significant change in the perception of the village which would be damaging to its hitherto rural ambience along with the intrinsic beauty of the landscape. In this respect they conclude that there is conflict with (Breckland District Council) Core Strategy policies CP 11 and DC 15. The Secretaries of State are satisfied that the harm from the visual impact on the landscape is such that planning permission should be withheld at this particular location. Furthermore, they consider that the possibility of locating an acceptable site elsewhere – as to which, as the Inspector indicated, there is scope for further assessment – also tells against the acceptance of the environmental consequences that would be associated with this particular development at Little Dunham. Development Committee 11 12 January 2012 Having weighed up all the relevant considerations, the Secretaries of State conclude that the factors which weigh in favour of the proposed development do not overcome the conflicts with the development plan which they have identified. They do not consider that there are any material considerations of sufficient weight to justify granting planning permission.” Following the dismissal of the appeal for the sub-station the applicants have confirmed that they are continuing to work with Breckland District Council and others to agree the best location for the sub-station within the Little Dunham/Necton area. The applicants stress that the cable route application through North Norfolk will remain unaffected by the events in Breckland, and unchanged irrespective of whether the sub-station is located near Little Dunham or Necton. It is accepted by Officers that this would be the case. It would be the route through the Breckland District that may be subject to change. If the sub-station were to be located well outside the Little Dunham/ Necton area then this could affect the cable route in this District. If this did happen then a further planning application for the route would be required. However, based on the information submitted by the applicants the District Council is required to determine the application as submitted and as requested by the applicants. In the light of this further information has been received from the applicants in response to points 2 to 6 of the Committee’s resolution above. A copy of this response is contained in full in Appendix 2. A summary of the applicants’ response is set out under the following issues:Issue 2: To seek the applicants’ views as to whether they are willing to delete stage 2 from the current application. Applicants’ Response There should be no misunderstanding of the intention to develop Stage 2, if offshore consent is granted in due course. If Stage 2 were removed from the application a misleading impression could be given to the local communities, the Council and to all other stakeholders. Whilst the timing is currently uncertain discussions with The Crown Estate are continuing. The delay in further licences for the area is related to a regionally sensitive offshore issue and the expected resolution of this matter later this year should allow programmes for both Stage 1 and Stage 2 to move forward. The inclusion of both stages allows the maximum impact scenario to be considered and mitigation and management to be planned in a holistic manner to minimise the overall impact of the development on the local community. The impacts on all stakeholders will be minimised if the work programmes for both stages can be coordinated. If the onshore elements of Stage 2 were subject to a new and separate planning application it is highly unlikely that it would be possible to link the onshore construction of the two stages. The agent also clarifies that the removal of Stage 2 from the application will not reduce the width of the cable working corridor from 40m. Development Committee 12 12 January 2012 Officers’ Comments It is agreed that the inclusion of both Stages 1 and 2 allow for the maximum impact to be considered, so that appropriate mitigation and management can be addressed to minimise the overall impact of the development. None of the technical consultees has objected to the application being considered on this basis. If only Stage 1 were to go ahead then the width of the working corridor would remain at the proposed 40m. This is because of the trench widths required, the distances required between the trenches, and the requirements for vehicular access, sub-soil and topsoil storage. In certain locations, such as hedge crossing points and for environmental reasons, the working corridor would be reduced to 20m in width. Given that the width of the working corridor would remain the same regardless of whether only one or both stages were to go ahead it is not considered that the removal of Stage 2 would reduce the overall impacts upon the landscape and local community compared with those already considered. Issue 3: To request the applicants to reconsider the precise route at Westwood Farm, Great Ryburgh. Applicants’ Response Minor changes to the route planned through the land Mr Boeson farms are shown on the amended plans. These changes were made at the request of the landowner, Mr Cook, to help minimise the impacts on his tenant, Mr Boeson. As with all landowner requests it was considered against stringent environmental and technical criteria; in this case a route change was considered appropriate. The amended route shown is considered by the applicants to represent the lowest impact route, following existing field boundaries where possible. This has the advantage of reducing the areas of farmland that might become temporarily isolated during construction, although such an impact is covered under the crop loss compensation process. The applicants have advised that following the concerns raised by Mr Boeson at the last Committee meeting they have contacted him again to try and review their proposal with him. Whilst Mr Boeson declined to meet with the applicants he appointed an agent to liaise with the applicants and a meeting took place on 31 August 2011. The route selection was discussed and fully explored and agreed that the optimum route had been adopted. The applicants also advise that constructive discussions have been held and are continuing with the agent acting for Mr and Mrs Runciman of Croxton Farm, in terms of avoiding impacts on their potato crops amongst other matters. Discussions are still ongoing with the agent for Kelling Estate. The applicants state that they will continue to liaise with all landowners and tenants to ensure minimal disruption is caused to their farming operations and to ensure that they are fully compensated for any direct or indirect loss of crops both during and following the proposed construction works. The applicants also clarify and reaffirm the compensation payments available for the leasing of the land in which the cables are laid and for crop losses if required. The lease payments go to the relevant landowner. Compensation for any crop losses are typically via the landowner and passed onto the tenant. However, the applicants have advised that they would be happy to directly contract with tenant farmers regarding compensation payments should it be considered helpful for particular landowners and tenants. Development Committee 13 12 January 2012 Officers’ Comments It is considered that the applicants have demonstrated careful consideration of route selection and, as a result of a request from the landowner at Great Ryburgh, Mr Cook, to help minimise the impacts on his tenant, Mr Boeson, have already made minor changes to the route through Westwood Farm. The applicants considered the further concerns raised by Mr Boeson, but consider the amended route in this location to have the lowest impact. None of the technical consultees has raised an objection to the amended route, which reinforces its acceptability. The ongoing discussions that the applicants are having with landowners and tenant farmers are welcomed. In the case of Westwood Farm at Great Ryburgh it has now been suggested that the agent acting for Mr Boeson agrees that the best route has been selected. Further discussions with Mr and Mrs Runciman and the Kelling Estate are continuing. It would appear that progress is being made in relation to this matter and that their concerns and objections raised are to some extent being allayed. It is considered that the further clarification on the compensation payments is helpful, but this is a civil matter between the landowner/tenant and the applicants and is not a planning matter. It is not considered that there would be justification in planning terms for further amendments to be sought. Issue 4: To seek further information on the short-term impact on tourism and agriculture. Applicants’ Response Following reinstatement of the land above the cable system it is unlikely that the presence of the cable system will be noticed, as it is no different from how existing infrastructure is buried and hidden from view. It is highlighted that less than a year after the construction of the cabling for the Sheringham Shoal project that it is doubtful that it could be identified where the cable runs due to the effectiveness of reinstatement works. It is accepted that during construction (approximately 2 years, limited to only a few months at each location) there will be a temporary localised impact on the landscape, traffic and communities. Some minor roads may be closed for a short period but main roads will remain unaffected as HDD techniques will be used. Where necessary road crossings could also be undertaken at night to further reduce any potential disruption. The applicants refer to the advanced techniques and machinery which are more efficient, quicker and less damaging to the environment. It is also stated that environmental laws, planning policy and health and safety laws have considerably increased the requirements for the implementation of best practice techniques. Such projects are well managed, strictly controlled and enforced by stringent measures. The short term impact of the project on the economy will be minor, temporary and primarily in the form of disturbance to traffic and communities. This can be managed and controlled by the development of acceptable timing, location and duration of the activities to ensure that disturbance is kept to a minimum and normality restored as soon as practically possible. Development Committee 14 12 January 2012 In terms of economic impacts it is estimated that the project will require around 100 workers for the onshore cable construction works. Whilst some will be hired locally, the others (technical specialists) will require accommodation locally, providing a significant boost to local B&B’s and hotels. These construction workers and managers will also utilise local stores, restaurants and retail facilities, providing direct income to local businesses over the two year construction period. It is likely that the project will engage local businesses for the supply of materials, such as aggregates (e.g. sand, concrete, hardcore), fencing, site establishment (welfare facilities), maintenance, machinery hire, as well as employing local firms such as environmental survey contractors, soil specialists, land drainage contractors and transport/haulage companies. Whilst difficult to quantify and guarantee the exact nature of these benefits, these locally sourced contracts and purchases will also provide a significant boost to the local economy running to several millions of pounds based on feedback from the recent Sheringham Shoal project. In the longer term the cable system will have no adverse impact on the daily lives or economy of North Norfolk. The wind farm will generate significant economic opportunities in the development, construction and maintenance of the wind farm and associated assets. The maintenance costs of the project are expected to be around £40m per year. The 2009 – 2010 Wells Harbour Commissioners Annual Report show over £1 million investment by Scira, the project owners of the Sheringham Shoal project, with investment continuing. An article is included in the applicants’ full response in Appendix .. from the Wells Harbour website. The applicants consider that Members should be encouraged by the potential benefits to the local community and that Stage 1 of the Dudgeon project alone has almost twice the generation capacity of the Sheringham Shoal project and greater infrastructure requirements. Officers’ Comments It is agreed that once reinstatement of the land above the cable has been completed the visual impact would be minimal. It is also agreed that techniques and machinery for such work are advanced, with strict controls in place to ensure that any impacts upon the environment would be appropriately mitigated against and remediation measures imposed. Clearly there would be some impact visually on the landscape as well as to traffic and local communities, which is accepted by the applicants. However, given that the works required for the construction of the cable route are temporary the impacts would also be temporary. Concerns were previously raised by the Committee on this matter together with impacts on tourism and agriculture which are important areas of income in North Norfolk. However, the impacts on agriculture would be addressed through compensation payments should any losses occur to landowners and tenants, which has been explained under Issue 3 of this report and explained in further detail by the applicants under point 2 of their letter dated 18 November 2011 in Appendix 2. The impact on traffic has also been considered and the applicants have explained the position that there may be some road closures for short periods of time and on a temporary basis. If any road closures are required the applicants have explained that these would be on minor roads. It is suggested that most traffic, particularly tourist traffic, would be using the main routes rather than minor roads. The main roads would be unaffected as HDD would be used at these crossing points. The applicants Development Committee 15 12 January 2012 have also suggested night-time working at road crossings to further reduce any potential disruption. This is a matter that requires consideration by the County Council as Highway Authority through a Traffic Management Plan. It should be noted that the Highway Authority has raised no objection to the application subject to a condition being imposed requiring the submission of a Traffic Management Plan. The County Council Public Rights of Way Officer has also raised no objection. The applicants have explained that if the application were approved this could benefit the local economy by creating employment locally, using local accommodation and facilities as well as local businesses for the supply of materials and equipment. It could also bring investment to the area as demonstrated by the Sheringham Shoal project and the 2009 – 2010 Wells Harbour Commissioners Annual Report. The Committee will note the comprehensive analysis of the impact of the energy industry on the economy of North Norfolk prepared by the Economic and Tourism Development Manager contained in Appendix 2, following receipt of the additional information submitted by the applicants. The analysis considers the impact of offshore wind energy developments in particular the North Norfolk economy and the significance of the current project. In summary, the Economic and Tourism Development Manager has explained how the growing importance of the energy industry has elevated the coastal and maritime area of North Norfolk to become one of the most important investor development areas in the region, and that the North Norfolk coastline is now one of the region’s largest markets for offshore wind turbine development, and also a major prospect for future carbon capture and storage. Wind energy development off the North Norfolk coastline is expected to generate positive economic effects for North Norfolk and the wider area over the next forty plus years. Given the likely total project investment cost to be applied to North Sea wind energy development, the effect on the local economy is considered to be beneficial. Positive effect will not only arise through direct employment opportunities but also via construction, supply chain and maintenance activities. As a result of this activity it is likely that there will be local employment generated as an indirect result of the construction of North Sea wind farm. Indirect employment will include supply chain benefits for local businesses, sub-contracted work relating to the transportation of labour and materials, and expenditure by construction employees in the local economy. A further benefit will arise in terms of wider ‘up-skilling’ of local people and the general aspiration of existing businesses to be part of the global effect of this industry. An example is the positive effect on the growth of the Wells economy as direct result of the Sheringham Shoal wind farm development. Wells-next-the-Sea and its harbour already shows gains both in terms of employment and localised business engagement. It is expected that this relatively small wind farm will attract further economic gains through supply chain and cluster development. The Economic Development Unit recognises this application as being one of the most fundamental prerequisites for kick-starting the emerging offshore wind energy industry in Norfolk. The Economic Development Unit fully supports this planning application recognising the benefits that underground cabling can bring to both the environment and the tourism economy. Development Committee 16 12 January 2012 In summary whilst it is considered that there would be temporary impacts on the landscape and the road network, there would also be benefits by generating employment and boosting the local economy which could have longer lasting impacts and are a material consideration in the determination of this application. Issue 5: To seek the applicants’ view as to the use of horizontal directional drilling across the Rivers Stiffkey and Wensum. Applicants’ Response The applicants have agreed to extend the HDD at the River Wensum in Great Ryburgh to further reduce impacts on the meadow. With regard to the River Stiffkey the position has not changed. The point of crossing is approximately 1m wide, and is not a designated River. The Stiffkey Valley SSSI area is located over 11.5km to the north of the crossing point. However, as a precaution and part of the agreed ecological mitigation strategy a full ecological watercourse and protected species survey is scheduled to be undertaken during the pre-construction surveys. HDD techniques may still be employed if appropriate to safeguard any sensitive species identified. In the event that there are no protected species or other sensitivities identified in agreement with Natural England and North Norfolk District Council, open cut trenching will be employed to reduce the direction of the crossing and minimise disturbance at this location. Officers’ Comments The applicants’ agreement to extend the HDD at Great Ryburgh is welcomed and supported. A meeting between Officers and the applicants has taken place on site to discuss the amended plan submitted, and clarify the length of the extension. It is proposed to extend the HDD at this location by 63m, making a total length of 268m. This amendment has been re-advertised on site and the relevant consultees including Ryburgh Parish Council and the District Council’s Conservation, Design and Landscape Manager re-consulted. The Conservation, Design and Landscape Manager advised that Natural England and the Environment Agency also needed to be re-consulted on this amendment. Whilst Ryburgh Parish Council maintain their objections for the reasons previously stated, the Conservation, Design and Landscape Manager and Environment Agency have raised no objection to the proposed extension to the HDD in this location. Natural England has confirmed its support. The Conservation, Design and Landscape Manager advises that the extension would conserve in situ an additional section of grazing marsh and the dyke which was formerly the main river channel. It is considered that this would also allow the appropriate siting of the drilling compounds within the flood plain. As will be noted with regard to HDD at the River Stiffkey, the applicants’ position has not changed. It was explained in the Committee report of 14 July 2011 that whilst the Conservation, Design and Landscape Manager originally had concerns over the proposal to open trench at this point further discussions took place with the applicants and an Ecological Mitigation Summary was received. This satisfied the Conservation, Design and Landscape Manager that open trenching was acceptable at this point as it would result in less disturbance to the water meadows than if directional drilling were to be used. This view has not changed. However, if following pre-construction surveys it is deemed necessary to HDD at the River Stiffkey to safeguard any sensitive species, there would also be no objection from the Conservation, Design and Landscape Manager. No technical consultees have objected to this. Development Committee 17 12 January 2012 Issue 6: To seek further information in respect of soil heating. Applicants’ Response The applicants have provided further information on soil heating and possible effects on crop yields, as well as the impact on the work programme limiting the removal of soil in dry conditions. The applicants reiterate that heat dissipation from buried cables represents a loss of energy from the electrical system which equates to loss of revenue for the project. The prime focus of the design of any electrical system is to minimise these ‘losses’ (i.e. heat) and a variety of engineering options are available to achieve this for different circumstances. The applicants explain that as the 45km cable route is made up of 76 sections, with an average length of 700m there is sufficient flexibility to vary the design of each section to eliminate any predicted adverse thermal impact that may be identified during the detailed design. They also advise that the design criteria of the cables will ensure that the first 500mm of topsoil will remain virtually unaffected by any heat generated even when operating under peak design conditions for long periods in summer conditions. The applicants consider that crop yields would be unaffected under all reasonably foreseeable conditions, but in the unlikely event that there is a negative impact then the compensation payment mechanisms already referred to in this report would be applied. The cable system design will be so as to ensure that the thermal limits for the cables are not exceeded at any point along the cable route. These limits are only ever expected to be approached in rare and exceptional circumstances and even then for a short period of time. A Distributed Temperature Sensor (DTS) system will be used on the project to monitor the cable system temperature to ensure that cable temperatures are maintained within acceptable limits. It has been suggested that the buried cables will operate continually at 90°C. This is incorrect; the 90°C figure is the maximum temperature at which the core could theoretically operate without degradation of the cables electrical insulation and risk of cable failure, i.e. it is the guarantee level from the cable manufacturer. It is not in the project’s best interests to design and export connection such that the cables run at these ‘hot’ temperatures, as has been suggested, due to the increased electrical losses. Using the standard industry techniques mentioned above the cables will be designed to ensure that they run ‘cold’, under predicted loading patterns, to minimise electrical losses. To clarify the terms ‘hot’ and ‘cold’ have been used here and previously as relative engineering terms, and are not meant as they are commonly used, in absolute terms. The electrical insulation and mechanical cable protection used around each cable core will also limit the amount of heat that passes to the surrounding sand and earth. The applicants re-iterate the views of National Grid that overheating risks can be designed out with a range of depths and cable sizes. The applicants have also advised that whilst the Sheringham Shoal project has buried cables, it is normal practice on cost grounds for most generation projects to use overhead lines and pylons in rural areas. This option eliminates any possible risk of soil heating impacts on crops, although it raises major visual impact challenges. Development Committee 18 12 January 2012 The applicants re-iterate that detailed considerations regarding the protection and handling of soils will be set out in a Soil Management Plan for agreement with the District Council prior to onshore works commencing. Soil handling practices will be employed on a field by field basis and dependent on a number of factors, and are expected to prioritise certain locations for ‘summer working’ where practicable particularly for the handling of topsoil. The applicants re-iterate their commitment to adhering to DEFRA best practice guidance on soil handling and reinstatement. The applicants have referred to a specific paragraph in the “Construction Code of Practice for the Sustainable Use of Soils on Construction Sites” (DEFRA 2009), which provides advice on how to treat different soil types after sustained heavy rainfall, which they will follow. Allowing for restrictions due to weather and soil conditions the applicants advise that there is adequate flexibility to ensure that the project programme has sufficient contingencies built in to cope with potential delays from extended periods of unfavorable weather conditions. The initial feedback from contractors experienced in undertaking this type of construction work has confirmed that a conservative timetable has been assumed for this project and that it contains adequate contingency for this and any other considerations. It is in the projects commercial interests that soils are handled in accordance with the above best practice so as to ensure that the land is restored at the earliest time to the same productiveness as the remainder of the fields through which it passes. Officers’ Comments The District Council’s Soil Consultant has responded to the applicant’s comments on soil issues, and subsequent correspondence and clarification on this matter has taken place and is contained in full in Appendix 2. In summary, the response received from the District Council’s Soil Consultant is that the soil issues raised are not insurmountable and that a detailed design of the cable system and Soil Management Plan should be conditioned to be submitted for agreement with the District Council and in consultation with the Soil Consultant prior to the commencement of the development. In particular the Soil Consultant advises that in relation to soil depth crops root into soil at different depths and that roots extract water from the soil to take up nutrients to prevent wilting. Water storage capacity of soils is finite but varies with texture, structure and stoniness. If crop demands for water exceed the available water reserves in the soil the growth of the crop will slow or cease and yield will be reduced. It is the Soil Consultant’s recommendation that crop extraction of water from the deeper subsoil is factored into the Soil Management Plan and the related design aspects of the scheme, such as cable depths. With regard to the impact of soil heating on crop growth the Soil Consultant advises that this is not limited to the potential for drying of the subsoil surrounding the cables as implied by the applicants. Any raising of soil temperature has the potential to alter the rate of growth and development of the crop along the line of the cables. This may constitute an acceleration of its rate of growth and development such that it advances to maturity ahead of the rest of the field. Such advancement may present challenges to management, protection from pests and harvesting of the crop. This principle needs to be addressed during the detailed design of the cable installation. Notwithstanding the above the Soil Consultant has advised that in his view it should be feasible to design and install the cables in such a way that potential impacts on subsequent crop growth are negated or at least minimised. It is understood that Development Committee 19 12 January 2012 compensation to landowners would be available in the event that any significant impact is evident. It is therefore considered that a detailed design of the cable system and Soil Management Plan should be conditioned if the application were to be approved to allow these matters to be addressed. It is therefore considered that whilst the Soil Consultant has raised some points in relation to soil heating and impacts on crops these are matters that can be addressed in the detailed design and Soil Management Plan to be agreed with Officers and the Soil Consultant. They are not considered to be issues of sufficient significance to justify the refusal of planning permission. Other Issues Clarification was also sought from the applicants regarding jointing bay covers and hedge transplantation as follows: 1. Confirmation that the jointing bay covers will be removed once the jointing of each length of cable is completed It is confirmed that the jointing bay covers, used as protective screens during cable jointing, would be removed when the jointing operations at each location have been completed. 2. Views on the circumstances under which the Applicants would consider hedge transplantation During the design of the mitigation strategy the utilisation of hedgerow translocation and transplantation was reviewed. However, due to the high failure rate this is not currently recommended by any of the ecologists that have been consulted, nor requested by any of the consultees, including the District Council, Natural England or the Environment Agency. Updates In terms of report updates an email has been received from an objector following the Little Dunham appeal decision being issued. The objector considers that: 1. The message given in the decision is that the substation was industrial in nature and should only be sited in an industrial location, not a rural location. 2. The decision states that the substation is not suitable for a rural location and any other rural location will face the same issues and will not be acceptable, unless it is a major industrial location, which given the size of 25 acres plus it would have to be in an industrial estate which would be Kings Lynn. 3. This means that the cable route proposed in North Norfolk has nowhere to link up to and therefore there is no evidenced need for it. In addition to the above the applicants have now confirmed in writing that the cable route would be constructed using an AC connection and not a DC connection. This does not affect the determination of this application. Both connections have been fully considered as part of the application. The submitted plans are based on an AC connection as this type of cable system requires earthing, and the need for the cable jointing bays and cross bonding locations. These would not have been required if a DC connection were used. With the use of an AC connection the cross bonding equipment would be placed in buried pits with a surface manhole of approximately 1m by 1.3m in size. It is accepted that this would have minimal visual impact. However, in certain locations it may be necessary to install above ground inspection pillars. The pillars would measure approximately 1.16m in height by 1.05 wide and 0.46m deep. It is considered that this would have minimal visual impact and minimise Development Committee 20 12 January 2012 the impact on the use of the land. The Conservation, Design and Landscape Manager has raised no objection on this matter, nor has any of the other technical consultees. Details of the underground cable layout and above ground features, including cross bonding pits and pillars, can be conditioned to be submitted to and approved in writing by the Local Planning Authority prior to the commencement of the development. Consultee responses following the receipt of amended plans in relation to extending the HDD location at Ryburgh: Ryburgh Parish Council - Object to the amended application for the reasons as previously set out. Environment Agency – The amendment does not alter our previous comments. Natural England – Support Conservation, Design and Landscape Manager - Further to a visit with the applicants at the site of the River Wensum section of the cable route and the receipt of amended plans detailing an extension to the HDD section within the flood plain of the river, the following comments are given. An extension to the HDD operation on the northern part of the flood plain of the River Wensum was suggested by both Officers and Members with a view to minimising the disruption to the water features and semi-natural habitat found at the site. Following a site visit and recent works by the Environment Agency to realign the river with the former channel, it was concluded by both the applicants and myself that a small extension to the proposed HDD section would be the most appropriate course of action. The proposed extension to the HDD operation would conserve in situ an additional section of grazing marsh and the dyke which was formerly the main river channel and would also allow the appropriate siting of the drilling compounds within the flood plain without causing undue damage to the habitat. It was not considered necessary to increase the HDD further as this would serve no purpose and cause greater disruption to the trees and hedges bordering the flood plain. Therefore CDL approve the amended plans, subject to appropriate conditions to safeguard trees, biodiversity and landscape (requested as part of the previous consultation process), and do not object to the application. Key Policy Issues The key policy issues are the compliance of the development with the relevant National, Regional and Local plan policies which are detailed in full in the report to the meeting on 14 July 2011 in Appendix 2. It also considered at some length the acceptability of the development having regard to the issues of landscape and visual impact, impact on nature conservation, impact on archaeology and cultural heritage, impact on residential amenities, impact on use of land by landowners including soil issues, highway safety, health concerns, principle of the need for development, consideration of alternative routes, East Coast Transmission Network (ECTN), and landfall point at Weybourne Hope. Other Material Considerations Other material considerations on this matter include ministerial advice from the Rt Hon Greg Clark MP – Minister for Decentralisation concerning Planning for Growth dated 23 March 2011. Development Committee 21 12 January 2012 The ministerial advice states, amongst other things, that: When deciding whether to grant planning permission, local planning authorities should support enterprise and facilitate housing, economic and other forms of sustainable development. Where relevant - and consistent with their statutory obligations - they should therefore: (i) consider fully the importance of national planning policies aimed at fostering economic growth and employment, given the need to ensure a return to robust growth after the recent recession (ii) take into account the need to maintain a flexible and responsive supply of land for key sectors, including housing (iii) consider the range of likely economic, environmental and social benefits of proposals; including long term or indirect benefits such as increased consumer choice, more viable communities and more robust local economies (which may, where relevant, include matters such as job creation and business productivity) (iv) be sensitive to the fact that local economies are subject to change and so take a positive approach to development where new economic data suggest that prior assessments of needs are no longer up-to-date (v) ensure that they do not impose unnecessary burdens on development. In determining planning applications, local planning authorities are obliged to have regard to all relevant considerations. They should ensure that they give appropriate weight to the need to support economic recovery, that applications that secure sustainable growth are treated favourably (consistent with policy in PPS4), and that they can give clear reasons for their decisions. The Committee is referred to the ministerial advice in full. It constitutes a material consideration to which appropriate weight should be afforded. It is a matter for the Committee to decide what weight to give this statement. In July 2011, the Department for Communities and Local Government issued Draft National Planning Policy Framework (NPPF) for consultation which, amongst other things, places greater emphasis towards securing sustainable economic growth. Whilst the NPPF is not yet adopted Government policy it does give a clear indication of the Government’s current intent. Again it is a matter for the Committee to decide what weight to afford this document as a material planning consideration given that it is only in draft at this stage and, following the consultation process, it may be revised or altered in light of that consultation process. It is considered that the NPPF is a matter which does attract some weight at this stage given that it is consistent with the previous statements of Government policy. Summary Whilst the appeal for the substation at Little Dunham has been dismissed the Secretaries of State concluded that a sub-station would be ‘vital to the utilisation and distribution of off-shore wind energy’. They attached significant weight to the wider environmental and economic benefits of the proposal in accordance with the requirements of PPS22. The need for the sub-station was therefore accepted but the location was not ‘given the harm proposed on the visual impact of the landscape and significant change to the perception of the village which was considered to be damaging to its rural ambience along with the intrinsic beauty of the landscape’. The development subject to that appeal was for a substation consisting of some 4 DC converter buildings measuring 70m long, 25m wide and 15m high, an array of electrical switch gear and connection apparatus up to 12m high, along with cable gantries at a maximum height of 15m as well as banks of external fans, filter banks, Development Committee 22 12 January 2012 control rooms, car park and access road with an inner compound containing all of the electrical apparatus being protected by a metal palisade security fence. These are all permanent above ground structures. The application for consideration by this Council is for the installation of buried electrical cables, which once installed would have minimal impact. The only above ground structures that may be required in certain places are the above ground inspection pillars at cross-bonding locations. The pillars would measure approximately 1.16m high, 1.05m wide and 0.46m deep. Clearly, during the construction phase the 40m wide working corridor (reduced to 20m wide at certain points) would have a substantial visual impact upon the landscape, but this would be for a temporary period only. Following the receipt of additional supporting information from the applicants on soil issues and clarifying a number of points the District Council’s Soil Consultant is of the opinion that it is feasible to design and install the cables in such a way that potential impacts on subsequent crop growth are negated or at least minimised, and that the issues in relation to soils raised by objectors can be addressed through a Soil Management Plan. It is not considered that the issues raised in relation to soils are insurmountable nor would there be sufficient grounds to support refusal of the application. The Committee will note the detailed response of the Economic and Tourism Development Manager who fully supports the application. It is considered that wind energy development off the North Norfolk coastline is expected to generate positive economic effects for North Norfolk and the wider area over the next forty plus years. The effect on the local economy is considered to be beneficial, and will have a positive effect through direct employment opportunities, as well as through construction, supply chain and maintenance activities. In respect of the project as a whole it is concluded that appropriate remediation and mitigation measures would be provided and would be required by conditions. No objections have been received from the technical consultees. The imposition of relevant conditions requested by the consultees are considered to be acceptable. The proposal is considered to accord with national and Development Plan policies. RECOMMENDATION: Approve, subject to the imposition of appropriate conditions, incorporating those required by consultees, and including the following: Working hours, noise mitigation, dust control, Traffic Management Plan, site investigation into contaminants, contamination mitigation and pollution control, pre-construction surveys, mitigation scheme for protected species, submission of a programme of archaeological work, hedgerow removal and reinstatement, phasing of cable installation, details of underground cable layout, positioning of cross bonding pits and pillars, proposals for reinstatement of cable trenches at the end of construction activities including timescales, preventing the commencement of the development unless or until the wind farm is approved including that proposed under Stage 2, Construction Method Statements, micro-positioning of compounds, Environmental Action Plan, soils including a Soil Management Plan to cover detailed site specific cable design, installation plans and soil management. (Source: Jo Medler – Senior Planning Officer , ext 6128) Development Committee 23 12 January 2012 PUBLIC BUSINESS - ITEM FOR DECISION 3. SALTHOUSE - Residential conversion of barns at Bard Hill (applications 20060642 and 20060736) A report seeking Committee’s approval to waive payment of first financial contribution towards affordable housing and renegotiate the second payment. Background The above planning applications were approved in June 2006 and February 2007 respectively, and allow the conversion of barns at Bard Hill, Salthouse into six dwellings. The approvals were given in the context of the North Norfolk Local Plan. A Section 106 Agreement signed on 8 February 2007 provides for the provision of a financial contribution in lieu of on site affordable housing. The financial contribution of £92,000 is to be paid in 2 tranches. The first tranche is to be paid “within 21 days from the completion of the sale of the third of the six dwellings to be created by the permissions and the second payment to be made within 21 days from the date of completion of the sale of the sixth dwelling to be created by the permission.” Four of the six dwellings have been provided through the conversion of the barns and three have been sold. The first tranche of the affordable housing contribution is now outstanding as the sale of the third dwelling was completed on 29 July 2011. The applicant has written to the Council to request that the affordable housing contribution is removed. The applicant states “The removal of the financial contribution will also relieve the bank pressure on us and as they are party to the 106 this will hopefully prevent the company going into some form of insolvency which will help nobody.” The Council has not received any independent confirmation that the applicant is facing some form of insolvency. Information provided by the applicant has been received which shows that when the financial contribution was agreed in 2007 it was viable for this contribution to be provided. As the financial contribution is to be paid in two tranches and only the trigger for the payment of the first tranche has been reached, the viability of paying the first tranche based on the costs of conversion and sale proceeds for the first three dwellings has been considered independently of the requirement to pay a second tranche. Consideration of whether it is viable for the applicant to pay some or all of the second tranche payment of £46,000 can only be carried out once the remaining barns have been sold and the full costs and actual sales income received are known. The Council’s Housing Strategy Team Leader has analysed the information provided by the developer on the cost of converting the barns and considers that the proceeds received from the sale of the three sold barn conversions show that it is not viable for the applicant to provide any of the first tranche of the affordable housing contribution at this stage. The sale of a fourth (converted) barn is currently on hold as the purchaser’s Solicitors do not want their purchaser to be liable for the outstanding contribution. (This would not be the case as the applicant is liable). Further information is being sought concerning the costs of works carried out to one barn which is in an unconverted state and is unsold. Development Committee 24 12 January 2012 In the light of the Housing Strategy Team Leader’s advice it is recommended that the request be granted. RECOMMENDATION That the developer be allowed to proceed with the conversion of the remaining units without being required to pay the first tranche of the affordable housing contribution at this time and that the viability of providing the second payment be considered when all the barns have been sold and all costs of the conversion are known. (Source: Gary Linder – Senior Planning Officer , ext 6152) PUBLIC BUSINESS – ITEM FOR DECISION 4. CHANGE TO PROCEDURE FOR RESOLVING ENFORCEMENT CASES This report requests the Committee’s consideration of a strategy for the management of Enforcement caseload. Members will recall that at the last meeting a long schedule of outstanding enforcement cases was considered and will have noted that a backlog of cases more than three months old had built up. As part of a strategy for dealing with this situation it is intended to group cases into District Ward areas and to seek to use delegated powers already available to the Head of Planning and Building Control in the Council’s Constitution to resolve cases with the agreement of local Members and the Chairman (or Vice-Chairman) of the Committee. Historically, cases have only been removed from the schedule when it has been established: 1) That there is no breach of planning control; 2) That the breach has been remedied on a voluntary basis; 3) That Enforcement action has been taken, either using delegated powers or with the Committee’s authority; or 4) That no further action should be taken, with the agreement of the Committee. With respect to this latter category, it is now proposed to use delegated powers, following discussion with local Members, to agree cases where it is not considered expedient to pursue Enforcement action as suggested above. If either a local Member or the Chairman of the Committee were to disagree, action would continue to be pursued or the matter reported to Committee in the normal way. It is hoped that by using this route a number of minor cases can be resolved efficiently, thus allowing effort to be concentrated on more significant breaches of control. Depending on the nature and number of outstanding cases, it may be more efficient to hold meetings with individual Ward Members and the Chairman where there are groups of cases to discuss, concentrating initially on those Wards where the largest number of cases exist. The process is likely to take several months to complete because of the size of the backlog. Development Committee 25 12 January 2012 Members will, of course, have the opportunity to review progress every quarter through scrutiny of the Schedule of Outstanding Cases. The Committee is asked to support this initiative with the aim of managing more effectively current enforcement workload. RECOMMENDATION That the Committee notes and supports the use of delegated powers to resolve outstanding Enforcement cases in consultation with local Ward Members and the Chairman/Vice-Chairman of the Development Committee. (Source: Steve Oxenham, Head of Planning and Building Control ext 6135) PUBLIC BUSINESS – ITEMS FOR DECISION PLANNING APPLICATIONS Note :- Recommendations for approval include a standard time limit condition as Condition No.1, unless otherwise stated. 5. HOLT - PF/11/0989 - Conversion of outbuilding to two-storey dwelling and erection of 2 two-and-a-half-storey dwellings; Land rear of 27 High Street for C T Baker Ltd Minor Development - Target Date: 05 October 2011 Case Officer: Miss T Lincoln Full Planning Permission See also application LE/11/1013 below. CONSTRAINTS Archaeological Site Primary Shopping Area Conservation Area Town Centre Listed Building Grade II RELEVANT PLANNING HISTORY PF09/0397 - Conversion of stable to two-storey dwelling and erection of two twostorey dwellings Refused 16/06/2009 PF/09/0872 - Conversion of stable to two-storey dwelling and erection of two-storey dwelling Withdrawn by Applicant 15/03/2009 THE APPLICATION Is for the conversion of a stable to a two-storey dwelling and the erection of two x two-and-a-half-storey dwellings. A stable adjacent to the listed building to the north-west would be converted to form a two-bedroom dwelling. Existing offices and storage areas would be demolished and two x two-bedroom dwellings built on the same footprint. Small courtyard gardens for each dwelling would be provided and a courtyard area to the front of the dwellings would provide a further shared area of outside space. Development Committee 26 12 January 2012 Pedestrian access would be taken from a private track off the highway with no vehicular parking provision. The application has been amended to reduce the height and scale of the two proposed dwellings from originally three-and-a-half-storey to two-and-a-half-storey dwellings and to amend window openings on the front elevation of unit 1. REASONS FOR REFERRAL TO COMMITTEE Managing director of applicant company is a Member of the Council. TOWN COUNCIL Comments on original application. Objects to the application for the following reasons: There are concerns relating to access on to High Street, access for emergency services, and exacerbating existing traffic congestion in the High Street. Comments on amended application - No objection. CONSULTATIONS Sustainability Co-ordinator - No objection subject to compliance with the submitted sustainability construction checklist and with the Code for Sustainable Homes level 3. County Highway Authority With reference to the consultation received recently to the above development proposal, I would be against any proposal to intensify the vehicular use of the access that serves these buildings The application form indicates that no vehicular parking provision is to be provided within the site. It is acknowledged that providing on site vehicular parking would be extremely difficult to provide for the 3 proposed dwellings, however in the previous application it was detailed that 6 cycle parking places were available, I would consider that the provision of these cycle spaces is beneficial and I would seek its inclusion in this application Given the town centre location and subject to the cycle parking being detailed and conditioned to prevent vehicular use, I have no objection to the proposal, therefore, should your Authority be minded to approve the application the following conditions should be appended to any consent notice issued:- No works shall commence on site until a scheme for the increased parking of cycles (6) has been submitted to and approved in writing by the Local Planning Authority. The scheme shall be fully implemented before the development is first occupied or brought into use and thereafter retained for this purpose. Conservation, Design and Landscape Manager - No objection to the principle of this development. Amendments to the window openings on the front elevation of unit 1 and clarification around the roof entrance to unit 2 are required. Following receipt of this it is anticipated C&D would be able to lend support to this scheme. Further comments are awaited on the amended plans received. Environmental Health - No objection subject to a condition requiring details of the method of demolition to be agreed. Development Committee 27 12 January 2012 HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. Having considered the likely impact on an individual's Human Rights, and the general interest of the public, approval of this application as recommended is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): Policy SS 1: Spatial Strategy for North Norfolk (specifies the settlement hierarchy and distribution of development in the District). Policy SS 5: Economy (strategic approach to economic issues). Policy SS 9: Holt (identifies strategic development requirements). Policy HO 1: Dwelling mix and type (specifies type and mix of dwellings for new housing developments). Policy HO 7: Making the most efficient use of land (Housing density) (Proposals should optimise housing density in a manner which protects or enhances the character of the area). Policy CT 5: The transport impact on new development (specifies criteria to ensure reduction of need to travel and promotion of sustainable forms of transport). Policy CT 6: Parking provision (requires compliance with the Council's car parking standards other than in exceptional circumstances). Policy EN 4: Design (specifies criteria that proposals should have regard to, including the North Norfolk Design Guide and sustainable construction). Policy EN 6: Sustainable construction and energy efficiency (specifies sustainability and energy efficiency requirements for new developments). Policy EN 8: Protecting and enhancing the historic environment (prevents insensitive development and specifies requirements relating to designated assets and other valuable buildings). MAIN ISSUES FOR CONSIDERATION 1. Principle of the development 2. Density 3. Scale and design 4. Impact on the adjacent listed building and Conservation Area 5. Residential amenity 6. Impact on the highway and parking provision APPRAISAL The site is located within the Holt Town Centre and designated primary shopping area as defined by the Core Strategy and is also within the Holt Conservation Area, where Core Strategy Policies SS 5, EN 4 and EN 8 are particularly relevant. Policy SS 5 states that in town centre locations residential proposals will be permitted, where they do not result in the loss of shops or other main town centre uses located within a defined Primary Shopping Area. Proposals should also have regard to the integration of public transport in town centres and seek to provide pedestrian friendly environments. Policies EN 4 and EN 8 require that all development will be designed to a high quality, reinforcing local distinctiveness and that design which fails to have regard to local context and does not preserve or enhance the character and appearance of an Development Committee 28 12 January 2012 area will not be accepted. In addition proposals should not have a significantly detrimental effect on the residential amenity of nearby occupiers and new dwellings should provide acceptable residential amenity. Given that there are no shops or other significant town centre uses being lost, the principle of new residential development is considered to be acceptable in this location under Policy SS5 of the adopted North Norfolk Core Strategy, subject to satisfactory compliance with other relevant Development Plan policies. The proposal complies with the housing density requirements in accordance with Policy HO7. In respect of the dwelling mix and type, Policy HO1 requires on schemes of three or four dwelling, at least one dwelling to comprise not more than 70sqm internal floor space and incorporate two bedrooms or fewer. In this case all proposed dwellings would have two bedrooms, but none of the dwellings would have a floor area less than 70sqm (they are all approx 80sqm). Given that all three dwellings would have only a limited additional floor area above 70sqm, ensuring that the dwellings would still be modest in scale, it is considered that the core aims of the policy would be met, i.e. that a high proportion of all new homes would be smaller properties. In terms of sustainable construction and energy efficiency, the proposal would comply with Policy EN 6, subject to the two new dwellings being built to meet a level three rating under the Code for Sustainable Homes and the conversion being completed in accordance with the submitted Sustainable Construction Checklist. The compact form of the proposal would be broadly in keeping with the form and character of this part of Holt with its close knit development. The scale and massing of the proposed buildings, following their reduction in scale, would generally relate sympathetically to the surrounding buildings, but further comments regarding design and visual appearance/impact of the proposal in the Conservation Area are awaited from the Conservation, Design and Landscape Manager. In respect of the impact on the adjacent listed building, given that the existing stable adjoining the listed building is to be retained and converted to form a dwelling, it is considered that no adverse impact on the fabric or character of the listed building is likely to result. In respect of residential amenity issues, the close relationship between the proposed dwellings would replicate other similar situations within the town and whilst the garden sizes are small and would not comply with the Design Guide criterion whereby gardens should be no smaller in area than that of the footprint of the dwelling, all three dwellings would also benefit from a shared, hard landscaped courtyard area to the front of the buildings and this would significantly increase their outside amenity area. Furthermore the North Norfolk Design Guide allows for flexibility with this requirement where it would harm design quality or the form and character of the area and to maximise housing density. In this case there is a clear tight knit form of the surrounding development and the scheme is considered acceptable in respect of provision of outside amenity space. With regard to neighbouring amenity, the close relationship between the proposed dwellings would replicate other similar situations within the town and whilst some overlooking of the garden areas of the dwellings to the south would result, since these are already overlooked by the other surrounding dwellings it is not considered that the addition of the proposed dwellings would result in any significantly adverse loss of privacy so as to justify refusal of the application. Development Committee 29 12 January 2012 In terms of the close relationship between proposed units 1 and 2 and the building to be converted to form unit 3, the internal layout of the dwellings and limited opening on the front north elevation of units 1 & 2 would ensure that the proposed courtyard garden for unit 1 would not result in adverse overlooking. Therefore, whilst the relationship between the three dwellings would be close it is considered that there would be no adverse impact on the amenities of any of the proposed dwellings due to the proposed elevation design and internal layout. In respect of the highway impact of the proposal, there is an existing access to the site onto High Street and this has formerly been used for the loading/unloading for the adjacent retail use. The scheme proposed would not provide on site parking and as such the access is not intended for vehicular use. The Highway Authority has confirmed that it would not want to see the use of that access intensified and so the scheme as proposed raises no highway objection. In respect of parking provision, although the proposal would not provide for any vehicular parking, the minimum requirement being a total of 6 spaces (2 per dwelling), Policy CT 6 allows for a reduction is the standard parking requirements in town centres where there are sufficient local services, where there is access to acceptable levels of public transport or where within a Conservation Areas the proposal would result in an improved building design which enhances the character of the built environment. In this case, whilst it is accepted that at the present time there is an under-provision of car parking within Holt, it is well served by public transport and local services. In addition it is considered that the development would enhance this part of the town centre. As such it is considered that the lack of car parking would provide insufficient grounds to justify refusal of the application, particularly since the Highway Authority has raised no objection, subject to cycle facilities being provided. In summary, subject to the Conservation, Design and Landscape Manager confirming no objection to the amended scheme, the proposal is considered to be acceptable and not to conflict significantly with the Development Plan. RECOMMENDATION: Delegated authority to approve, subject to no objection from the Conservation, Design and Landscape Manager in respect of changes to the fenestration on units 1 and 2 and the imposition of appropriate conditions, including submission of precise details of materials, the removal of permitted development rights for alterations, extensions and outbuildings, submission of a scheme for onsite cycle parking provision, compliance with the code for sustainable homes and sustainable construction checklist and any conditions recommended by the Conservation, Design and Landscape Manager. 6. HOLT - LE/11/1013 - Demolition of outbuildings; Rear of 27 High Street for C T Baker Ltd - Target Date: 18 October 2011 Case Officer: Miss T Lincoln Conservation Area Demolition See also application PF/11/0989 above. CONSTRAINTS Conservation Area Listed Building Grade II Development Committee 30 12 January 2012 THE APPLICATION Is for Conservation Area Consent for the demolition of outbuildings at land to the rear of 27 High Street. The buildings to be demolished are a combination of shallow pitched and flat roofed outbuildings to the rear of the site which were formerly used for storage and office use by Betty's of Holt. They would be replaced by residential development the subject of application PF/11/0989. REASONS FOR REFERRAL TO COMMITTEE Managing director of applicant company is a Member of the Council. TOWN COUNCIL No response CONSULTATIONS Environmental Health - no objection subject to a condition requiring a scheme for the method of demolition to be submitted and agreed. Conservation, Design and Landscape Manager - On the basis that the outbuildings in question are not of any particular architectural or historic merit there is no objection to the proposed demolition. Furthermore, as taking down the structures would not create a gap site within the Holt Conservation Area, it is not considered that this application needs to be tied to any redevelopment proposal. HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. Having considered the likely impact on an individual's Human Rights, and the general interest of the public, approval of this application as recommended is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): Policy EN 8: Protecting and enhancing the historic environment (prevents insensitive development and specifies requirements relating to designated assets and other valuable buildings). MAIN ISSUES FOR CONSIDERATION Impact of the proposed demolition on the Conservation Area. APPRAISAL The site is located within Holt Town Centre and designated primary shopping area as defined by the Core Strategy and is also within the Holt Conservation Area, where Core Strategy Policies EN8, EN13 are relevant. Policy EN8 states that proposals involving the demolition of non-listed buildings will be assessed against the contribution to the architectural or historic interest of the area made by that building. Where a building makes little contribution to the area, consent for demolition will be given provided that, in appropriate cases, there are acceptable and detailed plans for any redevelopment or after-use. Development Committee 31 12 January 2012 The scheme as proposed would involve the demolition of a flat roof and shallow pitched outbuilding to the rear of 27 High Street which is Grade II Listed. These outbuildings are separated from the listed building by an old stable which is to be retained and converted. The buildings to be demolished are not of any particular architectural or historic merit and as such it is not considered that their demolition would adversely affect the character or appearance of the adjacent listed building or the wider Conservation Area and this view has been confirmed by the Council’s Conservation, Design and Landscape Manager. A scheme for redevelopment of the site is for consideration under planning reference 11/0989, although as advised by the Conservation, Design and Landscape Manager, as the removal of these structures would not create a gap site within the Holt Conservation Area, it is not considered that this application needs to be tied to any redevelopment proposal by way of a condition. It is therefore considered that the demolition proposed is acceptable and would accord with Development plan policy. RECOMMENDATION: Approve, subject to the imposition of a condition requiring a scheme for the method of demolition to be submitted and agreed. 7. NORTH WALSHAM - PF/11/0372 - Conversion of A1 (retail)/office unit to residential flat; 4 Bank Loke for Anchor Homes Ltd Minor Development - Target Date: 30 May 2011 Case Officer: Miss S Tudhope Full Planning Permission CONSTRAINTS Conservation Area Primary Shopping Area Town Centre RELEVANT PLANNING HISTORY PLA/20060582 PF - Erection of eight flats and two shops Approved 25/05/2006 PLA/20081078 PF - Change of use of two class a1 retail units to offices Approved 29/08/2008 PLA/20050712 PF - Change of use from bakery/retail shop to a1 (retail) Approved 23/05/2005 PLA/20051269 PF - Erection of three shops and six flats Approved 06/10/2005 THE APPLICATION Is for conversion of a ground floor office unit to a one bedroom residential flat. The unit is within a modern building currently comprising of eight flats and two retail/office units, situated to the south east side of Bank Loke. The proposed conversion includes external alterations to the fenestration on the north elevation. Development Committee 32 12 January 2012 REASONS FOR REFERRAL TO COMMITTEE At the request of Councillor A Moore having regard to the following planning issue: Conflict with adopted Core Strategy Policy SS5 TOWN COUNCIL Supports CONSULTATIONS County Council (Highways): No objection, subject to a condition to prevent any overhanging or encroachment upon highway land. Environmental Health: No objection Community Safety Manager: Asked to be advised if permission is granted to enable activation of privacy patches to the CCTV system to prevent intrusion into the private dwelling. Sustainability Officer: No objection subject to imposition of appropriate condition. Planning Policy Manager: No objection. This site is located within the defined Primary Shopping Area of North Walsham Town Centre where the loss of retail units as a consequence of conversion to residential uses is contrary to Policy SS5. The objective of this policy is to support the overall vitality and viability of the town centre by ensuring that its core function as a shopping destination is not undermined. The evidence supplied by the applicant would suggest that this property has only made a very limited contribution to this objective. Since its construction in 2006/07 it has been vacant for approximately 35 months (70% vacancy rate) and despite evidence of marketing during this period there has been little interest. In my view this is likely to be a result of a number of factors including the site location, the limited size of the unit and the current economic climate. Given these circumstances I have no objection to the grant of planning permission. The decision notice should make clear the reasons for the departure from policy and should include reference to location, size, evidence of marketing and current economic climate. HUMAN RIGHTS IMPLICATIONS It is considered that the proposed development may raise issues relevant to Article 8: The Right to respect for private and family life. Article 1 of the First Protocol: The right to peaceful enjoyment of possessions. Having considered the likely impact on an individual's Human Rights, and the general interest of the public, approval of this application as recommended is considered to be justified, proportionate and in accordance with planning law. CRIME AND DISORDER ACT 1998 - SECTION 17 The application raises no significant crime and disorder issues. POLICIES North Norfolk Core Strategy (Adopted September 2008): Policy CT 6: Parking provision (requires compliance with the Council's car parking standards other than in exceptional circumstances). Development Committee 33 12 January 2012 Policy EN 4: Design (specifies criteria that proposals should have regard to, including the North Norfolk Design Guide and sustainable construction). Policy EN 6: Sustainable construction and energy efficiency (specifies sustainability and energy efficiency requirements for new developments). Policy EN 8: Protecting and enhancing the historic environment (prevents insensitive development and specifies requirements relating to designated assets and other valuable buildings). Policy SS 5: Economy (strategic approach to economic issues). MAIN ISSUES FOR CONSIDERATION 1. Impact on the vitality and viability of the town centre and conflict with Policy SS5 2. Impact on the Conservation Area 3 Amenity of parking drives APPRAISAL The site lies within the area designated as Town Centre, Primary Shopping Area and Conservation Area. The main issue for consideration is that the site is located within the defined Primary Shopping Area of North Walsham Town Centre where the loss of retail units as a consequence of conversion to residential uses is contrary to Policy SS5 and would normally be resisted. The objective of this policy is to support the overall vitality and viability of the town centre by ensuring that its core function as a shopping destination is not undermined. The applicant supplied evidence to demonstrate that the property has only made a very limited contribution to this objective. Since its construction in 2006/07 it has been vacant for approximately 35 months (70% vacancy rate) and despite evidence of marketing during this period there has been little interest. The Planning Policy Manager advises that this is likely to be a result of a number of factors including the site location, on the very edge of the Primary Shopping Area, the limited size of the unit and the current economic climate. Given these circumstances a departure from policy is considered acceptable. The applicant was contacted in November after information indicated that the premises may have become occupied by a business. The applicant confirmed that he had set up "the Business Base" as a further attempt to let the premises with the concept being that individuals or other businesses could rent 'business zones' of a size to suit their budget/business which may have been more affordable/relevant in the current climate. Despite this attempt, which has included new signage, flyers and a series of advertisement both locally and on the internet, the applicant has stated that no interest has materialised. The Planning Policy Manager has advised that this latest attempt to utilise the unit for business purposes does not negate the earlier recommendation that a departure from Policy SS5 is considered acceptable in this case. In terms of external amenity space, given the town centre location, provision of the usual private amenity space is not considered necessary. There is an existing bin storage area for the overall development. No parking provision is included, but no objection has been raised by the County Highway Authority which considers that there are extensive limited duration and public car parking facilities within the vicinity of the site. Other residential flats do not have dedicated parking within the development site. Development Committee 34 12 January 2012 The proposal includes some external alterations to the north elevation. Amended plans have been received following the advice of the Conservation Design and Landscape Manager. The amended external design is now considered to be acceptable, would preserve the appearance of the Conservation Area and is in compliance with Policies EN4 and EN8. RECOMMENDATION: Approve, subject to the imposition of the following conditions: 1 This permission is granted in accordance with the plans first submitted with the application (excepting the superseded proposed North elevation plan) and the amended plan received by the Local Planning Authority on 6 December 2011. Reason: To ensure the satisfactory layout and appearance of the development in accordance with Policy EN 4 of the adopted North Norfolk Core Strategy. 2 Unless otherwise approved in writing by the Local Planning Authority, the residential flat subject to this permission shall not be occupied until the following measures identified in the Sustainable Construction Checklist submitted with the planning application have been implemented: i. More than 80% of light fittings to be fitted with low energy (45 lumens/Watt or greater) bulbs. ii. All new timber used in construction to be from a certified sustainable (i.e. Forest Stewardship Council, or equivalent) source. iii. Water saving fixtures and fittings to be installed comprising showers with a maximum flow rate of 9l/min, aerated or reduced flow taps with a maximum flow rate of 6l/min and WCs with a 6/4l dual flush or lower. Reason: In the interests of achieving a satisfactory form of sustainable construction in accordance with Policy EN 6 of the adopted North Norfolk Core Strategy. Note: The applicants are advised that no part of the proposed structure (to include fascia board/rainwater goods and guttering) should overhang or encroach upon highway land and no gate/door/ground floor window, if installed, should open outwards over the highway. 8. APPLICATIONS APPROVED UNDER DELEGATED POWERS ALBY WITH THWAITE - PF/11/1268 - Use of land for siting 4 camping pods and shower pod; Land at Deers Glade, Hanworth for Deers Glade CCP (Full Planning Permission) ALDBOROUGH - PF/11/1197 - Erection of single-storey side extension; The Old Rectory, Hall Road for Mrs P Hammond (Householder application) ALDBOROUGH - PF/11/1221 - Creation of wildlife pond; East end of the Village Green for Aldborough Wildlife Group (Full Planning Permission) Development Committee 35 12 January 2012 ANTINGHAM - AI/11/1342 - Continued display of illuminated advertisement; Elderton Lodge, Cromer Road, Thorpe Market for Gunton Arms Ltd (Advertisement Illuminated) AYLMERTON - PF/11/1177 - Raising of roof to provide first floor habitable accommodation and erection of two-storey rear extension; Row Farm, Holt Road for Mr & Mrs C Pigott (Householder application) AYLMERTON - NMA1/09/0979 - Non-material amendment request for installation of two rooflights; Park Wall Farm, Park Road for Mr & Mrs A Colman (Non-Material Amendment Request-Household) BACTON - PF/11/1294 - Erection of replacement double garage; The Old Rectory, Rectory Road, Edingthorpe for Mr & Mrs Vincent (Full Planning Permission) BARTON TURF - PF/11/1314 - Variation of Condition 2 of permission reference: 11/0457 to permit insertion of gable window; Primrose Cottage, Common Road The Common for Mr P Sizmur (Full Planning Permission) BARTON TURF - NMA1/08/0012 - Non material-amendment request to change thatched roof to clay pantiles; Sheralon, Smallburgh Road for Mr Jewell (Non-Material Amendment Request-Household) BINHAM - PF/11/1143 - Removal of Condition 11 of permission ref: 07/1951 to permit full residential occupation; The Cartshed, Westgate Farm Barns, 91 Warham Road for Mr D Thompson (Full Planning Permission) BLAKENEY - PF/11/1071 - Demolition of attached workshop and detached carport, erection of one and a half storey side extension, one and a half storey annexe/garages with link extension, creation of balconies, dormer windows overhanging roof eaves, insertion of rooflights, first floor windows and doors, raising height of roof and installation of solar panels and skinning of the existing brickwork with brick and flint; Sedges, Back Lane for Draycott Developments Ltd (Householder application) BLAKENEY - LA/11/1091 - Removal of dormer and installation of two conservation rooflights; The Old Rectory, 6 Wiveton Road for Mr Smedley (Listed Building Alterations) BLAKENEY - PF/11/1315 - Installation of gable window; Moonrakers, Back Lane, Blakeney, Holt, NR25 7NP for Mrs S Rogerson (Householder application) BODHAM - PF/11/1062 - Erection of building to provide car showroom and two industrial units; Crayford And Abbs, Weybourne Road for Crayford & Abbs and North Norfolk Garden Machinery (Full Planning Permission) Development Committee 36 12 January 2012 BRISTON - PF/11/1249 - Erection of extension to cartshed to form annexe; Lark Rise, Craymere Road for Mr Glasspole (Householder application) BRISTON - NMA1/10/1147 - Non-material amendment request for revised roof profile to units 4-7; 125-131 Fakenham Road for Victory Housing Trust (Non-Material Amendment Request) CLEY-NEXT-THE-SEA - PF/11/1229 - Installation of front and rear dormer windows and extension of roof; Anterton, Hilltop for Mr Batten (Householder application) COLBY - PF/11/1154 - Conversion of outbuilding to residential annexe/holiday accommodation; Barn at Old Mill Farm, Mill Road, Banningham for Mr Clements (Full Planning Permission) COLBY - PF/11/1310 - Erection of single-storey rear extension (revised roof detail); Magnolia Cottage, Church Road for Mr A Blackburn (Householder application) CORPUSTY AND SAXTHORPE - PF/11/0747 - Conversion of barn to residential dwelling, erection of garage and creation of vehicular access; Barn adjacent, Manor House, Norwich Road for Mr P Edney (Full Planning Permission) CORPUSTY AND SAXTHORPE - PF/11/1336 - Installation of stand-alone solar array; Shrubbs Farm, Edgefield Road, Edgefield for C J C Lee (Saxthorpe) Ltd (Full Planning Permission) CROMER - NMA1/10/0150 - Non-material amendment request for alterations to windows, insertion of ground floor doors, enlargement of Holding Bay and installation of PV panels; Cromer & District Hospital, Mill Road for Norfolk & Norwich University Hospitals Foundation Trust (Non-Material Amendment Request) CROMER - PF/11/0965 - Change of use of ground floor shop and first floor flat to 4 one-bedroomed flats; 101-103 Mill Road for Mr Hall (Full Planning Permission) CROMER - PF/11/1317 - Erection of 18.04m telecommunications monopole with 3 antennae and equipment cabinet; Cromer Rail Station, Holt Road for Vodafone Ltd (Full Planning Permission) DILHAM - PF/11/1141 - Raising height of roof and installation of dormer windows to provide accommodation in roof space and erection of single-storey and two-storey rear extension; Hawthorn Cottage, The Street for Mr & Mrs Taylor (Householder application) EDGEFIELD - PF/11/0886 - Installation of photo voltaic panels and variation of condition 8 of planning permission reference PF/10/1176 to permit alternative tiles to be used on the single-storey buildings subject to the application; Lowes Farm, Hunworth Road for Mrs A MacNicol (Full Planning Permission) Development Committee 37 12 January 2012 EDGEFIELD - LA/11/0954 - Installation of photo voltaic panel to existing barn conversion and variation of condition 3 of Listed Building Consent reference LA/10/1177 to permit alternative tiles to be used on the single-storey buildings subject to that application; Lowes Farm Barns, Hunworth Road for Mrs MacNicol (Listed Building Alterations) EDGEFIELD - LA/11/1340 - Installation of replacement windows; Lowes Farm, Hunworth Road for Stody Estate (Listed Building Alterations) EDGEFIELD - NMA1/10/1187 - Non-material amendment request to omit the sun pipe and install roof light; Jordans, Pecks Lane for Belcoombe Limited (Non-Material Amendment Request) FAKENHAM - PF/11/1239 - Construction of rear dormer window; 11 Nelson Road for Mr & Mrs J Francis (Householder application) FAKENHAM - PF/11/1259 - Erection of two-storey side extension; 9 Nightingale Close for Mr & Mrs Fish (Householder application) FAKENHAM - PF/11/1261 - Conversion of garage to habitable accommodation and construction of link corridor; 49 Gwyn Crescent for Mr Denyer (Householder application) FAKENHAM - NMA1/09/0877 - Request for non-material amendment to use box gutters on east and south elevations of approved extension; 27 Sculthorpe Road for Mr Scoles (Non-Material Amendment Request-Household) GREAT SNORING - PF/10/1465 - Extension and conversion of former workhouse chapel to holiday dwelling; Thursford Castle, Thursford Road for Mr & Mrs Linn (Full Planning Permission) HAPPISBURGH - PF/11/1262 - Installation of photovoltaic panels; Church Rooms, The Street for St Mary's Church PCC (Full Planning Permission) HAPPISBURGH - PF/11/1298 - Erection of front conservatory; Rosemound, 5 Cart Gap Road for Mr & Mrs White (Full Planning Permission) HAPPISBURGH - LE/11/1387 - Demolition of 2 redundant brick and tile buildings; R N L I Lifeboat House, Beach Road for North Norfolk District Council (Conservation Area Demolition) HAPPISBURGH - DP/11/1388 - Prior notification of intention to demolish two brick and tile buildings; R N L I Lifeboat House, Beach Road for North Norfolk District Council (Prior Notification (Demolition)) HEMPSTEAD - PF/11/1338 - Installation of stand-alone solar array; Becketts Farm, Baconsthorpe Road for C J C Lee (Saxthorpe) Ltd (Full Planning Permission) Development Committee 38 12 January 2012 HIGH KELLING - PF/11/1256 - Erection of replacement garage; Auriol, Vale Road for Mr C Coleman (Householder application) HIGH KELLING - PF/11/1289 - Erection of single storey side/front extension; The Briar Patch, Warren Close for Mr & Mrs Stanley (Householder application) HIGH KELLING - PF/11/1320 - Erection of single-storey rear extension and detached garage; Silverbirches, 29 Pineheath Road for Ms J Venworth (Householder application) HIGH KELLING - PF/11/1334 - Erection of extension to entrance lobby and disabled toilet facilities; 15 Avenue Road for Mrs C Otty (Full Planning Permission) HOVETON - PF/11/1263 - Change of use from B8 (warehouse) to D1 (exhibition hall/museum); Unit 7, Station Road Business Park, Horning Road West for H Semmence & Co Ltd (Full Planning Permission) HOVETON - PF/11/1367 - Variation of conditions 2 and 3 of planning permission reference PF/11/0360 to change conservatory to garden room and reduction in glazing and amended size; 140 Stalham Road for Mrs G Gourlay (Householder application) KELLING - NMA1/10/0130 - Non material-amendment request to insert loft door in gable end of garage; Harebell Cottage, The Street for Mr Hall (Non-Material Amendment Request-Household) KETTLESTONE - PF/11/1254 - Erection of storage building with roof-mounted voltaic panels; Manor Farmhouse, The Street for Mr R Ives (Full Planning Permission) KNAPTON - LA/11/1295 - Internal alterations; Flat 3, Knapton House, North Walsham Road for Mr Cook (Listed Building Alterations) LUDHAM - PF/11/1286 - Installation of solar photo voltaic panel array to outbuilding; The Mill House, How Hill for Mrs E Ellis-Paul (Householder application) LUDHAM - LA/11/1359 - Installation of photovoltaic panel array to outbuilding; The Mill House, How Hill for Mrs Ellis-Paul (Listed Building Alterations) MORSTON - PF/11/1264 - Erection of single-storey rear extension; Anchor Inn, 20 The Street for Mr S Farrow (Full Planning Permission) MORSTON - LA/11/1265 - Alterations to facilitate erection of single-storey rear extension; Anchor Inn, 20 The Street for Mr S Farrow (Listed Building Alterations) Development Committee 39 12 January 2012 MUNDESLEY - PF/11/1269 - Erection of garden room extension; Meadow House, 38 Cromer Road for Mr Maddison (Householder application) MUNDESLEY - PF/11/1311 - Erection of bin store; 26 Paston Road for Society of the Sacred Heart (Householder application) NORTH WALSHAM - PF/11/1055 - Change of use from A1 (retail) to D2 (personal training/fitness studio); 5 St Nicholas Court, Vicarage Street for Len Bullimore & Sons (Full Planning Permission) NORTH WALSHAM - PF/11/1056 - Change of use of first and second floors and alterations, including dormer and rooflights to form 2 residential flats; 6 St Nicholas Court, Vicarage Street for Len Bullimore & Sons (Full Planning Permission) NORTH WALSHAM - PF/11/1166 - Erection of two-storey side extension; 1 Recreation Road for Mr D Coop (Householder application) NORTH WALSHAM - PF/11/1241 - Erection of two-storey side extension; 4 Hamilton Close for Mr Howes (Householder application) NORTH WALSHAM - DP/11/1432 - Prior notification of intention to demolish all buildings; Mace's Yard, Cromer Road for Bullen Developments Ltd (Prior Notification (Demolition)) NORTHREPPS - PF/11/1051 - Erection of front boundary fence; Croftnest, Norwich Road for Mrs L Knight (Householder application) NORTHREPPS - PF/11/1276 - Erection of first floor rear extension; Mardlers, 51 Crossdale Street for Mr Hayward (Householder application) OVERSTRAND - PF/11/0630 - Erection of two-storey dwelling; Land rear of 17 Mundesley Road for Mr & Mrs A Walker (Full Planning Permission) RUNTON - PF/11/1232 - Erection of single-storey side extension; 3 Golf Close, West Runton for Ms P Kilgour (Householder application) RUNTON - PF/11/1305 - Construction of two concrete hard standings for siting of LPG gas tanks; Ingleborough Fields Caravan Site, Station Close, West Runton for The Caravan Club (Full Planning Permission) RYBURGH - PF/11/1242 - Erection of single-storey rear extension and relocation of existing garage; 38 Fakenham Road, Great Ryburgh for Mr Collins (Householder application) Development Committee 40 12 January 2012 SCULTHORPE - PF/11/1296 - Variation of condition 3 of planning ref: 03/1618 to permit permanent residential occupancy; Barn 4, The Grange, Lynn Road for Mr Manchett (Full Planning Permission) SCULTHORPE - PF/11/1297 - Variation of condition 3 of planning ref: 03/1618 to permit permanent residential occupancy; Barn 5, The Grange, Lynn Road for Mr Riggott (Full Planning Permission) SEA PALLING - PF/11/1112 - Erection of two-storey side extension, singlestorey side and rear extensions to provide annexe; 3 St Margarets Place for Mr & Mrs Heward (Householder application) SHERINGHAM - PF/11/1231 - Conversion of one dwelling into two units; 53-54 Beeston Common for Mr & Mrs Masters (Full Planning Permission) SHERINGHAM - PF/11/1250 - Erection of single-storey side extension; 17 Abbey Road for Mr M Sheridan (Householder application) SHERINGHAM - PF/11/1308 - Installation of lantern light to allow conversion of attached garage to garden room; 6 Montague Road for Mr C Crouch (Householder application) SHERINGHAM - PF/11/1321 - Erection of single-storey front extension and alterations of part of roof; 6 Holt Road for Mr H Jamieson (Householder application) SOUTHREPPS - PF/11/1073 - Erection of two-storey dwelling accommodation in roof space; Plot 21, Beechlands Park for Mr Walsh (Full Planning Permission) with STALHAM - PF/11/1225 - Erection of 1.8m high front boundary wall and alteration to access; Holme House, Yarmouth Road, The Green for Mr & Mrs N Smith (Householder application) STALHAM - PF/11/1277 - Variation of condition 3 of planning permission reference: 03/2011 to permit permanent residential occupation; Barn 10 West End Farm, Chapel Field, Chapel Field Road for Mr L Platt (Full Planning Permission) STALHAM - PF/11/1330 - Erection of replacement 1.83m high boundary fence; Broadside Chalet Park for Stalham Chalets Ltd (Full Planning Permission) STIBBARD - PF/11/1150 - Alterations to outbuilding to create additional accommodation; Old Rectory, Fulmodeston Road for Mr & Mrs Douds (Householder application) SUTTON - PF/11/1019 - Erection of lean-to shed; Willow Barn, Hickling Road for Mrs F Bird (Householder application) Development Committee 41 12 January 2012 TATTERSETT - PF/11/1220 - Erection of two-storey front extension, singlestorey side extension with roof terrace and detached double garage; Pear Tree Cottage, 1 Dunton Road, Tatterford for Mr Sinclair (Householder application) TATTERSETT - PF/11/1253 - Erection of single-storey rear extension; 2 Halifax Crescent, Sculthorpe for Mr & Mrs A Easter (Householder application) TUNSTEAD - PF/11/1182 - Erection of single-storey side extension; Church Farm House, Church Road for Mr and Mrs T Place (Householder application) TUNSTEAD - PF/11/1208 - Variation of Condition 7 of permission reference 05/0764 to permit permanent residential occupation; 15 Laurel Farm Barns, Market Street for Mrs S Simpson (Full Planning Permission) TUNSTEAD - PF/11/1246 - Erection of first floor side extension and single-storey rear extension; Cedar Lodge, Market Street for Mrs Anderton (Householder application) WELLS-NEXT-THE-SEA - PF/11/1222 - Insertion of replacement dormer window to front elevation, creation of rear dormer window, side roof lights and the rendering and cladding to part of dwelling; 4 Shrublands, Polka Road for Mr C Wells (Householder application) WELLS-NEXT-THE-SEA - LA/11/1331 - Installation of replacement front door; Seafarers Cottage, 66 Freeman Street for Ms K Chandler (Listed Building Alterations) WELLS-NEXT-THE-SEA - NMA1/09/0528 - Non material-amendment request to revise internal layout of barns 1- 5, covered parking for barns 1-3, re-position roof lights and windows and demolition of outbuilding; Barns 1-7, Manor Farm for Hectors Housing Ltd (Non-Material Amendment Request) WEYBOURNE - NMA2/10/1400 - Non-material amendment request for change of finish to roof lantern; South Cottage, The Street for Mrs G Atkinson (Non-Material Amendment Request-Household) WEYBOURNE - NMA1/11/0788 - Non-material amendment request for reduction in length of extension and re-location of window; Gable End, The Street for Ms J Van der Heiden (Non-Material Amendment Request-Household) WIGHTON - PF/11/1270 - Conversion of barn to residential dwelling; Water Hall Barn, High Street for Mr & Mrs Hopkins (Full Planning Permission) WIGHTON - LA/11/1271 - Alterations to barn to facilitate conversion to residential dwelling; Water Hall Barn, High Street for Mr & Mrs Hopkins (Listed Building Alterations) Development Committee 42 12 January 2012 WOOD NORTON - PF/11/1288 - Erection of replacement extended porch; Chapel Cottage, Rectory Road for Mr & Mrs Wright (Householder application) WORSTEAD - LA/11/1194 - Internal alterations kitchen/dining room; The Manor House, Church Plain for Mr O'Connell (Listed Building Alterations) 9. APPLICATIONS REFUSED UNDER DELEGATED POWERS BACONSTHORPE - NMA2/10/0972 - Non-material amendment request for revised dormer roofs; Lokeside, Hall Lane for Mr B Dowman (Non-Material Amendment Request-Household) CROMER - PF/11/0460 - Erection of three-storey dwelling; Land at Cadogan Road for Mr Roberts (Full Planning Permission) NORTHREPPS - PF/11/1299 - Variation of condition 6 of planning ref: 07/0439 to permit alternative parking for plot 3 and creation of vehicle access; Land at Norwich Road, Cromer for SJD Enterprises (Full Planning Permission) TRIMINGHAM - AN/11/1168 - Continued display of advertisements; Sites at Cromer Road, Sidestrand and Mundesley Road for Woodland Holiday Park (Advertisement Non-Illuminated) APPEALS SECTION 10. NEW APPEALS CROMER - PF/11/0613 - Erection of detached single-storey dwelling; Land rear of 10 Park Road for Mr T Merchant WRITTEN REPRESENTATIONS STIFFKEY - PF/11/0947 - Erection of two-storey extension and alterations to existing single-storey wing; Warborough Place, Wells Road for Mr & Mrs Baker WRITTEN REPRESENTATIONS STIFFKEY - LA/11/0948 - Internal alterations, alterations to existing single-storey wing and erection of two-storey extension; Warborough Place, Wells Road for Mr & Mrs Baker WRITTEN REPRESENTATIONS 11. PUBLIC INQUIRIES AND INFORMAL HEARINGS - PROGRESS None Development Committee 43 12 January 2012 12. WRITTEN REPRESENTATIONS APPEALS - IN HAND BLAKENEY - PF/10/1371 - Change of use of land and field shelter from agricultural to D2 (leisure); Land at The Quay for Mr W Sankey SUSTEAD - PF/11/0804 - Conversion of building to one unit of holiday accommodation; Manor House Farm, New Road, Bessingham for Mr I Clark 13. APPEAL DECISIONS BODHAM - PF/11/0190 - Erection of agricultural storage building; Windrush Farm, Hart Lane for Mr D Gay APPEAL DECISION: ALLOWED Development Committee 44 12 January 2012