S-HIS Task List Critical Items Page 1 of 5 S-HIS Task List; Time Critical Actions Action Item Open Date Due Date / Responsible Close Date Party/Parties Comments 1.1 Replace broken temperature sensors (mirror motor, beamsplitter, aperture stop) 22-May-03 27-Oct-03 Paul Schnettler The broken mirror motor temperature sensor has been replaced. Beamsplitter and aperture stop thermistors have not been added to the system and will not be added prior to the ATOST deployment. 1.3 Replace loose hex standoffs in electronics box and stake down 22-May-03 27-Oct-03 Joe Taylor, Nick Ciganovich Hex stand-offs replaced and staked with 3M epoxy. Staked all accessible non-locked fasteners. Electronics box board source voltages measured, connectors visually inspected. PDS connector 3 was not accessible due to new fan/heater placement. Paul S made up some extra long DMM leads to reach other PDS connectors. The leads have been added to the S-HIS EGSE box. 1.4 Thorough electronics box checkout, especially SEK31 board. 1-Oct-03 29-Oct-03 Mark Werner, Joe Taylor 1.5 Replace dessicant in interferometer box. 1-Oct-03 27-Oct-03 Joe Taylor, Nick Ciganovich 1.6 Prep S-HIS for ATOST deployment. 1-Oct-03 30-Oct-03 Joe Taylor, Nick Ciganovich 1.7 Pack S-HIS for ATOST deployment 27-Oct-03 31-Oct-03 Joe Taylor, Nick Ciganovich, Steve Dutcher Legend: Closed Open, Medium Priority Open, High Priority Open, Critical 1/8/04 Old dessicant indicator beads still very blue. Purged interferometer box with N2. S-HIS Task List Maintenance (1) Page 2 of 5 S-HIS Task List; Required Maintenance Action Item Open Date Due Date / Responsible Close Date Party/Parties Comments 1.1 Replace broken temperature sensors (mirror motor, beamsplitter, aperture stop) 22-May-03 31-Oct-03 Paul Schnettler The broken mirror motor temperature sensor has been replaced. Beamsplitter and aperture stop thermistors have not been added to the system and will not be added prior to the ATOST deployment. 1.2 Determine nature of temperature sensor failures 22-May-03 31-Oct-03 Paul Schnettler No word on nature of failure. 1.3 Replace loose hex standoffs in electronics box and stake down 22-May-03 31-Oct-03 1.4 Thorough electronics box checkout, especially SEK31 board. 1-Oct-03 31-Oct-03 1.5 Replace dessicant in interferometer box. 1-Oct-03 31-Oct-03 1.6 Prep S-HIS for ATOST deployment. 1-Oct-03 31-Oct-03 Legend: Closed Open, Medium Priority Open, High Priority Open, Critical 1/8/04 Paul Schnettler, Joe Taylor, Hex stand-offs replaced and staked with 3M epoxy. Staked Nick Ciganovich all accessible non-locked fasteners. Electronics box board source voltages measured, connectors visually inspected. PDS connector 3 was not Mark Werner, Joe Taylor accessible due to new fan/heater placement. Paul S made up some extra long DMM leads to reach other PDS connectors. The leads have been added to the S-HIS Old dessicant indicator beads still very blue. Purged Joe Taylor, Nick Ciganovich interferometer box with N2. Joe Taylor, Nick Ciganovich S-HIS Task List Issues and Problems (1) Page 3 of 5 S-HIS Task List; Identified Issues, Problems, and Questions Action 2.1 2.2 2.3 2.4 2.5 2.6 Item Process flight data (030314, THORpex to Dryden flight) from mid to end of flight to see if the observed noise performance improvement at 0127 UTC is an artifact of our data processing methods. Pull in 030314 flight data through Matlab (shiscollectall) to verify that current processing is not creating compression artifacts. Include thorough analysis of sh030314 flight data in noise analysis work Open Date Due Date / Responsible Close Date Party/Parties 22-May-03 Steve Dutcher 22-May-03 Steve Dutcher 22-May-03 Joe Taylor Inspect ferrite beads for fractures. Determine if PC NR a substitute for new PV MW and LW detectors Compile and circulate details of PV MW and LW detector upgrade requirements 22-May-03 22-May-03 22-May-03 Bob Knuteson Dan LaPorte Review H2O startup problem. 22-May-03 2.8 Inspect SEK31 board for moisture sensitive component(s) 22-May-03 Mark Werner 22-May-03 Dan LaPorte 22-May-03 Ray Garcia, Steve Dutcher 2.10 2.11 Determine what would be required to integrate new BOMEM control board Determine where in the data processing the 1.1 scene mirror angle difference should be handled. Needs to be handled both on the programming and readout sides Laser noise/tilt signature; apply appropriate mask to metrology system. Need to return to this flight, after reprocessing with current rsh2fbf. UNASSIGNED 2.7 2.9 Comments 22-May-03 22-May-03 12-Sep-03 Legend: Closed Open, Medium Priority Open, High Priority Open, Critical 1/8/04 This has been discussed, but to my knowledge needs to be implemented. Henry Buijs is certain that the laser voltage signature is Nick Ciganovich, Dan LaPorte due to laser mode hopping and not an issue; a metrology system mask is not required. S-HIS Task List Instrument Upgrades (1) Page 4 of 5 S-HIS Task List; Instrument Upgrades Action 3.1 3.2 3.3 3.4 Item Visible imager: design and test packaging Visible imager: track down camera module, specifications, and manuals Visible imager: develop and bench test visible imager control software Visible imager: develop and test visible imager dashboard integration and post processing software Open Date Due Date / Close Date 22-May-03 22-May-03 Responsible Party / Parties Comments Nick Ciganovich 30-Jul-03 Joe Taylor Items are in Joe's office, Rm 519 Ray Garcia, Joe Taylor Steve Dutcher 3.5 ELW band addition: perform dewar hold time bench test 22-May-03 Fred Best 3.6 ELW band addition: performance analysis of ELW band (fold into unfiltered IGM bench tests) 22-May-03 Ray Garcia, Joe Taylor 3.7 Unfiltered IGM bench tests 22-May-03 Ray Garcia, Joe Taylor 3.8 Determine expectations / uses of unfiltered IGM data 22-May-03 Bob Knuteson, Hank Revercomb Unfiltered data has been produced for ice body, LN2 body, and AERI blackbody lab tests. Bench version of unfiltered programs still under development. Engineering Data naming units: 3.9 • review all eng data output by RSH2FBF 22-May-03 Ray Garcia, Steve Dutcher 3.10 • fold in name changes, add units and labels to all quantities 22-May-03 Ray Garcia, Steve Dutcher 3.11 • release new RSH2FBF 22-May-03 Ray Garcia, Steve Dutcher 3.12 • add table of quantities to S-HIS User's Guide (HTML) 22-May-03 Ray Garcia, Steve Dutcher 3.13 • add CDL schema file to S-HIS User's Guide (HTML) 22-May-03 Ray Garcia, Steve Dutcher I believe this task is closed. Need to confirm with RKG. 3.14 3.15 Distribute S-HIS Heater circuit with updated sensor naming conventions Add computer power and ethernet connectors to the baffle area 3.16 Add Firewire or USB transport 3.17 IR imaging system 22-May-03 23-May-03 Joe Taylor Distributed via email. May also be found online at http://www.ssec.wisc.edu/~joet/ under the S-HIS link. Mark Werner, Paul Schnettler, Nick Ciganovich 22-May-03 Joe Taylor Legend: Closed Open, Medium Priority Open, High Priority Open, Critical 1/8/04 NETD calcs complete. Need to contact vendor. S-HIS Task List General Tasks (1) Page 5 of 5 S-HIS Task List; General Tasks Action Item Open Date Due Date / Responsible Close Date Party / Parties 4.1 Online storage of processed S-HIS field data. 22-May-03 Steve Dutcher, Denny Hackel 4.2 Develop full S-HIS instrument model. 22-May-03 Joe Taylor 4.3 Draw cockpit circuit; to be sent to Anna Noe for integration of the S-HIS with the NAST-I on the Proteus 22-May-03 Mark Werner 4.4 Version tracking on all FBF processing 22-May-03 Steve Dutcher 4.5 XML metadata extraction for database tests (SRB/THREDDS) 22-May-03 Steve Dutcher, Denny Hackel 4.6 4.7 4.8 4.9 4.10 4.11 4.12 S-HIS noise analysis. Determine optimum ABB configuration for DC-8 and Proteus platforms Address issues wrt Proteus baffling; interferometer gets too cold during flight without baffles in place, and rear baffle was knocked loose during last set of Proteus flights Examine scientific advantages of a third BB for ER-2 and DC-8 flights Acquire specifications for INTESA 77K blackbody Review critical sensors, and determine which of these indicators should continue to generate fail lights and instrument shutdown S-HIS noise analysis - radiance "spikes" associated with fbf processing. 22-May-03 15-Oct-03 Joe Taylor 22-May-03 Fred Best 22-May-03 UNASSIGNED 22-May-03 Bob Knuteson, Hank Revercomb, Dave Tobin? 22-May-03 Bob Knuteson 22-May-03 Dan LaPorte Comments Ben H and Steve D have confirmed that the growing noise problem was only associated with a recent version of the DMV processing software. The problem has been corrected, and a new version has been released. Joe will release a summary report (November 2003). Joe Taylor, Ray Garcia, Steve Solved. See request tracker for details. New rsh2fbf Dutcher addresses the problem. 1-Oct-03 Legend: Closed Open, Medium Priority Open, High Priority Open, Critical 1/8/04