S-HIS Task List Critical Items Page 1 of 5

advertisement
S-HIS Task List
Critical Items
Page 1 of 5
S-HIS Task List; Time Critical Actions
Action
Item
Open Date
Due Date /
Responsible
Close Date
Party/Parties
Comments
1.1
Replace broken temperature sensors (mirror motor,
beamsplitter, aperture stop)
22-May-03
27-Oct-03
Paul Schnettler
The broken mirror motor temperature sensor has been
replaced. Beamsplitter and aperture stop thermistors have
not been added to the system and will not be added prior to
the ATOST deployment.
1.3
Replace loose hex standoffs in electronics box and stake
down
22-May-03
27-Oct-03
Joe Taylor, Nick Ciganovich
Hex stand-offs replaced and staked with 3M epoxy. Staked
all accessible non-locked fasteners.
Electronics box board source voltages measured,
connectors visually inspected. PDS connector 3 was not
accessible due to new fan/heater placement. Paul S made
up some extra long DMM leads to reach other PDS
connectors. The leads have been added to the S-HIS
EGSE box.
1.4
Thorough electronics box checkout, especially SEK31
board.
1-Oct-03
29-Oct-03
Mark Werner, Joe Taylor
1.5
Replace dessicant in interferometer box.
1-Oct-03
27-Oct-03
Joe Taylor, Nick Ciganovich
1.6
Prep S-HIS for ATOST deployment.
1-Oct-03
30-Oct-03
Joe Taylor, Nick Ciganovich
1.7
Pack S-HIS for ATOST deployment
27-Oct-03
31-Oct-03
Joe Taylor, Nick Ciganovich,
Steve Dutcher
Legend:
Closed
Open, Medium Priority
Open, High Priority
Open, Critical
1/8/04
Old dessicant indicator beads still very blue. Purged
interferometer box with N2.
S-HIS Task List
Maintenance (1)
Page 2 of 5
S-HIS Task List; Required Maintenance
Action
Item
Open Date
Due Date /
Responsible
Close Date
Party/Parties
Comments
1.1
Replace broken temperature sensors (mirror motor,
beamsplitter, aperture stop)
22-May-03
31-Oct-03
Paul Schnettler
The broken mirror motor temperature sensor has been
replaced. Beamsplitter and aperture stop thermistors have
not been added to the system and will not be added prior to
the ATOST deployment.
1.2
Determine nature of temperature sensor failures
22-May-03
31-Oct-03
Paul Schnettler
No word on nature of failure.
1.3
Replace loose hex standoffs in electronics box and stake
down
22-May-03
31-Oct-03
1.4
Thorough electronics box checkout, especially SEK31
board.
1-Oct-03
31-Oct-03
1.5
Replace dessicant in interferometer box.
1-Oct-03
31-Oct-03
1.6
Prep S-HIS for ATOST deployment.
1-Oct-03
31-Oct-03
Legend:
Closed
Open, Medium Priority
Open, High Priority
Open, Critical
1/8/04
Paul Schnettler, Joe Taylor, Hex stand-offs replaced and staked with 3M epoxy. Staked
Nick Ciganovich
all accessible non-locked fasteners.
Electronics box board source voltages measured,
connectors visually inspected. PDS connector 3 was not
Mark Werner, Joe Taylor
accessible due to new fan/heater placement. Paul S made
up some extra long DMM leads to reach other PDS
connectors. The leads have been added to the S-HIS
Old dessicant indicator beads still very blue. Purged
Joe Taylor, Nick Ciganovich
interferometer box with N2.
Joe Taylor, Nick Ciganovich
S-HIS Task List
Issues and Problems (1)
Page 3 of 5
S-HIS Task List; Identified Issues, Problems, and Questions
Action
2.1
2.2
2.3
2.4
2.5
2.6
Item
Process flight data (030314, THORpex to Dryden flight)
from mid to end of flight to see if the observed noise
performance improvement at 0127 UTC is an artifact of our
data processing methods.
Pull in 030314 flight data through Matlab (shiscollectall) to
verify that current processing is not creating compression
artifacts.
Include thorough analysis of sh030314 flight data in noise
analysis work
Open Date
Due Date /
Responsible
Close Date
Party/Parties
22-May-03
Steve Dutcher
22-May-03
Steve Dutcher
22-May-03
Joe Taylor
Inspect ferrite beads for fractures.
Determine if PC NR a substitute for new PV MW and LW
detectors
Compile and circulate details of PV MW and LW detector
upgrade requirements
22-May-03
22-May-03
22-May-03
Bob Knuteson
Dan LaPorte
Review H2O startup problem.
22-May-03
2.8
Inspect SEK31 board for moisture sensitive component(s)
22-May-03
Mark Werner
22-May-03
Dan LaPorte
22-May-03
Ray Garcia, Steve Dutcher
2.10
2.11
Determine what would be required to integrate new
BOMEM control board
Determine where in the data processing the 1.1 scene
mirror angle difference should be handled. Needs to be
handled both on the programming and readout sides
Laser noise/tilt signature; apply appropriate mask to
metrology system.
Need to return to this flight, after reprocessing with current
rsh2fbf.
UNASSIGNED
2.7
2.9
Comments
22-May-03
22-May-03
12-Sep-03
Legend:
Closed
Open, Medium Priority
Open, High Priority
Open, Critical
1/8/04
This has been discussed, but to my knowledge needs to be
implemented.
Henry Buijs is certain that the laser voltage signature is
Nick Ciganovich, Dan LaPorte due to laser mode hopping and not an issue; a metrology
system mask is not required.
S-HIS Task List
Instrument Upgrades (1)
Page 4 of 5
S-HIS Task List; Instrument Upgrades
Action
3.1
3.2
3.3
3.4
Item
Visible imager: design and test packaging
Visible imager: track down camera module, specifications,
and manuals
Visible imager: develop and bench test visible imager
control software
Visible imager: develop and test visible imager dashboard
integration and post processing software
Open Date
Due Date /
Close Date
22-May-03
22-May-03
Responsible
Party / Parties
Comments
Nick Ciganovich
30-Jul-03
Joe Taylor
Items are in Joe's office, Rm 519
Ray Garcia, Joe Taylor
Steve Dutcher
3.5
ELW band addition: perform dewar hold time bench test
22-May-03
Fred Best
3.6
ELW band addition: performance analysis of ELW band
(fold into unfiltered IGM bench tests)
22-May-03
Ray Garcia, Joe Taylor
3.7
Unfiltered IGM bench tests
22-May-03
Ray Garcia, Joe Taylor
3.8
Determine expectations / uses of unfiltered IGM data
22-May-03
Bob Knuteson, Hank
Revercomb
Unfiltered data has been produced for ice body, LN2 body,
and AERI blackbody lab tests. Bench version of unfiltered
programs still under development.
Engineering Data naming units:
3.9
• review all eng data output by RSH2FBF
22-May-03
Ray Garcia, Steve Dutcher
3.10
• fold in name changes, add units and labels to all quantities
22-May-03
Ray Garcia, Steve Dutcher
3.11
• release new RSH2FBF
22-May-03
Ray Garcia, Steve Dutcher
3.12
• add table of quantities to S-HIS User's Guide (HTML)
22-May-03
Ray Garcia, Steve Dutcher
3.13
• add CDL schema file to S-HIS User's Guide (HTML)
22-May-03
Ray Garcia, Steve Dutcher
I believe this task is closed. Need to confirm with RKG.
3.14
3.15
Distribute S-HIS Heater circuit with updated sensor naming
conventions
Add computer power and ethernet connectors to the baffle
area
3.16
Add Firewire or USB transport
3.17
IR imaging system
22-May-03
23-May-03
Joe Taylor
Distributed via email. May also be found online at
http://www.ssec.wisc.edu/~joet/ under the S-HIS link.
Mark Werner, Paul Schnettler,
Nick Ciganovich
22-May-03
Joe Taylor
Legend:
Closed
Open, Medium Priority
Open, High Priority
Open, Critical
1/8/04
NETD calcs complete. Need to contact vendor.
S-HIS Task List
General Tasks (1)
Page 5 of 5
S-HIS Task List; General Tasks
Action
Item
Open Date
Due Date /
Responsible
Close Date
Party / Parties
4.1
Online storage of processed S-HIS field data.
22-May-03
Steve Dutcher, Denny Hackel
4.2
Develop full S-HIS instrument model.
22-May-03
Joe Taylor
4.3
Draw cockpit circuit; to be sent to Anna Noe for integration
of the S-HIS with the NAST-I on the Proteus
22-May-03
Mark Werner
4.4
Version tracking on all FBF processing
22-May-03
Steve Dutcher
4.5
XML metadata extraction for database tests
(SRB/THREDDS)
22-May-03
Steve Dutcher, Denny Hackel
4.6
4.7
4.8
4.9
4.10
4.11
4.12
S-HIS noise analysis.
Determine optimum ABB configuration for DC-8 and
Proteus platforms
Address issues wrt Proteus baffling; interferometer gets too
cold during flight without baffles in place, and rear baffle
was knocked loose during last set of Proteus flights
Examine scientific advantages of a third BB for ER-2 and
DC-8 flights
Acquire specifications for INTESA 77K blackbody
Review critical sensors, and determine which of these
indicators should continue to generate fail lights and
instrument shutdown
S-HIS noise analysis - radiance "spikes" associated with fbf
processing.
22-May-03
15-Oct-03
Joe Taylor
22-May-03
Fred Best
22-May-03
UNASSIGNED
22-May-03
Bob Knuteson, Hank
Revercomb, Dave Tobin?
22-May-03
Bob Knuteson
22-May-03
Dan LaPorte
Comments
Ben H and Steve D have confirmed that the growing noise
problem was only associated with a recent version of the
DMV processing software. The problem has been
corrected, and a new version has been released. Joe will
release a summary report (November 2003).
Joe Taylor, Ray Garcia, Steve Solved. See request tracker for details. New rsh2fbf
Dutcher
addresses the problem.
1-Oct-03
Legend:
Closed
Open, Medium Priority
Open, High Priority
Open, Critical
1/8/04