UVIS TEAM MEETING OPERATIONS UPDATE 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 1 Instrument Status • On/Off Cycle: 28. – +1 since last meeting. – S/C safing on 11/1/2010 in S64 • Hours On: ~90,500 hours. – Longest continuous operations: 9/11/2007 – 11/1/2010. • HDAC Filament Modulation: – – – – – Filament 1: 122.28 hours (H cell), 100.28 (D cell). Filament 2: 12.22 hours. Last: In S63 during T72 (H cell only). Lost: In S64 during T73 (did not execute). Next: In S67 during T75 (H cell and D cell). 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 2 Significant Data Issues S61 None S62 UVIS_136SW_IPHSURVEY004 UVIS_137OT_OUTERSAT003 Data loss: Station problem Data loss S63 UVIS_138TI_LMBINT001_CIRS UVIS_138SW_IPHSURVEY016 Wrong target: target was Saturn Total Loss S64 UVIS_139IC_ALPVIR001 UVIS_139SW_IPHSURVEY006 UVIS_139SA_AURSLEW001 All data from 306-21 to 328-10* Data loss: Rain Data loss: Station problem Data Loss: Lighting strike Total loss: S/C safing S65 UVIS_141SW_IPHSURVEY013 UVIS_141SW_IPHSURVEY010 UVIS_141SW_IPHSURVEY011 UVIS_142SW_IPHSURVEY002 UVIS_142SA_MOS142APO002 Data loss: Rain Total loss: Station problem Total loss: Station problem Data loss: Rain Data loss: Rain & station pb * Includes: UVIS_140SA_MOS140APO001 & 002, UVIS_141IC_ALPVIR001 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 3 First Time Events • New SSR allocation for IEB (starting S65). • Use of “cyclic” to send commands to UVIS during system scan: – Starting S65 (should have been S64 but…). – Save command memory space on-board the S/C: • UVIS_142SA_MOS142APO001_PRIME with cyclic: 5 commands. • UVIS_142SA_MOS142APO001_PRIME without cyclic:545 commands. • UVIS_142SA_MOS142APO001: timing looks Ok. 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 4 Note on System Scan • Need to increase the SSR allocation by 0.6% from what is given by the spreadsheet: – The spreadsheet assumes un-interrupted data acquisition. – In the system scan there is one integration per mosaic stop… The last packet of each integration is not fully filled… The spreadsheet does not take that into account. – In UVIS_142SA_MOS142APO001 expected 545 integrations. Got 542+. 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 5 Note on System Scan Un-interrupted data acquisition Packet 1 Packet 2 Packet n Integration 1 Packet n+1 Packet n+2 Integration 2 Interrupted data acquisition Packet 1 Packet 2 Integration 1 01/04/11 Packet n Packet n+1 Unused UVIS TEAM MEETING OPERATIONS UPDATE Packet n+2 Integration 2 6 Rbot: Workload Impact • The impact of Rbot on the ops team workload is highly variable: – S64: 1 out of 6 designs – S65: 3 out of 10 designs – S66: 1 out of 10 designs – S67: 0 out of 15 designs – S68: Don’t know yet. • The up-front job done by SP and the lowering of the keep-out values (to +/300 rpm starting S67) help a lot. 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 7 Major Local Issues • Uplink side: None • Downlink side: – Beginning of S65: problem ingesting data with the correct CIMS labels due to a clock kernel switch in FSIV. • Consequence of the S64 safing – In S65: problem processing large files generated by long (32 hours) system scans. • We have a workaround 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 8 XM Data Utilization Summary S42 – S61 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 9 XM Data Utilization Summary S62 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 10 XM Data Utilization Summary S63 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 11 Notes and Reminders • Use UVIS_SOLAR_OFF to Sun in CIMS for all solar occultation instead of ISS_NAC to Sun (-20.0, 0.0, -0.11 deg) offset. • HDAC modulation is a non-standard power mode. • Before requesting sponge bits let us know what you want as we may have a good understanding of instrument SSR loading. • The list of ring occultations that contain an atmospheric occultation is on the team web site at http://lasp.colorado.edu/cassini/team-site/archive/docs/pdf/Atmospheric_Occ.pdf • The list of all the tour calibrations is on the team web site at http://lasp.colorado.edu/cassini/team-site/archive/docs/pdf/UVIS_Tour_Calibration.pdf • The UVIS PEFs are on the team web site at http://lasp.colorado.edu/cassini/team-site/operations_planning/planning_info/ 01/04/11 UVIS TEAM MEETING OPERATIONS UPDATE 12