Yonge Subway Extension Preliminary Planning for Transit Project Assessment Public Consultation Centre #2 September 25, 2008 yonge subway extension study where we are today Te Today Te 2 public outreach • 28,000 postcards • 8,000 letters • Newspaper ads: Toronto Star Markham Economist & Sun Richmond Hill Liberal Vaughan Citizen • Posters • 4,000 email notices 3 public consultation centres – june 17 & 18 public input results Option 1/ Over Bridge/ Don River Crossing: 94 Option 1 Subway Stations: 10 What's important when planning a subway? Centre St. Heritage Station Options: 46 Option 3 Option 2 Services 14 Option 3 Yearly 102 Option 2 Destination 132 Total Surveys 20 5 87 Option 1 Connection s Option 3/ Under 12 Option 2 Option 1 Convenient Richmond Hill Centre: Option 2 / Above River 89 Option 3 Local Env. 47 Royal Orchard 47 126 Option 4 Option 5 Option 6 23 29 46 Option 4 Stations Option 5 Shoppin g 23 7 Option 4 Amenitie s Option 5 Planning 15 73 127 114 132 None 67 30 143 4 public consultation centres what’s important when planning a subway? Top three priorities: 1. Connections to other transit 2. Careful planning of existing neighbourhoods and future growth 3. Destinations, places to go and sensitivity to the local environment were tied for the third priority Feedback from June 17/18 5 potential station locations…what we heard Feedback from June 17/18 6 east don river crossing option 1 | bridge – choice of the majority Feedback from June 17/18 7 what’s important when planning the richmond hill centre station? parking Top three priorities: 1. Connections to transit services 2. Year round weather protection and comfort 3. Convenient pedestrian access Feedback from June 17/18 8 building on that feedback recap of july 31 public workshop • Summarized results from technical analysis two mandatory stations four other potential stations East Don River crossing options Richmond Hill Centre alignment alternatives 9 recap of august 26 public workshop • Approximately 50 attendees • Four working groups built their “ideal subway” • What we heard: Six stations Cross East Don River with a bridge Alignment C, preferred for Richmond Hill Centre Station Passenger pick-up and drop-off north of Steeles 10 where we are today Recommended Yonge Subway Extension • Six stations • Two terminal Steeles – Bus Terminal RHC – Bus Terminal • Bridge over East Don River • Alternative alignments into Richmond Hill 11 what comes with the subway stations? Station Pedestrian Entrances Cummer / Drewry Steeles PPUDO Bus Terminal Park’n Ride Substation Line station with minimal surface requirements Bus turn-around loop Summary Transit hub Line station with minimal surface requirements Royal Orchard Line station with minimal surface requirements Bunker / Longbridge Richmond Hill Centre Clark Commuter hub Transit hub 12 Yonge Street steeles station key considerations Steeles Avenue 13 east don river crossing Bridge preferred: Martin Grove Bridge Allows for shallow, relatively flat subway tunnel that will be operationally least costly Allows for a shallow subway station at Royal Orchard – easier pedestrian access, quicker emergency response and lower station cost Presents an opportunity to improve road profile on Yonge Street for pedestrians and drivers Presents an opportunity to naturalize the valley Vaughan Mills Bridge John Street Bridge 14 development of east don river crossing 15 longbridge/langstaff station considerations • Protection of Holy Cross Cemetery • Significant development site east of Yonge • Provision of commuter parking facility • Passenger Pick-up and Drop-off facility • Minimize impact to Hydro One’s 230/500kV transmission facilities 16 design features that address community concerns • Noise buffers • Maintain a green corridor • Bio swales • Sustainable treatments for parking 17 key considerations at richmond hill centre 407 transitway subway GO train GO bus YRT/ Viva 18 richmond hill centre station alignments YONGE STREET 19 richmond hill centre alignments 8 9 Minimize impact on stable residential 8 YONGE STREET 3 3 Integrate with Langstaff TOD 10 Minimize impact on Pomona Creek 5 Access to Langstaff TOD 13 Minimize impact on hydro corridor 6 Pedestrian access to GO 5 6 12 Minimize impact 7 on storm water pond 7 Protect woodlot 4 2 8 Minimize construction impact on Yonge 1 Richmond Hill Centre Station 4 5 Pedestrian access to intermodal 4 1 Compact transit intermodal 4 Langstaff Station 11 Integrate with 407 transitway 2 2 Support Commuter Parking 5 6 6 Proximity to GO rail 4 Integrate with Richmond Hill TOD 20 have your say 21