York Region Rapid Transit Corporation Davis Drive and Yonge Street Updates Town of Newmarket, Committee of the Whole April 28, 2014 agenda 1. Opening/Introduction 2. Project update 3. Summary of 2014 milestones 4. Business Support 5. Yonge Street 6. Information sharing 1 construction status: utilities › Newmarket-Tay Power – 95% complete › New pole installation, framing, stringing, old pole removals › Enbridge – 95% complete › Telecommunications – 55% complete › Utility relocation work will be complete by late 2014 2 construction status: retaining walls › 15 retaining walls constructed › Coping and handrail installation underway › The last wall, on the northeast corner at Davis and Yonge, will be completed this summer 3 construction status: structures › Keith Bridge › Bridge construction scheduled for completion November 2014 › Number of traffic lanes will be dependent on the staging of other work in the vicinity of the bridge › Tom Taylor Trail will re-open by the end of the year › Union Hotel › Remobilizing this spring, construction of the new foundations will begin › Move to permanent location scheduled for this summer construction status: structures › Eastern Creek › Culvert construction completed › Number of travel lanes will be dependent on traffic staging through the area › Western Creek › South side widening will begin in July, completion scheduled for this fall › North side completed 5 construction status: road work › Road widening › This year the following segments will be widened from: › Yonge to Vincent on the north side › Keith Bridge to Bolton on the north side › Bolton to Roxborough on the south side › Base-layer paving › Will follow road widening › Traffic staging › There will continue to be one travel lane in each direction with a dedicated left turn lane [where possible] from Yonge to Roxborough for the remainder of the year 6 construction status: road work › Boulevards › Planters with interlocking paving stones and concrete sidewalks will be installed in segments this year › A full boulevard will be constructed on the south side of Davis east of Parkside 7 construction status: vivastations › The canopies are coming! › The first two canopies will be constructed at Longford and Davis on the eastbound and westbound platforms this year › Construction of three other canopies will start later this year, including in front of the hospital › Construction of the final canopy will start next year › There will be three centre-lane vivastations [6 canopies] 8 minimizing disruption is a top priority 9 summary of 2014 milestones › A number of achievements will be reached this year: › Utility completion › Road widening › Union Hotel move to permanent location › Vivastation construction started and delivery of first canopy steel structure › Keith Bridge completion › Boulevards in sections › Completion of these milestones will be communicated using a variety of tactics 10 business support program › ShopDavis – Business Support Program › Partner with the Newmarket Chamber of Commerce to help support businesses during construction › Campaigns include: › Newspaper, radio, digital ads; › On-street billboards; › Community engagement; › Social media posts; › Website posts and online business profiles; and › Education programs offered through the Chamber 11 yonge street bundle (Y2.1, Y2.2, Y3.2) Y3.2 › Mulock to Davis Dr › 2.4 km › 3 stations Y2.2 › Levendale Rd to 19th Ave › 2.9 km › 3 Stations Y2.1 › Hwy 7 to Major Mackenzie › 3.6 km › 4 stations yonge street project update › Design Build Contract awarded › Next steps: work plans, schedule development and design work › Preliminary construction activities expected to begin later this year in Newmarket › Land acquisition completed in Newmarket, possession secured March 2014 › Substantial completion by the end of 2018 13 information sharing 14 partnering with communities to manage growth 16 YONGE & DAVIS 2. 1 ST. Ph a s e E YONG Future Ph a s e 1. A B V ivaNe xt B A R. D DAVIS 1 Ph a s e d) e (dot t 4. V ivaNe xt 3. N Plan View of Yonge St. and Davis Dr. TOWN OF NEWMARKE T PL ACEMAKING CONCEPTS 9 YONGE & EAGLE 2. G YON E ST. C 1. C T. ES EAGL 4. 3. N Plan view of Yonge St. and Eagle St. TOWN OF NEWMARKE T PL ACEMAKING CONCEPTS 13 MAIN & DAVIS . N ST MAI 1. 1. DAVIS DR. V iva Nex t D Ph a s Future Potential to widen ROW to improve streetscape Ph a s D E e1 2. e1 re Futu e Phas 2. re Futu e a Ph s Plan View of Main St. and Davis Dr. 16 IBI GROUP | MARCH 2014 E N R.O.W R.O.W MAIN & DAVIS PAINTED LETTERING CORTEN STEEL PANEL CORTEN STEEL POSTS CORTEN STEEL PANEL WITH STAINLESS STEEL LETTERS AND NEWMARKET LOGO ~ URBAN PARK ~ ~ COMMERCIAL AREA ~ 6.0 M CLEARANCE PROPOSED NEWMARKET GATEWAY 4 LANE ROADWAY CONCRETE SIDEWALK WITH ACCENT UNIT PAVING 1.5M WIDTH GATEWAY STRIP - PLANTER AND SEAT WALL 1.5M WIDTH GATEWAY STRIP - PLANTER AND SEAT WALL CONCRETE SIDEWALK WITH ACCENT UNIT PAVING Elevation D - Southwest and Southeast Corner of Main St. TOWN OF NEWMARKE T PL ACEMAKING CONCEPTS 17 MAIN & DAVIS MAIN & DAVIS Perspective looking south along Main Street towards the future Urban Park TOWN OF NEWMARKE T PL ACEMAKING CONCEPTS 19 Cross Section under Keith Bridge East West Existing Walkway New Walkway River rock in concrete South Elevation TOM TAYLOR TRAIL LINK-DAVIS DRIVE UNDERPASS 5