Québec Compliance Questionnaire and Reliability Standard Audit Worksheet (QRSAW) TOP-003-1 —

advertisement
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet (QRSAW)
TOP-003-1 — Planned Outage Coordination
Registered Entity: (Must be completed by NPCC)
Régie Identification Number: (Must be completed by NPCC)
Applicable Function(s): Generator Operators – GOP, Transmission Operators – TOP, Balancing
Authorities – BA, Reliability Coordinators – RC
Auditors:
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
1
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Disclaimer
This Québec Reliability Standard Audit Worksheet (QRSAW) was developed to facilitate NPCC’s assessment
of a registered entity’s compliance with this Reliability Standard and its appendix specific to Quebec (the
Appendix). This QRSAW contains all of the same substantive questions and issues as the NERC RSAW used in
the United States. QRSAW language is written to specific versions of each Reliability Standard and its
Appendix. Entities using this QRSAW should choose the version of the QRSAW applicable to the Reliability
Standard being assessed. While the information included in this QRSAW provides some of the methodology
that NPCC has elected to use to assess compliance with the requirements of the Reliability Standard, this
document should not be treated as a substitute for the Reliability Standard or viewed as additional Reliability
Standard requirements. In all cases, the Regional Entity should rely on the language contained in the Reliability
Standard itself, and not on the language contained in this QRSAW, to determine compliance with the Reliability
Standard. The Reliability Standards can be found on the Régie’s website at http://www.regieenergie.qc.ca/en/audiences/NormesFiabiliteTransportElectricite/NormesFiabilite.html. Additionally, Reliability
Standards are updated frequently, and this QRSAW may not necessarily be updated with the same frequency.
Therefore, it is imperative that entities treat this QRSAW as a reference document only, and not as a substitute
or replacement for the Reliability Standard. It is the responsibility of the registered entity to verify its
compliance with the latest version of the Reliability Standards, approved by the applicable governmental
authority,
relevant
to
its
registration
status
(http://www.regieenergie.qc.ca/en/audiences/NormesFiabiliteTransportElectricite/RegistreEntites.html).
This QRSAW provides a non-exclusive list, for informational purposes only, of examples of the types of
evidence a registered entity may produce or may be asked to produce to demonstrate compliance with the
Reliability Standard. A registered entity’s evidence submitted as per the examples contained within this
QRSAW does not necessarily constitute compliance with the applicable Reliability Standard, and NPCC
reserves the right to request additional evidence from the registered entity that is not included in this QRSAW.
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
2
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Subject Matter Experts
Identify your company’s subject matter expert(s) responsible for this Reliability Standard.
Response: (Registered Entity Response Required)
SME Name
Title
Organization
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
3
Requirement
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Reliability Standard Language
TOP-003-1 — Planned Outage Coordination
Purpose:
Scheduled generator and transmission outages that may affect the reliability of interconnected operations must
be planned and coordinated among Balancing Authorities, Transmission Operators, and Reliability
Coordinators.
Applicability:
Functions
Generator Operators
Transmission Operators
Balancing Authorities
Reliability Coordinators
Facilities
This standard only applies to the facilities of the Main Transmission System (RTP).
Reliability Standard effective date in Québec: January 1, 2016
Requirements:
R1.
Generator Operators and Transmission Operators shall provide planned outage information.
R1.1.
Each Generator Operator shall provide outage information daily to its Transmission Operator
for scheduled generator outages planned for the next day (any foreseen outage of a generator
greater than 50 MW). The Transmission Operator shall establish the outage reporting
requirements.
R1.2.
Each Transmission Operator shall provide outage information daily to affected Balancing
Authorities and Transmission Operators for scheduled generator and bulk transmission
outages planned for the next day (any foreseen outage of a transmission line or transformer
greater than 100 kV or generator greater than 50 MW) that may collectively cause or
contribute to an SOL or IROL violation or a regional operating area limitation.
R1.3.
Such information shall be available by 1200 Central Standard Time for the Eastern
Interconnection and 1200 Pacific Standard Time for the Western Interconnection.
Québec Appendix:
Specific provisions applicable to requirements R1.1 and R1.2:
o The Generator Operator shall also provide the information required under requirements R1.1 and
R1.2 for any generator of a generation facility with a capability greater than 50 MVA.
o Generators of wind farms are excluded.
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
4
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Specific provisions regarding generation facilities for industrial use applicable to requirements
R1.1 and R2:
o The Generator Operator whose facilities are mainly used to supply industrial loads is not required
to provide the information required under requirements R1.1 and R2. However, it shall
coordinate any generation variation that has an impact on the flow at the connection points of the
system that facilities are mainly used to supply industrial loads with the Transmission Operator.
Specific provision applicable to requirement R1.3:
o The information shall be available by 1200 Central Standard Time for the Quebec
Interconnection.
Describe, in narrative form, how you meet compliance with this requirement: (Registered Entity
Response Required)
Question: Describe your methodology for determining transmission or generation elements that do no need to
be reported.
Entity Response: (Registered Entity Response Required)
R1 Supporting Evidence and Documentation
Response: (Registered Entity Response Required)
-
Provide the following:
Document Title and/or File Name, Page & Section, Date & Version
Title
Date
Audit Team: Additional Evidence Reviewed:
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
5
Version
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
This section must be completed by NPCC.
Compliance Assessment Approach Specific to TOP-003-1 R1
-
Review data submittals and confirm that they conform to established reporting requirements.
-
Review the evidence provided to verify that the Transmission Operator has established documented
outage reporting procedures.
-
Review outage schedules for transmission and/or generation as applicable and compare to outage
submissions
-
Review methodology or criteria of determining if a transmission or generation element does not need
to be reported because it does not cause or contribute to an SOL or IROL
-
Review logs of data submittal times.
-
Review any applicable software applications that are used for requesting, tracking, performing, or
transmitting outages
Auditors detailed notes:
R2.
Each Transmission Operator, Balancing Authority, and Generator Operator shall plan and coordinate
scheduled outages of system voltage regulating equipment, such as automatic voltage regulators on
generators, supplementary excitation control, synchronous condensers, shunt and series capacitors,
reactors, etc., among affected Balancing Authorities and Transmission Operators as required.
Québec Appendix:
Specific provisions regarding generation facilities for industrial use applicable to requirements
R1.1 and R2:
o The Generator Operator whose facilities are mainly used to supply industrial loads is not required
to provide the information required under requirements R1.1 and R2. However, it shall
coordinate any generation variation that has an impact on the flow at the connection points of the
system that facilities are mainly used to supply industrial loads with the Transmission Operator.
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
6
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Describe, in narrative form, how you meet compliance with this requirement: (Registered Entity
Response Required)
Question: Did you experience a planned outage of system voltage regulating equipment during the audit
period? If yes, provide evidence of coordination.
Entity Response: (Registered Entity Response Required)
R2 Supporting Evidence and Documentation
Response: (Registered Entity Response Required)
-
Provide the following:
Document Title and/or File Name, Page & Section, Date & Version
Title
Date
Audit Team: Additional Evidence Reviewed:
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
7
Version
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
This section must be completed by NPCC.
Compliance Assessment Approach Specific to TOP-003-1 R2
-
Review coordination methods or procedures
-
Review communications, logs, or other evidence to confirm that coordination occurred.
Auditors detailed notes:
R3.
Each Transmission Operator, Balancing Authority, and Generator Operator shall plan and coordinate
scheduled outages of telemetering and control equipment and associated communication channels
between the affected areas.
Describe, in narrative form, how you meet compliance with this requirement: (Registered Entity
Response Required)
Question: Did you experience a planned outage of telemetering or control equipment and associated
communication channels during the audit period? If yes, provide evidence of coordination.
Entity Response: (Registered Entity Response Required)
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
8
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
R3 Supporting Evidence and Documentation
Response: (Registered Entity Response Required)
-
Provide the following:
Document Title and/or File Name, Page & Section, Date & Version
Title
Date
Version
Audit Team: Additional Evidence Reviewed:
This section must be completed by NPCC.
Compliance Assessment Approach Specific to TOP-003-1 R3
-
Review coordination methods or procedures
-
Review communications or logs indicating that coordination occurred
NOTE: Coordination methods or procedures do not have to be in a formal written document.
Auditors detailed notes:
R4.
Each Reliability Coordinator shall resolve any scheduling of potential reliability conflicts.
Describe, in narrative form, how you meet compliance with this requirement: (Registered Entity
Response Required)
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
9
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
R4 Supporting Evidence and Documentation
Response: (Registered Entity Response Required)
-
Provide the following:
Document Title and/or File Name, Page & Section, Date & Version
Title
Date
Version
Audit Team: Additional Evidence Reviewed:
This section must be completed by NPCC.
Compliance Assessment Approach Specific to TOP-003-1 R4
-
Identify reliability conflict resolution process, procedures, or empowerment agreements that verify the
Reliability Coordinator has the authority to resolve scheduling conflicts.
-
Review logs or decisions of any scheduling conflicts.
Auditors detailed notes:
Supplemental Information
Other - The list of questions above is not necessarily all the evidence required to show compliance with the
Reliability Standard. Provide additional information here, as necessary that demonstrates compliance with this
Reliability Standard.
Entity Response: (Registered Entity Response)
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
10
Québec Compliance Questionnaire and Reliability Standard Audit Worksheet
Compliance Findings Summary
(to be filled out by auditor)
Req. NF PNC OEA NA
Statement
1
2
3
4
NF-No Finding; PNC-potential non-compliance; OEA-Open Enforcement Action; NA-Not applicable
Revision History
Version
1
Date
February 2016
Reviewers
Initial Document
Revision Description
Document Created from NERC RSAW
Compliance Questionnaire and Reliability Standard Audit Worksheet
Registered Entity: _____________________
Régie Registration Number: ______________________
Compliance Assessment Date: _____________
QRSAW Version: QRSAW_TOP-003-1_v1EN
Revision Date: February 2016
11