C A N A D A RÉGIE DE L'ÉNERGIE PROVINCE DE QUÉBEC

advertisement
Page i
Régie de l'énergie - Dossier R-3669-2008
Cause tarifaire 2009 de TransÉnergie
CANADA
RÉGIE DE L'ÉNERGIE
PROVINCE DE QUÉBEC
DISTRICT DE MONTRÉAL
DOSSIERS R-3669-2008
CAUSE TARIFAIRE 2009
DE TRANSÉNERGIE
HYDRO-QUÉBEC
En sa qualité de Transporteur (TransÉnergie)
Demanderesse
-etSTRATÉGIES ÉNERGÉTIQUES (S.É.)
ASSOCIATION QUÉBÉCOISE DE LUTTE
CONTRE LA POLLUTION ATMOSPHÉRIQUE
(AQLPA)
Intervenantes
ONTARIO POWER AUTHORITY (OPA)
OEB Docket EB-2007-0707
Exhibit D, Tab 5, Schedule 1, Attachment 4 Corrected
Section 5.0 - Capacity Value of Existing Hydroelectric Generators -andSection 6.0 - Capacity Value of New Hydroelectric Projects
pp. 8-10
http://www.powerauthority.on.ca/Storage/53/4871_D-5-1_Att_4_corrected_071019.pdf
Pièce déposée par:
Stratégies Énergétiques (S.É.)
Association québécoise de lutte contre la pollution atmosphérique (AQLPA)
Le 18 novembre 2008
Pièce SÉ-AQLPA-3 - Document 3
ONTARIO POWER AUTHORITY (OPA), OEB Docket EB-2007-0707, Exhibit D, Tab 5, Sch 1, Att 4 Corrected
Section 5.0 - Capacity Value of Existing Hydroelectric Generators
And Section 6.0 - Capacity Value of New Hydroelectric Projects
Pièce déposée par Stratégies Énergétiques et l'AQLPA
Page ii
Régie de l'énergie - Dossier R-3669-2008
Cause tarifaire 2009 de TransÉnergie
Pièce SÉ-AQLPA-3 - Document 3
ONTARIO POWER AUTHORITY (OPA), OEB Docket EB-2007-0707, Exhibit D, Tab 5, Sch 1, Att 4 Corrected
Section 5.0 - Capacity Value of Existing Hydroelectric Generators
And Section 6.0 - Capacity Value of New Hydroelectric Projects
Pièce déposée par Stratégies Énergétiques et l'AQLPA
Corrected: October 19, 2007
EB-2007-0707
EB-2007-0707
Exhibit
Exhibit D
D
Tab
Tab 55
Schedule
Schedule 11
Attachment
Attachment 44
Page
Page 88 of
of 10
10
1
5.0
2
There is currently 7,788 MW of existing installed hydroelectric capacity. However,
3
experience has shown that not all of this capacity will be available at the time of the
4
summer peak demand. To determine the capacity contribution of existing hydroelectric
5
stations at the hour of the summer peak, OPA completed the following assessment:
6
•
the total system hydroelectric production coincident with the hour of the summer peak
was determined for each year from 1996 to 2005. The hours when the summer peak
occurred are shown in Table 2 below along with the coincident hydroelectric capability;
and
•
the 10 year mean of the hydroelectric capability coincident with the system peak was
then determined to be 5,459 MW;
•
hydroelectric reserve was accounted for by adding 500 MW to the mean hydroelectric
capability coincident with system peak. Historically, there has been an average of
500 MW of hydroelectric reserve accepted by the IESO during the hour of the summer
peak in the operating reserve markets.
7
8
9
10
11
12
13
14
15
CAPACITY VALUE OF EXISTING HYDROELECTRIC GENERATORS
16
17
For capacity adequacy assessment purposes, based on the above analysis, the IPSP
18
assumes that 5,959 MW of existing hydroelectric capacity will be available at the time of the
19
summer peak.
20
Table 4: Hydroelectric Production Coincident with System Peak
Year
Peak Day
1996
1997
1998
1999
2000
2001
2002
2003
2004
2005
Aug 7
July 14
July 15
July 5
Aug 31
Aug 8
Aug 13
Jun 26
July 22
July 13
Source: OPA
21
Peak Load
Hour
Hydro
Contribution
(MW)
17
16
16
16
16
16
14
16
16
16
Average
5,943
5,652
5,061
5,766
5,651
5,297
5,304
5,151
5,775
4,986
5,459
EB-2007-0707
Exhibit D
Tab 5
Schedule 1
Attachment 4
Page 9 of 10
1
6.0
CAPACITY VALUE OF NEW HYDROELECTRIC PROJECTS
2
The capacity value of new hydroelectric facilities is determined by applying either the river-
3
specific, or “fleet” ratio of the mean actual capacity contribution (at the summer peak) to the
4
total installed capacity as a “de-rating” factor to the installed capacity of new hydroelectric
5
facilities. The river-specific value is used for those new generators located on rivers with
6
existing hydroelectric facilities. The “fleet” value is used for those new generators located
7
on rivers with no existing hydroelectric facilities.
8
The de-rating factor for new hydroelectric projects on the Ottawa River, for example, is
9
determined by dividing the mean capacity contribution of all hydroelectric facilities on the
10
river at the summer peak by the total installed capacity on the river. The de-rating factor for
11
the Ottawa River is 80%.
12
For new facilities on undeveloped rivers or rivers for which hydroelectric production data is
13
not available, the fleet new hydroelectric de-rating factor is the ratio of mean capacity
14
contribution of all existing hydroelectric facilities at the summer peak in Ontario to the total
15
installed hydroelectric capacity. The fleet new hydroelectric de-rating factor is 73%.
16
Table 5 summarizes the new hydroelectric de-rating factors for specified river systems in
17
Ontario. The shaded cells represent those de-rating factors that are determined using
18
actual river specific data, whereas the unshaded cells indicate the fleet de-rating factor.
19
The de-rating factors were applied to 975 MW of “Active and Committed” new hydro units.
EB-2007-0707
Exhibit D
Tab 5
Schedule 1
Attachment 4
Page 10 of 10
1
Table 5 : De-rating Factors for New Hydroelectric Projects by River System
River System
Abitibi
Aguasabon
Black River
English
Kapuskasing
Madawaska
Mattagami
Montreal River
Muskoka
Niagara
Nipigon
Ottawa
Rideau
Serpent
South Nation
Spanish
Trent
Wanapitei
Welland
White River
Source: OPA
2
New Hydro “De-rating” Factor
73%
64%
73%
62%
73%
50%
62%
76%
73%
73%
74%
80%
73%
73%
73%
73%
73%
73%
84%
73%
Download