RÉGIE DE L’ÉNERGIE FILE R-3405-98 REGULATORY PRINCIPLES AND ELECTRICITY TRANSMISSION RATES EVIDENCE OF JOHN TODD ON BEHALF OF OPTION CONSOMMATEURS ET ACTION RESEAU CONSOMMATEUR APRIL 9, 1999 Régie de l’énergie Transmission Rates (R-3405-98) -1- Evidence of John Todd BACKGROUND TO THE HEARING The Régie de l’énergie (the «Régie») initiated this proceeding (R-3405-98) with procedural decision D-98-391 to assist it in establishing certain aspects of the methodology to be used in determining transmission rates for Hydro-Québec in future rate hearings. The mandate of the Régie with respect to transmission rate determination is set out in section 48 of the «Act respecting the Régie de l’énergie». «48. The Régie shall, on the application of an interested person or on its own initiative, fix or modify the rates and conditions for the transmission or supply of electric power by Hydro-Québec or for the transmission, delivery or supply of natural gas by a natural gas distributor or for the storage of natural gas. The Régie may ask Hydro-Québec or a natural gas distributor to file a modification proposal...» In accordance with s. 48 of the Act, Hydro-Québec requested a determination of an average unit transmission price and modification of transmission rates.2 Following this submission, Hydro-Québec submitted a further document3 containing seven issues that it proposed should be examined by the Régie. Concurrent with D-98-39, the Régie 1 Décision procédurale, D-98-39 R-3405-98, le 12 juin 1998. 2 Within the context of Régie-3401-98, le 1er mai 1998. 3 Enoncé de principes réglementaires, Direction des Affaires réglementaires d’Hydro-Québec, le 8 mai 1998. Régie de l’énergie Transmission Rates (R-3405-98) -2- Evidence of John Todd ordered Hydro-Québec to file a formal request related to these issues. In this request4, Hydro-Québec reduced the number of issues to be examined to three: 1. projected test year; 2. the establishment of a rate base and capital structure using the 13-month average; and 3. the recognition of transmission assets in operation and under construction, as well as existing contracts affecting transmission service. 4 Hydro-Québec Direction Affaires réglementaires, Principes généraux pour la détermination et l’application des tarifs de transport d’électricité, le 17 juin 1998. Régie de l’énergie Transmission Rates (R-3405-98) -3- Evidence of John Todd At the September 1998 preparatory meeting to determine the issues to be examined, intervenors requested that the Régie expand the scope of the proceeding. Consequently in D-98-885, the Régie decided that two additional issues should be addressed: 4. the choice of the test period to be used by Hydro-Québec for rate and regulatory matters with respect to its fiscal year; and 5. the determination of the principal criteria to be used to identify and separating regulated activities from non-regulated activities. On January 27, the Quebec government issued a Decree from the Ministry of Natural Resources (Decree no 53-99, Directive no 1), which directed the Régie to recognize Hydro-Québec’s existing transmission assets as well as those under construction. In effect, the Decree eliminated the issue of recognizing transmission assets in operation and under construction.6 This evidence therefore comments only on Issues 1,2, 4 and 5: Issue 1: the use of the projected test year for determining transmission rates; Issue 2: the establishment of a rate base and capital structure using a 13 month average; Issue 4: the choice of a test period to be used by Hydro-Québec for rate and regulatory matters with respect to its fiscal year; Issue 5: the determination of principal criteria to be used to identify and separate regulated activities from non-regulated activities. 5 Décision procédurale, D-98-88 R-3405-98, le 24 septembre 1998, p 8. 6 The legality of this decree is not addressed in this evidence. In Décision procédurale, D-99-34 R-3405-98, le 9 mars 1999, p 11 the Régie indicated that administrative acts should be presumed valid unless they are found to be illegal by the courts. Régie de l’énergie Transmission Rates (R-3405-98) -4- Evidence of John Todd Option consommateurs and Action Réseau Consommateur have engaged me7 to assist them in their intervention in this proceeding by providing evidence on these four issues. My comments are divided into four corresponding sections. 1. COMMENTS ON THE ISSUES 1.1 Issue 1: the use of the projected test year for determining rates The standard approach in North American jurisdictions that rely on rate-base rate of return (RBROR) methodologies is to use a future, or projected, test year to determine rates.8 Interestingly, the performance-based regulation (PBR) schemes that have been adopted by West Kootenay Power and BC Gas, under British Columbia Utilities Commission jurisdiction, and more recently proposed by Enbridge Consumers Gas to the Ontario Energy Board (E.B.R.O. 497-01), involve what is essentially an adjusted historic test year methodology. In these PBR schemes, test year costs that are subject to PBR are not based on forecasts; hence, they do not exhibit the primary characteristic of RB-ROR 7 John Todd, President of Econalysis Consulting Services, Inc., has specialized in the theory and practice of government regulation, re-regulation and de-regulation for 20 years. He has participated as an advisor or witness in over 100 proceedings before regulators including the Ontario Energy Board, the Public Utility Board of Manitoba, the British Columbia Utilities Commission, the Régie de l’énergie and the Canadian Radio-television and Telecommunications Commission. See Appendix 2 for Mr. Todd’s full curriculum vitae. 8 Centra Gas Manitoba, which I believe was the last Canadian utility using an Historic Test Year, with «known and measurable adjustments» converted to a Future Test Year in 1994. See Manitoba Public Utilities Board, Order No. 89/94, May 26, 1994. Régie de l’énergie Transmission Rates (R-3405-98) -5- Evidence of John Todd future test year regimes – they are based essentially on adjusted historic year actual costs and revenues. Given that Hydro-Québec will be regulated with a rate-base rate of return methodology, the use of the projected test year is acceptable, in my view, subject to the following minimum conditions that are necessary to enable the Régie and intervenors to test the reasonableness of the company’s cost and revenue forecasts. (i) Cost and revenue data should be provided on a consistent and comparable basis for the projected test year, the bridge year and at least one historic year; it is common in other Canadian jurisdictions to require up to five years of historic data. (ii) Data for historic years should be provided on both a normalized and actual basis to permit trend analysis using comparable annual data. (iii) The methodology used for developing all forecast expenditures and revenues, (including the weather normalization methodology, trends in use per customer, loss calculations, etc.) should be fully transparent. Put simply, sufficient information should be on the record, or available through information requests, to enable the Régie, or intervenors to replicate the company’s forecasts. As Hydro-Québec’s SaintAix expert testimony (HQPR-7, Document 2, p. 3) states: In order to judge the relevancy and accuracy of the forecasted data, most jurisdictions require upon filing, that the utility to (sic) provide a comparison and an explanation of variances between historic, current and projected data. Where forecast, rather than actual, cost information is being relied on, the company has the obligation, or burden of proof, to demonstrate that its forecasts are reasonable. This implies that the «explanations» must be complete, comprehensive and clear. Régie de l’énergie Transmission Rates (R-3405-98) -6- Evidence of John Todd Other Canadian regulators recognize that when a projected test year RB-ROR regime is used, it is essential to ensure that the utility reports cost and revenue data on a consistent basis to allow the regulator and interested parties to make meaningful comparison between the forecast for the future test year and actual historic data years. An examination of cost and revenue trends, with explanations for any trends that are unusual, is a key element of the review of the forecasts. In other jurisdictions (including for example, Ontario, Manitoba and B.C.), a minimum of five years of data (3 historic years, the current year, and the projected year) is required in order to test whether the forecast is a reasonable extrapolation of the past. For example, if transmission rates are being set for the year 2000 in 1999, then, at a minimum, cost and revenue data should be required for the following years: · 1996 to 1998 (historic years), using actual historic data; · 1999 (bridge year), using available actual cost and revenue data, supplemented by estimating data for the balance of the year; and · 2000 (projected test year) using the best available and most recent forecast. In addition, in cases where three years of historic data are insufficient to demonstrate an acceptable trend, a longer time series of historic data may be required. Furthermore, detailed breakdowns of the budget are often required to allow for meaningful comparisons and adequate scrutiny of forecast costs and revenues. For example, if spending in a category, such as information technology capital, is volatile, a detailed breakdown showing categories of expenditures (e.g., telecommunications, computer hardware, computer software, etc.) may be needed to explain the historic pattern and demonstrate that the forecast is reasonable. If the utility has undergone restructuring, costs and revenues for all the data must be provided on a consistent basis (e.g., adjust historic data to reflect the new structure) so that meaningful comparisons can be made between the projected test year and the previous years. Consequently, if Hydro-Québec is planning on using a projected test year, it is important that the utility has the accounting capability to present historic data on a basis that is consistent with the future test year data that it provides. A standard approach to facilitating meaningful comparisons is to use a weather normalization methodology (normal temperatures as measured in heating and cooling degree-days and normal Régie de l’énergie Transmission Rates (R-3405-98) -7- Evidence of John Todd rainfall conditions). Weather normalization is particularly important in the case of a hydroelectric utility since revenues are so heavily dependent on weather both from a supply and demand perspective. Cold weather in winter or hot weather in summer increases the demand for electricity and hence the revenues derived from sales. Heavy rainfall increases the supply and hence may increase export sales revenues. Revenues are typically forecast based on normal weather and rainfall. It is therefore important to rely on a credible and consistent weather normalization methodology and to compare the «weather normal» forecast with «weather normal» historic data. Given the critical role that historic cost and revenue information plays in assessing the reasonableness of forecast data, it is essential that the current rate freeze not be used as a rationale for delaying the development of systems to ensure that the necessary historic data will be available in the next rate case. Detailed actual revenue and cost data could be provided to the Régie and intervenors on an annual basis until the next rate case. Furthermore, it may also be appropriate for the Régie to review cost and revenue information during the current rate freeze period because these financial results affect the company’s rate stabilization reserves. Given that a regulatory system is now in place, the Régie should review these costs on an annual basis to ensure that they are reasonable and prudent. Hydro-Québec’s interrogatory responses relating to the use of the projected test year raise concerns that the utility does not appreciate the importance of consistent and comparable reporting of historic data. In response R14.1 to ARC-OC’s interrogatory relating to the utility’s plans to provide, in addition to the projected test year forecast, comparable information for the bridge year and five historic years on a consistent basis, Hydro-Québec states that: Si le principe de l’année témoin projetée est adopté, Hydro-Québec soumettra également les informations nécessaires de l’année de base. De plus, une comparaison sommaire des résultats réels d’une année précédente avec les projections déjà soumises sera également fournie lors d’audiences tarifaires, sauf lors des premières audiences où seuls les résultats réels seront disponibles.9 [emphasis added] 9 Réponses d’Hydro-Québec aux questions de ARC/OC, HQPR-11 Document 5, p. 7. Régie de l’énergie Transmission Rates (R-3405-98) -8- Evidence of John Todd This response raises doubts as to whether Hydro-Québec will voluntarily meet the conditions described above. In addition, Hydro-Québec’s responses to interrogatories relating to forecasting methodology provide very limited information on weather normalization methodology (see R15.1 and R15.310); methodologies to develop forecast costs for capital and operation budget (see R2.1-2.311); and methodologies for determining the capital structure and the cost of equity for rate setting purposes (see R3.212). In order for Hydro-Québec to meet the third condition identified above (transparent methodology), the utility will have to provide detailed information on the methodologies it uses to develop its forecasts. 1.2 Issue 2: The establishment of a rate base and capital structure using a 13 month average In my view, use of a thirteen-month average of end of month balances (or average-of-averages) to calculate the average rate base is appropriate. The Saint-Aix Group notes (HQPR-7, Document 2, p. 3): The use of a mid-year average methodology is appropriate to utilities in a stable growth or declining rate base environment, i.e., where variations from month to month are consistent and comparable, while a twelve or thirteen-month average of end of month balances is accepted, with the latter considered a more appropriate, 10 Réponses d’Hydro-Québec aux questions de ARC/OC, HQPR-11 Document 5.1, p. 2. 11 Réponses d’Hydro-Québec aux questions de ARC/OC, HQPR-11 Document 5, pp. 2-3. 12 Réponses d’Hydro-Québec aux questions de ARC/OC, HQPR-11 Document 5, p. 3. Régie de l’énergie Transmission Rates (R-3405-98) -9- Evidence of John Todd and fair methodology to both consumers and investors, since more accurate when important monthly fluctuations in customers and investments are recorded. In my experience, the mid-year average methodology can result in a significant bias, in part because it creates an incentive for utilities to «game the regulatory system» by delaying spending within the year, thus overstating the average rate base. At the other extreme, monthly or daily averages are impractical since utilities’ accounting reporting generally takes place on a monthly basis. The additional precision gained by a more precise calculation than the thirteen month average is unlikely to justify the additional cost. For these reasons, the thirteen-month average is generally considered as a simple, practical and acceptably accurate solution for determining the average rate base. 1.3 Issue 4: the choice of a test period to be used by Hydro-Québec for rate and regulatory matters with respect to its fiscal year The standard approach in utility regulation is to use matching fiscal, test and rate years so as to minimize administrative complexity and resulting regulatory burden. If the fiscal and test periods do not coincide, significant effort can be required in reconciling accounting statements. Without a detailed reconciliation of publicly available financial information, based on the company’s fiscal year, and the information provided in the regulatory forum, transparency is compromised. Given that Hydro-Québec’s fiscal year is January 1 to December 31, there are clear advantages to using the same period for regulatory purposes. Further, if the rate year does not match the test period, administrative procedures must be put in place to ensure that the mis-match does not result in inadvertent over- or under-recovery of costs in the event that a rate hearing is not required. One way to avoid this problem would be to increase rates effective January 1, instead of on May 1, as has traditionally been done. The disadvantage of this approach in the case of Hydro-Québec, which has customers with significant heating load, is that January 1 rate increases (when consumption is high) are less palatable to consumers than May 1 rate increases. Régie de l’énergie Transmission Rates (R-3405-98) - 10 - Evidence of John Todd If the Regie decides to maintain the status quo, it is essential that a May 1 increase is not implemented in such a way as to result in over-recovery of costs during the following fiscal year. The problem is illustrated in Figure 1 (see Appendix 1). In Figure 1, the gray shaded area represents the revenue requirement. For illustrative simplicity, it is assumed that the revenue requirement is the same in year 1 and year 2, with sales also being constant so that the rates that would be required to recover the revenue requirement are the same in each year. The rate in the previous year (R0) is assumed to be insufficient to recover this revenue requirement, however. As a result, a rate increase is needed in year 1. If the rate increase does not go into effect until May 1, and the total revenue in the year is to be equal to the revenue requirement, then the increased rates will exceed the annualized rate that would be appropriate. If the full rate increase were to remain in effect throughout year 2, the company would be over-recovering its revenue requirement in that year. This over-recovery is shown in Figure 1. One way to avoid this problem would be to require rates to be reviewed by the Régie every year. Annual rate reviews by the Régie could adjust rates in on May 1 of each year so that the total forecast revenues for the year neither exceed nor fall short of the approved revenue requirement. Figure 2 (see Appendix 1) shows this case. Over-recovery in year 2 is avoided by decreasing rates as of May 1 in the second year. This approach has two disadvantages, however. First, it could result in unstable rates even if the annualized rates needed to recover the revenue requirement were constant. Second, if stable rates can be justified, it would be undesirable to adopt a mechanism that forces the Régie to hold a hearing every year. An alternate solution to the problem, illustrated in Figure 3 (see Appendix 1), would be to implement rates to generate annualized revenue sufficient to recover the year 1 revenue requirement. That is, the rate implemented as of May 1 of the first year would be the rate that would recover the revenue requirement if it were in effect for the full year. The disadvantage of this approach is that while it Régie de l’énergie Transmission Rates (R-3405-98) - 11 - Evidence of John Todd would avoid the over-recovery problem in year 2, it would under-recover revenue in year 1. Furthermore, if rates were generally increasing from year-to-year, there would be an on-going problem of under-recovery. In my view, the best solution to the problem of over-recovery in year 2 would be to use a rate rider, as shown in Figure 4 (see Appendix 1). A rate rider is a temporary surcharge, added to the base rate, designed to offset the revenue shortfall incurred from January 1 to May 1, over the balance of the fiscal year (i.e. by December 31). In the case of a rate reduction, the rate rider would, of course, be negative. The rate rider would only be in effect for the May to December period. With this approach, the base rate is the annualized rate that would recover the company’s year 1 revenue requirement. Since the rate rider is not applied beyond December 31, the effective rate would automatically decline to the correct annualized rate in January of year 2. No further rate changes would be required unless costs were rising to the point that an increase in the annualized rate was justified. In that event, the company would have to request an increase from the Régie. It is unclear from Hydro-Québec’s evidence and interrogatory responses (R18.1-18.413) exactly how the utility intends to put in place a solution that addresses the annualized effect of a May 1 rate increase. In Régie de l’énergie (Demande de renseignement no. 1 - 99-02-11), R8.214, Hydro- Québec states the following: Hydro-Québec est cependant consciente que l’application de l’écart entre les revenus requis totaux de l’année témoin et les revenus générés par les tarifs existants 13 Réponses d’Hydro-Québec aux questions de ARC/OC, HQPR-11 Document 5, pp. 8-9. 14 Réponses d’Hydro-Québec aux questions de la Régie de l’énergie, HQPR-11 Document 2, pp. 5-6. Régie de l’énergie Transmission Rates (R-3405-98) - 12 - Evidence of John Todd s’effectue sur une période résiduelle de huit mois. Néanmoins, l’application systématique de ce modèle en assure un contrôle adéquat et une stabilité tarifaire en période de forte consommation hivernale, tel que plus amplement détaillé à la pièce HQPR-5, document 1. According to this response, Hydro-Québec is aware of the problem and is applying «a model which ensures adequate control and rate stability» during the winter period. The utility goes on to state that this model is more amply described in HQPR-5, document 1.15 However, the level of detail about the mechanism provided in this document is insufficient to allow outside observers to understand how the problem is being addressed.16 15 HQPR-5, Document 1, p. 16. 16 In Régie de l’énergie (Demande de renseignement no. 1 - 99-02-11), R5.1, Réponses d’Hydro-Québec aux questions de la Régie de l’énergie, HQPR-11 Document 2.1, p. 2, Hydro-Québec explains its position against retroactive rate-making. This position should not be confused with a solution to compensate for the problem described here resulting from increasing rates during the rate year. Rates are set on a test year basis, using an approved forecast of revenues and costs. It is a well-established regulatory principle that if the company subsequently overearns or under-earns in the year for which final rates have been approved, no attempt is made to recover the excess earnings or compensate for the shortfall, except in the case of a pre-approved variance account. Compensating for unforseen variances from forecast for a test year is considered to be retroactive rate-making, which is not an acceptable standard Régie de l’énergie Transmission Rates (R-3405-98) - 13 - Evidence of John Todd practice. The solution sought here to compensate for over- or under-recovery due to the annualized effect of a May 1 increase, however, is not one of unforeseen forecasting errors. This is a foreseeable consequence of adopting a methodology with a test period that does not match the rate year. Taking this into account would not be retroactive rate-making. Failure to take it into account would constitute a violation of the regulatory principle of setting rates so that total revenue equals revenue requirement in each test year. Régie de l’énergie Transmission Rates (R-3405-98) - 14 - Evidence of John Todd If Hydro-Québec is unwilling to fully disclose and use an acceptable mechanism to address the overrecovery of rates due to the annualized effect, the Régie may wish to consider the option of having the rate year period coincide with the test year. There are several considerations that may limit the negative effect of a January 1 rate increase on customers. One, if the rate increases are expected to be fairly small, then the negative effects of the abandonment of the status quo will be limited. On the other hand, if forecast rate increases are more substantial, the negative effects could be mitigated if customers are encouraged to adopt the equal billing plan, which smooths monthly payments over the year. In this case, the Regie may consider using incentives to encourage Hydro-Québec to promote equal billing plans to customers. To make a more informed decision regarding the possible use of the equal billing plan to mitigate the negative effects of January rate increases, the Régie would need to more closely examine the level of customer participation in Hydro-Québec’s existing equal billing plan, as well as the possibility of increasing this participation.17 1.4 Issue 5: Determination of principal criteria to be used to identify and separate regulated activities from non-regulated activities Transmission activities, in general, should be regulated since transmission is a natural monopoly. However, there may be a few situations where transmission activities should not be regulated, if it can be shown that such activities are competitive. It is currently unclear which, if any, transmission activities in Quebec should not be regulated.18 At the moment, other jurisdictions are considering how to impute costs for such activities. A current regulatory view is that utilities should be expected 17 This explains the purpose of the ARC/OC interrogatory Q8.2 which asked how many residential clients were subscribed to the equal billing plan. Hydro-Québec’s answer was that quantitative numbers are not part of this proceeding. However, our goal was simply to determine an approximate level of participation in this program in order to recommend options to the Régie. (See HQPR-11 Document 5, p. 5) 18 Hydro-Québec’s interrogatory responses R9.1 and R10.1 (See HQPR-11, Document 5, pp. 5-6) provide no indication about which transmission activities should and should not be regulated, save the example of international consulting in the transmission field, which the utility cites as a non-regulated transmission activity. Régie de l’énergie Transmission Rates (R-3405-98) - 15 - Evidence of John Todd to recover the full costs of non-regulated activities, so that the regulated customers are not unfairly subsidizing such activities.19 Given that there is no experience in the separation of regulated and non-regulated activities in Quebec, in my view it would be premature to espouse binding principles at this time. Every situation is unique and as such, it would be better to develop, at most, some guidelines for the identification and activities for which separation might be considered. Specific criteria cannot be established on a generic basis. In fact, there should be no criteria that allows an activity to become exempt from regulation without a hearing. In other jurisdictions, case-by-case hearings to deregulate activities are common practice. If there is to be a guideline to be used for establishing when consideration might be given to separating an activity that will not be regulated, it should be that the activity is subject to effective competition. SUMMARY OF CONCLUSIONS Issue 1: the use of the projected test year for determining transmission rates Given that Hydro-Québec will be regulated with a rate-base rate of return methodology, the use of the projected test year is acceptable, subject to the following minimum conditions that are necessary 19 In the case of (Enbridge) Consumers Gas, the Ontario Energy Board ruled that the utility should apply a fully allocated costing methodology to ancillary and non-affiliate programs and activities. See Ontario Energy Board, EBRO 495, Decision with Reasons, August 21 1997, pp. 29-34. This Decision was reconfirmed in the current Enbridge Consumers Gas Decision. See Ontario Energy Board, EBRO 497, Decision with Reasons, August 31 1998, pp. 13-14, 27-30. Régie de l’énergie Transmission Rates (R-3405-98) - 16 - Evidence of John Todd to enable the Régie and intervenors to test the reasonableness of the company’s cost and revenue forecasts. (i) Cost and revenue data should be provided on a consistent and comparable basis for the projected test year, the bridge year and at least one historic year; it is common in other Canadian jurisdictions to require up to five years of historic data. (ii) Data for historic years should be provided on both a normalized and actual basis to permit trend analysis using comparable annual data. (iii) The methodology used for developing all forecast expenditures and revenues, (including the weather normalization methodology, trends in use per customer, loss calculations, etc.) should be fully transparent. Put simply, sufficient information should be on the record, or available through information requests, to enable the Régie, or intervenors to replicate the company’s forecasts. Issue 2: the establishment of a rate base and capital structure using a 13 month average The thirteen-month average is generally considered as a simple, practical and acceptably accurate solution for determining the average rate base. In my view, the use of this methodology to calculate the average rate base is appropriate. Issue 4: the choice of a test period to be used by Hydro-Québec for rate and regulatory matters with respect to its fiscal year The standard approach in utility regulation is to use matching fiscal, test and rate years so as to minimize administrative complexity and resulting regulatory burden. If the fiscal and test periods do not coincide, significant effort can be required in reconciling accounting statements. Without a detailed reconciliation of publicly available financial information, based on the company’s fiscal year, and the information provided in the regulatory forum, transparency is compromised. Régie de l’énergie Transmission Rates (R-3405-98) - 17 - Evidence of John Todd If the Regie decides to maintain Hydro-Québec’s status quo (which results in a mis-match between the rate year and the test year), it is essential that a May 1 increase is not implemented in such a way as to result in over-recovery of costs during the following fiscal year. In my view, the best solution to the problem of over-recovery in year 2 would be to use a rate rider, as explained in section 1.3. A rate rider is a temporary surcharge, added to the base rate, designed to offset the revenue shortfall incurred from January 1 to May 1, over the balance of the fiscal year (i.e. by December 31). If Hydro-Québec is unwilling to fully disclose and use an acceptable mechanism to address the overrecovery of rates due to the annualized effect, the Régie may wish to consider the option of having the rate year period coincide with the test year. The negative effect of a January 1 rate increase may be mitigated if (i) rate increases are small; or (ii) in the case of more substantial increases, the equal billing plan is more widely used. Issue 5: the determination of principal criteria to be used to identify and separate regulated activities from non-regulated activities. Transmission activities, in general, should be regulated since transmission is a natural monopoly. However, there may be a few situations where transmission activities should not be regulated, if it can be shown that such activities are subject to effective competition. Given that there is no experience in the separation of regulated and non-regulated activities in Quebec, in my view it would be premature to espouse binding principles at this time. Specific criteria cannot be established on a generic basis. In fact, there should be no criteria that allows an activity to become exempt from regulation without a hearing.