Public-Private Partnerships: some lessons from global experience Assessing global

advertisement
10/11/2013
Public-Private Partnerships:
some lessons from
global experience
Seminar on Public-Private Partnerships and
public account sustainability: compatible realities?
October 7, 2013
Banco de Portugal, Lisbon
Rui Sousa Monteiro
(World Bank Institute)
Assessing global
PPP experience
Currently there is a significant global PPP
experience
– Very good results in terms of effectiveness
– Good results, also, in terms of efficient delivery of
services
– Some concerns regarding “affordability” and
project selection
2
1
10/11/2013
What do we call PPPs?
3
What is a PPP
Public-private partnerships (PPPs) are long-term
contractual relationships between a public
sector entity and a private sector entity
The private partner
commits itself to providing
a set of services according
to some specified
performance levels
The public partner monitors
the performance and pays
the services or grants the
private partner the right to
collect fees from users
Economic reasoning tells us that PPPs should only
be used for services that require long-life assets
4
2
10/11/2013
Rationale for PPPs
Tradit.
D-B
PPP
PPP
PPP
PPP
design of infrastructure
core
construction of infrastructure
maintenance of infrastructure
provision of equipment
maintenance of equipment
provision intermediate services
provision services to end-users
In each case, services provided according to public sector rules
5
PPP and public service
• In locking the private partner in a long-term
relationship, the public sector is also locked for
a long period
• Because PPPs relate to public service, the public
partner is very sensitive to service disruption,
giving the private partner added bargaining
power
• When change affects the project, the private
partner may benefit from it; the private partner
may even engage in strategic moves for
inducing change for its own benefit
6
3
10/11/2013
Foundations
of PPP efficiency
• Output-based long-term contracts:
– Core: design + construction + maintenance
– Performance-based payments
whole-life costing
• Private capital at stake
credible commitment
• Good project selection (CBA, VFM, affordability)
• Competitive procurement
• Adequate contract management
– Partnering
– Contract enforcement
– Prevention of strategic moves
7
Is the PPP experience
relevant?
8
4
10/11/2013
Were the Egyptian pyramids PPPs?
9
Initial PPP experience:
large programs
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
10
5
10/11/2013
Initial PPP experience:
proliferation
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
11
Current PPP experience:
new large programs
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
12
6
10/11/2013
Current PPP experience:
proliferation
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
13
Current PPP experience:
countries with PPP programs
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
14
7
10/11/2013
Basis for
PPP efficiency
long-term contract with effective risk transfer
requires demand-based or availability-based
credible long-term risk transfer
requires private capital at stake, no easy way out
keeping efficiency in the long term requires proper
contract management and oversight of fiscal risks
but, most of all, PPP efficiency requires good
project selection, identifying costs, benefits & risks
15
Why do we need PPPs?
16
8
10/11/2013
Public infrastructure
but
often
affected
by
basic for economic growth
and for the quality of life
poor
maintenance
▪
The (non-PPP) case of Lima
metro, Peru
The 7-station elevated metro,
equipped with 32 cars, was officially
opened in 1990 but never operated,
due to poor demand; its operation
started only 21 years later, after
enlargement to 16 stations.
The planned 2nd line will be a PPP !
18
9
10/11/2013
The case of
Joá Penteado tunnel 2, Brazil
The 300-meter tunnel was
inaugurated in 2009, 23 years
after the beginning of
construction. Linking downtown
Campinas (in São Paulo state) to
its industrial district on the other
side of a hill, its construction
stopped after one year, for lack of
public funds, when the tunnel was
half dug; it took 20 years to
obtain funds for digging the
remaining 130 meters.
19
The case of Salvador da Bahía
metro, Brasil
Half-built and not operational
for 12 years, completed 2012
and still not operational.
20
10
10/11/2013
The (non-PPP) case of
Barcelona subway line 9, Spain
Cost forecasts: €2,600m in 2003; then €3,700m; later
€6,900m; currently €16,000m; beginning of construction:
2003; end of construction: unknown (for lack of financing)
21
A non-PPP case: Requena-Utiel
HSR station, Valencia, Spain
Cost: €12m; surrounded by vineyards, midway between
Requena and Utiel; demand is slowly growing, having
reached 50 passengers/day
22
11
10/11/2013
The (non-PPP) case of
Cuenca HSR station, Spain
Cost: €20m; the first “green” rail station in Spain: noncontaminant materials, geothermal water supply; 250-car
parking; demand is so low that Renfe suppressed a few trains
23
The case of
Laredo marina, Spain
Cost €90m (half of that still owed to the banks by Municipality),
but still incomplete; no users; locals complain the beach
nearby is being eroded by the changes in sea currents
24
12
10/11/2013
The case of the marina of
Lugar de Baixo, Madeira (1)
Initial expected cost €24m; current cost €44m according to
regional gov’t (or €100 according to the opposition); opened
in 2004, with berths for 291 yachts; destroyed in 2005
25
The case of the marina of
Lugar de Baixo, Madeira (2)
26
13
10/11/2013
The case of the marina of
Lugar de Baixo, Madeira (3)
27
Casa da Música, Porto, Portugal
House of Music, Porto, Portugal, €100m
28
14
10/11/2013
Ciudad de las Artes y las
Ciencias
City of Arts and Sciences, Valencia, Spain, $500m
29
The (non-PPP) case of
Jaén tram, Spain
Cost: €100m, completed in 2011, procured by the regional
government, then transferred to the municipality, who operated
the service for two weeks and closed it for lack of funds to
operate a tram service with scarce users (even with zero fee)
30
15
10/11/2013
The case of
Ciudad Real airport, Spain
Cost €1,100m; 4,000m runway; the first private international
airport in Spain; capacity: 2,500,000 pass; demand in 2010:
33,520; closed in April 2012 after three years in operation
31
The case of
Huesca airport, Spain
Cost €40m; opened in 2007; with no commercial activity since
February 2011; demand: zero passengers August 2011, four
in September, all from small private planes
32
16
10/11/2013
The case of Castellon airport,
Valencia, Spain
Cost: €150m; officially declared “open” in March 2011; not
licensed due to design errors; a $375,000, 79-feet tall statue
of Carlos Fabra, a local politician, was erected in the airport
33
The case of
Pamplona-Noáin airport, Spain
Cost €50m; capacity for 1,100,000 passengers/year; demand in
2010: 291,553
34
17
10/11/2013
The case of
León airport, Spain
Three times enlarged in the past decade; after the last
enlargement, costing €29m, it presents capacity for 500,000
passengers, i.e. 5 times current demand
35
Spanish “ghost” airports
(“aeropuertos fantasmas”)
• Spain has more international airports for commercial flights
than any other country in Europe: 48 public and 2 private
• 20 of those airports handle fewer than 100,000
passengers/year
• Too many airports? (And also too many rail lines, ports, and
highways? And too many sport and entertainment facilities?)
• Or were they simply built in the wrong location, in order to
serve local politicians’ interests?
36
18
10/11/2013
PPP projects:
Highways in Spain
Significant cost overruns, in some cases over 50 percent; low
demand, reaching 1/10 of expected traffic. In 2012, AP41
Madrid-Toledo, Radial 4R4, and Cartagena-Vera concessionaires
filed for bankrupcy. Several more are close to bankrupcy.
37
The empirical evidence:
unintended consequences
•
38
19
10/11/2013
The empirical evidence
A
•
•
•
•
•
large track-record of poorly managed projects:
Poor project selection
Cost overruns
Insufficient demand
Collapsed and struggling projects
Insufficient governance
But also examples of well managed projects (many of them
PPP projects)
And mixed cases of great service effectiveness (users ☺)
and poor use of public resources (taxpayers )
39
We have hundreds of
successful PPP projects
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
40
20
10/11/2013
Chile is an example
41
And also a few successful
non-PPP projects
Worldmapper.org
© Copyright SASI Group (University of Sheffield) and Mark Newman (University of Michigan)
42
21
10/11/2013
Øresund bridge, between
Sweden and Denmark
• Cost: $5700m
• User-fees will repay
the bridge until 2035
43
The new railway station in
Stuttgart (Germany) (1)
44
22
10/11/2013
The new railway station in
Stuttgart (Germany) (2)
• Original cost estimate: €3100 million.
• In December 2009, Stuttgart21 project approved
(by Deutsche Bahn and the federal, state and
municipal governments) with a cost estimate of
€4100 million, on condition that its cost does not
exceed €4500 million
• The approving entities (DB and governments) did
commit on funding the expected cost, and on a
€400 million contingency provision
• Works started February 2010
45
The new railway station in
Stuttgart (Germany) (3)
• Cost expectation €4100m + €400m = €4500m
• But currently, after three years of construction,
the cost estimate reached €6800 million (with a
4-year delay)
• State and municipal governments refused to
provide more funds, and the Finance Ministry did
consider the option of cancelling Stuttgart21
• But Stuttgart21 will be completed because the
cost of cancelling the project will be higher than
the cost of completing it.
46
23
10/11/2013
Stuttgart21
and fiscal risks
• This Stuttgart21 project provides an example
of the fiscal risks that always affect public
infrastructure projects
• But we should emphasize a few points:
– Its budget included a provision for contingencies (in
the current case, an insufficient one)
– The realization of cost overruns did induce strategic
behavior by all involved public entities (DB and the
federal, state and municipal governments)
– Besides fiscal risks, political risks are present: the
opposition complained, as well as environmentalists
47
Public infrastructure and
fiscal risks
Bent Flyvbjerg, Nils Bruzelius and Werner Rothengatter
did investigate public infrastructure all over the world
and identified a tendency for cost under-estimation:
managers and decision makers present low cost
estimates and hide risks, in order for their
projects to obtain government approval
Adverse selection: "Those who provide honest
estimates for projects from the very beginning have
little chance of getting them off the ground“
See (2003) Megaprojects and Risk: An Anatomy of
Ambition, Cambridge University Press
48
24
10/11/2013
New Berlin-Brandenburg
airport
• PPP option abandoned; first tender canceled
• Cost: €2000m en 2006
• Completion date: 2011
€4300m + compensations
2014?
49
Rail tunnel in Leipzig
• Cost: €572m
€960m
• Completion date: 2009
Dec 2013
50
25
10/11/2013
New North-South metro
line, in Koln
• Cost: €600m in 2000
€1040m
• Collapse of municipal archive (€1000m damage)
• Vibration in the Cathedral
51
Second rail tunnel in Munich
• Cost: €2047m in November 2012, plus €500m for
contingencies; but the current estimate is €2433m
• Completion date: 2020
2021 or 2022
52
26
10/11/2013
Some good practices
• Cost of public projects (including PPPs) is
presented in the budget and fiscal reports
• German governments, federal and sub-national,
do not adopt the out-of-the-book approach
• Large projects require co-funding schemes
between different levels of government (federal,
state, municipal), inducing better analysis
• Provisions for risks are budgeted
• Role of MoF
53
How can PPPs help?
54
27
10/11/2013
PPPs as credible commitment
• PPPs present a credible commitment for
implementing a transport project
– project revenue is dependent on
reaching the operational phase, creating
a strong incentive for completion
– the private partner starts the project
with a full financing scheme, avoiding
the usual public finance troubles
55
PPPs and economic rationality
Allocating project implementation to a
private entity allows for the private partner
to use full economic rationality in designing
and building infrastructures and in
selecting and procuring equipment,
services and staff
And PPPs may present additional benefits…
56
28
10/11/2013
A non-standard approach:
PPPs as project filtering
• The case of Dublin’s metro
• The case of UK’s light rail projects
• The case of Fertagus rail service
57
The case of
Dublin subway
• Project decided in 1996
– studies by the state-owned public
transport operator
• In 2001, new agency
– a rail procurement agency
• PPP studies:
– subway lines cancelled
– tram lines approved (38km Luas)
– Luas started operating 2004
• Subway lines
(Dublin Metro)
– deferred again in 2011
58
29
10/11/2013
The case of UK’s light rail
59
The case of Fertagus railway
60
30
10/11/2013
The case of
Fertagus rail service
• The project
• The solutions
• The negotiation
(2004)
– challenging the private
operator
– facing lobbies:
•
•
•
•
rail-line design
regulation
trains
safety systems
61
The case of St Barts hospital
62
31
10/11/2013
How can PPPs harm?
63
Case: Canal du Midi / Garonne
“mettre en risque mon bien et mon honneur à
défault de réussite et, par contre-coup,
acquérant un peu de l'un et un peu de l'autre,
en cas que j'en sorte heureusement”
Riquet, a local tax collector,
presented to Louis XIV this
unsolicited proposal: building a
canal connecting the Atlantic
Ocean to the Mediterranean at
no cost to the taxpayer or
royal purse
64
32
10/11/2013
Case:
Canal du Midi / Garonne
Riquet was awarded
a perpetuous
concession in 1666,
with the right to
collect a special
purpose new tax.
The canal, built in
1666-1683, was a
success, but the
public partner paid
two thirds of its cost.
65
Vasco da Gama bridge
66
33
10/11/2013
Skye bridge
67
Sources of fiscal risks
•
•
•
•
•
•
•
•
Bad projects
Poorly researched projects
Bad contracts
Technological or commercial change
Demographic change
Political or legal change
Poor contract management
Lack of global affordability
68
34
10/11/2013
Alternative perspectives
on PPPs
• PPPs may be perceived as a convenient way
for some decision-makers to circumvent
existing budgetary rules
or
• PPPs may be perceived as a way for some
private firms to capture government and
create long-term sources of rents
69
PPPs,
rent-seeking and corruption
• PPPs as a rent-seeking tool
– rents extracted from users, or
– rents extracted from the government
• The role of MoF
– project appraisal (CBA or similar)
– contractual review (evaluation of fiscal risks)
– project prioritization (affordability checks)
• PPPs as a corruption tool
• The role of transparency and external auditing
70
35
10/11/2013
Preventing and managing
•
•
•
•
•
•
Good project appraisal
Careful draft contract design
Gateway processes: costs and risks
The role of audit offices / courts of auditors
Continuous evaluation of fiscal risks & costs
Contract management
71
PPP and
fiscal accountability
• Budgetary costs:
– certain
– contingent
• Budgetary risks are much more than
contingent liabilities
• Fiscal accountability requires much more than
accounting rules
– effective fiscal management
– contract disclosure
– contract oversight and fiscal risk management
72
36
10/11/2013
On the sustainability of
non-contingent liabilities
or:
• The fiscal iceberg
73
Transport in Portugal:
the fiscal iceberg
74
37
10/11/2013
Transport in Portugal:
the fiscal iceberg
Translating:
– Transport expenditure (Min. Public Works)
– Transport expenditure (Min. Finance)
€449m
€251m
• Total reported expenditure 2008: €700m
• Net change in assets in transport sector SOE:
€2,500m to €3,000m
• Net change in (out-of-budget) PPP commitments:
€3,000m
75
Effectiveness and efficiency
effective
76
38
10/11/2013
Effectiveness and efficiency
effective
77
Effectiveness and efficiency
effective
efficient from
the viewpoint of
public purse
78
39
10/11/2013
Effectiveness and efficiency
effective
efficient from
the viewpoint of
public purse
efficient from
the viewpoint of
society
79
Effectiveness and efficiency
effective
efficient from
the viewpoint of
public purse
efficient from
the viewpoint of
society
80
40
10/11/2013
Sydney’s BD tunnel
81
Managing fiscal risks
Fiscal risks refer to the possibility of
deviations in fiscal variables from what
was expected at the time of the budget
or other forecast
82
41
10/11/2013
Selecting the adequate
infrastructure projects
• cost-benefit analysis
• long-term resilience
technological change
policy change
demographical change
• prioritization
83
Checking for affordability
• assessing long-term expected costs
• assessing long-term contingent costs
• fiscal and political commitment
84
42
10/11/2013
Designing proper PPP
schemes and contracts
• allocating risks
• designing incentive schemes
• measuring performance
85
Preventing free-riding by
sub-national governments
• affordability challenges
• efficiency concerns
• fiscal and financial reporting
86
43
10/11/2013
Promoting competition
• double concern:
- selecting the best partner
- at the lowest cost
87
Preparing for
contract management
contract
enforcement
partnering
strategic
analysis
88
44
10/11/2013
Change management and
risk management
• assessing change
• identifying risks
• mitigating impacts
89
Managing
contingent liabilities
• assessing liabilities
• reporting liabilities
• managing liabilities
90
45
10/11/2013
Overseeing and controlling
PPP commitments
• Ministry of Finance
• Auditing entities
• Media, taxpayers, general public
91
Institutional capacity:
government
• Is government able to assess project risks?
• Is government able to define the KPI?
• (Tendering is the “easiest” part)
• Is government able to manage the contract?
• Is there a gateway process?
Is government able to increase its capacity?
92
46
10/11/2013
Thank you
Rui Sousa Monteiro
senior public-private partnerships specialist
World Bank Institute
1818 H Street, N.W.
Washington, D.C. 20433, USA
tel: +1-202-473-9450
e-mail: RMonteiro@WorldBank.org
93
47
Download