Agenda Item 8-A Action Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Authorization to Execute a Contract for Elevator Rehabilitation or Replacement at Franconia-Springfield and Rippon Stations Recommendation: The VRE Operations Board is asked to authorize the Chief Executive Officer to execute a contract with Nichols Contracting, Inc. of Sandy Spring, Maryland for elevator rehabilitation or replacement at Franconia-Springfield and Rippon stations in the amount of $1,078,480, plus a 10% contingency of $107,848, for a total amount not to exceed $1,186,328. Background: In recent years, the frequency of failures and required maintenance service calls have increased for the two elevators at the Franconia-Springfield station and the elevator at the Rippon station, creating an inconvenience to VRE riders. The failures are due to aging elevator cabs and associated equipment. The project scope of work includes the modernization of elevator cabs, controls, support structures and systems. On March 20, 2015, the VRE Operations Board approved a request to issue an Invitation for Bids (IFB) for the Elevator Rehabilitation or Replacement at Franconia-Springfield and Rippon Stations project. A mailing list of fifty-seven (57) prospective Bidders was established for the solicitation to ensure access to adequate sources of services. Additionally, the IFB was posted on eVA. On July 24, 2015, an IFB was issued and bids were due on August 24, 2015. Only one (1) response was received. The staff conducted a survey to determine why only a single Bid was received and is satisfied with the result. The following reasons were given for why Bidders did not respond to the solicitation: Current workload does not allow time for additional projects; Lack of manpower; Pricing obtained from prospective subcontractors was not competitive; Steel supplier was unable to provide pricing prior to the due date for Bids; and, Considerable amount of effort is required to address the level of rust observed at the site visits. Staff has certified the price is fair and reasonable. The bid abstract is as follows: Bidder Bid Amount Nichols Contracting, Inc. of Sandy Spring, MD $1,078,480.00 The Contract includes the modernization of three (3) passenger elevators to be completed as follows: Franconia-Springfield Station East Elevator (Elevator No. 1) - One hundred and twenty (120) calendar days from the date set forth in the written Notice-ToProceed. Franconia-Springfield Station West Elevator (Elevator No. 3) - One hundred and fifty (150) calendar days from the date set forth in the written Notice-To-Proceed. Rippon Station Elevator - One hundred and twenty (120) calendar days from the date set forth in the written Notice-To-Proceed. Fiscal Impact: The total cost of this project is funded with Federal FY 2016 State of Good Repair formula grants (5337), matched with state and local funds. 2 Virginia Railway Express Operations Board Resolution 8A-09-2015 Authorization to Execute a Contract for Elevator Rehabilitation or Replacement at Franconia-Springfield and Rippon Stations WHEREAS, the elevators at the Franconia-Springfield and Rippon stations have experienced increased failures and required maintenance service calls due to aging elevator cabs and associated equipment; and, WHEREAS, the project scope of work includes the modernization of elevator cabs, controls, support structures and systems; and, WHEREAS, the VRE Operations Board in March 2015 approved issuance of an Invitation for Bids (IFB) for the Elevator Rehabilitation or Replacement at Franconia-Springfield and Rippon Stations project; and, WHEREAS, VRE advertised an Invitation for Bids on July 24, 2015; and, WHEREAS, on August 24, 2015, one response was received; and, WHEREAS, subsequent to a review of the references and financial stability, VRE staff recommends the VRE Operations Board award a contract to Nichols Contracting, Inc. of Sandy Spring, Maryland; NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board does hereby authorize the Chief Executive Officer to execute a contract with Nichols Contracting, Inc. of Sandy Spring, Maryland for elevator rehabilitation or replacement at Franconia-Springfield and Rippon stations in the amount of $1,078,480, plus a 10% contingency of $107,848, for a total amount not to exceed $1,186,328. Approved this 18th day of September 2015 ______________________________ John C. Cook Chairman ____________________________ Paul Smedberg Secretary 3 Agenda Item 8-B Action Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Authorization to Execute a Contract for Replacement of Platform Canopies, Gutters and Downspouts at L’Enfant and Leeland Road Stations Recommendation: The VRE Operations Board is asked to authorize the Chief Executive Officer to execute a contract with Elite Sheet Metal Works, Inc. of Beltsville, Maryland for replacement of platform canopies, gutters and downspouts at L’Enfant and Leeland Road stations in the amount of $286,400, plus a 10% contingency of $28,640, for a total amount not to exceed $315,040. Background: The platform canopies, gutters and downspouts at several VRE stations were installed many years ago. Due to years of exposure to the elements, these items at the L’Enfant and Leeland Road stations have experienced rusting, leaking, peeling and flaking. The scope of work for the IFB includes the replacement of canopy roofing, gutters and downspouts at both stations. Similar replacements at additional stations will occur in subsequent years as necessary to maintain optimal performance and appearance. On March 20, 2015, the VRE Operations Board approved a request to issue an Invitation for Bids (IFB) for the Replacement of Platform Canopies, Gutters and Downspouts at L’Enfant and Leeland Road Stations project. A mailing list of thirty-five (35) prospective Bidders was established for the solicitation to ensure access to adequate sources of services. Additionally, the IFB was posted on eVA. On July 31, 2015, an IFB was issued and bids were due on September 3, 2015. The bid tabulation is as follows: Bidders Bid Amount 1. Elite Sheet Metal Works, Inc. of Beltsville, MD $286,400.00 2. CHU Contracting, Inc. of Chantilly, VA $299,000.00 After review of the bids, it was determined that Elite Sheet Metal Works, Inc. was the lowest responsive-responsible bidder. Staff has certified that the price is fair and reasonable. The Contract includes the replacement of platform canopies, gutters and downspouts at two stations to be completed as follows: L’Enfant Station – Thirty (30) calendar days from the date set forth in the written Notice-To-Proceed. Leeland Road Station – Thirty (30) calendar days from the date set forth in the written Notice-To-Proceed. Fiscal Impact: The total cost of this project is funded with Federal FY 2016 State of Good Repair formula grants (5337), matched with state and local funds. 2 Virginia Railway Express Operations Board Resolution 8B-09-2015 Authorization to Execute a Contract for Replacement of Platform Canopies, Gutters and Downspouts at L’Enfant and Leeland Road Stations WHEREAS, the platform canopies, gutters and downspouts at several VRE stations were installed many years ago; and, WHEREAS, these items at the L’Enfant and Leeland Road stations have experienced rusting, leaking, peeling and flaking; and, WHEREAS, the scope of work includes replacement of canopy roofing, gutters and downspouts at both stations; and, WHEREAS, the VRE Operations Board in March 2015 approved issuance of an Invitation for Bids (IFB) for the Replacement of Platform Canopies, Gutters and Downspouts at L’Enfant and Leeland Road Stations project; and, WHEREAS, VRE advertised an Invitation for Bids on July 31, 2015; and, WHEREAS, on September 3, 2015, two responses were received; and, WHEREAS, subsequent to a review of the references and financial stability, VRE staff recommends the Operations Board award a contract to Elite Sheet Metal Works, Inc. of Beltsville, Maryland; NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board does hereby authorize the Chief Executive Officer to execute a contract with Elite Sheet Metal Works, Inc. of Beltsville, Maryland for replacement of platform canopies, gutters and downspouts at L’Enfant and Leeland Road stations in the amount of $286,400, plus a 10% contingency of $28,640, for a total amount not to exceed $315,040. Approved this 18th day of September 2015 ______________________________ John C. Cook Chairman ____________________________ Paul Smedberg Secretary 3 Agenda Item 8-C Action Item To: Chairman Cooke and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Referral of Preliminary FY 2017 VRE Operating and Capital Budget to the Commissions Recommendation: The VRE Operations Board is asked to authorize the Chief Executive Officer to refer the Preliminary FY 2017 VRE Operating and Capital Budget to the Commissions for their consideration, so the Commissions, in turn, can refer these recommendations to the jurisdictions for their review and comment. Background: In accordance with the VRE Master Agreement, which outlines the process for annual budget approval, the preliminary FY 2017 VRE Operating and Capital Budget is attached for review. The Budget Key Issues considered by the Operations Board in July are also provided as an attachment. Since July, VRE staff has met with the CAO Taskforce to discuss jurisdictional budget issues and concerns and to review current VRE budget projections. During the FY 2017 budget year, VRE will operate 32 daily revenue trains and continue our safety and customer service outreach programs. The capital budget for FY 2017 will focus on state of good repair of equipment and facilities and replacement of the mid-day storage facility. Five expansion railcars will be received during the fiscal year and an additional nine will be under construction. The major budget issues for FY 2017 are adequate and timely funding of the replacement facility for mid-day storage of rolling stock equipment, and meeting required and necessary increases to operating expenses. Discussion: The FY 2017 preliminary budget totals $119.8 million. The budget includes a 5% subsidy increase with no fare increase and has a current net unfunded amount of $2.8M. As in the past, VRE will submit a balanced budget to the jurisdictions in the beginning of December for evaluation prior to submission to the Operations Board later that month. Both revenue and expenses are still under review and these projections are expected to change considerably over the next several months. The assumptions used in preparing the preliminary draft are as follows: 1. Fare revenue: Fare revenue is budgeted at $39.4 million with no fare increase recommended. A fare increase of 4% occurred at the beginning of FY 2016. Ridership is estimated at 19,900 Average Daily Riders (ADR) with service at the current budgeted level of 34 daily trains (32 revenue trains). ADR in FY 2015 was 18,547. 2. Jurisdictional subsidy: The subsidy is currently budgeted at $17.25 million, a 5% increase from FY 2016, which is the amount included in the Six-Year Financial Forecast. The last subsidy increase was in FY 2013 and the recommended amount of $17.25 is approximately equal to the amount paid in FY 2009. 3. Federal funds: Congress approved a short term extension to the current transportation authorization through May 2015. All indications are the full reauthorization will provide approximately $27M in formula funding for VRE in FY 2016 or about $900k less than the amount budgeted. The FY 2017 preliminary budget is based on the most recent funding level of $27M. 4. State operating funds: Commonwealth operating assistance of $9.2 million was received in FY 2016. The FY 2017 preliminary budget is based on $9.0 million. 5. State capital funds: Commonwealth capital funding is currently projected at either: a) 16% of the total project cost, when used as match to 80% federal funding; or b) one of the three funding tiers of 68%, 34% or 17% of gross project costs, regardless of the amounts of federal funding assigned to the project. State match for the replacement of the mid-day equipment storage facility is budgeted at the 34% level. 6. Access fee funding: Since FY 2015, DRPT has allowed VRE to apply for multiyear agreements for track access fee reimbursement. For FY 2017, reimbursements are currently being estimated at a level similar to FY 2016, with an 84% combined rate for both federal STP funds allocated through the state and a state capital match. 2 7. Capital program: Capital needs have been identified and prioritized and funding sources have been considered within the available federal formula funds and existing allocations through CMAQ, NVTA regional funds or other sources. The multi-year CIP will also include needed projects for which funding has not yet been identified. The largest capital expense is $21.8M for the equipment storage project. An annual capital reserve contribution of $3 million is also included. 8. Contractual increases: The CSX access fees have an annual contractual increase of 4%. Access fees paid to Norfolk Southern are based on changes to the AAR, a nationally published index of railroad costs, and increases to Amtrak access fees for FY 2017 will be based on a three year average of their annual costs, inflated to the budget year. Currently, Norfolk Southern and Amtrak increases are budgeted at 4%. The bulk of the Keolis contract costs increase by the annual change to the CPI, currently budgeted at 3%. 9. Fuel costs: Fuel expenses of $5.2 million are budgeted based on a per gallon cost of $3.25. 10. Staff changes: VRE staff recommends adding four FTE employees to various departments. As VRE has grown in size and complexity and as regulatory and performance requirements have increased, staff resources have not kept pace. The FY 2016 budget included three new permanent positions and the replacement of three contract positions with VRE staff positions. The following additional positions are included in the FY 2017 preliminary budget: Finance and Administration – Associate Accountant - Responsible for various accounting functions, including accounts payable, payment and card processing and providing vital accounting and administrative support for other finance staff. The position is needed due to the expanding workload and duties within the finance and human resources functions within VRE. Facilities – Facilities Specialist – Responsible for assisting with management of scheduled maintenance, repairs and state of good repair projects at all station and equipment maintenance facilities. With additional VRE stations, expansion of existing stations and additional equipment facilities coming online, additional VRE staff support is required. Project Implementation – Project Manager - A licensed engineer who will manage the final design and construction of VRE capital improvement projects. The number and complexity of VRE capital projects is increasing as a result of System Plan 2040. An additional Project Manager is needed to handle the workload in a timely and effective manner. 3 Project Implementation – Project Administrator - Responsible for administration of project controls (schedule and budgets), quality control, invoicing, procurement coordination, and routine reporting for VRE capital improvement projects as well as management of minor planning and design projects. The number and complexity of VRE capital projects is increasing as a result of System Plan 2040. The addition of a Project Administrator is needed to handle the workload in a timely and effective manner. More detail on these positions will be provided as part of the presentation at the Board meeting. The preliminary cost of the four positions is $500k. The major significant changes in the FY 2017 proposed budget compared to the adopted FY 2016 budget are as follows, including those issues discussed in more detail above: Revenue: $821k increase in Jurisdictional Subsidy as described above $480k increase in Fare Revenue due to the projected level of ridership $1.6M decrease in Other Sources, primarily one-time funds used for local match to capital projects and one-time expenditures. One-time funds will be included in future drafts of the FY 2017 budget, as appropriate. $19M decrease in grant funds for CMAQ and REF projects included in the FY 2016 budget and the 68% funding received from the state for the railcar project; these decreases are offset by a decrease in project costs. Decrease of $900,000 to the budget for federal formula funds, as noted above. Increase of $900,000 to the $8.1M budgeted in FY 2016 for state operating assistance. (Actual amount received in FY 2016, as noted above, was $9.2M.) Operating and capital expenses: $1.2M increase related to the estimated ongoing operating costs of the PTC system. $500k increase for the four positions noted earlier in this memorandum. $945k for contractual increases for train operations and maintenance, mid-day services and access fees. $255k increase in Facilities Maintenance for contractual and utility cost increases. 4 Increases of $200k in safety and security for enhanced security contracts; $639k in IT for additional professional services and computer equipment upgrades; and $200k for increased costs for credit card processing related to fare media purchases. The total capital budget is projected at $34.4 million. Projects include: o $3.9 million for facilities infrastructure lifecycle maintenance o $4.9 million for equipment life cycle maintenance o $600k for replacement of security cameras o $21.8 million for mid-day and overnight train storage o $210k for security enhancements/associated transit improvements (a 5307 grant requirement) o $3.0 million annual contribution to the capital reserve Fiscal Impact – FY 2017 Budget: Additional draft budgets will be formulated during the fall and reviewed with the CAO Budget Task Force resulting in a balanced budget by December 2016. Attached are the following: FY 2017 Key Budget Issues FY 2017 Sources and Use FY 2017 Summary Budget 5 Virginia Railway Express Operations Board Resolution 8C-09-2015 Referral of Preliminary FY 2017 VRE Operating and Capital Budget to the Commissions WHEREAS, the VRE Master Agreement requires the VRE Operations Board submit to the Commissions a preliminary fiscal year budget by September 30 each year; and, WHEREAS, the VRE Chief Executive Officer has provided the VRE Operations Board with the preliminary FY 2017 Operating and Capital Budget; NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board refers the preliminary FY 2017 Operating and Capital Budget to the Commissions for their consideration; and, BE IT FURTHER RESOLVED THAT, the VRE Operations Board recommends the budget be forwarded to the jurisdictions for further formal review and comment; and, BE IT FURTHER RESOLVED THAT, VRE staff is directed to consider and address comments by the jurisdictions and to forward a final recommended budget to the VRE Operations Board at the December 2015 meeting for consideration and referral to the Commissions for adoption in January 2016. Approved this 18th day of September 2015. _______________________________ John C. Cooke Chairman ____________________________ Paul Smedberg Secretary 6 FY 2017 Key Budget Issues The key issues described below apply to the development of the FY 2017 Budget and CIP and to the six-year financial plan, which provides a consolidated financial projection over a multi-year time frame. Key Issue #1: Level of service: Some trains are currently at or over 100% capacity. Planned service improvements include the new Fredericksburg line train (fall 2015, in conjunction with the opening of Spotsylvania Station – revised from original) and the lengthening of peak trains as additional railcars are received. The addition of the Fredericksburg line train scheduled to begin service in fall 2015 (revised from original) is expected to somewhat mitigate the overcrowding and the capacity issues at stations further up the line. The service will run with the legacy gallery railcars until additional new railcars are available mid-way through FY 2016. Five railcars were ordered in FY 2015 and an additional nine are budgeted in FY 2016. These additional 14 cars along with related infrastructure improvements to stations and storage yards will allow for the lengthening of existing peak trains and the conversion of a “deadhead” train on the Manassas line to revenue service in FY 2017. Key Issue #2: Maintenance and Replacement of VRE Assets: Federal formula funds devoted to maintaining transit assets in a “State of Good Repair” are expected to provide for the ongoing capital cost of maintaining VRE assets over their life-cycle. However, replacement of the fleet at the end of the expected useful life of the equipment will require additional funding mechanisms. The federal priority under MAP-21 of maintaining transit systems in a “State of Good Repair” has been included in the current versions of the next transportation authorization and the funds to adequately maintain equipment and facilities will be available from this source. The recently completed asset management strategy for facilities will be used to refine the costs included in the FY 2017 budget and CIP for this group of assets. Because VRE’s current fleet of railcars and locomotives were purchased during a compressed time period, the replacement of the fleet at the end of its useful life is projected to be needed during a five-year period beginning in FY 2030, at an estimated cost of approximately $450M. Although this need falls well beyond the projection period in the annual budget and CIP, this issue was highlighted in the longer-term Financial Plan forecast. 7 Key Issue #3: Midday Storage: The construction of alternate midday storage facilities will require a significant funding commitment over the next several years. VRE is currently hampered by limited midday track space at Union Station and must deadhead one trainset daily back to the Broad Run yard. In addition, the current contract with Amtrak includes provisions for Amtrak to reclaim VRE’s current storage space at the Ivy City yard for their own use during the next several years. As a result, VRE must proceed expeditiously to both increase midday train storage beyond what is currently available and to fully replace the storage yard now used at Ivy City. A substantial portion of available federal formula funds were devoted to this project during the six-year time frame covered by the FY 2016 – FY 2021 CIP. However, recent cost projections indicate that additional funding will need to be identified. Key Issue #4: Capital improvements to support the VRE System Plan: Capital improvements needed to meet the expected demand for VRE service and to increase railroad infrastructure capacity in the VRE service territory require the identification and commitment of funds beyond those currently available to VRE. During FY 2014 the Operations Board and Commissions endorsed the VRE System Plan, which provides for the logical, incremental expansion of VRE infrastructure and service. The Financial Plan will detail VRE’s ability to maintain and expand service based on current and future fiscal restraints. An important component of future capital needs is the commitment to ensure the development of the railroad infrastructure in the CSXT territory. NVTA regional funding continues to be available on a discretionary basis for certain VRE capital projects, but only for those located within the NVTA jurisdictions, which has highlighted the need for funding sources in the non-NVTA area served by VRE. Key Issue #5: VRE staff level: VRE needs the staff resources necessary to operate and administer the commuter rail system safely, efficiently and in compliance with all federal and state requirements. Since inception, the administration and oversight of the commuter rail system has been accomplished by a relatively small permanent staff, supplemented at times with assistance on a contract or temporary basis. As the system itself has grown and developed, along with a continuing increase in internal and external requirements, the staff level has not kept pace. The FY 2016 budget included three new permanent positions and the replacement of three contract positions with VRE staff positions. While the new positions have helped address needs, the FY 2017 proposed budget is expected to include the need for further additional staff resources. 8 Key Issue #6: Jurisdictional subsidy and the need for additional funding sources: The VRE service currently must be supported within the confines of jurisdictional budget constraints. The Financial Plan forecast is the first step in quantifying the need for additional ongoing funding sources to support the commuter rail service. The subsidy level in FY 2017 will be evaluated based on a variety of factors, including contractual increases, expected changes to state and federal funding levels and the jurisdiction’s ability to contribute using fuel tax revenue or other sources of funding. The FY 2016 six-year financial forecast projected a subsidy increase of 5% for FY 2017. VRE will work with jurisdictional staff on formulating future subsidy levels and will fully utilize all existing other funding sources. The total jurisdictional subsidy of $16.4 million has been flat for the last four years and the level has not changed appreciably over the last seven years. The limitations of the reliance on jurisdictional funding and the need for alternate ongoing funding will be addressed through the Financial Plan forecast, as noted above. 9 FY17 Sources and Use Leases LEVEL OF SERVICE FOR FY17 34 trains 16,850,000 16,850,000 19,700 average daily riders Total Access Fees SOURCES OF FUNDS |-----------------STATE -----------------| USES OF FUNDS Operating Expenses FARE INCOME 78,635,562 39,370,000 INTEREST 25,000 MISC LOCAL SUBSIDY OTHER SOURCES 200,000 15,366,562 0 OTHER SOURCES - STATE OPERATING 9,000,000 Amtrak NS CSX Total 6,340,000 3,480,000 7,030,000 16,850,000 |----------------FEDERAL------------------| STATE CAPITAL STATE STP 5,729,000 5307/5337 8,425,000 OTHER TOTAL 520,000 78,635,562 Non-Operating Expenses: Operating Reserve Debt Svc (Gallery IV) (11 Cabcars) Debt Svc 60 Railcars (Local) Debt Svc 60 Railcars (Fed/State/Local) 54,000 1,931,357 110,442 4,673,071 Non-Operating Summary 6,768,870 Total Expenses (Subtotal) 85,404,432 Capital Projects: Equpment Life Cycle Maintenance Facilities Infrastructure Lifecycle Maintenance Security Cameras NY Ave. Mid-day Train Storage Enhancement Grant - Security Assoc. Transit Improvements Capital Reserve 4,900,000 3,933,000 612,000 21,771,000 105,000 105,000 3,000,000 Capital Project Summary 34,426,000 54,000 77,254 110,442 186,923 39,370,000 25,000 200,000 428,619 309,017 747,691 - 15,795,181 0 - 9,000,000 196,000 157,320 24,480 870,840 4,200 4,200 3,000,000 - - - 1,056,708 6,785,708 3,738,457 8,425,000 784,000 629,280 97,920 7,402,140 16,800 16,800 4,257,040 0 - - 8,946,940 54,000 1,931,357 110,442 4,673,071 1,545,086 5,283,542 - 6,768,870 5,803,542 - 85,404,432 3,920,000 3,146,400 489,600 13,498,020 84,000 84,000 - 21,222,020 4,900,000 3,933,000 612,000 21,771,000 105,000 105,000 3,000,000 - 34,426,000 CMAQ/REF CMAQ Summary 0 TOTAL 119,830,432 39,370,000 25,000 200,000 - 0 - 0 - 0 0 - 0 0 - 20,052,221 FY17 subsidy surplus (deficit) 16,428,800 (3,623,421) FY17 Subsidy (incld.+ 5%) Suplus (deficit) 17,250,240 (2,801,981) 10 0 - 9,000,000 15,732,648 Soft Capital Projects Debt Service 11 Cabcars Access lease funding Local only Debt Service 60 Railcars Fed/State/Local Debt Service 60 Railcars Fed/State/Local Debt Service 60 Railcars Grant & Project Management Grant & Project Management Subtotal Capital Projects/Earmarks Federal Cap Program 8,425,000 Program 1,931,357 16,850,000 110,442 1,947,113 2,725,958 650,000 24,214,870 34,426,000 58,640,870 27,025,562 Funding 5337 SSTP/State 5337 5307 5307 - 0 0 0 0 119,830,432 Federal Amt 1,545,086 8,425,000 1,557,690 2,180,766 520,000 State Amt 309,017 5,729,000 311,538 436,153 6,785,708 8,946,940 15,732,648 21,222,020 35,450,562 FY17 Summary Proposed Budget GL Account FY16 Operating FY16 Capital FY17 Operating FY17 Capital Changes % Chg Revenue: Fare Revenue Miscellaneous Revenue Jurisdictional Subsidy Other Sources Federal/State Subsidy - Operating Federal/State Subsidy - Capital Operating/Capital Reserves Interest Income 38,890,000 165,000 12,991,760 330,000 28,979,851 Total Revenue 82,116,611 3,437,040 1,285,000 50,092,960 - 740,000 20,000 54,815,000 39,370,000 200,000 12,993,200 30,014,251 25,000 82,602,451 4,257,040 30,168,960 - 34,426,000 480,000 35,000 821,440 (1,615,000) 1,034,400 (19,924,000) (740,000) 5,000 1% 21% 5% -100% 4% -40% -100% 25% (19,903,160) Operating/Non-Operating Expenses: Insurance/Reserve/Mobilization Executive Management Chief of Staff/Public Affairs Marketing Office of Development Operations and Communications Budget and Finance Communication and Information Technology Engineering and Construction Facilities Maintenance Procurement Equipment Operations Safety, Security, and Emergency Preparedness PRTC NVTC Train Operations Amtrak Maintenance of Equipment Amtrak Access Fees Norfolk Southern Access Fees CSX Access Fees 5,090,091 1,095,000 459,000 402,200 1,568,500 2,047,250 3,116,000 1,627,000 718,800 4,316,900 459,000 11,176,500 830,500 104,000 80,000 15,060,000 4,640,000 5,871,000 6,390,000 3,340,000 6,960,000 Total Operating/Non-Operating Expenses 75,351,741 CIP Expenditures Debt Service/Allowance for Doubtful Accts 6,764,870 Total CIP and Other Expenditures 6,764,870 54,815,000 82,116,611 54,815,000 Grand Total Expenses Difference by Fund 5,516,462 1,134,500 539,500 423,200 971,150 1,992,500 3,496,500 2,266,000 885,100 4,686,650 479,000 11,603,500 1,096,500 104,000 80,000 15,505,000 4,975,000 6,035,000 6,340,000 3,480,000 7,030,000 - 78,639,562 54,815,000 - 34,426,000 (20,389,000) 0 6,764,870 34,426,000 (20,389,000) 85,404,432 34,426,000 (17,101,179) 6,764,870 - - Total Difference - 11 426,371 39,500 80,500 21,000 (597,350) (54,750) 380,500 639,000 166,300 369,750 20,000 427,000 266,000 445,000 335,000 164,000 (50,000) 140,000 70,000 3,287,821 (2,801,981) (2,801,981) (2,801,981) (2,801,981) 8% 4% 18% 5% -38% -3% 12% 39% 23% 9% 4% 4% 32% 0% 0% 3% 7% 3% -1% 4% 1% Agenda Item 9-A Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: New Spending Authority Report On May 15, 2015, the VRE Operations Board approved increasing the Chief Executive Officer’s spending authority from $50,000 to $100,000. It was resolved that any purchase of greater than $50,000 would be communicated to the Board as an information item. No procurements, contracts or purchases greater than $50,000 were made on the CEO’s sole authority during the months of June or July. In August, two purchase orders and one Independent Contractor Agreement were issued within the CEO’s new spending authority. They were as follows: On August 11, 2015, a purchase order was issued to Walco Electric Company in the amount of $100,000. This is a blanket purchase order that will allow mechanics to send traction motors to the vendor for repair and return services as needed. On August 3, 2015 VRE issued a Request for Quotes for seven 55 inch weatherproof LCD video monitors for the Spotsylvania Station. Seven quotes were received and on August 13, 2015, VRE issued a purchase order to SDF Professional Computers, Inc. of Greenville, NC in the amount of $50,393. On August 25, 2015, VRE executed an Independent Contractor Agreement amendment with Thomas Frawley increasing the amount from $43,200 to $97,200. Mr. Frawley is a railroad shop and yard specialist working on behalf of VRE to develop plans for expanding midday and overnight train storage facilities and to facilitate associated coordination with Amtrak. 2 Agenda Item 9-B Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: 2015 Customer Service Survey Results VRE conducted its annual customer service survey on board all northbound VRE and Amtrak cross-honor trains on the morning of May 6, 2015. The survey gives riders an opportunity to evaluate VRE operations and system performance. We received 5,831 completed surveys, which is approximately 61% of the riders that morning. There are year to year improvements in more than half of the rated categories. Train Crew performance was rated higher in nearly every category this year with an overall performance rating of 94%, up from last year’s record high of 92%. Only nine of the categories were rated lower than last year and most of those had only a one point drop. We also recognize there are areas where with opportunities to improve. These include: Quality of Website (New website to launch this fall), and Timeliness and Quality of Train Talks. Riders were asked what was most important to them. The top two responses remained: 1. On Time Performance (OTP) – 20.6% of respondents 2. Cost – 20.4% These were followed by: 3. Frequency of Service – 14.2% 4. Lack of Seats - 10.6% 5. Wifi – 10.4% 79.6% of respondents told us that our service was the same as or has improved over the past year, while only 2.4% said service level has declined. The other 18% had no comment. The overall rating for our service has remained flat for three years at 88%. We are very pleased with the positive scores we receive from our passengers and maintain our commitment to continuous improvement. Service enhancements such as the new website, VRE Mobile, the Spotsylvania Station, and the new Fredericksburg Line train are examples of our commitment to constant improvement of the service and passenger experience. Future planned improvements include projects like Automatic Passenger Counters, Parking Counters, and improved platform informational displays. The survey results are illustrated in the attached summary and full results are available at www.vre.org as downloadable Microsoft Word or PDF files. 2 2015 VRE Customer Service Survey Results Customer Service: 1 Responsiveness of VRE Staff 2 Friendliness of VRE Staff 2011 85% 83% 2012 88% 89% 2013 89% 88% 2014 90% 89% 2015 90% 90% VRE Follow-Up to Delays or Problems 50% Lost and Found 68% Usefulness of Rail time 72% Timeliness of E-mail Responses 51% Quality of E-mail Responses 56% Timeliness of Social Media Responses Quality of Social Media Responses Quality of Information in RIDE Magazine Quality of Website 74% Timeliness of Website Information 67% Timeliness of Train Talk 65% Quality of Train Talk 69% Overall Communication with Passengers 67% Train Crew Members: 2011 1 Are Knowledgeable About VRE Operations 83% 2 Are Helpful 84% 3 Are Courteous 83% 4 Make Regular Station Announcements 75% 5 Make Timely Delay Announcements 68% 6 Check Tickets Regularly 78% 7 Present A Professional Appearance 91% 8 Overall Crew Performance 85% VRE Operations: 2011 1 Convenience of Schedules 59% 2 On-time Performance 62% 3 Cleanliness of Trains 89% 4 Cleanliness of Stations 83% 5 Communication between VRE Staff & Riders 71% 6 Automated Telephone System 59% 7 Reliability of Ticket Vending Machines 51% 8 Ease of Buying a Ticket 70% 9 Ease of Using SmartBenefits 61% 10 Station Parking Availability 56% 11 Public Address System On Train 52% 12 Public Address System On Platform 45% 13 Timeliness of Platform Information 40% 14 Personal Security at Station & On Train 63% 15 Safety of Train Equipment 79% 16 Station Signage 67% 17 Lighting at Morning Station 79% 18 Lighting at Evening Station 79% 19 Traffic Circulation 49% 20 Level of Fare for Quality and Value of Service 63% 21 Overall Service Quality 78% *Percentages represent ratings of "excellent" or "good" 61% 70% 77% 58% 65% 65% 69% 80% 62% 67% 68% 68% 79% 64% 68% 75% 69% 65% 67% 72% 2012 90% 90% 89% 82% 76% 78% 93% 90% 2012 59% 85% 91% 84% 77% 67% 58% 75% 63% 57% 58% 51% 50% 68% 84% 71% 82% 82% 53% 61% 84% 75% 70% 68% 70% 77% 2013 92% 90% 89% 84% 78% 81% 93% 90% 2013 62% 89% 93% 88% 81% 72% 58% 79% 70% 66% 64% 58% 58% 75% 87% 76% 85% 85% 58% 67% 88% 74% 70% 71% 72% 76% 2014 93% 92% 91% 85% 81% 86% 94% 92% 2014 60% 84% 93% 87% 82% 73% 56% 77% 71% 65% 64% 62% 61% 76% 88% 77% 86% 86% 57% 64% 88% 69% 68% 78% 63% 67% 65% 69% 65% 72% 69% 66% 69% 75% 2015 93% 93% 92% 86% 82% 86% 95% 94% 2015 61% 84% 94% 88% 83% 74% 64% 80% 75% 68% 65% 62% 60% 78% 90% 78% 87% 86% 58% 65% 88% 3 4 5 6 7 8 9 10 11 12 13 14 15 Agenda Item 9-C Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Financial Plan Discussion VRE staff and our consultants, the PFM Group, have been working on the development of a long term strategic planning model since February 2015. At the July 17, 2015 Operations Board meeting, the PFM Group provided a presentation on the operating and capital costs associated with the implementation of System Plan 2040 and a range of other system alternatives. Because of time constraints, the presentation was not completed and the Board did not have the planned discussion. At the Operations Board meeting on September 18, 2015, PFM and VRE staff will provide a summary of the information prepared for the July Board meeting. The purpose of the discussion will be to develop a consensus regarding the future service profile for the system and the desired next steps. The key conclusions from the financial forecasting effort are summarized below: Regardless of the service profile: o Operating expenses will escalate and additional revenue will be needed for VRE to be financially balanced over the long term. o A significant level of capital investment is required that cannot be handled with currently identified capital funding sources. o NVTA funding has created an imbalance among the VRE jurisdictions in the ability to identify funding sources for VRE related capital needs. Raising fares to close the financial gap is not a viable solution on its own. Higher ridership associated with enhanced service levels could defray some of the future operating and capital costs. VRE needs additional dedicated revenue beyond the sources which exist today, even to maintain the status quo. The following additional materials are provided: VRE Financial Plan Analysis o Appendix A – charts showing the average additional operating revenue needed for each scenario and the total additional capital revenue needed for each scenario o Appendix B - charts showing the additional average annual revenue needed to meet both operating and capital needs and to create a financially balanced plan o Appendix C - an updated version of the presentation prepared for the July 17, 2015 Operations Board meeting, which includes the underlying assumptions for service level, ridership, operating expense and capital expenditures imbedded in each scenario 2 VRE Financial Plan Analysis September 18, 2015 VRE and PFM have been working on the development of a long term strategic financial planning model since February 2015. The primary objective of this effort was to provide a financial forecast (revenue, operating expense and capital expense) to match varying operational and service profiles that VRE might pursue in its efforts toward implementing its System Plan 2040. Five scenarios were developed for evaluation. The purpose of this report is to summarize the forecasted financial results and primary conclusions that have come from evaluating each of these scenarios. Scenario Descriptions and Key Findings Based upon discussion with the Operations Board at their May 15, 2015 meeting and discussions with VRE executive, finance, planning and operating staff, five scenarios were developed, as described on the following pages. The underlying assumptions for service level, ridership, operating expense and capital expenditures imbedded in each scenario are detailed in the three attachments to this memo. Attachments A and B are a series of bar charts, and Attachment C is an updated copy of the presentation offered to the Operations Board at the July 17, 2015 meeting pertaining to this topic. Since the time of the presentation, additional data has been incorporated in the model. None of these enhancements substantially alter the outcomes and conclusions in this memo or previously. Since the presentation on July 17, 2015, VRE staff have made estimates of potential discretionary funding that could reduce the unfunded capital expenditures. These estimates were of various types and include: 1) funding from discretionary sources such as NVTA and CMAQ, based on historical experience; 2) DRPT funding of the 3rd track project; and 3) receipt of major capital investment grants from FTA without which certain large-scale projects could not be implemented (Long Bridge and Gainesville-Haymarket extension). Baseline of Financially Constrained Scenario: The Baseline Scenario is a financially constrained scenario that demonstrates what operations would look like with no additional resources beyond 3% fare and subsidy increases in alternating years. The scenario starts with a forecasted amount of constrained revenue and then illustrates the operational impacts of reducing operating expenses and service to match the constrained revenue. Given the operational nature of this scenario, it was developed outside the model. Operationally, this scenario results in the unwinding of VRE’s service, trains being taken out of service and raises concern regarding VRE’s financial obligations to meet the federal interest in its equipment. Key Findings for Baseline Financially Constrained Scenario: This scenario requires a repeating pattern of service reductions to stay within the available revenue. Service reductions would cause overcrowding, eventually leading to fewer riders using VRE. The scenario showed VRE ceasing operation by 2033 under this alternative, even with the 3% subsidy and fare increase every other year. Ridership Equal Scenario: This scenario keeps VRE service and ridership levels as they are currently. Local subsidy escalates at 3% every other year, yet operating costs still exceed operating revenue. Financial balance is achieved by raising fares to the level necessary to eliminate any gap between revenue and expense. Key Findings for Ridership Equal Scenario: This scenario achieves fiscal balance for operations primarily through higher fares (fares increase to over $20 in FY40 (in current year dollars)). Such fare increases would likely change VRE ridership’s profile. This scenario could result in deferred boarding and shifting subsidy burden to outer jurisdictions. Although operating revenue and operating expense are balanced, this scenario has future capital requirements of $2.6B, approximately $770M of which is funded, $1.4B is assumed to be available from other parties, and $500M remains unfunded. The unfunded projects are primarily related to match contributions for the Long Bridge and system projects such as the replacement of rolling stock. VRE would continue to serve around 19,000 daily riders in this scenario. Natural Growth Scenario: This scenario reflects VRE continuing to serve our base market and the “natural” growth in the region that is expected, based on Metropolitan Washington Council of Governments cooperative forecasts of regional growth in population and employment. This is achieved with longer trains, longer platforms, more parking and expanded rail yards. The Natural Growth scenario assumes fares and the local subsidy grow at 3% in alternating years. Key Findings for Natural Growth Scenario: Average additional annual operating revenue would be needed ($5.2M in the near term, defined as FY2016-FY2030, to $15.5M in the longer term, FY2031 to FY2040) primarily for contracted train operations and access fees. The future capital requirements for this scenario would be $3.2B, primarily for track and signal, station and parking, and rolling stock investments. Of this $3.2B, approximately $800M is funded, $1.5B is assumed to be available from other parties, and $870M remains unfunded. It is important to note that $2.6B of this capital requirement represents core capital projects that would be required regardless of the scenario chosen. Even though the number of trains remains at 32 peak-oriented trips per day, ridership levels would increase to over 30,000 riders per day in the out years because of the increased capacity. Modified Service Expansion Scenario: This scenario builds off the Natural Growth scenario and reflects some of the System Plan 2040 service recommendations such as adding peak trains (eventually doubling the number of daily trains to 64) and the GainesvilleHaymarket extension. Even assuming that fares and the local subsidy grow at 3% every other year, this scenario forecasts a need for additional operating revenue to achieve financial balance. Key Findings for Modified Service Expansion Scenario: Average additional annual revenue would be needed ($5.4M in the near term to $20M in longer term) primarily for contracted train operations and access fees. The future capital requirements would be $4B, primarily for track and signal, station and parking, and rolling stock investments. Of this $4B, approximately $820M is funded, $2B is assumed to be available from other parties, and $1.3B remains unfunded. The increased capacity with more frequent trains and lengthened span of service, including more frequent midday service and reverse peak service, along with the Gainesville-Haymarket extension would result in approximately 45,000 daily riders. System Plan 2040: This scenario forecasts the financial outcomes expected with the full implementation of VRE’s System Plan 2040. Assuming that fares and the local subsidy grows at 3% every other year, this scenario forecasts a need for additional revenue to achieve financial balance. Key Finding for System Plan 2040 Scenario: Average additional annual revenue needed would be similar to the previous scenario ($4.2M in the near term to $16.5M in longer term) primarily for contracted train operations and access fees. This scenario needs slightly less additional operating revenue compared to the Modified Service Expansion scenario because the higher ridership generates more fare revenue. The future capital requirements would also be similar (to the Modified Service Expansion scenario) at $4.1B, primarily for track and signal, station and parking, and rolling stock investments. Of this $4.1B, approximately $830M is funded, $2B is assumed to be available from other parties, and $1.3B remains unfunded. The increased capacity with the additional trains and lengthened span of service, including midday service would result in approximately 52,000 daily riders. To help with the comparison among scenarios, tables accompany this memo that show the additional operating and capital funds needed by scenario and the estimated daily ridership associated with each scenario. A table is also included that provides an estimate of the additional revenue needed on an annual basis in order to meet a combination of the unfunded operating and net, unfunded capital needs during the period reviewed. Conclusions Without intending to minimize the level of detailed analysis underpinning each scenario, we offer the following key conclusions and takeaways from the review of each scenario, individually and as a group: A. Under any service profile, forecast growth in VRE’s operational expenses is driven primarily by VRE’s contractual agreements with its operator and the obligation to pay access fees to host railroads. Taken together, these categories of cost were budgeted at $31.5 million in VRE’s FY2016 budget, nearly 40% of its total operating expenses. Whether VRE pursues an expansion of its service profile or continues existing service levels, operating expenses will escalate. Even with a multi-year plan for regular, modest fare increases and regular local subsidy increases (such as 3% every other year), additional revenue will be needed for VRE to be financially balanced over the long term. B. Regardless of scenario, VRE has a core level of capital investment that is significant. While each scenario has a differing level of capital investment, all scenarios have a common universe of needed capital investment totaling $2.6 billion that must be met over the period from FY2016 to FY2040. This capital need is driven by the VRE-DRPT-CSX MOU to complete a third main track between Washington, D.C. and Fredericksburg (including expansion of the Long Bridge over the Potomac River) and the need to maintain, renew and replace existing rolling stock over the next 20+ years. VRE is able to fund approximately $2.2B of the $2.6 billion, on average, between the various scenarios, using estimates of both federal formula funds and the funds provided by other parties, including the funds committed by DRPT for the 3rd track project. However, the core amount of capital expenditures cannot be fully defrayed with existing sources of funds alone. Moreover, there is a significant imbalance between the capital funds available for projects within the NVTA region and those outside the NVTA region. This imbalance constrains the ability to implement needed capital improvements in non-NVTA jurisdictions and limits the funds available to the system as a whole. C. Raising fares to close the financial gap is not a viable solution on its own. Ridership Equal assumes that fares are raised to close the financial gap, resulting in an average fare of $20.56 incurred in FY40 (in 2016 dollars, vs. the current average fare of $7.90) and a reduction in ridership due to expectations regarding the elasticity of demand. The other scenarios are based on every other year fare increases of 3%; however, to close the annual operating financial gaps in the Modified Service Expansion and System Plan 2040 scenarios using fare increases alone, average fares would need to be raised to $15.04 and $13.81, respectively. While these levels of fare increases eliminates financial deficits for operations, it also drives VRE’s fare box recovery ratio to 68% and would tend to skew the ridership away from those who do not have transit benefits or are otherwise particularly sensitive to fare levels. Moreover, VRE has not consistently implemented multiple fare increases over a short period of time as contemplated by the financially balanced versions of these two scenarios; in practice, a significant rate rising regime could result in lower ridership than what the model’s demand elasticity assumption contemplates. D. Higher ridership due to enhanced service levels could defray future operating & capital costs. As noted above in A and B, VRE faces escalating costs even under the status quo. The financial forecasts for enhanced service levels in the Modified Service Expansion and System Plan 2040 scenarios illustrate that VRE could realize certain operating economies of scale and generate additional revenue from new riders, despite the higher capital expenditures needed to implement these scenarios. E. VRE needs additional revenue beyond the sources which exist today, even if it is to maintain the status quo. Each of VRE’s existing sources of revenue has its limitations. State and federal sources of funds are outside of VRE’s direct control and subject to a wide range of influencing factors. Local subsidies are limited by individual jurisdictions’ ability to pay, and their need to balance their local budgets to meet many competing priorities. Lastly, fares are driven by market factors, and demand is elastic. A reliable and predictable revenue stream is needed to meet a forecast of known escalating costs tied to contractual obligations with VRE’s operator and the railroads. A new revenue stream is also needed to fund a core amount of capital expenditures necessary to maintain, renew and replace VRE’s equipment to assure a state of good repair. A reliable and predictable revenue stream for both operating and capital (equipment-related) expenses would permit VRE to be financially sustainable over the long term. Next Steps These scenarios portray different operating profiles that VRE may decide to pursue and the attendant financial forecasts. The next step in the process is to develop a consensus regarding the future service profile for the system and develop a multi-year financial plan which is financially balanced reflecting that vision. A key part of developing a balanced financial plan will entail the identification and evaluation of potential new revenue streams beyond those that VRE currently employs today. Appendix A The charts below show the average additional operating revenue needed for each scenario, and the breakdown of total capital expenditures required to support the buildout of each scenario. Average Annual Operating Revenue Needed $16,000 60,000 $14,000 52,240 $12,000 50,000 40,000 31,138 $8,000 $6,000 $4,000 30,000 $14,679 $12,797 18,822 $12,557 $11,238 $9,347 20,000 $9,116 10,000 $2,000 N/A $2,523 $- Ridership Equal Natural Growth Assuming 3% EOY Subsidy Growth --FY16-40 Modified Service Expansion Assuming 0% Subsidy Growth--FY16-40 $4,000 (millions) $506 31,138 30,000 $2,000 $1,490 18,822 40,000 $1,266 $871 $2,500 50,000 $1,303 44,947 $3,000 $500 60,000 52,240 $3,500 $1,000 Ridership 2040 Total Capital Expenditures (FY16-FY40) $4,500 $1,500 System Plan 2040 $1,945 $1,947 $1,356 20,000 10,000 $767 $806 $823 $828 Ridership Equal Natural Growth Modified Service Expansion System Plan 2040 $- - Unfunded Potentially Funded Funded Ridership 2040 (Riders) (000s) $10,000 (Riders) 44,947 Appendix B The charts below show the average annual additional operating revenue and capital expenditure funding needed for each scenario in order to create a financially balanced plan. Total Average Operating Revenue and Capital Expenditure Funding Needed 70,000 60,000 52,240 60,000 40,000 40,000 31,138 61,874 30,000 18,822 10,000 61,234 30,000 (Riders) (millions) 50,000 20,000 50,000 44,947 20,000 44,175 10,000 20,253 - Ridership Equal Natural Growth Modified Service Expansion System Plan 2040 Average Annual Additional Operating Revenue and Capital Expenditures Needed Ridership 2040 Average Operating Revenue and Capital Expenditure Funding Needed 70,000 60,000 52,240 60,000 44,947 50,000 40,000 40,000 31,138 9,347 30,000 30,000 20,000 10,000 52,118 50,636 18,822 20,253 20,000 34,828 10,000 - Ridership Equal Natural Growth Modified Service Expansion System Plan 2040 Average Annual Additional Operating Revenue Needed Average Annual Additional Capital Expenditures Needed Ridership 2040 (Riders) (millions) 50,000 9,116 11,238 Agenda Item 9-D Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Draft 2016 Legislative Agenda The VRE Operations Board is asked to provide comment on the draft 2016 VRE Legislative Agenda. The Operations Board will be asked to take action in October recommending a Legislative Agenda to the Commissions. Background: Annually, VRE prepares a Legislative Agenda to communicate VRE Legislative priorities in coordination with the Commissions and local jurisdictional staff. Advocacy positions related to specific federal and state legislation are presented. VRE 2016 Legislative Issues Federal Legislative Issues: Issue 1: Congressional Approval of an extension to the deadline for Positive Train Control (PTC) Implementation Continue working with the Virginia Congressional delegation and other members of Congress to extend the PTC deadline. The Rail Safety Improvement Act of 2008 requires the implementation of interoperable positive train control systems for passenger trains and trains carrying hazardous materials by December 31, 2015. VRE, as well as most commuter rail agencies and Class I railroads, are not able to comply with the year-end deadline and need to request Congress extend the PTC implementation deadline to allow time to achieve full implementation of PTC. Unless Congress acts to extend the December 31, 2015 deadline, VRE will likely be forced to cease service. Issue 2: Commuter Benefits Equity Advocate for legislation to make commuter benefits permanently equal to parking benefits in the Internal Revenue Code. On July 21, 2015 the Senate Finance Committee passed a tax extenders bill that proposed to increase the commuter benefit from $130 to $250/month, retroactive to January 1, 2015, extending through December 2016. The Senate bill was not assigned a bill number before they left for recess. U.S. Representative King (D-NY) introduced H.R. 990 that would permanently extend the benefit at $235/month with an annual inflation adjustment. Representative Holmes-Norton (D-DC) introduced H.R. 1046 a $250/month plus inflation and permanent parity bill. While VRE is supportive of both bills, H.R. 990 is revenue positive over ten years and may have a greater chance of success in the House as H.R. 1046 affects the deficit. Issue 3: Reauthorization of a Long-term Federal Transportation and Infrastructure Authorization Bill MAP-21, the current authorization law, expires October 29, 2015. Support long-term, dedicated funding mechanisms that ensure the solvency and supplement the Highway Trust Fund and its Mass Transit Account. Support robust funding levels for Capital Investment Grants (New Starts & Core Capacity) that may assist VRE in funding major capital expansion projects such as third tracking on the Fredericksburg Line, extension of service to Gainesville – Haymarket, and construction of a new or expanded Long Bridge over the Potomac River from Virginia into Washington, D.C. 2 Issue 4: Commuter Rail Liability Insurance Limit Work with the Virginia Congressional delegation and other members of Congress to oppose the increase to the liability cap. The U.S. Senate passed its version of a six year authorization bill which includes language increasing the rail liability award cap from $200 million to $295 million and index it to inflation. The cost to VRE to increase its liability insurance from $250 million (the current amount of insurance coverage VRE is contractually obligated to purchase) to $295 million is estimated at $225,000-$250,000 annually. Beyond the increased operations costs of this proposed legislation, VRE host railroads and peer agencies oppose the increased cap as it raises the potential for ever larger and continuous costs and liability requirements for the industry. Issue 5: Definition of the Northeast Corridor (NEC) The existing legal definition of the NEC includes the District of Columbia as the southern end of the corridor (49 U.S.C. 24102(5)), but operationally has not included tracks south of CP Avenue where Washington Terminal Company (WTC) territory begins. VRE currently contracts to run on WTC tracks and does not go north of CP Avenue. The Senate passed H.R. 22 on July 30, 2015 with language that appears to extend the NEC to encompass the WTC territory. VRE is concerned that extending the NEC to encompass the WTC territory may expose VRE to increased costs and complicate our ability to use the Surface Transportation Board (STB) to intercede on issues regarding access to Washington Union Station. (The STB does not have jurisdiction over Amtrak but does over the WTC). Staff proposes to work with the Virginia Congressional delegation and other members of Congress to analyze the effects of this language and pursue options that resolve VRE concerns. State Legislative Issues: Issue 1: Protective Floor for the Regional 2.1% Motor Fuels Tax VRE will work with its parent commissions on the creation of a “protective floor” for the regional 2.1% motor fuels tax. The existing regional 2.1% motor fuels tax generated less revenue than expected due to the drop in fuel prices. 3 We support a “protective floor” similar to what the General Assembly provided for the statewide fuels sales tax as part of HB 2313. The VRE member jurisdictions where the 2.1% tax is levied have seen a drop in the tax yield of 25% in the past year. Enacting a “protective floor” for the regional gas tax will provide an equitable solution for dropping fuel prices and put the regional motor fuels tax in the same posture as the statewide motor fuels tax. Issue 2: Explore, Identify and Secure Additional VRE Capital and Operating Funding As VRE implements the 2040 System Plan, it is developing an accompanying Financial Plan that identifies capital and operating requirements needed to implement the plan. One of the key findings in the Financial Plan is the clear need for increased funding, even without the proposed expansion of service. The local jurisdiction members of VRE are financially constrained in their ability to fund existing VRE operations and capital needs and will experience even greater challenges in securing funding for operational and capital costs identified in the System Plan. VRE needs to explore, identify and secure a long term, dependable funding source for both existing and future operations and capital costs. Options for increased funding will be pursued to fund future operating scenarios. Issue 3: State Law related to Architectural and Engineering Term Contracting Transportation District Commissions, such as NVTC and PRTC, are limited in their ability to contract for Architectural and Engineering (A&E) services for multiple construction projects (e.g. General Engineering Contracts) to $500,000 in any one year period. Since all VRE contracts are on behalf of and in the name of our parent Commissions, this limitation affects the ability to obtain these services for VRE. Staff recommends pursuing an amendment to State law to include Transportation District Commissions in existing exceptions to limits on contracting for A&E services for multiple construction projects so that the sum of all projects performed in a oneyear contract term can increase from $500,000 to up to $6 million. The suggested change to §2.2-4303.1.B.2 is insertion of the bolded language: o 2. Any locality or any authority, sanitation district, metropolitan planning organization, TRANSPORTATION DISTRICT COMMISSION, or planning district commission with a population in excess of 80,000, or any city within Planning District 8, the sum of all projects performed in a one-year contract term shall not exceed $6 million and those awarded for any airport as defined in § 5.1-1 and aviation transportation projects, the sum of all such projects shall not exceed $1.5 million. 4 Agenda Item 9-E Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Website Redesign Update The redesigned VRE website will launch this fall. Staff will provide a presentation at the September Operations Board meeting on the new website. VRE tasked Pulsar Advertising (VREs marketing and communications firm) and its subcontractor, The Redmon Group, with the following objectives for this effort: Provide a creative, intuitive and user-friendly experience for VRE passengers across varying devices (desktop, mobile, tablet) with a responsive design and create the website with a mobile-first strategy with auto-detection capabilities for smartphones, tablets and geo-location services Provide easy and efficient access to the most requested service information and create effective, compelling communications for breaking news, real-time alerts and important information Simplify way-finding through new visual elements and maps Integrate with social media Utilize a content management system that will reduce staff time required to update and maintain the website and reduce operations staff time by providing self-service tools for customers and information seekers Design to be accessible for people with physical, sensory or cognitive disabilities Compatible with major browsers (Internet Explorer, Firefox, Opera, Chrome and Safari) with a load time of less than two seconds Integrate a multi-language translator powered by Google Translate to translate pages 2 Agenda Item 9-F Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Gainesville – Haymarket Update An update on the progress of project development activities for the Gainesville Haymarket Extension will be provided to the VRE Operations Board. Current activities include: Gainesville Haymarket Extension Planning and Environmental Services (AECOM contract) House Bill (HB) 2 Project Application Agenda Item 9-G Information Item To: Chairman Cook and the VRE Operations Board From: Doug Allen Date: September 18, 2015 Re: Management Audit Recommendations Update At the January 16, 2015 meeting, the Operations Board accepted the Management Audit. Included in the Management Audit Report were recommended improvements to VRE’s organizational structure and practices, VRE’s functions and processes, and VRE Operations Board oversight. Attached are the short-term (less than 12 months) actions recommended in the report and their current disposition. Since the July Operations Board meeting, the following action has occurred: Recommendation: Develop annual meeting schedule of the VRE Coordination Committee (VCC)/Chief Administrative Officers’ (CAO) Task Force, with meetings in both Woodbridge and Alexandria to facilitate access by all member jurisdictions. Action: A schedule of VCC/CAO Task Force meetings to be held at PRTC in Woodbridge has been developed: September 15, 2015 – 9am to 11:30am (VCC and CAO Task Force) December 15, 2015 – 9am to 11:30am (VCC and CAO Task Force) March 15, 2016 – 9am to 10:30am (VCC only – no CAO Task Force Scheduled) June 14, 2016 – 9am to 11:30am (VCC and CAO Task Force) The remainder of the meetings will be at VRE’s offices in Alexandria. VRE MANAGEMENT AUDIT RECOMMENDATIONS Short Term (less than 12 months) Recommendation Description VRE Lead Progress Update Target Date/ Complete Organizational Alignment with Strategic Develop a strategic business plan and financial plan to implement the Plan 2040 System Plan and enhance other business processes, including performance measures and a multiyear financial plan. J. Swartz Work on the financial plan has begun (Board update at March meeting). A consultant Task Order Request to support staff in development of the business plan has been forwarded to the Management Audit consultant team. Business Plan: TBD Financial Plan: Capacity/Staffing to Support Strategic Goals D. Boxer Hired additional Finance position and three warehouse positions. COMPLETE D. Allen First meeting was held on Monday, June 15th. COMPLETE VRE Structure and Practices Relationship Between Executive Directors and CEO Oversight of VRE by Commisions VRE Functions and Processes Purchasing Cards Procurement Protocals Implement VRE staff changes as proposed in VRE management’s FY 2016 budget (including transfer of three employees from the rail maintenance contractor to VRE) and implement a review of staffing needs as part of the annual budgeting process. Develop a schedule for regular roundtable discussions between the Executive Directors, the VRE CEO, and chairs of each Commission and the VRE Operations Board (or designee) to coordinate issues jointly concerning VRE and the two Commissions. Develop and deliver an informational presentation to each Commission on members’ roles and responsibilities with respect to VRE in their capacity as Commissioners. Evaluate advantages and disadvantages of replacing its current credit cards with purchasing cards. S. MacIsaac D. Boxer Procurement staff analyzing advantages/disadvantages; writing position paper. October New templates are under development October Job Descriptions Update procurement templates to reflect new technologies and expand use of blanket purchase orders. Develop Job Descriptions/Classifications for New Staff Positions A. Gotthardt Finalized for recruitment of new positions COMPLETE Training Develop an annual schedule and guidelines for routine staff training. A. Gotthardt Under development December CEO Evaluation Legal Councel Review Periods Document the process for CEO evaluation. Document timeframes required for items commonly reviewed by legal counsel to establish reasonable expectations for all parties of how long reviews should take. Identify assistant attorneys able to directly field inquiries from VRE staff. A. Gotthardt Under development J. Swartz Reviewing information TBD October S. MacIsaac On-going On-going Examine staffing levels and opportunities to quarter legal staff at VRE. S. MacIsaac Reviewing information September Legal Councel Review by Assistant Attorneys Legal Staffing Levels G. Hill Under development Establish Legal/VRE staff progress meetings Establish quarterly progress meetings between legal counsel and the VRE management team. J. Swartz Agreed on one monthly in-person meeting in addition COMPLETE to weekly conference calls. Grant Reimbursement Support PRTC in exploring options to streamline federal grant reimbursements by better utilizing IT systems such as additional features of the Microsoft SharePoint program to post a draw calendar (including staff absences) so timing can be better coordinated between VRE and PRTC. As PRTC completes the implementation of a new financial management system and addresses the noted deficiencies, provide support to PRTC as needed. Provide a copy of PRTC’s periodic progress reports to VRE Operations Board members as an information item, so that they are kept abreast of progress towards resolution of this issue. D. Boxer On-going On-going D. Boxer On-going On-going Audits Work with external reviewers (to the extent that VRE is able) to optimize the efficiency of file sharing and other protocols of the review. Continue to examine additional steps to productively support external reviews, including use of technology and additional staffing. D. Boxer On-going On-going Technology Management Hire a senior IT manager-level position, as recommended in VRE management’s FY 2016 budget, and consider the appropriate reporting relationship for this hire. Perform a detailed assessment of VRE technology needs to understand where technology gaps exist. C. Henry Sr. IT Manager position hired COMPLETE J. Duque Under development TBD S. MacIsaac Presented in April COMPLETE S. MacIsaac Board Item on May's agenda COMPLETE D. Boxer/S. MacIsaac Developed by Procurement with guidance from Legal COMPLETE PRTC Financial System Progress Technology Assessment Operations Board Oversight Board Involvement in Procrement Provide annual briefing on procurement process. Process Procurement Authorization Thresholds Review and adopt recommended procurement authorization and approval thresholds Board Packets Develop revised template for board agenda items regarding procurements to provide more detail on the fiscal impacts of purchases and the rationale for the selected procurement approach. Board Calendar Add an information item to each month’s Operations Board agenda that summarizes major issues anticipated for the next month’s meeting, as well as any known major items planned for discussion at subsequent meetings over the next 12 months. CEO Report Augment the existing CEO Report by including a dashboard performance summary, executive letter from the CEO, and additional performance measures for each department tied to the organization’s strategic business goals. L. Lamb A CY2015 Major Board Actions calendar and a Recuring Annual Board Actions calendar have been developed and presented to the Operations Board at the February meeting. B. Jungwirth Under development COMPLETE September Board Orientation andTraining Implement a full-day orientation program for new Operations Board members. Develop comprehensive board orientation and training materials. Develop a mailing list to electronically disseminate notice of agendas and meeting packets and other documents to local agency staff, other interested stakeholders, and members of the public. J. Swartz Board Meeting Public Access Public Access to VRE Operations Board Meetings: Investigate video or audio recording meetings and posting video/audio online for access by the public. J. Duque VRE IT staff are working with Commission staff to October investigate new technologies that would give VRE this capability. CAO Task Force/VCC Meetings Develop annual meeting schedule, with meetings in both Woodbridge and Alexandria to facilitate access by all member jurisdictions. R.Dalton Schedule complete Dissemination of Board Information to Stakeholders Board Item on June's Agenda L. Lamb COMPLETE COMPLETE COMPLETE