Project Report Project Management May 10, 2016, 12:08 PM Phase Column Descriptions: • Scoping/Estimating - Project manager has been assigned and development of a cost estimate for the project is underway. • Awaiting Funding - Cost estimate has been provided to the customer. Funding has not been received. • Procurement - Funding is in place. Contracting process is underway. • Design - Contract for design services has been awarded. Design is in progress. • Construction - Contract for construction services has been awarded. Construction is underway. • On Hold • Complete - Work has been completed and accepted by the customer. • Closeout - Financial closeout is underway. SP/CI PROJ FUND NO 5230 SOURCE FUND TITLE 882000 121030-945850803 S. COLLEGE ROAD RENOVATION INTO COLLABORATIVE WORKSPACE 803 S. COLLEGE ROAD, SUITE A INSTALL CARD READER, SECURITY CAMERA, AND SMOKE DETECTOR ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 6/15/16 $100K SPR RECEIVED 2/19/16. FUNDING REQUESTED 3/4/16. FUNDING RECEIVED 3/9/16. PICKARD 5230 PROJ MGMT DESIGN T.B.D. $6.8K SPR RECEIVED 1/19/16. FUNDING FOR CAMERA AND DOOR CARD ACCESS REQUESTED 2/4/16. PICKARD 5199 SPONSOR AWAITING FUNDING 5205 882000 162540-945866ALDERMAN HALL - FLOORING AND TRIM REPLACEMENT IN ROOMS 101, 101A, 101B 4/30/16 $6.6K SPR RECEIVED 1/25/16. FUNDING REQUESTED 2/25/16. FUNDING RECEIVED 3/7/16. PICKARD 5205 PROJ MGMT CONSTRUCTION 5283 882000 152360-945864ALDERMAN HALL - INSTALL CHARGING STATION FOR GEM CAR 5/31/16 $2.8K SPR RECEIVED 4/8/16. FUNDING REQUESTED 4/25/16. FUNDING RECEIVED 4/29/16. WORK AWARDED. SOUTHERLAND 5283 PROJ MGMT PROCUREMENT 5201 882000 172000-945850ALDERMAN HALL - RECONFIGURE SPACES IN SUITES 201 AND 203 5/30/16 $50.1K SPR RECEIVED 1/20/16. FUNDING REQUESTED 2/5/16. FUNDING RECEIVED 2/22/16. WORK IN PROGRESS. MCCARLEY PROJ MGMT CONSTRUCTION 1 5201 Project Report SP/CI PROJ FUND NO 5158 SOURCE FUND TITLE 882000 177700-945850ALDERMAN HALL - REPLACE FLOORING AND TRIM IN SUITES 104, 108, 202, 204 ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 3/31/16 $55K SPR RECEIVED 11/2/15. FUNDING REQUESTED 1/28/16. FUNDING RECEIVED 2/9/16. PICKARD 5158 PROJ MGMT CONSTRUCTION ALLIED HEALTH - PLANNING & PROGRAMMING T.B.D. T.B.D. SPR RECEIVED 12/2/14. MORGAN 4951 ACSVCS SCOPE & ESTIMATING ALMKUIST-NIXON - CONSTRUCT PERMANENT WALL FOR ROOM 112 T.B.D. $9K SPR RECEIVED 10/26/15. FUNDING REQUESTED 11/17/15. BLUME 5153 SPONSOR AWAITING FUNDING AQUACULTURE RESEARCH LAB SURVEY UTILITIES IN PARKING AREA T.B.D. $2.4K SPR RECEIVED 3/24/15. MEETING WITH SPONSOR 4/13/15. FUNDING REQUESTED 4/29/15 MCCARLEY 5017 SPONSOR AWAITING FUNDING 5186 882000 121981-945850BEAR HALL - RENOVATE ROOM 110 6/10/16 $18K SPR RECEIVED 12/8/15. FUNDING REQUESTED WILLIAMS 2/9/16. FUNDING RECEIVED 3/22/16. PO HAS BEEN ISSUED; WORK TO BEGIN WEEK OF MAY 9, 2016 (30 DAY JOB). 5186 PROJ MGMT PROCUREMENT 5197 882000 121981-945850BEAR HALL - RENOVATIONS TO SUITE 109 6/10/16 $31K SPR RECEIVED 1/14/16. FUNDING REQUESTED 2/9/16. FUNDING RECEIVED 3/22/16. PO ISSUED; WORK TO BEGIN WEEK OF MAY 9, 2016 (30 DAY JOB). WILLIAMS 5197 PROJ MGMT PROCUREMENT T.B.D. $288K SPR RECEIVED 8/5/15. FUNDING REQUESTED 10/08/15. MCCARLEY 5087 SPONSOR AWAITING FUNDING 6/15/16 $150K SPR RECEIVED 12/15/14. DESIGNER INTERVIEWS CONDUCTED 1/15/15. DESIGNER HAS BEEN SELECTED. DESIGN IS UNDERWAY. AWAITING DESIGNER PROPOSAL. FUNDING REQUESTED 12/8/15. FUNDING RECEIVED 12/16/15. MORGAN 4959 ACSVCS DESIGN BOSEMAN FIELD: ESTIMATE FOR LOCKER ROOM BUILDING 4959 882000 319098-945966BROOKS FIELD - INDOOR PRACTICE FACILITY (DESIGN) 2 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE BROOKS FIELD - INSTALL FENCING UNDER BLEACHERS ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. T.B.D. SPR RECEIVED 6/11/15. MCCARLEY 5058 PROJ MGMT SCOPE & ESTIMATING 5200 882000 319052-945861BROOKS FIELD - INSTALL NEW GAME DAY HITTING FACILITY 6/10/16 $130K SPR RECEIVED 1/19/16. FUNDING REQUESTED 1/20/16. FUNDING RECEIVED 1/22/16. CONTRACTED AWARDED. ENGINEERING DRAWINGS AND PLANS RECEIVED 4/1/16. WORK SCHEDULED TO BEGIN THE WEEK OF APRIL 11. SLAB IS READY TO BE POURED. WILLIAMS 5200 PROJ MGMT CONSTRUCTION 5119 882000 319080-945966BROOKS FIELD - REPLACE WOODEN BLEACHERS 3/15/16 $75K SPR RECEIVED 9/24/15. INITIAL PROPOSALS ARE DUE 12/8/15. FUNDING REQUESTED 12/9/15. FUNDING RECEIVED 12/16/15. THE CONTRACT IS AWARDED AND MATERIAL HAS BEEN ORDERED. WORK IS COMPLETE. FINAL INVOICE PAID. PREPARING CLOSEOUT. WILLIAMS 5119 PROJ MGMT COMPLETE BURNEY CENTER - REMOVE WALLPAPER AND PAINT WOMEN'S RESTROOM T.B.D. T.B.D. SPR RECEIVED 12/17/15. MCCARLEY 5190 PROJ MGMT SCOPE & ESTIMATING BURNEY CENTER - REPAIR PARTITION WALL T.B.D. T.B.D. SPR RECEIVED 2/19/16. BLUME 5229 PROJ MGMT SCOPE & ESTIMATING 416290 416290-945864BURNEY CEP - CONTROLS UPGRADE T.B.D. $97.8K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14. MCCARLEY 4820 PROJ MGMT SCOPE & ESTIMATING 5179 882000 180730-945866BURNEY CEP - INSTALL ISOLATION VALVES AT BOILERS 1/15/16 $4.1K SPR RECEIVED 11/24/15. FUNDING REQUESTED 12/3/15. FUNDING RECEIVED 12/15/15. VALVES HAVE BEEN INSTALLED. AWAITING CONTROLS WORK TO BE COMPLETED. WORK IS COMPLETE. FINAL INVOICE HAS BEEN PAID. PREPARING FOR CLOSEOUT. CLOSEOUT IS UNDERWAY. WILLIAMS 5179 FAC ADMIN CLOSEOUT R&R 416250 416250-945868CAB - REPLACE CHILLER COMPRESSOR 6/30/15 $55K SPR GENERATED 4/10/13. R&R FUNDING ESTABLISHED 4/9/14. REPAIR OF COMPRESSOR MOTOR IS COMPLETE. ADDITIONAL WORK BEING CONSIDERED. MCCARLEY 4816 PROJ MGMT 3 CONSTRUCTION Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE CAB - REPLACE FLOOR COVERING ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. $26K SPR RECEIVED 5/27/14. FUNDING REQUESTED 7/17/14. SEIFERT 4860 SPONSOR AWAITING FUNDING SP14-014 883106 218019-945940CAHILL DRIVE - INSTALL CURB & GUTTER 9/30/15 $350K PROJECT HAS BEEN APPROVED BY THE BUILDINGS AND GROUNDS COMMITTEE AND THE DESIGN REVIEW COMMITTEE. FUNDING REQUEST FORWARDED TO PROJECT SPONSOR ON 4/24/13. FUNDING RECEIVED 7/30/13. PERMIT RECONCILIATION IS COMPLETE. CAHILL DRIVE WORK IS COMPLETE. SCOPE OF PROJECT EXPANDED TO INCLUDE LIGHTING IMPROVEMENTS ALONG WALTON DRIVE. BID OPENING CONDUCTED ON 2/26/15. PO FOR THE ADDITIONAL WORK HAS BEEN AWARDED. LIGHTING WORK IS 60% COMPLETE. MCCARLEY 4617 PROJ MGMT CONSTRUCTION 5068 882000 125260-945865CAMERON HALL - EQUIPMENT UPGRADE IN ROOM 241 3/15/16 $60.4K SPR RECEIVED 7/16/15. FUNDING REQUESTED 7/28/15. FUNDING RECEIVED 1/7/16. PROCUREMENT IN PROCESS. EQUIPMENT RECEIVED. MCCARLEY 5068 PROJ MGMT PROCUREMENT CAMERON HALL - INSTALL ONE HOUR RATED WALL IN ROOM 100 T.B.D. $51.6K SPR RECEIVED 3/2/16. FUNDING REQUESTED 4/8/16. MCCARLEY 5244 SPONSOR AWAITING FUNDING CAMERON HALL - RENOVATIONS TO LOUNGE 213A T.B.D. $60K SPR RECEIVED 10/8/15. FUNDING REQUESTED 1/29/16. BLUME 5125 SPONSOR AWAITING FUNDING 5/20/16 $960 SPR RECEIVED 3/23/16. FUNDING REQUESTED 4/8/16. FUNDING RECEIVED 4/21/16. PROJECT AWARDED 5/3/16. MCCARLEY 5259 PROJ MGMT PROCUREMENT T.B.D. $2K SPR RECEIVED 3/2/16. FUNDING REQUESTED 4/8/16. MCCARLEY 5245 SPONSOR AWAITING FUNDING 5259 882000 217770-945940CAMPUS COMMONS - INSTALL LEGACY WALK PAVERS PLACEHOLDERS CAMPUS COMMONS - REPAIR EROSION ALONG POND BANK 4 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE CAMPUS COMMONS - REPLACE WORN WOOD ON COMMONS BRIDGES T.B.D. $19.6K SPR RECEIVED 8/10/15. FUNDING REQUESTED 8/20/15. WILLIAMS 5089 SPONSOR AWAITING FUNDING CAMPUS WIDE - FIRE ALARM DIALER REPLACEMENTS T.B.D. $350K SPR RECEIVED 2/15/16. GUINN 5227 PROJ MGMT SCOPE & ESTIMATING 5204 882000 180180-945871CAMPUS WIDE - LANDSCAPING IMPROVEMENTS 3/31/16 $150K SPR RECEIVED 1/21/16. FUNDING REQUESTED 1/22/16. FUNDED IN PART ON 1/29/16. WORK IS IN PROGRESS. FUNDING UPGRADE RECEIVED 2/22/16 FOR FULL AMOUNT. WORK IN PROGRESS. FUNDING UPGRADE RECEIVED ON 4/5/16. PREPARING TO CLOSE. MCCARLEY 5204 PROJ MGMT CONSTRUCTION 4948 180180 180180-945860CAMPUS WIDE - PERFORMANCE CONTRACT # 2 - OVERSIGHT 6/30/16 $100K SPR GENERATED 12/1/14. FUNDS PROVIDED 12/1/14. SHARPE 4948 ACSVCS DESIGN 5215 418210 418210-945966CAMPUS WIDE - PERFORMANCE CONTRACT #2 - CONSTRUCTION PHASE 7/1/17 $6.3M SPR RECEIVED 2/2/16. FUNDING IS IN PLACE FOLLOWING CONTRACT EXECUTION IN DECEMBER. CONSTRUCTION IS UNDERWAY. SHARPE 5215 ACSVCS CONSTRUCTION T.B.D. $50K SPR RECEIVED 2/18/14. FUNDING REQUESTED 2/18/14. REVISITING CAMPUS APPROACH TO AUTOMATING METERS ON 10/8/15. REINMANN 4776 SPONSOR AWAITING FUNDING 413320 413320-945863CENTRAL ENERGY PLANT UPGRADE CONTROLS 6/30/15 $164.5K SPR GENERATED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13. MCCARLEY 4741 PROJ MGMT PROCUREMENT 416260 416260-945868CEP TO DOBO HALL INFRASTRUCTURE 6/30/15 $100K MCCARLEY 4817 PROJ MGMT SCOPE & ESTIMATING CAMPUS WIDE - REPAIR OR REPLACE UTILITY METERS R&R SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14. 5 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5044 882000 180187-923590CHANCELLORS WALK - LEVEL BRICK PAVERS 6/15/16 $100K SPR RECEIVED 5/20/15. FUNDING RECEIVED 3/9/16. FIRST SECTION EAST OF CLOCK TOWER COMPLETE. OBTAINING PROPOSALS FOR ADDITIONAL SECTIONS. MCCARLEY 5044 PROJ MGMT 5042 882000 172800-945850CIE - ADDITIONAL COUNTER WORK SPACES 7/31/15 $8.7K SPR RECEIVED 5/15/15. FUNDING REQUESTED 5/22/15. FUNDING RECEIVED 6/2/15. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. MCCARLEY 5042 FAC ADMIN CLOSEOUT CIE - EVALUATE INSTALLATION OF NEW FIRE ALARM T.B.D. T.B.D. SPR RECEIVED 11/9/15. PICKARD 5169 PROJ MGMT SCOPE & ESTIMATING CIE - EVALUATION AND UPGRADES TO HVAC SYSTEM T.B.D. $18.2K SPR RECEIVED 11/9/15. FUNDING REQUESTED 12/23/15. PICKARD 5170 SPONSOR AWAITING FUNDING 9/30/15 $8K SPR RECEIVED 10/28/14.FUNDING REQUESTED 12/4/14. FUNDING RECEIVED 7/8/15. WORK AWARDED. BIKE RACKS INSTALLED. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. MCCARLEY 4922 FAC ADMIN CLOSEOUT CIE - INSTALL PATIO T.B.D. $31.1K SPR RECEIVED 6/10/15. CONCEPT AND DRAWINGS ACCEPTED BY SPONSOR. WORKING ON APPROVALS. FUNDING REQUESTED 12/17/15. PICKARD 5057 SPONSOR AWAITING FUNDING CIE - INVESTIGATE AND/OR REPLACE LIGHTING T.B.D. T.B.D. SPR RECEIVED 7/27/15. PICKARD 5080 PROJ MGMT SCOPE & ESTIMATING 8/25/15 $60K SPR RECEIVED 1/21/15. FUNDING REQUESTED 2/3/15. FUNDING RECEIVED 4/23/15. DELAY DUE TO INCREASE IN SCOPE. PICKARD 4971 PROJ MGMT SCOPE & ESTIMATING 4922 882000 172800-945966CIE - INSTALL BIKE RACK AND OUTDOOR FURNITURE 882000 904664-945850CIE - PHASE 2 - MULTIMEDIA IMPROVEMENTS 6 CONSTRUCTION Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5275 882000 172800-945850CIE - RENOVATE BATHROOMS 6/20/16 $36K SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/13/16. FUNDING RECEIVED 4/20/16. PICKARD 5275 PROJ MGMT PROCUREMENT 5176 882000 121981-945850CIS - RENOVATE ROOM 2007 INTO RESEARCH LAB 6/15/16 $12K SPR RECEIVED 11/24/15. FUNDING REQUESTED 1/29/16. FUNDING RECEIVED 3/22/16. BLUME 5176 PROJ MGMT CONSTRUCTION 4887 882000 125601-945850CIS - RENOVATIONS TO RM 1020 6/15/16 $52.2K SPR RECEIVED 7/24/14. FUNDING REQUESTED 9/12/14. RESCOPING PROJECT FOR NEW FLOOR PLAN. NEW ESTIMATE TO FOLLOW. FUNDING REQUESTED 2/16/16. FUNDING RECEIVED 3/7/16. BLUME 4887 PROJ MGMT PROCUREMENT T.B.D. T.B.D. SPR RECEIVED 10/28/15. BLUME 5155 PROJ MGMT SCOPE & ESTIMATING $56.3K SPR RECEIVED 3/2/16. FUNDING REQUESTED 3/3/16. REVISED ESTIMATE LETTER SENT 3/14/16. FUNDING RECEIVED 4/1/16. PO ISSUED. WORK TO BEGIN SOON. GUINN 5234 PROJ MGMT PROCUREMENT T.B.D. T.B.D. SPR RECEIVED 4/20/16. MCCARLEY 5289 PROJ MGMT SCOPE & ESTIMATING 443751 443751-945868CMS - MARBIONC T.B.D. T.B.D. NOTICE TO PROCEED ISSUED 10/5/11. WORK IS COMPLETE. SEIFERT 3915 ACSVCS OPEN 882000 148610-945966CMS - MODIFY SEAWATER DISCHARGE PIPING 1/30/16 $6.2K SPR RECEIVED FROM INACTIVE FILES ON REINMANN 11/20/15. FUNDING REQUESTED 11/25/15. FUNDING RECEIVED 12/9/15. FUNDING IS FOR ENGINEERING ONLY. ENGINEERING IN PROGRESS AS OF 1/25/16. WORK COMPLETE 4/25/16. FUNDING UPGRADE RECEIVED 4/27/16. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. 4503 FAC ADMIN CLOSEOUT CIS - REPAIR PORTICO DOOR LEAKS 5234 882000 180187-945863CIS AND LEUTZE HALL: IAQ ISSUES: 6/15/16 CLEAN DUCTWORK AND INSTALL UV LIGHTS CMS - INSTALL PROPERTY LINE FENCE 4503 7 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE CMS MARBIONC - VENTILIATION AND LAB ACH OPTIMIZATION 5178 5106 882000 121981-945850CMSMG - CONSTRUCT WET LAB CMSMG - ERECT CELL TOWER. FUNDED BY AMERICAN TOWER COMPANY ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. T.B.D. SPR RECEIVED 7/23/15. WILLIAMS 5078 PROJ MGMT SCOPE & ESTIMATING 5/15/16 $35K SPR RECEIVED 11/24/15. FUNDING REQUESTED 1/7/16. SCOPE OF PROJECT WAS CHANGED AS REQUESTED AND A NEW ESTIMATE PROVIDED 2/3/16. PROJECT IS CURRENTLY FOR DESIGN ONLY. FUNDING RECEIVED 2/12/16. PICKARD 5178 PROJ MGMT DESIGN T.B.D. $0 SPR RECEIVED 9/11/15. PRE-CON ON 10/6 WITH CONSTRUCTION FOLLOWING. COMPLETION BY 1/31/16. PICKARD 5106 PROJ MGMT CONSTRUCTION SP14-028 883120 214802,573750-945966 CMSMG - EXPAND FLOATING DOCKS 2/28/15 $332.8K SPR RECEIVED 9/30/13. FUNDING REQUESTED 9/30/13. FUNDING RECEIVED 10/17/13. BID OPENING CONDUCTED ON 4/29/14. WORK IS UNDERWAY. FUNDING UPGRADE RECEIVED 8/22/14. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. MCCARLEY 4693 FAC ADMIN CLOSEOUT 5219 882000 180180-923590CMSMG - INSTALL PROTECTIVE SYSTEM AROUND REFLECTIVE POND 5/31/16 $5.8K SPR RECEIVED 2/11/16. FUNDING REQUESTED 3/16/16. FUNDING RECEIVED 4/8/16. WORK IS UNDERWAY. PICKARD 5219 PROJ MGMT CONSTRUCTION 5280 882000 121981-945866CMSMG - INSTALL STEEL SHEET TO 6/10/16 SUPPORT OVERHEAD CABINETS $3.6K SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/25/16. FUNDING ESTABLISHED 5/3/16. WORK AWARDED 5/3/16. SOUTHERLAND 5280 PROJ MGMT CONSTRUCTION T.B.D. SPR RECEIEVED 11/5/15. SHARPE 5165 SPONSOR AWAITING FUNDING $9.6K SPR RECEIVED 2/11/16. FUNDING REQUESTED 2/17/16. FUNDING RECEIVED 2/22/16. WORK IS COMPLETE. APPROVED INVOICE 4/6/16. CLOSEOUT IS UNDERWAY. WILLIAMS 5218 FAC ADMIN CLOSEOUT CMSMG - LABORATORY EXHAUST DAMPER REPLACEMENT 5218 T.B.D. 882000 180180-923590CMSMG - MAIN BUILDING: REPLACE 3/15/16 FAILING ON DEMAND WATER HEATERS 8 Project Report SP/CI PROJ FUND NO 5091 SOURCE FUND TITLE 882000 121981-945863CMSMG - REFURBISH ENVIRONMENTAL CHAMBERS ESTM'D CPLTN 5/15/16 PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE $107.6K SPR RECEIVED 8/13/15. FUNDING REQUESTED 9/24/15. REBID 9/24/15 WITH LOW BIDDER SELECTED. AWAITING FUNDING AND ALTERNATE SELECTIONS. FUNDING RECEIVED 2/12/16. AWAITING ENGINEERING DRAWINGS. AWAITING SUBMITTAL DATA FROM CONTRACTOR. WILLIAMS 5091 PROJ MGMT DESIGN CMSMG - RELOCATE NATURAL GAS T.B.D. METERS $69K PROJECT MADE ACTIVE AGAIN 4/14/16. WILL REBID PROJECT SO ESTIMATE MAY CHANGE. BLUME 4904 PROJ MGMT SCOPE & ESTIMATING CMSMG - REPAIR CRACK IN FLOOR OF ROOM 1348 T.B.D. $1.7K SPR RECEIVED 3/23/16. FUNDING REQUESTED 4/8/16. BLUME 5260 SPONSOR AWAITING FUNDING SPR RECEIVED 2/11/15. FUNDING REQUESTED 2/15/16. FUNDING RECEIVED 3/2/16. EAKINS 5221 PROJ MGMT PROCUREMENT 5121 PROJ MGMT PROCUREMENT 5221 882000 180180-953990CMSMG - SURVEYING, AERIAL PHOTOGRAPHY, AND PHOTOGRAMMETRIC MAPPING 6/1/16 $22K 5121 882000 319156-945850CMSMG MARBIONC - INSTALL 2 NEW FUME HOODS IN LAB 2018 7/15/16 $159.6K SPR RECEIVED 9/28/15. FUNDING REQUESTED 11/3/15. FUNDING RECEIVED 2/9/16. ENGINEERING DRAWINGS RECEIVED 4/1/16. BIDS RECEIVED 4/28/16. WILLIAMS T.B.D. $11K SPR RECEIVED 4/13/16. FUNDING REQUESTED 4/29/16. SOUTHERLAND 5286 SPONSOR AWAITING FUNDING COLLEGE ROAD SEAHAWK T.B.D. COUNTRY SIGN - PULL POWER AND INSTALL PHOTO CELLS AND NEW LIGHTS $25K SPR RECEIVED 4/1/16. FUNDING REQUESTED 4/28/16. GUINN 5270 SPONSOR AWAITING FUNDING CORNERSTONE HALL - REPLACE BATHROOM PARTITIONS $1.5K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. GUINN 5135 SPONSOR AWAITING FUNDING COLLEGE ROAD ENTRANCES CONCEPTUAL LANDSCAPING DESIGN FOR ENTRANCE WING WALLS T.B.D. 9 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE CORNERSTONE HALL - REPLACE COMMON SPACE FLOORING ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. T.B.D. SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. GUINN 5136 SPONSOR AWAITING FUNDING 5/15/16 $1K SPR RECEIVED 3/2/16. FUNDING REQUESTED 3/8/16. FUNDING RECEIVED 4/11/16. WORK IS UNDERWAY. PICKARD 5241 PROJ MGMT CONSTRUCTION $20.8K SPR RECEIVED 4/19/16. FUNDING REQUESTED 4/19/16. FUNDING RECEIVED 4/20/16. WORK IN PROGRESS. MCCARLEY 5288 PROJ MGMT CONSTRUCTION 5241 882000 180310-923590CROSS CITY TRAIL - TEXTURE WALKING SURFACE AND CUT DOWN RAILINGS 5288 882000 121981-945550CULTURAL ARTS BUILDING 6/20/16 BECKWITH RECITAL HALL LIGHTING CONTROLS REPLACEMENT CULTURAL ARTS BUILDING REPAIR WALL IN RESTROOM 2045A T.B.D. $2.5K SPR RECEIVED 3/3/16. FUNDING REQUESTED 4/8/16. MCCARLEY 5246 SPONSOR AWAITING FUNDING CULTURAL ARTS BUILDING - SEAL MECHANICAL ROOM FLOORS T.B.D. $44K SPR RECEIVED 1/20/15. FUNDING REQUESTED 3/2/15. BLUME 4869 SPONSOR AWAITING FUNDING 5238 882000 180187-923510DELOACH HALL - CONVERT HOT WATER SYSTEM TO PRIMARY/ SECONDARY LOOP 6/15/16 $24K SPR RECEIVED 3/2/16. FUNDING REQUESTED 3/3/16. FUNDING RECEIVED 4/1/16. WILLIAMS 5238 PROJ MGMT PROCUREMENT 5187 882000 121981-945850DELOACH HALL - RENOVATE ROOMS 210 AND 211 4/15/16 $47.3K SPR RECEIVED 12/8/15. FUNDING REQUESTED 1/21/16. FUNDING RECEIVED 2/12/16. PICKARD 5187 PROJ MGMT CONSTRUCTION 5168 882000 216370-945850DEPAOLO HALL - ADD NEW OFFICE IN SUITE 1033 1/31/16 $13.2K SPR RECEIVED 11/9/15. FUNDING REQUESTED 11/30/15. FUNDING RECEIVED 12/15/15. WORK IS COMPLETE AS OF 1/8/16. AWAITING FINAL INVOICE. INVOICE RECEIVED AND CLOSEOUT UNDERWAY. WILLIAMS 5168 FAC ADMIN CLOSEOUT 10 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5287 882000 162535-945850DEPAOLO HALL - BUILD PARTIAL AND DOOR IN ROOM 1008 5/31/16 $6.4K SPR RECEIVED 4/13/16. FUNDING REQUESTED 4/15/16. FUNDING RECEIVED 4/27/16. SOUTHERLAND 5287 PROJ MGMT PROCUREMENT 5208 882000 137301-945850DEPAOLO HALL - REPURPOSE SPACE IN SUITE 1092 6/10/16 $13.2K SPR RECEIVED 1/28/16. FUNDING REQUESTED 3/10/16. REVISED FUNDING REQUEST SUBMITTED 4/27/16. FUNDING RECEIVED 4/29/16. WORK IS UNDERWAY. PICKARD 5208 PROJ MGMT CONSTRUCTION T.B.D. $3.5K SPR RECEIVED 10/17/14. FUNDING REQUESTED 10/22/14. SEIFERT 4913 SPONSOR AWAITING FUNDING $18.8K SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/26/16. FUNDING RECEIVED 5/3/16. SOUTHERLAND 5279 PROJ MGMT PROCUREMENT DOBO HALL - INSTALL 4" DUCT 5279 R&R 882000 121981-945864DOBO HALL - INSTALL OUTLETS 6/10/16 AND DATA IN ROOMS 121D AND 245 DOBO HALL - INSTALL SNORKEL HOODS T.B.D. $17K SPR RECEIVED 4/30/14. FUNDING REQUESTED 7/29/14. SPONSORE INQUIED SEPTEMBER 2015. PROJECT MAY BE FUNDED IN THE NEAR FUTURE. MCCARLEY 4842 SPONSOR AWAITING FUNDING DOBO HALL - LAB EXHAUST DAMPER REPLACEMENT/ CONTROLS T.B.D. $100K SPR RECEIVED 3/31/16. FUNDING REQUESTED 3/31/16. MCCARLEY 5267 SPONSOR AWAITING FUNDING 413230 413230-945863DOBO HALL - REFRIGERANT MONITORING 6/30/15 $210K SPR GENERATED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13. MCCARLEY 4739 PROJ MGMT CONSTRUCTION 416230 416230-945868DOBO HALL - REFRIGERANT MONITORING 6/30/15 $60K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14. MCCARLEY 4814 PROJ MGMT SCOPE & ESTIMATING 11 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5156 882000 121981-945850DOBO HALL - RENOVATE CLASSROOMS 202 AND 205 1/15/16 $41.3K SPR RECEIVED 11/2/15. FUNDING REQUESTED 12/8/15. FUNDING RECEIVED 12/9/15. FURNITURE WORK STARTED 1/5/16. TO BE COMPLETED BY 1/9/16. WORK IS COMPLETE. PREPARING CLOSEOUT. WILLIAMS 5156 PROJ MGMT COMPLETE 5161 882000 121981-945850DOBO HALL - RENOVATE ROOMS 117 AND 119 INTO RESEARCH LABS 6/15/16 $49.5K SPR RECEIVED 11/2/15. FUNDING REQUESTED 4/6/16. FUNDING RECEIVED 4/13/16. GUINN 5161 PROJ MGMT PROCUREMENT R&R 416270 416270-945868DOBO HALL - REPLACE BOLIER T.B.D. $250K SPR GENERATED 4/10/14. R&R FUNDING MCCARLEY ESTABLISHED 4/9/14. DESIGN FEE PROPOSAL HAS BEEN REQUESTED. 4818 PROJ MGMT PROCUREMENT 5071 882000 152420-945850EDUCATION BUILDING - DIVIDE ROOM 346 INTO TWO OFFICES 9/25/15 $11.5K SPR RECEIVED 7/16/15. FUNDING REQUESTED 8/6/15. FUNDING RECEIVED 8/24/15. WORK IS COMPLETE. WAITING ON ROOM NUMBERS TO BE MADE. GUINN 5071 PROJ MGMT COMPLETE 5268 882000 180187-945866FACILITIES BUILDINGS - INSTALL CARD READERS AND SECURITY CAMERAS 6/15/16 $60K SPR RECEIVED 3/31/16. FUNDING REQUESTED 3/31/16. FUNDING RECEIVED 4/1/16. WORK AWARDED AND MATERIALS ORDERED. FUNDING REDUCED BY $20,000 ON 5/5/16. MCCARLEY 5268 PROJ MGMT PROCUREMENT 5214 882000 180180-945510FACILITIES EQUIPMENT REPLACEMENT 5/31/16 $158K SPR RECEIVED 1/29/16. FUNDING RECEIVED IN FULL ON 2/22/16. PROCUREMENT IN PROGRESS. FUNDING UPGRADE RECEIVED 4/5/16. TWO VANS AND PRINTER RECEIVED. MCCARLEY 5214 PROJ MGMT PROCUREMENT FISHER STUDENT CENTER MODIFY ADA DOORS 1007 T.B.D. $6K SPR RECEIVED 1/28/15. FUNDING REQUESTED 3/24/15. BLUME 4973 SPONSOR AWAITING FUNDING FISHER STUDENT CENTER MODIFY ADA DOORS IN ROOM 1006 T.B.D. $6.8K SPR RECEIVED 1/28/15. FUNDING REQUESTED 3/27/15. BLUME 4974 SPONSOR AWAITING FUNDING 12 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE FISHER STUDENT CENTER RECOMMISSIONING UPGRADES ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. T.B.D. SPR RECEIVED 10/13/15. AWAITING DECISIONS ON RECOMMENDATIONS FOR PROJECT. WILLIAMS 5146 PROJ MGMT SCOPE & ESTIMATING 4897 882000 644550-945850FISHER STUDENT CENTER RENOVATIONS TO SHARKY'S 3/1/16 $8K SPR RECEIVED 9/16/14. FUNDING REQUESTED 1/20/15. SPONSOR HAS INDICATED THEY WILL BE FUNDING PROJECT SOON. DESIGN FEE VERIFIED. FUNDING RECEIVED 11/24/15. CONTRACT FOR DESIGN AWARDED ON 12/1/15. DESIGN MEETING SCHEDULED 3/14/16. THIS PROJECT WILL BE COMPLETED DURING SUMMER 2016. MCCARLEY 4897 PROJ MGMT DESIGN 5292 882000 319157-923510FISHER STUDENT CENTER REPAIR DAMAGED GABLE 5/31/16 $3.8K SPR RECEIVED 4/29/16. FUNDING REQUESTED 5/2/16. FUNDING RECEIVED 5/3/16. MCCARLEY 5292 PROJ MGMT CONSTRUCTION FISHER STUDENT CENTER REPAIR LUMINA STEP LIGHTS T.B.D. T.B.D. SPR RECEIVED 7/16/15. WORK IN PROGRESS VIA ALTERNATE MEANS. GUINN 5069 PROJ MGMT SCOPE & ESTIMATING FISHER STUDENT CENTER REPLACE FIRST FLOOR FLOORING T.B.D. $475K SPR RECEIVED 8/18/15. MEETING WITH SPONSOR AND CONTRACTOR 9/2/15. DESIGN MEETING 11/17/15. NEXT MEETING SCHEDULED FOR 2/10/16. MET WITH SPONSOR 3/3/16. FUNDING REQUESTED 4/8/16. MCCARLEY 5092 SPONSOR AWAITING FUNDING 3/15/16 $22.1K SPR RECEIVED 10/13/15. FUNDING REQUESTED 11/20/15. FUNDING RECEIVED 1/7/16. MATERIAL HAS BEEN ORDERED. WORK BEGAN 3/2/16. WORK TO BE COMPLETE WEEK OF 4/11/16. WILLIAMS 5147 PROJ MGMT CONSTRUCTION FISHER UNIVERSITY UNION ENERGY CONSERVATION MEASURES IMPLEMENTATION T.B.D. $120K SPR RECEIVED 11/17/15. FUNDING REQUESTED 11/18/15. MCCARLEY 5175 SPONSOR AWAITING FUNDING FISHER UNIVERSITY UNION INVESTIGATE ADDING NEW FOOD VENUE (ARAMARK PROJECT) T.B.D. T.B.D. SPR RECEIVED 2/4/16. BLUME 5217 PROJ MGMT SCOPE & ESTIMATING 5147 882000 644550-945865FISHER STUDENT CENTER AND CAMPUS LIFE BUILDINGS - INSTALL CARD SWIPE ACCESS 13 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5203 882000 162550-945850FISHER UNIVERSITY UNION RENOVATE SUITE 2035 TO BUILD ADDITIONAL OFFICE 5/30/16 $28.2K SPR RECEIVED 1/21/16. FUNDING REQUESTED 2/3/16. FUNDING RECEIVED 2/22/16. WORK IS UNDERWAY. BLUME 5203 PROJ MGMT CONSTRUCTION 5202 882000 162550-945850FISHER UNIVERSITY UNION RENOVATIONS TO LOBBY IN SUITE 2035 6/15/16 $8.4K SPR RECEIVED 1/21/16. FUNDING REQUESTED 2/3/16. FUNDING RECEIVED 2/22/16. WORK IS UNDERWAY. BLUME 5202 PROJ MGMT CONSTRUCTION T.B.D. T.B.D. SPR RECEIVED 3/23/16. BLUME 5262 PROJ MGMT SCOPE & ESTIMATING 2/15/16 $4.3K SPR RECEIVED 8/31/15. FUNDING REQUESTED 12/17/15. FUNDING RECEIVED 1/7/2016. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. GUINN 5104 FAC ADMIN CLOSEOUT T.B.D. $10.3K SPR RECEIVED 5/19/15. TOMMY GUINN MET WITH SPONSOR. FUNDING REQUESTED 6/8/15. CART NOT ACCEPTED BY THE STATE. PROJECT ON HOLD. GUINN 5043 PROJ MGMT ON HOLD 5/31/16 $41.6K SPR RECEIVED 9/15/15. REPLACED TWO FAILED WILLIAMS UNITS UNDER EMERGENCY PO THROUGH PHYSICAL PLANT. BID DOCUMENTS SPECIFICATIONS ARE COMPLETE. FUNDING REQUESTED FOR OTHER UNITS 3/17/16. FUNDING RECEIVED 4/1/16. BID SETUP MAY 3,2016. FUNDING REDUCED BY $10,000 ON 5/5/16. 5109 PROJ MGMT PROCUREMENT GALLOWAY HALL - PRESSURE WASHING AND TREATING EXTERIOR T.B.D. $60K SPR RECEIVED 7/31/15. FUNDING REQUESTED 10/15/15. GUINN 5082 SPONSOR AWAITING FUNDING GALLOWAY HALL - REPLACE INTERIOR HALL FLOORING T.B.D. T.B.D. SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. DELAYED UNTIL NEXT SPRING. WILLIAMS 5138 PROJ MGMT ON HOLD FISHER UNIVERSITY UNION AND STUDENT CENTER - CONVERSION OF MEETING ROOMS INTO SMART ROOMS 5104 5043 5109 5138 882000 644550-945966FISHER UNIVERSITY UNION/ STUDENT CENTER - INSTALL BIKE RACKS FRIDAY ANNEX - INSTALL GOLF CART CHARGING STATION 882000 180187-923510FRIDAY ANNEX - REPLACE ALL HVAC PACKAGE UNITS 14 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE GRAHAM/HEWLETT CONNECTOR RE-COVER FRONT DESK AND INSTALL NEW TOP 5123 PROJ BDGT STATUS PROJ MGR PM NO PHASE 5140 SPONSOR AWAITING FUNDING $5.6K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. POSSIBLY DELAYED UNTIL NEXT SPRING. GRAHAM/HEWLETT HALLS T.B.D. REPLACE FIRE DETECTOR DEVICES T.B.D. SPR RECEIVED 10/23/15. MET WITH FIRE ALARM MCCARLEY TECHNICIAN ON 12/22/15. PREPARING SUBMITTAL FOR SCO APPROVAL. 5151 PROJ MGMT SCOPE & ESTIMATING GREENE TRACK: ESTIMATE FOR PORTAL/GATEWAY BUILDING T.B.D. $1.1M SPR RECEIVED 8/5/15. FUNDING REQUESTED 10/08/15. MCCARLEY 5086 SPONSOR AWAITING FUNDING GROUNDS - CONSTRUCT NEW SURFACE PARKING LOT T.B.D. T.B.D. SPR RECEIVED 10/8/15. MCCARLEY 5141 PROJ MGMT SCOPE & ESTIMATING 4/15/16 $2.5K SPR RECEIVED 9/23/15. FUNDING REQUESTED 9/23/15. FUNDING RECEIVED 10/8/15. BENCHES INSTALLED. WORK IS COMPLETE. BLUME 5123 PROJ MGMT COMPLETE T.B.D. $22.6K SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/20/16. MCCARLEY 5278 SPONSOR AWAITING FUNDING 6/30/16 $215K SPR GENERATED 3/2/15. FUNDING ESTABLISHED 3/3/15. DESIGN IS COMPLETE. PRE-BID HELD 3/31/15. BIDS DUE 4/14/15. CONTRACT AWARDED 4/16/15. CONSTRUCTION STARTED 5/18/15. SEWER COMPLETE 7/1/15. ADDED WORK BUILDING 4D SITE PAD AND UTILITIES COMPLETE 7/17/15. ADDED WORK BUILDING 7C SITE STARTED 7/30/15. THOMSON CORDER CONTRACTED. SEIFERT 4998 ACSVCS CONSTRUCTION 882000 212139-945966GROUNDS - INSTALL CONCRETE BENCHES AT SUNDIAL 180540 18015A, GROUNDS - OUTDOOR 180540-945982ENHANCEMENT GRAVITY SEWER 15 WILLIAMS ACTION OFFICE T.B.D. GROUNDS - INSTALL DIRECT POWER SUPPLY TO RAIN COLLECTION SITE 4998 ESTM'D CPLTN Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN CI13-007 443783 443783-945860GROUNDS - OUTDOOR ENHANCEMENT MASTER PLAN 4919 882000 212139-945966GROUNDS - SUNDIAL INSTALLATION 4/30/15 5277 5222 PROJ MGR PM NO ACTION OFFICE PHASE DESIGN CONTRACT HAS BEEN AWARDED. WORK IS COMPLETE ON BASEBALL PRACTICE FIELD. BID FAILED FOR FIELDS. RECONFIGURING DESIGN PACKAGES FOR RE-BID. BUILDING 4D AWARDED TO BARBOZA 8/4/15. 4D WORK STARTED 8/24/15. LIGHTING CONSTRUCTION COMPLETE. 7C CONTRACT AWARDED 12/21/15. LIGHTING FINAL INSPECTION 3/2/16, TRAINING 3/8/16. SEIFERT 4743 ACSVCS $11K SPR RECEIVED 10/24/14. FUNDING REQUESTED 12/9/14. FUNDING RECEIVED 12/18/14. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. BLUME 4919 FAC ADMIN CLOSEOUT $0 SPR RECEIVED 4/7/16. PROJECT IS FUNDED BY VERIZON BUT REQUIRES STATE INSPECTIONS AND THAT IS BEING OVERSEEN BY STEVE PICKARD. PICKARD 5277 PROJ MGMT CONSTRUCTION HANOVER HALL - REPAIR AND T.B.D. LOWER MOTORS FOR BASKETBALL GOAL WINCHES $23.9K SPR RECEIVED 2/4/16. FUNDING REQUESTED 4/7/16. GUINN 5216 SPONSOR AWAITING FUNDING HENWOOD - MOVE CONTAINERS AND REMOVE TIN BUILDING $5.8K SPR RECEIVED 4/13/16. MET WITH CONTRACTORS ON 4/27/16. AWAITING ESTIMATE. FUNDING REQUESTED 5/4/16. SOUTHERLAND 5284 SPONSOR AWAITING FUNDING $4.2K SPR RECEIVED 2/11/16. FUNDING REQUESTED 2/24/16. FUNDING RECEIVED 3/7/16. WORK IN PROGRESS. MCCARLEY 5222 PROJ MGMT CONSTRUCTION T.B.D. SPR RECEIVED 3/21/16. MCCARLEY 5251 PROJ MGMT SCOPE & ESTIMATING $2.2K SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/12/16. FUNDING RECEIVED 4/26/16. WORK AWARDED. SCHEDULING IN PROGRESS. SOUTHERLAND 5282 PROJ MGMT PROCUREMENT T.B.D. T.B.D. 882000 152530-945861HOGGARD HALL - INSTALL WINDOW 4/15/16 BETWEEN ROOMS 177 AND 178 HOGGARD HALL - RENOVATION OF ROOMS 123-137 5282 STATUS $7.5M GROUNDS - VERIZON WIRELESS MONOPOLE EQUIPMENT UPGRADE 6/30/16 PROJ BDGT T.B.D. 882000 171500-945865HOGGARD HALL - REPLACE 5/31/16 SECURITY CAMERAS IN ITS SPACES 16 CONSTRUCTION Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE HONORS HOUSE - REPLACE COMMON SPACE FLOORING T.B.D. T.B.D. SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. BLUME 5133 SPONSOR AWAITING FUNDING HONORS HOUSE- REPLACE BATHROOM PARTITIONS T.B.D. $1.5K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. BLUME 5132 SPONSOR AWAITING FUNDING HOUSEKEEPING BUILDING INSULATE WALLS AND CEILINGS T.B.D. $2K SPR RECEIVED 3/2/16. FUNDING REQUESTED 3/10/16. PICKARD 5240 SPONSOR AWAITING FUNDING WILLIAMS 5084 FAC ADMIN CLOSEOUT 5084 882000 318500,318505,318510,318515-923510 HOUSING MULTIPLE BUILDINGS CONDENSATE CLEANING 1/15/16 $28.6K SPR RECEIVED 7/31/15. FUNDING REQUESTED 8/4/15. FUNDING RECEIVED 9/23/15. WORK COMPLETED ON 12/18/15. PREPARING CLOSEOUT. CLOSEOUT IS UNDERWAY. 5115 882000 318500-945850HOUSING MULTIPLE BUILDINGS HOUSING R&R PHASE I, FY16 6/15/17 $70K SPR RECEIVED 9/18/15. SCOPE MEETINGS ARE REINMANN CONTINUING, FIRST COST ESTIMATE IS $7.5M. CM@R PRE-BID SCHEDULED FOR 11/10/15. DESIGN FUNDING IDENTIFIED 12/8/15. CM@R RECOMMENDATION WILL BE PRESENTED TO BOT IN MID-JANUARY. BALFOUR BEATTY SELECTED AS CM@R. 5115 PLANTADMINDESIGN T.B.D. $38K SPR RECEIVED 2/27/15. FUNDING REQUESTED 5/6/15. SEIFERT 4980 SPONSOR AWAITING FUNDING 8/15/16 $200K SPR RECEIVED 8/19/15. FUNDING REQUESTED SEIFERT 8/19/15. FUNDING RECEIVED 8/26/15. CONSTRUCTION UNDERWAY. FUNDING UPGRADE REQUESTED 1/22/16. FUNDING UPGRADE RECEIVED 1/25/16. DRAWINGS SENT TO SCO, CONSTRUCTION DELAYED, PENDING REVIEW. 5093 ACSVCS CONSTRUCTION T.B.D. $1.5K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. 5129 SPONSOR AWAITING FUNDING HOUSING MULTIPLE BUILDINGS INSTALL BIKE RACKS 5093 882000 318300-945866HUB BUILDING - INFRASTRUCTURE - PHASE I INNOVATION HOUSE - REPLACE BATHROOM PARTITIONS 17 BLUME Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE INNOVATION HOUSE - REPLACE COMMON SPACE FLOORING ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. T.B.D. SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. BLUME 5130 SPONSOR AWAITING FUNDING 5150 882000 275100-945864JAMES HALL - INSTALL LENEL CARD READERS 2/29/16 $4.6K SPR RECEIVED 10/23/15. FUNDING REQUESTED 1/7/16. FUNDING RECEIVED 1/25/16. WORK AWARDED 3/2/16. MCCARLEY 5150 PROJ MGMT PROCUREMENT 5224 882000 152982-945866JAMES HALL - RECARPET SECOND FLOOR (GRADUATE SCHOOL) 6/15/16 $13.4K SPR RECEIVED 2/11/16. FUNDING REQUESTED 4/7/16. FUNDING RECEIVED 4/11/16. WORK TO BE COMPLETED WEEKEND OF MAY 13 OR 20. GUINN 5224 PROJ MGMT PROCUREMENT T.B.D. T.B.D. SPR RECEIVED 3/30/16. MET WITH CONTRACTORS; AWAITING PROPOSALS. MCCARLEY 5265 PROJ MGMT SCOPE & ESTIMATING 4/30/16 $10K SPR RECEIVED 2/11/16. FUNDING REQUESTED 3/10/16. FUNDING RECEIVED 3/22/16. BLUME 5223 PROJ MGMT PROCUREMENT 5/30/16 $700 SPR RECEIVED 3/23/16. FUNDING REQUESTED BLUME 4/8/16. PROJECT DIRECTLY FUNDED BY PHYSICAL PLANT. WORK TO BE SCHEDULED. 5261 PROJ MGMT CONSTRUCTION KENAN AUDITORIUM - PAINT AUDITORIUM CEILING 5223 5261 882000 152033-945850KENAN AUDITORIUM - REMODEL SPACE INTO STORAGE BUILDING KENAN AUDITORIUM - REPAIR HOLE IN CEILING IN ROOM 212 5127 882000 180187-923510KENAN AUDITORIUM - REPLACE HVAC DIFFUSERS 5/31/16 $12.5K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/29/15. FUNDING RECEIVED 4/1/16. PROCUREMENT IN PROCESS. GRILLS TO BE DELIVERED 5/17/16. WORK WILL START UPON DELIVERY. WILLIAMS 5127 PROJ MGMT PROCUREMENT 5004 882000 121750-945866KENAN AUDITORIUM: INSTALL WASHER/DRYER 5/30/16 $14K SPR RECEIVED 3/9/15. FUNDING REQUESTED 10/6/15. FUNDING RECEIVED 12/15/15. BLUME 5004 PROJ MGMT CONSTRUCTION 18 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE KENAN HOUSE - COURTYARD REFURBISHMENT ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE T.B.D. T.B.D. SPR RECEIVED 12/23/15. PICKARD 5194 PROJ MGMT PHASE SCOPE & ESTIMATING 5062 882000 218010-945850KENAN HOUSE - FY2016 INTERIOR/ EXTERIOR REPAIRS AND REFURBISHMENTS 7/31/15 $110K SPR GENERATED 6/24/15. FUNDING REQUESTED 6/24/15. FUNDING RECEIVED 6/25/15. WORK IS COMPLETE. PREPARING CLOSEOUT. CLOSEOUT IS UNDERWAY. MCCARLEY 5062 FAC ADMIN CLOSEOUT 4914 882000 680100-945850KENAN HOUSE - REPAIRS & IMPROVEMENTS 6/30/15 $15K SPR GENERATED 10/17/14. FUNDING RECEIVED 10/21/14.WORK IS UNDERWAY. WORK IS COMPLETE. MCCARLEY 4914 PROJ MGMT COMPLETE KENAN HOUSE - REPLACE HEATING T.B.D. HOT WATER BOILER T.B.D. SPR RECEIVED 9/15/15. PHYSICAL PLANT HAS COMPLETED SOME INITIAL WORK PRIOR TO PROJECT FUNDING. CURRENTLY EXAMINING POSSIBLE CHANGES IN VENTING FIRST. WILLIAMS 5108 PROJ MGMT SCOPE & ESTIMATING KENAN HOUSE - SECURITY FENCE MODIFICATIONS T.B.D. T.B.D. SPR RECEIVED 12/23/15. PICKARD 5193 PROJ MGMT SCOPE & ESTIMATING SP13-107 883066 680100-945850KENAN HOUSE - SOLARIUM REFURBISHMENT STUDY 8/1/14 $125K SPR RECEIVED 1/11/13. FUNDING RECEIVED 4/26/13. PREBID CONDUCTED 11/19/13. PREWORK CONFERENCE CONDUCTED 1/7/14. WORK IS UNDERWAY. ADDITIONAL FUNDING RECEIVED 7/14/14. SCOPE OF WORK HAS BEEN INCREASED. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. BLUME 4523 FAC ADMIN CLOSEOUT 5209 882000 121981-945850KING HALL - RENOVATE AUDITORIUM (ROOM 101) 6/10/16 $26K SPR RECEIVED 1/28/16. FUNDING FOR INITIAL TESTING REQUESTED 2/4/16. FUNDING FOR TESTING RECEIVED 2/12/16. TESTING IS COMPLETE. FUNDING UPGRADE FOR CONSTRUCTION REQUESTED 3/10/16. FUNDING RECEIVED. WORK TO BEGIN 5/9/16. WILLIAMS 5209 PROJ MGMT CONSTRUCTION T.B.D. T.B.D. SPR RECEIVED 9/15/15. WILLIAMS 5110 PROJ MGMT SCOPE & ESTIMATING KING HALL - REPLACE ALL AIR HANDLERS 19 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE LANDSCAPING NURSERY - INSTALL CONCRETE BARRIERS FOR LOOSE MATERIAL STORAGE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. $4.2K SPR RECEIVED 3/28/16. FUNDING REQUESTED 4/27/16. MCCARLEY 5264 SPONSOR AWAITING FUNDING 6/10/16 $14.8K SPR RECEIVED 7/23/14. FUNDING REQUESTED 7/28/14. UPDATED FUNDING REQUEST SENT 4/13/16. FUNDING RECEIVED 4/19/16. WORK AWARDED; MATERIALS ORDERED. MCCARLEY 4885 PROJ MGMT PROCUREMENT 4885 882000 173160-945866LEUTZE HALL - INSTALL ADA PUSH BUTTON 5154 882000 180180-923590LOT EE - STRUCTURAL REPAIRS TO 6/10/16 BRIDGE BETWEEN LOT EE AND SUITES $7.7K SPR RECEIVED 10/28/15. FUNDING REQUESTED 11/11/15. FUNDING RECEIVED 4/7/16. WORK TO BEGIN 5/9/16. WILLIAMS 5154 PROJ MGMT CONSTRUCTION 5237 882000 319248-945950LOT FF - CONSTRUCT ADDITIONAL PARKING 6/15/16 $38K SPR RECEIVED 3/2/16. FUNDING REQUESTED 3/4/16. FUNDING RECEIVED 3/14/16. DESIGN PROPOSAL REQUESTED 4/6/16. BLUME 5237 PROJ MGMT DESIGN 5162 882000 121030,152030-945850 MCNEILL HALL - AV UPGRADE IN ROOM 3084 5/30/16 $170K SPR RECEIVED 11/2/15. FUNDING REQUESTED BLUME 12/15/15. FUNDING RECEIVED 12/18/15. PROPOSALS RECEIVED 2/2/16. EVALUATING PROPOSALS. FUNDING UPGRADE REQUESTED 2/8/16. FUNDING UPGRADE RECEIVED 2/8/16 WITH NEW FOAP. CHANGED IN BANNER TO ENCUMBRANCE PM5162A. WORK IS UNDERWAY. 5162 PROJ MGMT CONSTRUCTION 5220 882000 121030-945866MCNEILL HALL - INSTALL CARD ACCESS READERS 5/21/16 $5K SPR RECEIVED 2/11/16. FUNDING REQUESTED 3/11/16. FUNDING RECEIVED 3/16/16. EQUIPMENT ORDERED. FUNDING REDUCED 5/3/16. INSTALLATION CONTRACT AWARDED. MCCARLEY 5220 PROJ MGMT PROCUREMENT 5063 882000 1AP100-945850MCNEILL HALL - MULTI-OFFICE RENOVATIONS IN MCNEILL AND TRASK 6/15/16 $480K SPR RECEIVED 6/29/15. FUNDING REQUESTED 6/30/15. FUNDING RECEIVED 7/22/15. WORK IS UNDERWAY. FUNDING UPGRADE REQUESTED 8/13/15. FUNDING UPGRADE RECEIVED 9/28/15. PUNCHLIST WALK-THROUGH HELD ON 12/1/15. FUNDING UPGRADE REQUESTED 12/15/15. FUNDING UPGRADE RECEIVED 12/17/15. DESIGN FOR PHASE II IS UNDERWAY. FUNDING UPGRADE ($275K) REQUESTED 3/11/16. FUNDING UPGRADE RECEIVED 3/11/16. BLUME 5063 PROJ MGMT CONSTRUCTION 20 Project Report SP/CI PROJ FUND NO 5247 SOURCE FUND TITLE 882000 127000-945850MCNEILL HALL - REDESIGN CRITICAL CARE LAB AND ADD OFFICE SPACE MCNEILL HALL - REPAIR COLUMNS ON PORCHES ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 6/15/16 $60K SPR RECEIVED 3/7/16. FUNDING REQUESTED 3/10/16. FUNDING RECEIVED 3/14/16. BLUME 5247 PROJ MGMT PROCUREMENT T.B.D. $8K SPR RECEIVED 3/23/16. FUNDING REQUESTED 4/7/16. BLUME 5263 SPONSOR AWAITING FUNDING MCCARLEY 4819 FAC ADMIN CLOSEOUT R&R 416280 416280-945868MORTON HALL - REPLACE COOLING TOWER 6/30/15 $95K SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. 5149 882000 180187-923510MORTON HALL - REPLACE DOOR HARDWARE 5/30/16 $46K SPR RECEIVED 10/23/15. FUNDING REQUESTED GUINN 11/3/15. FUNDING RECEIVED 3/9/16. PO HAS BEEN ISSUED. WALKTHROUGH WEEK OF MAY 9. 5149 PROJ MGMT PROCUREMENT R&R 413220 413220-945863MORTON HALL - UPGRADE CHILLER 6/30/15 CONTROLS $80K SPR GENERATED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13. MCCARLEY 4738 PROJ MGMT PROCUREMENT MULTIPLE ATHLETIC FACILITIES REPLACE SOUND SYSTEMS T.B.D. $88.7K SPR RECEIVED 8/26/15. FUNDING REQUESTED 1/15/16. BLUME 5099 SPONSOR AWAITING FUNDING MULTIPLE BUILDINGS - BIKE RACK REPLACEMENT PROJECT T.B.D. $21.7K SPR RECEIVED 11/4/15. FUNDING REQUESTED 5/2/16. GUINN 5164 SPONSOR AWAITING FUNDING MULTIPLE BUILDINGS - DESIGN ELECTRICAL UPGRADE FOR MAIN SWITCH GEAR AT BELK/GRAHAM/ HEWLETT T.B.D. T.B.D. SPR RECEIVED 5/4/16. MCCARLEY 5293 PROJ MGMT SCOPE & ESTIMATING 21 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE MULTIPLE BUILDINGS - DESIGN HVAC EMERGENCY BACKUP PLAN FOR BELK/GRAHAM/HEWLETT ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. T.B.D. SPR RECEIVED 5/4/16. MCCARLEY 5294 PROJ MGMT SCOPE & ESTIMATING 5211 882000 271603-945865MULTIPLE BUILDINGS - INSTALL ADDITIONAL WIRELESS ACCESS POINTS 6/6/16 $66K SPR RECEIVED 1/28/16. FUNDING REQUESTED 1/28/16. FUNDING RECEIVED 2/4/16. WORK HAS BEEN AWARDED AND IS IN PROGRESS. MCCARLEY 5211 PROJ MGMT CONSTRUCTION 5120 882000 319080-945866MULTIPLE BUILDINGS - INSTALL LENEL KEYPAD SYSTEM 2/29/16 $1.7K SPR RECEIVED 9/24/15. ACCESS MANAGEMENT IS MCCARLEY SCOPING PROJECT. FUNDING REQUESTED 1/7/16. FUNDING RECEIVED 1/22/16. INSTALLED 1 LOCK AT SWIM TEAM LOCKER ROOM. 5120 PROJ MGMT CONSTRUCTION 5290 882000 180186-945866MULTIPLE BUILDINGS - LED LIGHTING UPGRADES (1292) 5/31/16 $27.3K SPR RECEIVED 4/29/16. FUNDING ESTABLISHED 4/29/16. SHARPE 5290 ACSVCS PROCUREMENT 5213 882000 180180-945861MULTIPLE BUILDINGS - PAINTING AND IMPROVEMENTS 3/31/16 $150K SPR RECEIVED 1/29/16. FUNDING REQUESTED 1/29/16. FUNDED IN PART 1/29/16. FUNDING UPGRADE REQUESTED AND RECEIVED 2/3/16. WORK IS IN PROGRESS. FUNDING UPGRADE RECEIVED ON 2/22/16 FOR FULL AMOUNT. WORK IS IN PROGRESS. FUNDING UPGRADE RECEIVED 4/5/16. WORK IS COMPLETE. PREPARING CLOSEOUT. MCCARLEY 5213 PROJ MGMT COMPLETE 5102 882000 180187-923510MULTIPLE BUILDINGS - REPAIR AND 6/15/16 REPLACE CHEMICAL EQUIPMENT $25K SPR RECEIVED 8/28/15. FUNDING REQUESTED 9/2/15. FUNDING RECEIVED 4/1/16. BLUME 5102 PROJ MGMT CONSTRUCTION 5255 882000 318500-945866MULTIPLE BUILDINGS 8/15/16 RESIDENTIAL PAINTING CONTRACT A $70K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. MCCARLEY 5255 PROJ MGMT PROCUREMENT 5256 882000 318500-923510MULTIPLE BUILDINGS 8/15/16 RESIDENTIAL PAINTING CONTRACT B $70K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. MCCARLEY 5256 PROJ MGMT PROCUREMENT 22 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5257 882000 318500-923510MULTIPLE BUILDINGS 8/15/16 RESIDENTIAL PAINTING CONTRACT C $70K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. MCCARLEY 5257 PROJ MGMT PROCUREMENT 5258 882000 318505,318510,318515-923510 MULTIPLE BUILDINGS 8/15/16 RESIDENTIAL PAINTING CONTRACT D $70K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. MCCARLEY 5258 PROJ MGMT PROCUREMENT 5192 NATATORIUM - INSTALL POOL WATER HEATING SYSTEM T.B.D. T.B.D. SPR RECEIVED 11/17/15. THIS PROJECT WILL LIKELY BE INCLUDED IN PERFORMANCE CONTRACT #2 CAPITAL PROJECT. AWAITING FUNDING FROM PC #2. WILLIAMS 5171 PROJ MGMT SCOPE & ESTIMATING NATATORIUM - INSTALL WATER BELT TRAINING SYSTEM T.B.D. $26.1K SPR RECEIVED 7/7/15. FUNDING REQUESTED 10/29/15. GUINN 5064 SPONSOR AWAITING FUNDING 6/10/16 $4.5K SPR RECEIVED 12/18/15. FUNDING REQUESTED 1/19/16. FUNDING RECEIVED 5/10/16. BLUME 5192 PROJ MGMT PROCUREMENT NATATORIUM - INVESTIGATE FOUNDATION FOR SETTLING T.B.D. T.B.D. SPR RECEIVED 3/2/16. THIS WORK WILL BE ACCOMPLISHED IN A COMPREHENSIVE STUDY. MCCARLEY 5242 PROJ MGMT SCOPE & ESTIMATING NATATORIUM - RE-ORIENTATE ROOF ACCESS HATCHES T.B.D. $11.9K SPR RECEIVED 11/6/15. FUNDING REQUESTED 11/23/15. WILLIAMS 5167 SPONSOR AWAITING FUNDING NATATORIUM - REPLACE HVAC DEKTRON UNIT T.B.D. T.B.D. SPR RECEIVED 9/15/15. THIS PROJECT WILL LIKELY BE INCLUDED IN PERFORMANCE CONTRACT #2 CAPITAL PROJECT. WILLIAMS 5112 PROJ MGMT SCOPE & ESTIMATING 882000 171008-923510NATATORIUM - INSTALL WATER FOUNTAIN ON POOL DECK 23 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5198 882000 121981-945864OSPREY HALL - INSTALL ELECTRICAL OUTLETS IN ROOMS 1001C, 1024, 2017A, 2021A 4/30/16 $7.2K SPR RECEIVED 1/14/16. FUNDING REQUESTED GUINN 3/8/16. FUNDING RECEIVED 3/22/16. PO HAS BEEN ISSUED. WORK TO BEGIN 5/9/16. 5198 PROJ MGMT CONSTRUCTION 5097 443811 443811-923510PADRICK HOUSE - REPAIRS AND IMPROVEMENTS 9/30/15 $10.1K SPR RECEIVED 8/26/15. FUNDING ESTABLISHED 8/26/15. WORK IS UNDERWAY. WORK IS COMPLETE. WAITING FOR FINANCIAL CLOSEOUT. CLOSEOUT IS UNDERWAY. BOYD 5097 FAC ADMIN CLOSEOUT 5148 882000 319246-945950PARKING DECK - ADDRESS 11/30/16 $180K PREVENTIVE MAINTENANCE NEEDS SPR RECEIVED 10/26/15. FUNDING REQUESTED 12/9/15. SCOPING DISCUSSIONS ARE IN PROGRESS. SCOPE REDUCED FOR SUMMER 2016; REQUESTED FUNDING ADJUSTED TO REFLECT THAT. FUNDING RECEIVED 3/14/16. DESIGN CONTRACT AWARDED 3/24/16. SEIFERT 5148 ACSVCS DESIGN PARKING DECK - CONSTRUCT CUSTOMER SERVICE BOOTH GUINN 5177 SPONSOR AWAITING FUNDING T.B.D. $41.4K SPR RECEIVED 11/24/15. FUNDING REQUESTED 4/7/16. $210K SPR RECEIVED 5/28/14. FUNDING REQUESTED SEIFERT 6/12/14. FUNDING RECEIVED 7/2/14. DESIGN IS UNDERWAY. BIDS OPENED 12/3/14. BIDS EXCEEDED AVAILABLE FUNDING. PROJECT TO BE REBID ON 4/15/15. ADDITIONAL FUNDING REQUESTED 4/10/15. ADDITIONAL FUNDING RECEIVED 4/13/15. BIDS RECEIVED, PO WRITTEN. WORK BEGINS 5/11/15. WORK IS COMPLETE. PUNCHLIST ITEMS REMAINING. PUNCHLIST ITEMS COMPLETE. CLOSEOUT IS UNDERWAY. 4867 FAC ADMIN CLOSEOUT SP15-003 883241 319246-945950PARKING DECK - REPAIRS & MAINTENENCE 8/30/15 5028 882000 319248-945950PARKING LOT B - ADD ADDITIONAL PARKING 10/15/15 $38K SPR RECEIVED 4/16/15. FUNDING REQUESTED 6/11/15. FUNDING RECEIVED 8/5/15. WORK IS UNDERWAY. CURRENT FUNDING IS FOR DESIGN ONLY. BLUME 5028 PROJ MGMT R&R 413270 413270-945868PHYSICAL PLANT - UPGRADES TO FUEL STATION 6/16/14 SPR GENERATED 11/22/13. FUNDED WITH R&R FUNDS. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. MCCARLEY 4729 FAC ADMIN CLOSEOUT $36.5K 24 DESIGN Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE 5296 882000 180187-945850RANDALL LIBRARY - DEMO SMALL OFFICES 2019-2038 6/15/16 $30K SPR RECEIVED 5/5/16. FUNDING REQUESTED 5/5/16. FUNDING RECEIVED 5/5/16. BLUME 5296 PROJ MGMT 5181 882000 151100-945510RANDALL LIBRARY - INSTALL 2/15/16 SECURITY CAMERAS IN ROOM 2043 $3.9K SPR RECEIVED 12/3/15. FUNDING REQUESTED 12/22/15. FUNDING RECEIVED 1/7/16. AWARDED 1/7/16. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. MCCARLEY 5181 FAC ADMIN CLOSEOUT T.B.D. $36.7K SPR RECEIVED 3/3/15. MET WITH SPONSOR 3/19/15. FUNDING REQUESTED 4/29/15. REVISED FUNDING REQUEST SUBMITTED 2/16/16. MCCARLEY 5000 SPONSOR AWAITING FUNDING RANDALL LIBRARY - REMODEL TAC PROCUREMENT 5182 882000 151100-945850RANDALL LIBRARY - RENOVATE SECOND FLOOR INTO TRUE QUIET SPACE 8/15/16 $30K SPR RECEIVED 12/3/15. FUNDING REQUESTED 2/3/16. FUNDING RECEIVED 2/9/16. FUNDING REDUCED TO $30,000 ON 4/5/16. BLUME 5182 PROJ MGMT DESIGN 5183 882000 151100-945850RANDALL LIBRARY - RENOVATIONS TO ROOMS 2061 AND 2062 5/30/16 $17K SPR RECEIVED 12/3/15. FUNDING REQUESTED 2/22/16. FUNDING RECEIVED 3/7/16. WORK IS UNDERWAY. GUINN 5183 PROJ MGMT CONSTRUCTION 5212 882000 151100-945860RANDALL LIBRARY - RESTROOM DESIGN 5/30/16 $50K SPR RECEIVED 1/28/16. REQUESTED FUNDING 1/28/16. FUNDING RECEIVED 1/29/16. DESIGN IS IN PROGRESS. SEIFERT 5212 ACSVCS DESIGN R&R 413280 413280-945860RANDALL LIBRARY - STRUCTURAL STUDY 8/15/14 $15K SPR DEVELOPED 12/20/13. R&R FUNDING ESTABLISHED 12/20/13. DESIGN IS COMPLETE. ANALYSIS OF REPORT IS UNDERWAY. DESIGN OF INTERMEDIATE REPAIRS IS COMPLETE. MCCARLEY 4740 FAC ADMIN CLOSEOUT T.B.D. SPR RECEIVED 5/4/16. MCCARLEY 5295 PROJ MGMT RESIDENTIAL SUPPORT PROGRAM T.B.D. FACILITY - DESIGN HVAC UPGRADE 25 SCOPE & ESTIMATING Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO CI13-006 416290 416290-945867S&BS RENOVATIONS T.B.D. T.B.D. DESIGN FIRM HAS BEEN SELECTED. DESIGN IS UNDERWAY. CMR HAS BEEN SELECTED. WORK IS UNDERWAY. DESIGNER PRE-FINAL INSPECTION 6/4/15. SCO FINAL APPROVAL OBTAINED 8/3/15. SP14-025 883110 180540,319248-945950 SCHWARTZ HALL - MODIFICATIONS TO PARKING LOT 5/15/16 $460K SPR RECEIVED 4/15/13. FUNDING REQUESTED BLUME 5/9/13. FUNDING RECEIVED 9/12/13. DESIGN CONTRACT HAS BEEN AWARDED. DESIGN IS UNDERWAY. DENR REVIEW IS UNDERWAY. BIDS HAVE BEEN OPENED. PO FOR CONSTRUCTION IN PROCESS. FUNDING INCREASE RECEIVED 3/18/15. 5253 882000 318515-923510SEAHAWK CROSSING BUILDING 1 ROLLOVER CONTRACT 7/31/16 $55K 5254 882000 318515-923510SEAHAWK CROSSING BUILDING 3 ROLLOVER CONTRACT 8/15/16 5252 882000 318505-923510SEAHAWK VILLAGE - INSTALL NEW DHW HEATERS IN EACH APARTMENT 5250 882000 576200-945968SHELLFISH RESEARCH HATCHERY - INSTALL SEAWATER GRAVITY DRAIN LINE 5029 PHASE 4716 FAC ADMIN CLOSEOUT 4603 PROJ MGMT CONSTRUCTION SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. SOUTHERLAND 5253 PROJ MGMT PROCUREMENT $55K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. SOUTHERLAND 5254 PROJ MGMT PROCUREMENT 8/15/16 $65K SPR RECEIVED 3/23/16. FUNDING RECEIVED 4/4/16. WORK AWARDED. MCCARLEY 5252 PROJ MGMT PROCUREMENT 4/30/16 $50.4K SPR RECEIVED 3/21/16. FUNDING REQUESTED REINMANN 3/21/16. FUNDING RECEIVED 3/21/16. CONSTRUCTION BEGAN 4/4/16. WORK COMPLETE 4/25/16. 5250 PLANTADMINCOMPLETE SHOPS AT THE CROSSING T.B.D. INSTALL OUTSIDE WALK-UP ORDER WINDOW T.B.D. SPR RECEIVED 4/16/15. PROJECT IS ON HOLD. SEIFERT 5029 ACSVCS ON HOLD SOCCER FIELD - GRADE PRACTICE SOCCER FIELD $7.2K SPR RECEIVED 2/12/15. FUNDING REQUESTED 2/20/15. BLUME 4979 SPONSOR AWAITING FUNDING T.B.D. 26 SEIFERT ACTION OFFICE Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE ESTM'D CPLTN SOCCER FIELD - INSTALL WALKWAY T.B.D. PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. SPR RECEIVED 6/11/15. MCCARLEY 5060 PROJ MGMT SCOPE & ESTIMATING MCCARLEY 5051 PROJ MGMT CONSTRUCTION 5051 882000 319080-945512SOCCER FIELD - REPLACE BLEACHERS 4/30/16 $100K SPR RECEIVED 5/22/15. SCOPING IN PROGRESS. FUNDING REQUESTED 1/27/16. FUNDING RECEIVED 2/10/16. REPAIR WORK AWARDED. WORK IN PROGRESS. 5095 882000 319080-945974SOCCER FIELD - REPLACE IRRIGATION SYSTEM 5/29/16 $51.2K SPR RECEIVED 8/21/15. FUNDING REQUESTED WILLIAMS 10/29/15. DESIGN COMPLETE AND PROJECT WILL BE PUT OUT TO BID FOR PRICING PURPOSES. BID OPENING IS THE WEEK OF MARCH 7. BIDS RECEIVED AND AWAITING FUNDING. FUNDING RECEIVED 4/14/16. WORK BEGAN 4/25/16. 5095 PROJ MGMT CONSTRUCTION SOFTBALL TRAINING FACILITY DESIGN T.B.D. T.B.D. SPR RECEIVED 4/29/16. MORGAN 5291 ACSVCS SCOPE & ESTIMATING STUDENT REC CENTER - REPAIR DITCH BEHIND BUILDING T.B.D. T.B.D. SPR RECEIVED 10/8/15. MCCARLEY 5126 PROJ MGMT SCOPE & ESTIMATING 5233 882000 180186-945866TEACHING LAB - ENERGY CONSERVATION PROJECT (1292) 6/15/16 $50K SPR RECEIVED 3/2/16. 1292 FUNDING REQUESTED 3/2/16. FUNDING RECEIVED 3/7/16. SHARPE 5233 ACSVCS DESIGN 5159 882000 121981-945850TEACHING LAB - INSTALL BACK-UP CAGE WASHER IN ROOM 2040 5/30/16 $13.2K SPR RECEIVED 11/2/15. FUNDING REQUESTED 11/30/15. FUNDING RECEIVED 3/22/16. WORK TO START 4/13/16. WORK SHOULD BE COMPLETED BY 5/12/16. WILLIAMS 5159 PROJ MGMT CONSTRUCTION 446904 446904-945861TEACHING LAB - STORMWATER T.B.D. T.B.D. FUNDING REQUESTED 12/14/11. FUNDING RECEIVED 2/24/12. ANALYSIS UNDERWAY. WORK IS COMPLETE. CLOSEOUT IN PROGRESS. MORGAN 4336 ACSVCS OPEN 27 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE TELECOM CENTER - CONNECT HVAC UNIT TO GENERATOR ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO SEIFERT ACTION OFFICE PHASE 4900 SPONSOR AWAITING FUNDING CONSTRUCTION T.B.D. $40.9K SPR RECEIVED 9/16/14. FUNDING REQUESTED 10/17/14. $498K SPR RECEIVED 4/1/16. FUNDING ESTABLISHED MCCARLEY 4/27/16. MULTIPLE CONTRACTS AWARDED; WORK IN PROGRESS. 5273 PROJ MGMT 5273 882000 180180-923510TRASK COLISEUM - ADDRESS CODE RELATED ISSUES 6/10/16 4926 180187 180187-945850TRASK COLISEUM - CONSTRUCT ACADEMIC CENTER 11/20/15 $129K SPR RECEIVED 11/4/14. FUNDING REQUESTED 1/28/15. FUNDING FOR DESIGN ONLY RECEIVED 5/19/15. FUNDING UPGRADE REQUESTED 6/4/15. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. BLUME 4926 FAC ADMIN CLOSEOUT TRASK COLISEUM - EVALUATE POWER NEEDS IN LOBBY T.B.D. T.B.D. SPR RECEIVED 1/15/15. MORGAN 4963 ACSVCS SCOPE & ESTIMATING TRASK COLISEUM - INSTALL DOMESTIC HEATING HOT WATER SYSTEM T.B.D. T.B.D. SPR RECEIVED 11/17/15. AWAITING QUOTE. WORK LIKELY TO BE CONDUCTED THROUGH PC#2. WILLIAMS 5172 PROJ MGMT SCOPE & ESTIMATING 6/15/16 $2K SPR RECEIVED 1/26/16. FUNDING RECEIVED 4/1/16. SHARPE 5206 ACSVCS PROCUREMENT T.B.D. T.B.D. SPR RECEIVED 2/12/15. SCOPING IN PROGRESS. MCCARLEY 4978 PROJ MGMT SCOPE & ESTIMATING 5/31/16 $475K SPR RECEIVED 9/24/14. ESTIMATE AND FUNDING REQUEST FORWARDED TO PROJECT SPONSOR ON 9/25/14. FUNDING RECEIVED 10/9/14. ORIGINAL CONTRACT IS AT 95% COMPLETE. SPONSOR HAS REQUESTED DOOR CHANGES AND WILL REQUIRE NEW WORK. WAITING ON CHANGE ORDER MATERIALS (DOORS). MCCARLEY 4902 PROJ MGMT CONSTRUCTION 5206 882000 180180-945880TRASK COLISEUM - LEAD AND ASBESTOS SURVEY AND ABATEMENT TRASK COLISEUM - PROVIDE ADDITIONAL STORAGE 4902 882000 319099-945850TRASK COLISEUM - RENOVATIONS TO MEN'S BASKETBALL LOCKER ROOM 28 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE TRASK COLISEUM - REPLACE STEAM BOILERS ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE AWAITING FUNDING T.B.D. $10K SPR RECEIVED 10/6/15. SCOPING REPAIR POSSIBILITIES BEFORE PROVING ESTIMATE. FUNDING REQUESTED 11/23/15. PO ISSUED FOR EXISTING BOILER REPAIR (THROUGH PHYISCAL PLANT, NOT PROJECT). WORK IS LIKELY TO BE CONDUCTED THROUGH PC #2. WILLIAMS 5124 SPONSOR SPR GENERATED 4/10/14. R&R FUNDING ESTABLISHED 4/9/14. WORK IS COMPLETE. CLOSEOUT IS UNDERWAY. MCCARLEY 4815 FAC ADMIN CLOSEOUT R&R 416240 416240-945862TRASK COLISEUM - SANITARY SEWER REPAIRS 6/30/15 $100K R&R 414210 414210-945860TRASK COLISEUM - UPGRADE FIRE ALARM SYSTEM (DESIGN) (R&R FUNDS) 6/30/15 $282.7K SPR RECEIVED 4/5/13. ESTIMATE AND FUNDING REQUEST FORWARDED TO PROJECT SPONSOR ON 4/5/13. R&R FUNDING RECEIVED. ANALYSIS AND DESIGN IS UNDERWAY. MCCARLEY 4595 PROJ MGMT DESIGN TRASK COLISEUM/HANOVER HALL COURTYARD: GOLF CART PAD AND AWNING T.B.D. $35K SPR RECEIVED 3/5/15. FUNDING REQUESTED 4/23/15. SEIFERT 5002 SPONSOR AWAITING FUNDING TRASK COLISEUM/HANOVER HALL: ANNUAL FLOOR SANDING/ REPAINTING/RESURFACING T.B.D. T.B.D. SPR RECEIVED 2/17/16. PLANNING TO BID DURING THIRD WEEK OF JUNE. WILLIAMS 5228 PROJ MGMT SCOPE & ESTIMATING 6/10/16 $160K SPR RECEIVED 4/1/16. FUNDING REQUESTED 4/27/16. FUNDING RECEIVED 4/28/16. PREPARING BID DOCUMENTS. MCCARLEY 5272 PROJ MGMT PROCUREMENT T.B.D. $21K SPR RECEIVED 2/27/15. FUNDING REQUESTED 3/4/15. BLUME 4994 SPONSOR AWAITING FUNDING 8/15/15 $140.6K SPR RECEIVED 3/19/14. FUNDING REQUESTED 3/31/14. FUNDING RECEIVED 4/13/14. CURRENT SCOPE IS COMPLETE. ADDITIONAL BUILDINGS WILL BE COMPLETED IN SUMMER 2016. FUNDING UPGRADE RECEIVED 3/14/16 FOR SUMMER 2016. WORK AWARDED. MCCARLEY 4800 PROJ MGMT CONSTRUCTION 5272 882000 180187-923510TRASK/HANOVER: REPLACE INTERIOR DOOR HARDWARE UNIVERSITY APARTMENTS ASSESS ROOF CONDITION SP14-110 883195 318500-945850UNIVERSITY APARTMENTS REPLACE FLOORING 29 Project Report SP/CI PROJ FUND NO SOURCE FUND TITLE UNIVERSITY APARTMENTS REPLACE FLOORING ESTM'D CPLTN PROJ BDGT STATUS PROJ MGR PM NO ACTION OFFICE PHASE T.B.D. $3K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. GUINN 5137 SPONSOR AWAITING FUNDING 5134 882000 318500-923510UNIVERSITY APARTMENTS REPLACE INTERIOR DOORS AND FRAMES 7/15/16 $89.1K SPR RECEIVED 10/8/15. FUNDING REQUESTED 10/22/15. FUNDING RECEIVED 4/4/16. WORK SCHEDULED TO BEGIN 5/9/16. BLUME 5134 PROJ MGMT CONSTRUCTION 5226 882000 180180-945864UNIVERSITY POLICE - FIRE ALARM HEAD END SYSTEM INSTALLATION 6/30/16 $403K SPR RECEIVED 2/15/16. FUNDING FOR DESIGN PHASE WAS ENCUMBERED FOR PROJECT FROM 180180 ON 3/29/16. CONSTRUCTION FUNDING ENCUMBERED 5/4/16. GUINN 5226 PROJ MGMT CONSTRUCTION T.B.D. $600 SPR RECEIVED 4/7/16. FUNDING REQUESTED 4/27/16. SOUTHERLAND 5276 SPONSOR AWAITING FUNDING UNIVERSITY POLICE BUILDING 3 REPAIR CEILING IN HALLWAY 5249 882000 180540-945866UNIVERSITY POLICE DEPARTMENT - REPLACE ROTTEN BOARDS AND DRIP EDGE 6/15/16 $6.7K SPR RECEIVED 3/11/16. FUNDING REQUESTED 3/30/16. FUNDING RECEIVED 4/15/16. WORK BEGAN 4/25/16. GUINN 5249 PROJ MGMT CONSTRUCTION 5107 882000 180187-945960WAGONER CEP - COOLING TOWER MAKE-UP WATER REDESIGN 5/31/16 $30K SPR RECEIVED 9/15/15. AWAITING APPROVAL FROM DESIGNER BEFORE ESTIMATE. AWAITING PRICES FROM ESTIMATE IN ORDER TO PREPARE ESTIMATE LETTER FOR SPONSOR. AWAITING ENGINEERING PLANS. FUNDING RECEIVED 4/1/16. AWAITING ENGINEERED DRAWINGS. WILLIAMS 5107 PROJ MGMT DESIGN WAGONER HALL - ATTACH NEW GAS HOSES TO GRILL T.B.D. $0 SPR RECEIVED 1/28/16. WORK IN PROGRESS. DESIGNER IS INVOLVED TO MAKE FA INTEGRATE WITH BUILDING AUTOMATION. WORK IN PROGRESS VIA OTHER CONTRACTS THROUGH ARAMARK. WORK COMPLETE. MCCARLEY 5207 PROJ MGMT COMPLETE WAGONER HALL - RENOVATIONS TO MADELINE SUITE T.B.D. $10K SPR RECEIVED 12/5/14. AUTHORITY REQUESTED FROM GA. PROPOSAL FOR MECHANICAL DESIGN RECEIVED 4/6/16. FUNDING REQUESTED FOR MECHANICAL DESIGN ON 4/12/16. MCCARLEY 4956 SPONSOR AWAITING FUNDING 5207 30 Project Report SP/CI PROJ FUND NO 5105 SOURCE FUND TITLE 882000 318300-945866WAGONER HALL - REPLACE WALKIN FREEZER STATUS PROJ MGR PM NO ACTION OFFICE PHASE SPR RECEIVED 9/4/15. FUNDING REQUESTED 9/14/15. FUNDING RECEIVED 10/7/15. PO ISSUED, DELIVERY EXPECTED IN EARLY DECEMBER. WORK TO START DECEMBER 14. WORK COMPLETED 12/23/15. CLOSEOUT IS UNDERWAY. WILLIAMS 5105 FAC ADMIN CLOSEOUT T.B.D. T.B.D. SPR GENERATED 11/25/14. DESIGNER GENERATING CONCEPT DESIGNS. MORGAN 4947 ACSVCS SCOPE & ESTIMATING 9/19/14 $25K SPR GENERATED 6/16/14. FUNDING REQUESTED 6/16/14. FUNDING RECEIVED 7/2/14. PRELIMINARY DESIGN IS UNDER REVIEW. COORDINATION MEETING CONDUCTED ON 8/19/14. PROJECT PRESENTED TO DESIGN REVIEW COMMITTEE 10/7/14. DESIGN REVISIONS HAVE BEEN COMPLETED. FUNDING FOR CONSTRUCTION HAS BEEN REQUESTED. LIGHTING PACKAGE PAID FOR OUT OF PM 4617, CAHILL CURB AND GUTTER. LIGHTING PHASE IN PROGRESS. LIGHTING PHASE I IS COMPLETE. MCCARLEY 4872 PROJ MGMT COMPLETE T.B.D. $69.6K SPR RECEIVED 9/15/15. AWAITING INITIAL ESTIMATE FROM CONTRACTOR. WORKING ON PROPOSAL IN ORDER TO PUT OUT PROJECT FOR BID. FUNDING REQUESTED 4/7/16. WILLIAMS 5111 SPONSOR AWAITING FUNDING 5/15/16 $12K SPR RECEIVED 3/2/16. FUNDING REQUESTED WILLIAMS 3/3/16. FUNDING RECEIVED 3/14/16. WORK IS 75% COMPLETE. 5239 PROJ MGMT CONSTRUCTION WARWICK CENTER - CASHIER'S OFFICE ADA WINDOW AND DOOR OPENER T.B.D. $18K SPR RECEIVED 4/1/16. FUNDING REQUESTED 4/8/16. MCCARLEY 5274 SPONSOR AWAITING FUNDING WARWICK CENTER - INSTALL CAMERAS AND CARD SWIPE ACCESS IN ROOM 166 T.B.D. $16.7K SPR RECEIVED 2/22/16. FUNDING REQUESTED 3/30/16. MCCARLEY 5231 SPONSOR AWAITING FUNDING 883237 319248-945966WALTON DRIVE - INSTALL TRAFFIC SIGNAL AT CHANCELLORS WALK CROSSING WAREHOUSE - REPLACE ALL HVAC PACKAGE UNITS 5239 PROJ BDGT 12/23/15 $31.6K WALTON DRIVE - FEASIBILITY STUDY SP15-004 ESTM'D CPLTN 882000 180310-945850WAREHOUSE / EH&S OFFICE INSTALL CONFERENCE ROOM OFFICE PARTITION 31 Project Report SP/CI PROJ FUND NO 5232 SOURCE FUND TITLE ESTM'D CPLTN 882000 172010-923510WARWICK CENTER - INSTALL CARD 6/15/16 SWIPE ACCESS IN ROOMS 144 AND 146 WARWICK CENTER - PATCH AND PAINT DRYWALL IN LOBBY AND BALLROOM PROJ BDGT STATUS PROJ MGR PM NO $5.5K SPR RECEIVED 2/25/16. FUNDING REQUESTED 3/30/16. FUNDING RECEIVED 4/5/16. WORK AWARDED; MATERIALS ORDERED. MCCARLEY 5232 T.B.D. $5K SPR RECEIVED 4/1/16. FUNDING REQUESTED 4/27/16. SOUTHERLAND 5269 ACTION OFFICE PHASE PROJ MGMT PROCUREMENT SPONSOR AWAITING FUNDING 5225 882000 180187-923510WARWICK CENTER - REPLACE WALL TILES, FLOOR TILES, AND COUNTER TOPS IN ROOMS 106 AND 107 5/15/16 $38K SPR RECEIVED 2/11/16. FUNDING REQUESTED BLUME 3/4/16. FUNDING RECEIVED 4/1/16. PREPARING TO BID. 5225 PROJ MGMT PROCUREMENT 5248 882000 318300-923510WARWICK CENTER: REPAIR OR 4/15/16 REPLACE FLOOR IN RESTROOM 172 $7.7K SPR RECEIVED 3/8/16. FUNDING REQUESTED 3/10/16. FUNDING RECEIVED 3/14/16. FUNDING UPGRADE REQUESTED 3/31/16. PO ISSUED 4/7/16. FUNDING UPGRADE RECEIVED 4/7/16. AWAITING DECISION ABOUT TYPE OF FLOOR DESIRED BY SPONSOR. WILLIAMS 5248 PROJ MGMT CONSTRUCTION 15-018 882000 217112-945966WATER TOWER - STRUCTURAL REPAIRS 9/30/16 $110K SPR RECEIVED 9/16/14. FUNDING REQUESTED 9/16/14. FUNDING RECEIVED 10/7/14. INITIAL DESIGN IS COMPLETE. FEE PROPOSAL HAS BEEN REQUESTED FOR ADDITIONAL DESIGN EFFORT. SEIFERT 4901 ACSVCS DESIGN T.B.D. $55.2K SPR RECEIVED 4/13/16. FUNDING REQUESTED 5/5/16. SOUTHERLAND 5285 SPONSOR AWAITING FUNDING 4/1/16 $12.5K SPR RECEIVED 1/20/15. FUNDING REQUESTED 3/2/15. FUNDING RECEIVED 11/24/15. FOUNTAIN ORDERED. WORK IS UNDERWAY. PICKARD PROJ MGMT CONSTRUCTION WISE HOUSE - PAINT HOUSE EXTERIOR 4969 882000 990320-945966WISE HOUSE - REPLACE FOUNTAIN 32 4969