AGENDA ITEM 10-A ACTION ITEM TO: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD FROM: DALE ZEHNER DATE: DECEMBER 16, 2011 SUBJECT: REFERRAL OF THE REVISED FY 2012 AND RECOMMENDED FY 2013 VRE OPERATING AND CAPITAL BUDGETS TO THE COMMISSIONS AND LOCALITIES RECOMMENDATION: The VRE Operations Board is being asked to adopt the revised FY 2012 VRE Operating and Capital Budget and the recommended FY 2013 VRE Operating and Capital Budget, and refer them to the Commissions for their consideration and subsequent referral to the jurisdictions for their formal review and adoption. BACKGROUND: In accordance with the VRE Master Agreement, which outlines the process for annual budget approval, the preliminary FY 2013 VRE Operating and Capital Budget was submitted for review at the August VRE Operations Board meeting. Since that time, it has been discussed at numerous meetings of the CAO Task Force. The CAO Task Force met on December 8th to present their final recommendations and discuss VRE responses to those recommendations. DISCUSSION: The major assumptions in the FY 2013 budget are as follows: Jurisdictional subsidy of $16,428,800, an increase of $484,882 or 3% compared to the FY 2012 level. A payment by Spotsylvania County of the amounts waived in prior years will be a mid-year credit to the other jurisdictions. Fare increase of 3% and a projected average daily ridership of 19,000 passengers, which in combination increases projected fare revenue by $3.9 million over the FY 2012 adopted budget amount to a total of $34.5M. A reduction in federal formula funds for capital projects based on a reduction to VRE’s FY 2012 award plus an additional 1% decrease in anticipated FY 2013 funding. Final projections continue to be decided at the congressional level. Continuation of a 32-train operation (30 revenue trains). Capital matching funds from the State of 50% of the non-federal share for new projects. State operating funds of $6.1 million, compared to $5.3M budgeted in FY 2012. Actual award for FY 2012 was $6.9M. Fuel estimated at $3.25/gallon for a total cost of $5.6 million. The capital budget includes the following system capital projects for FY 2013, including required local match: Spotsylvania third track - $8.2M (completion of funding required for $20.3M project) Fare collection upgrade - $1.8M (completion of funding required for estimated cost of purchase and installation of new fare collection system – options will be reviewed after requirements study is completed) Rolling stock (railcars) - $5.5M (second year of funding for multi-year project to purchase 15 replacement Gallery rail cars) Material expenditure line item changes are noted below; adjustments are in comparison to the FY 2012 adopted budget. Fuel budget has increased by $790k based on an average per gallon cost of $3.25 compared to the FY 2012 adopted budget per gallon estimate of $2.70. Retail sales commissions in Budget and Finance were increased by $675,000, based on WMATA’s discontinuation of the Smart Benefits card. This has caused the bulk of the ridership to purchase tickets through the 2 Commuter Direct system, which has a higher commission rate based on the higher level of service required. Equipment maintenance increased by $500k to reflect additional oversight for the equipment maintenance contract and higher than anticipated costs for the required ten year periodic maintenance (COT&S) for the remaining older Gallery railcars. Keolis contract costs are budgeted at a net increase of $710,000 to reflect a 3.5% increase to the 12-month October CPI, in accordance with the contract requirements. Access fee costs increased by $1.1 million to reflect an estimated increase to the AAR index for the first quarter of calendar 2012 for Amtrak and the contractual increase of 4% for CSX and NS. The budget also includes a six-year financial forecast for the period FY 2013 through FY 2018. A six-year forecast was prepared that includes a 4% fare increase in FY 2015 and FY 2017 plus a 0% subsidy increase in years FY 2014 – FY 2018. REVISED FY 2012 OPERATING AND CAPITAL BUDGET The FY 2012 budget has been revised to reflect current projections for revenue and expenses. The major changes are as follows: Fare revenue is increased by $2.4M based on current ridership projections to $33.0M. The State operating grant is increased by $1.5 to reflect the actual higher grant award. Access fee reimbursement decreased by $600k based on transition to state funding of match to federal access fee grant; state match will not be available until older grant funds are depleted. State capital grants are increased by $17.0 million and federal capital grants by $15.6M to reflect the following: o Additional funding provided through DRPT for the Spotsylvania third track ($4.6M) and purchase of replacement rail cars ($17.6M) o STP (formerly bonus obligation) funds for locomotives ($3.0M) o VDOT/locally administered project funds for the Alexandria tunnel ($7.4M) Use of capital reserve for additional match for Spotsylvania third track, rail car projects ($2.2M), and additional capital needs ($1.5M) Increase of $1.0M for higher cost per gallon of fuel 3 TO: FROM: DATE: RE: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD DALE ZEHNER DECEMBER 16, 2011 REFERRAL OF THE REVISED FY 2012 AND RECOMMENDED 2013 VRE OPERATING AND CAPITAL BUDGETS TO THE COMMISSIONS AND LOCALITIES RESOLUTION 10A-12-2011 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, the VRE Master Agreement requires that the Commissions be presented with a fiscal year budget for their consideration at their respective January meetings prior to the commencement of the subject fiscal year; and, WHEREAS, the VRE Chief Executive Officer has provided the VRE Operations Board with the FY 2013 Operating and Capital Budget within the guidelines developed in concert with the jurisdictional chief administrative officers; and, WHEREAS, VRE staff recommends a budget built on an average daily ridership of 19,000 and 32 trains. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board does hereby recommend that the Commissions adopt the revised FY 2012 and recommended FY 2013 VRE Operating and Capital Budgets and forward the FY 2013 budget to the local jurisdictions for inclusion in their budgets and appropriations in accordance with the Master Agreement; and, BE IT FURTHER RESOLVED THAT, the VRE Operations Board recommends that the Executive Directors of both PRTC and NVTC submit to the Transportation Planning Board of the National Capital Region and to the Federal Transit Administration or other federal agencies, the appropriate Transit Improvement Program and grant applications for FY 2012 and FY 2013; and, BE IT FURTHER RESOLVED THAT, the VRE Operations Board recommends that the Executive Director of NVTC be authorized to submit to the Commonwealth the approved budget as part of the FY 2013 state aid grant applications. 4 AGENDA ITEM 10-B ACTION ITEM TO: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD FROM: DALE ZEHNER DATE: DECEMBER 16, 2011 RE: AUTHORIZATION TO AMEND THE CONTRACT WITH SCHEIDT & BACHMANN FOR FARE COLLECTION EQUIPMENT MAINTENANCE _____________________________________________________________________ RECOMMENDATION: The VRE Operations Board is being asked to authorize the Chief Executive Officer to amend the Scheidt & Bachmann (S&B) contract for fare collection system maintenance in order to add three years and five months of maintenance services in an amount not to exceed $2,438,931, for a total contract value not to exceed $9,876,968. BACKGROUND: In June 2000, the VRE Operations Board authorized a contract with S&B for the delivery of a new fare collection system. In October 2002, the system was accepted and four years of maintenance support, which includes two full-time fare collection maintenance technicians, began. The Operations Board has since authorized extensions to this contract in 2006, 2007 and 2011. The current maintenance agreement is set to expire on January 31, 2012 and a further contract extension for this work is required due to warranty issues and proprietary licenses. This proposed extension continues the support of two full-time technicians, while also adding a software support module which has become necessary due to increasingly stringent requirements for data security and compliance with the Payment Card Industry (PCI) standards. This Service Level Agreement provides for equipment preventative maintenance and repair, replenishment of the fare collection spare parts inventory, software revisions, and updates required for fare collection database maintenance and 1 to maintain PCI compliance. The amendment also aligns the term of the maintenance agreement with the VRE fiscal calendar. This item was presented to the VRE Operations Board in November 2011. The Board requested additional information on pricing and other options to extending the contract. A white paper was forwarded to Board members after the meeting, which included additional background information on pricing and the reasons for sole sourcing the system maintenance based on proprietary and warranty issues (see Attachment). No concerns were raised based on the information provided so authorization is being sought at this time. FISCAL IMPACT: Funding for this project is included in VRE’s Capital Improvement Program as part of the fare collection project. Total project funding over FY 2012 – 2015 is $2,438,931. The project is included in the FY 2012 and FY 2013 budgets using operating funds. This amendment would bring the total contract value to an amount not to exceed $9,876,968. 2 TO: FROM: DATE: RE: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD DALE ZEHNER DECEMBER 16, 2011 AUTHORIZATION TO AMEND THE CONTRACT WITH SCHEIDT & BACHMANN FOR FARE COLLECTION EQUIPMENT MAINTENANCE RESOLUTION 10B-12-2011 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, on June 16, 2000, the VRE Operations Board authorized a contract with Scheidt & Bachmann for the delivery of a new fare collection system; and, WHEREAS, on October 31, 2002, the system was accepted and maintenance support began; and, WHEREAS, the current maintenance agreement is set to expire on January 31, 2012; and, WHEREAS, this proposed extension continues the support of two full-time technicians, while also adding a software support module which has become necessary due to increasingly stringent requirements for data security and compliance with the Payment Card Industry (PCI) standards. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board authorizes the Chief Executive Officer to amend the Scheidt & Bachmann contract for fare collection system maintenance in order to add three years and five months of maintenance services in an amount not to exceed $2,438,931, for a total contract value not to exceed $9,876,968. 3 Fare Collection Equipment Maintenance Agreement Summary Background In June of 2000, after a competitive procurement, the VRE Operations Board authorized a contract with Scheidt & Bachmann (S&B) for the design and delivery of a new fare collection system. This system included Ticket Vending Machines (TVMs) at every VRE station as well as in VRE’s offices and at all vendors – currently 69 TVMs, 13 Ticket Operating Machines (TOMs), and 8 servers are in service. Since then, as permitted in the original contract, a series of upgrades to the system have occurred as well as ongoing general maintenance. Because VRE is a cashless system, the fare collection system must produce every single ticket that passengers use to board VRE trains. As an order of magnitude, in October 2011 alone, the fare collection system produced nearly 50,000 tickets and collected over $3 million in fare revenue, approximately $36 million annually. The addition of a second technician in 2006 was determined necessary based on the length of service hours (5AM – 7PM) and a significant number of complaints being received by passengers. Approved expenditures to date are shown below. Description Period Covered Contract Amount Fare collection system design, installation, spare part inventory Post-installation maintenance and upgrades (48 months, 1 technician) Post-warranty maintenance (add 2nd technician) Post-warranty maintenance and upgrades (3 months, 2 technicians) One Year Post-warranty maintenance and upgrades One Year Post-warranty maintenance and upgrades One Year Post-warranty maintenance and upgrades August 18, 2000 $2,952,040 November 1, 2002 to October 31, 2006 February 18, 2006 to October 31, 2006 November 1, 2006 to January 31, 2007 February 1, 2007 to January 31, 2008 February 1, 2008 to January 31, 2009 February 1, 2009 to January 31, 2010 $593,716 TVM/TOM and PCI upgrade July 2011 $824,130 One Year Post-warranty maintenance and upgrades February 1, 2010 to January 31, 2011 $511,298 One Year Post-warranty maintenance and upgrades February 1, 2011 to January 31, 2012 $511,621 Total $173,626 $83,639 $558,412 $573,730 $582,446 $7,364,658 1 More than Maintenance It is important to note that while the description of work is termed “maintenance,” the scope has and will continue to include mid-life renewal and larger capital maintenance items – including parts and labor. For example, in 2007 the card readers and touch screens were replaced on all equipment. In 2009, all equipment received new ticket printing mechanisms and in 2010 central processing units and PIN pads were replaced. As part of the maintenance contracts, we have also replaced the system servers and upgraded software to comply with the new Payment Card Industry (PCI) data security requirements. As the system ages, there has been a proactive focus on preventative maintenance and life-cycle renewal. As these needs will continue to grow, incorporating such improvements into the maintenance contract allows us to control expenses and shift some cost exposure to S&B. Contract Extension Because of the proprietary nature of the fare collection system and warranty requirements, S&B is the only practical vendor able to perform the ongoing system maintenance. While a third party could maintain certain components of the system, the contract requires that S&B maintain all proprietary aspects of the system (i.e., fare collection software application and some TVM/TOM component maintenance). The additional cost of third party maintenance for only a portion of the system proved cost prohibitive. The contract holds no provisions for a month to month extension. However, a year to year extension was considered as an option over a multi-year extension. However, negotiations showed that a savings was being offered by S&B in return for a longer commitment. As such, the overall cost is significantly higher for an annual contract than a multi-year contract and is, therefore, not being recommended. Annual Cost Analysis VRE costs for maintenance services are summarized in the following table. VRE costs have increased, on average, by about 2% annually over the past five years. Pricing for monthly maintenance is tied to the Consumer Price Index (CPI) for annual adjustments. This resulted in a decrease in monthly costs between 2009 and 2010 and a very small increase for 2011. 2 Year Monthly Preventative Maintenance Remedial Maintenance, Software Support, Spare Parts Inventory TVM/TOM Upgrade Total 20032006 2006 $593,716 $0 $0 $593,716 $207,723 $49,542 $0 $257,265 2007 $384,287 $90,000 $84,125 $558,412 2008 $397,730 $90,000 $86,000 $573,730 2009 $412,446 $105,000 $65,000 $582,446 2010 $411,298 $100,000 $0 $511,298 2011 $411,621 $100,000 $0 $511,621 Cost Analysis of Current System vs. New System The ultimate goal of the VRE fare collection system is full interoperability with the WMATA SmarTrip card. As such, the timeframe for implementing a new system has been coordinated with WMATA’s schedule for the New Electronics Payment Program (NEPP). VRE staff is actively participating in the NEPP process to make sure that our system and WMATA’s new system will work together. This contract amendment is meant to continue the viability of the current system until WMATA is far enough along in their process that VRE can make the most informed choices regarding our fare collection future. When VRE first extended the maintenance contract several years ago, staff recommended, and the Operations Board concurred, that the development of a new VRE fare collection system should be deferred until a time when integration into a regional system was more certain. As such, an investment in maintaining the current equipment and extending its useful life was determined to be the most responsible approach. To change this approach now is not feasible given that a new system will take several years to design, fabricate, install, test and implement. Knowing that, in December of 2010, the Operations Board authorized a contract award for technical support services for VRE’s next generation fare collection system. Work underway includes an assessment of the current system, analysis of VRE requirements for a new system, a market assessment of new products/technologies, and development of a concept of operations for the new system. Based on work completed to-date, the cost of a full system replacement is estimated at between $5 to $7 million; other options being considered include additional equipment being integrated into the existing system, which would be slightly less expensive. 3 In summary, the proposed approach is cost effective not only in its ability to allow interoperability, but also in its volume of production. An investment of roughly $625,000 per year in maintenance costs provides for a system that has an up time of 98% and provides $34 – $36 million in fare revenue per year – a cost of 1.75-1.85% to benefit. Current Maintenance Agreement Request The current Operations Board request is for renewal of the fare collection maintenance agreement for a three year, five month period. The initial five month term will align the term with VRE’s fiscal year. Agreement Scope Base annual hardware maintenance fee - $530,000 o hardware preventative and corrective maintenance o two full-time technicians* o two maintenance vehicles o consumable supplies o S&B overhead Base annual software maintenance (covers general system updates, PCI upgrades, and patches) - $74,690 Spare parts and inventory restocking - $60,000 Contingency - $221,722 TOTAL - $2,438,941** *Note – VRE requires on-site technical support from 5 am until 7 pm on each service day. This has maintained a 98%+ system reliability, and same day resolution of passenger issues. The skill level of these technicians is high because they are required to complete maintenance work, system configuration, and programming. **Note - the agreement includes an annual escalation on the base fee and software maintenance based on the CPI beginning in July 2012. A 3.5% escalation rate is assumed. 4 Proposed Fare Collection Maintenance Pricing Sheet for Period February 1, 2012 – June 30, 2015 Period 1 2 3 4 Description Preventative and Remedial Maintenance (as described in SLA) Preventative and Remedial Maintenance Software Maintenance Total Period 2 Preventative and Remedial Maintenance Software Maintenance Total Period 3 Preventative and Remedial Maintenance Software Maintenance Total Period 4 Start End Duration Base Contract Amount 2/1/2012 6/30/2012 5 Mos. $213,175 7/1/2012 6/30/2013 1 Year $530,000 Estimated Discretionary Escalation Inventory (3.5%) $213,175 $0 Estimate by Period $213,175 $74,690 7/1/2013 6/30/2014 $604,690 $604,690 1 Year $625,854 $20,000 $645,854 $647,759 $20,000 $667,759 $670,431 $2,157,219 $20,000 $60,000 $690,431 $2,217,219 $2,217,219 $74,690 7/1/2014 6/30/2015 $604,690 $604,690 1 Year $74,690 $604,690 $2,027,245 Total Estimated Contract Value Contingency (10%) $221,722 Total VRE Operations Board Authorization $2,438,941 Notes: Period 1 pricing is based on existing maintenance price and is only valid as a onetime package when combined with Periods 2-4. 5 AGENDA ITEM 10-C ACTION ITEM TO: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD FROM: DALE ZEHNER DATE: DECEMBER 16, 2011 SUBJECT: AUTHORIZATION TO EXTEND AMENDED OPERATING/ACCESS AGREEMENT WITH NORFOLK SOUTHERN RECOMMENDATION: The VRE Operations Board is being asked to recommend that the Commissions authorize the Chief Executive Officer to execute an extension of the existing Amended Operating/Access Agreement with Norfolk Southern to July 31, 2012. BACKGROUND: VRE has an Operating/Access Agreement with Norfolk Southern (NS) relating to VRE operations in the Manassas to Washington corridor. That agreement, entered into in 1999, has been amended and extended several times, most recently this past June, with an agreed upon extension to January 31, 2012. A further extension is being requested at this time to provide sufficient time to complete negotiations of a new agreement. Following detailed negotiation sessions with Norfolk Southern representatives, an agreement in principle was reached on all contract items with the exception of liability coverage. The Operations Board and Commissions approved these terms at their June and July 2005 meetings respectively, and authorized execution of a new agreement that conformed to each of those items. Progress slowed, however, due to a failure to reach an agreement on the level of liability coverage. Despite this progress, an extension of the current agreement is needed while this issue is resolved. Recent informal discussions with Norfolk Southern indicate that they may be ready to restart negotiations. The major issue in the negotiation remains the level of liability coverage. FISCAL IMPACT: Funding for the Norfolk Southern track access fee has been budgeted in the FY 2012and FY 2013 budgets, including an escalation of 4%. 2 TO: FROM: DATE: RE: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD DALE ZEHNER DECEMBER 16, 2011 AUTHORIZATION TO EXTEND AMENDED OPERATING/ACCESS AGREEMENT WITH NORFOLK SOUTHERN RESOLUTION 10C-12-2011 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, the Commissions currently have an Operating/Access Agreement with Norfolk Southern related to VRE operations in the Manassas to Washington corridor, with said agreement ending on January 31, 2012; and, WHEREAS, staff has reached an agreement in principle on many substantive items relating to a new agreement following detailed negotiation sessions with Norfolk Southern representatives; and, WHEREAS, a proposal to extend the existing agreement to July 31, 2012, without any changes to the existing agreement is expected from NS; and, WHEREAS, the purpose of this extension is to allow time to negotiate and resolve the outstanding insurance issues relating to a new agreement; and, WHEREAS, necessary funding has been incorporated into the FY 2012 and FY 2013 budgets to allow VRE to continue its operations over Norfolk Southern tracks via this contract extension. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board recommends that the Commissions authorize the Chief Executive Officer to execute an extension of the existing Amended Operating/Access Agreement with Norfolk Southern to July 31, 2012. 3 AGENDA ITEM 10-D ACTION ITEM TO: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD FROM: DALE ZEHNER DATE: DECEMBER 16, 2011 RE: AUTHORIZATION TO AMEND THE AIR CONDITIONING SERVICES CONTRACT RECOMMENDATION: The VRE Operations Board is being asked to authorize the Chief Executive Officer to execute a contract amendment in the amount of $250,000, for the VRE air conditioning services contract, for a total contract value not to exceed $600,000. BACKGROUND: In February of 2009, the VRE Operations Board authorized a contract with RAM Industrial Services, Inc. of Camp Hill, Pennsylvania for the purpose of providing air conditioning repair services for VRE passenger cars. The contract was for $350,000 over a three year term and was recommended following the evaluation of four proposals. Based on concerns regarding the performance of the air conditioning on VRE’s legacy fleet, VRE and RAM conducted a complete evaluation of the legacy car fleet air conditioning systems in February 2011. Structural and system components were identified as being in need of repair and/or replacement. As allowed in the contract, VRE has subsequently been scheduling repair services with RAM based on this evaluation. VRE has 11 more legacy cars in need of air conditioning repairs prior to the return of the warm weather. This contract amendment will allow for a continuation of this work during the winter months until the contract with RAM expires in March 2012. FISCAL IMPACT: Funding for this project is included in the capital reserve and is incorporated in the Amended FY12 Budget. TO: FROM: DATE: RE: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD DALE ZEHNER DECEMBER 16, 2011 AUTHORIZATION TO AMEND THE AIR CONDITIONING SERVICES CONTRACT RESOLUTION 10D-12-2011 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, VRE has a need for air conditioning repair services; and, WHEREAS, VRE has a contract with RAM Industrial Services, Inc. for air conditioning repair services; and, WHEREAS, in February 2011, VRE and RAM Industrial Services, Inc. conducted an evaluation of the legacy car fleet air conditioning systems; and, WHEREAS, continuation of the repairs identified in the evaluation during the winter months is necessary to ensure the legacy cars are fully operational prior to the return of the warmer weather. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board authorizes the Chief Executive Officer to execute a contract amendment in the amount of $250,000 for the air conditioning services contract, for a total contract value not to exceed $600,000. AGENDA ITEM 10-E ACTION ITEM TO: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD FROM: DALE ZEHNER DATE: DECEMBER 16, 2011 RE: AUTHORIZATION TO AWARD A CONTRACT FOR THE PURCHASE OF WETLAND MITIGATION CREDITS FOR THE PARKING LOT EXPANSION PROJECT AT THE BROOKE STATION _____________________________________________________________________ RECOMMENDATION: The VRE Operations Board is being asked to authorize the Chief Executive Officer to award a contract to Buena Vista Holdings LLC, of Richmond, Virginia, to purchase wetland mitigation credits for the parking lot expansion project at the Brooke station. The total contract value shall be $49,255, plus a 5% contingency of $2,463, for total amount not to exceed $51,718. BACKGROUND: Due to significant increases in ridership, VRE designed a Brooke station parking lot expansion of approximately two hundred thirty-four (234) parking spaces. The project will be located to the south of the existing lot and access road. The Virginia Department of Environmental Quality (DEQ) requires VRE to purchase wetland credits to mitigate for on-site wetlands that will be disturbed during the construction process. The Virginia DEQ issued a permit to VRE that outlined the mitigation requirements. At the November 2011 meeting, the Board authorized the solicitation of bids for the purchase of wetland mitigation credits. Following a public procurement, three bids were received on December 8, 2011. The bids were as follows: Bidders Bid Amounts 1. Buena Vista Holdings, LLC $49,254.03 2. Wetlands Development, LLC $55,125.00 3. North Fork Wetlands Bank, L.C. $56,700.00 Following a review of the bids, VRE staff is recommending award to the lowest responsive and responsible bidder, Buena Vista Holdings LLC for the purchase of wetland mitigation credits at the Brooke Station Parking Expansion. FISCAL IMPACT: Funding for the Brooke parking lot expansion project is included in VRE’s Capital Improvement Program using CMAQ and RSTP funds. No local match is required. Total project funding is $2.56M, with $1.1M having been spent to-date on environmental, design, and property acquisition. An additional $1.4M has been encumbered for construction related costs, including the construction contract, inspection, utilities and wetland mitigation. TO: FROM: DATE: RE: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD DALE ZEHNER DECEMBER 16, 2011 AUTHORIZATION TO AWARD A CONTRACT FOR THE PURCHASE OF WETLAND MITIGATION CREDITS FOR THE PARKING LOT EXPANSION PROJECT AT THE BROOKE STATION RESOLUTION 10E-12-2011 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, due to significant increases in ridership, VRE has initiated a parking lot expansion project at the Brooke VRE station; and, WHEREAS, at the November 2011 meeting, the Operations Board authorized the solicitation of bids for the purchase of wetland mitigation credits for the parking lot expansion project; and, WHEREAS, on December 8, 2011, three bids were opened and Buena Vista Holdings LLC was found to be the lowest responsive and responsible bidder. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board authorizes the Chief Executive Officer to award a contract to Buena Vista Holdings LLC to purchase wetland mitigation credits for the parking lot expansion project at the Brooke station; and, BE IT FURTHER RESOLVED THAT, the total contract value shall be $49,255, plus a 5% contingency of $2,463, for total amount not to exceed $51,718; and, BE IT FURTHER RESOLVED THAT, the VRE Operations Board authorize the Chief Executive Officer execute permits and other documents related to the purchase of the wetland mitigation credits. AGENDA ITEM 10-F ACTION ITEM TO: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD FROM: DALE ZEHNER DATE: DECEMBER 16, 2011 RE: AUTHORIZATION TO AMEND THE PARKING LEASE AT RIPPON STATION RECOMMENDATION: The VRE Operations Board is being asked to authorize the Chief Executive Officer to extend the current lease agreement with Kettler for 320 parking spaces at the Rippon Station. The lease extension would be in the amount of $158,475 for one year. BACKGROUND: In May 2002, the Operations Board approved a three year lease with Hazel Land for 320 parking spaces at the Rippon VRE Station. These additional spaces were instrumental in reducing the parking shortage at this station where the parking lot was routinely 97% full. The lot was constructed by Hazel Land and opened in March of 2004, which also commenced the lease term. The lease agreement was subsequently assigned by Hazel Land to Kettler and extended for five years through March 2012; following Operations Board approval in November 2006, February 2009, February 2010, and January 2011. In March 2011, a Proffer Statement / Development Plan submitted by Kettler was approved by Prince William County, which includes the construction of a parking garage by Kettler on the County owned property where current parking lot is located. The Plan further stipulates that until such time that the parking garage is constructed and available for use, Kettler shall continue to allow VRE to lease the surface parking at an annual increase in rent of two percent (2%) per year. VRE staff is requesting permission to extend the lease for one year, at a cost not to exceed $158,475 during that period. The average cost of $41.27 per space, per month is comparable to the current market value VRE is paying elsewhere. FISCAL IMPACT: Funding for this project is included in the FY 2012 and FY 2013 operating budgets. TO: FROM: DATE: RE: CHAIRMAN BULOVA AND THE VRE OPERATIONS BOARD DALE ZEHNER DECEMBER 16, 2011 AUTHORIZATION TO AMEND THE PARKING LEASE AT RIPPON STATION RESOLUTION 10F-12-2011 OF THE VIRGINIA RAILWAY EXPRESS OPERATIONS BOARD WHEREAS, in May 2002, the Operations Board approved a three year lease with Hazel Land for 320 parking spaces at the Rippon VRE Station; and, WHEREAS, these additional spaces were instrumental in reducing the parking shortage at Rippon where the parking lot was routinely 97% full; and, WHEREAS, the lease has been renewed several times since that time, with the current extension set to expire in March 2012; and, WHEREAS, VRE staff is requesting permission to extend the lease for one additional year. NOW, THEREFORE, BE IT RESOLVED THAT, the VRE Operations Board authorizes the Chief Executive Officer to extend the current lease agreement with Kettler for 320 parking spaces at the Rippon Station. The lease extension would be in the amount of $158,475 for one year.