American Disabilities Act (ADA) / Department of Insurance (DOI) Requirements

advertisement
American Disabilities Act (ADA) / Department of Insurance (DOI) Requirements
Maintenance Backlog
Need
Repair known ADA/DOI deficiencies and maintenance backlog items
Target Audience
Potential and Current Students, Faculty and Staff
Charter
Develop and implement a long-term plan to reduce the maintenance backlog across campus,
as well as address any ADA/DOI compliance issues
Strategic Goals
Identify, prioritize, and execute the repair of key maintenance backlog items and known
ADA/DOI deficiencies through the use of one-time state funds on a recurring basis
2013 - 2014
Approved Priorities
1. Replace Cameron Hall Fire Alarm System
2. Replace Trask Cooling Tower
3. Design the replacement of Randall Library Fire Alarm System
4. Replace Morton Hall Chiller
5. Replace Warwick Fire Alarm System
6. Design the modification to the Nixon Annex Entrance
7. Install automatic door openers to Warwick, Dobo, Bear, and Alderman
8. Begin Elevator Upgrades across campus
Performance Targets
Reduce the number of ADA/DOI deficiencies and maintenance backlog items. Maintenance
Backlog is currently $214M.
Core Team Members
Tom Freshwater, Ed Shuford, Sharon Baucom, Mark Morgan, Stan Harts, and Sarah Schaeffer
Project Management
1. If project costs come in under budget, the funds will be used for the next priority project,
staying within the annual total budget amount
2. Funds realigned into Banner 1XXXX
3. Each item will have a unique special project code and a Banner 8-Fund
4. Each project will be classified as a Chancellor Approved project to ensure carry-forward of
unexpended funds into subsequent the year
5. A Mid-Year Review will be conducted to track the progress
6. Process updated annually in the spring with final priortized list completed by July 1st