Addendum #3 New Residence Hall Site Package Alabama A & M University May 13, 2016 Prepared by 4Site (Civil Engineer) and Moody Nolan (Architect) This revision forms a part of and modifies the Bidding Documents dated April 22, 2016, and is to be acknowledged in the Proposal Form. This addendum consists of 2 pages and 5 attachments. The descriptions below are intended as a summary only of the changes to the Drawings. Bidders are required to incorporate all changes to the Drawings into their Bid, regardless of whether or not the changes are listed below. CHANGES TO DRAWINGS: 1. C103 a. b. c. 2. C104 a. b. c. Removed note #2 regarding the gas line (it is covered on sheet C104) Enlarged mechanical yard length to 75’ Modified layout of asphalt drive to accommodate larger mechanical yard Edited gas labels for clarity Edited note #2 for clarity regarding the gas line Added a new power pole, a new transformer location, overhead electric line, and underground electric line 3. C105 a. Added note #3 regarding the spreading of topsoil required once earthwork activity is complete b. Added note #4 regarding excess material to be hauled offsite c. Re-graded the mechanical yard area and the asphalt drive 4. C108 a. Changed top elevation on structure B4 CHANGES TO THE SPECIFICATIONS: 1. Section 00 40 01 Proposal Form— a. Replace in its entirety with the form attached. CLARIFICATIONS: 1. Bidder question: Huntsville Utilities typically runs the gas line and sets the new meter with the mechanical contractor picking it up from there. Will the site contractor have any responsibility for the new gas service? Answer: No. Huntsville Utilities will construct the gas line from the existing main up to the meter; they will also install the meter. Beyond the meter, the building contractor will install the new gas line to the building. The site contractor will have no responsibility for the installation of gas service. All of this is covered in note #2 on sheet C104. 2. Bidder question: Can you confirm that the Pedestrian Bridge and Picnic Tables should be included in the Civil Site package? Answer: Yes. Both of these items, as well as anything shown on the civil drawings (excluding the gas service), are to be considered a part of the civil site package, unless specifically noted as being in the Building Contractor’s or Owner’s scope. 3. Bidder question: The demo shown on sheet C102, is it actually part of this bid package and not part of the previous Demo Bid package? Just want to clarify that the demo items on this sheet C102are to be included in this bid. Answer: Yes. The demolition plan shown on sheet C102 takes into account what will already be demolished as a result of the previous demolition package handled by the university. All items on this demolition plan (sheet C102) are to be included in this bid package. 4. Bidder question: What are the build-ups on the residence hall building pad and the mechanical yard building pad? Answer: This design is not yet complete, and will be a part of the Building Package. 5. C107— a. Clarifications to Note 4 about the ADEM permit -i. Before the site contractor (SC) commences work, the SC is responsible for transferring the ADEM permit from Alabama A&M to the SC within 30 days of execution of the SC’s contract. The SC is responsible for installation and maintenance of erosion control measures until the permit is transferred to the building contractor (BC). ii. Before the BC commences work, the BC is responsible for transferring the ADEM permit from the SC to the BC within 30 days of execution of the BC’s contract. The BC is responsible for installation and maintenance of erosion control measures until construction is complete. b. Clarification to Note 5 about the temporary fence -- The Building Contractor will become responsible for maintaining the fence within 30 days after execution of the Building Contractor’s contract. It is anticipated that the Building Contractor’s contract be executed by July 29. ATTACHMENTS: C103 – Site Development Plan C104 – Utility Plan C105 – Grading Plan C108 – Storm Sewer Plan Section 00 40 01 Proposal Form END OF ADDENDUM # 3 PROPOSAL FORM Project Name: Addenda Received: (Acknowledge all addenda by listing each number in the box) BIDDER INFORMATION Scope of Work Contractor: Address: City/State/Zip Signature of Party authorized to enter into contracts X Contact: Phone: Name: E-Mail: Title: License # (s): Date: BASE PRICE $ 1. $ Total Price $ COST BREAKOUTS Total Material Value: $ - Tax on Materials Total Value On-Site Labor: $ - Total On-Site Man Hours: $ - UNIT PRICES Unit Price Description (including material, tax, delivery & installation) Qty. Add Unit Price Unit Credit Unit Price 1. Seeding and mulching of berms constructed from excess stockpile materials, cost per acre. per acre $ $ 2. Undercut and replacement of unsuitable material encountered during construction with offsite borrow (includes cost of removal of unsuitable material from site and compacted in place borrow from offsite), cost per cubic yard in place. per CY in $ place $ 3. Undercut and replacement of unsuitable material encountered during construction with onsite material (includes cost of excavation of unsuitable material and “spoil” of this material onsite, and compacted in place material from onsite “borrow areas”), cost per cubic yard in place. per CY in $ place $ 4. Haul off and proper disposal of excess soils from site, cost per cubic yard in place (includes removal from site of any excess soils not to remain). per CY in $ place $ 5. Offsite Borrow for Topsoil (includes offsite borrow of any required topsoil not available on site and proper placement for final landscaping), cost per cubic yard in place. per CY in $ place $ 6 Offsite Borrow (structural fill), cost per cubic yard in place. 7,000 CY per CY in $ place $ 7 Undercut of materials from building pad and placement onsite, cost per cubic yard in place. 1,300 CY per CY in $ place $ 8 Undercut of onsite materials and disposal offsite, cost per cubic yard (quantity based on physical dimensions of excavated area). 8a. Undercut from building pad and dispose of offsite 1,300 CY per CY $ $ 8b. Undercut alluvium from parking areas and dispose offsite 3,000 CY per CY $ $ 8c. Topsoil removal and disposal offsite 3,400 CY per CY $ $ Unit Prices are to be all inclusive net cost change including overhead and profit. Page 1/1 © 2016 Moody/Nolan Inc. 2 land planning civil engineering X X X X X DUMPSTER PAD (SEE DETAIL ON SHEET C109) X X X X X land surveying X 319.38' 7500 S. Memorial Pky., Ste. 209 Huntsville, AL 35802 phone 256.539.1221 fax 256.539.1220 www.4siteinc.biz APPROXIMATELY 1,829 LF TEMP. CONSTRUCTION FENCE landscape architecture X X X 2 X X X 5. 00 ' 1 X F/O F/O X F/O X 46.14' X R5 1 NOTES: 1. PRIOR TO CONSTRUCTION COMMENCEMENT, SITE CONTRACTOR TO INSTALL 6' CHAIN LINK PERIMETER CONSTRUCTION FENCE TO PREVENT PEDESTRIAN TRAFFIC FLOW DURING CONSTRUCTION. COORDINATE W/ ARCHITECT FOR TIMING OF REMOVAL OF FENCE. 0' .0 W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS DUCTILE IRON X CURB & GUTTER 24.00' 1 5.00' WALK N: 1558394.20 E: 434174.22 (3) STEPS REQ'D (SEE GRADING PLAN) W 24.00' 2. FOR THE MECHANICAL YARD, THE SITE CONTRACTOR IS RESPONSIBLE FOR CONSTRUCTION OF THE DRIVE UP TO THE CONCRETE PAD. THE BUILDING CONTRACTOR IS RESPONSIBLE FOR WORK INSIDE THE WALL. 5.00' WALK R 0 5. W X DUCTILE IRON 0' 3 X F/O F/O 15.00' X 26.00' 9.00' 0' 5.0 X R1 0' 5 R4. R238.00' X 24.00' X 26.00' R2 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST W X 7.00' WALK DUCTILE IRON PF 20.00' (TYP) 5.00' WALK 9'-8" WALK DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST MERIDIAN ST. 9'-8" WALK W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST S ' 00 K 6. AL W 9.00' (TYP) X 0' NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS R50 .0 DUCTILE IRON 37.00' 23.00' 0' .5 R4 X (7) HANDICAP SPACES (2% MAX SLOPE ANY DIRECTION) W R NEW RESIDENCE HALL F.F.E.= 708.50 9.00' WALK 6.00' CROSS WALK X 0' 4. 5 10.00' WALK NYLOPLAST DUCTILE IRON .70' W 5.00' 5.00' 311.00' R56 9.00' CONC. ' 0 .5 R4 DO NOT POLLUTE DRAINS TO WATERWAYS X DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON ABBREVIATIONS LEGEND BOC BACK OF CURB CONC. CONCRETE EL., ELEV. ELEVATION EOP EDGE OF PAVEMENT ESM'T EASEMENT EX. EXISTING F.F.E. FINISHED FLOOR ELEVATION FG FINISHED GRADE F.S.L. FRONT SETBACK LINE I.E. INVERT ELEVATION INV. INVERT LF LINEAR FEET OVERHEAD TELEPHONE LINE LOC. LOCATION OVERHEAD ELECTRIC LINE MAX. MAXIMUM M.B.L. MINUMUM BUILDING LINE M.H. MANHOLE MIN. MINIMUM N.I.C. NOT IN CONTRACT PVMT. PAVEMENT REQ'D REQUIRED REQ'TS REQUIREMENTS R.S.L. REAR SETBACK LINE R.O.W. RIGHT-OF-WAY S.S. SANITARY SEWER S.S.L. SIDE SETBACK LINE TEMP. TEMPORARY TOC TOP OF CURB EXISTING FIRE HYDRANT TYP TYPICAL PROPOSED WATER LINE U&D UTILITY AND DRAINAGE U.N.O. UNLESS NOTED OTHERWISE STR STRUCTURE CONCRETE MONUMENT, FOUND CONCRETE MONUMENT, SET PROPERTY CORNER, FOUND PROPERTY CORNER, SET DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON DUCTILE IRON ' 5.00LK WA W R56 .70' DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST ' 00 K 6. AL W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON R1 24.00' 5. 5.00' WALK 00 ' W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 20.00' (TYP) X S 7.00' WALK 25.00' F/O EXISTING SANITARY SEWER MANHOLE EXISTING SANITARY SEWER LINE S PROPOSED SANITARY SEWER MANHOLE PROPOSED SANITARY SEWER LINE EXISTING UTILITY POLE EXISTING LIGHT POLE DO NOT POLLUTE DRAINS TO WATERWAYS F/O W F/O DO NOT POLLUTE DRAINS TO WATERWAYS .00' R144 DO NOT POLLUTE DRAINS TO WATERWAYS 11.73' OH E F/O G GAS F/O X 24.00' GAS UGE X 12.00' 5.00' R GAS F/O X 21.00' 0' 0 5. WW WW GAS WW GAS WW GAS F/O GAS F/O X W GAS EXISTING WATER LINE EXISTING WATER VALVE PROPOSED WATER VALVE PROPOSED FIRE HYDRANT Y F/O X W X X S EXISTING GAS LINE X W X W X F/O ASPHALT DRIVE TO MECHANICAL YARD X X X 1 DUCTILE IRON W 16.92' X X X X X X X X X X X UNDERGROUND ELECTRIC LINE H DUMPSTER PAD (SEE DETAIL ON SHEET C109) F/O W NYLOPLAST GAS W F/O DUCTILE IRON GAS W F/O 0' .0 F/O 3 R3 F/O R132.00' X APPROXIMATELY 1,829 LF TEMP. CONSTRUCTION FENCE F/O ' R3.00' 180.00' F/O 00 W R200.00' 5. R1 W R88.00' W NYLOPLAST DUCTILE IRON 0' R144.0 ' 00 2. 1 ' .00 15.00' DIRECTION OF FLOW NYLOPLAST X 9.00' 0' R1 R ' 00 5. R3 .0 R3 X W 5'X5' CONC. PAD GAS W CURB & GUTTER 5.00' WALK X 9.00' W (3) STEPS REQ'D (SEE GRADING PLAN) CONCRETE D X 24.00' FENCE 25' X 75' CONC. PAD FOR MECHANICAL YARD (BUILDING CONTRACTOR'S SCOPE) PROPOSED GAS LINE EXISTING CONTOURS PEDESTRIAN BRIDGE FOR CREEK CROSSING (DESIGN BY OTHERS) EG 661.2 MECHANICAL YARD WALL (ADD "WEEPS" ON SOUTH SIDE FOR DRAINAGE) (DESIGN BY OTHERS) (BUILDING CONTRACTOR'S SCOPE) EXISTING SPOT ELEVATION PROPOSED CONTOURS FG 662.50 SCALE: 1" = 30' 0 2 30' 60' 90' PROPOSED SPOT ELEVATION TREE LINE EXISTING TREES x TEMPORARY SILT FENCE TEMPORARY STONE CHECK DAM TEMPORARY STRAW WATTLE (2) H'CAP SIGNS (VAN ACCESSIBLE) H'CAP SIGNS (TYP) NOTE: SEE SHEET C109 FOR DETAILS REGARDING HANDICAP SPACES EXISTING STORM PIPE DEMO EXISTING ASPHALT 9.00' WALK EXISTING AREA TO REMAIN 6.00' 6.00' 5.00' WALK AREA INLET PRINT DATE: 4/15/2016 2:55:11 PM A360://Alabama University - New Residence Hall/15447_AAMU_ARCH - CORE.rvt FILE INFO: 5.00' LANDING REQ'D (SEE DETAIL) 5.00' 8.00' 8.00' 8.00' 8.00' 8.00' 5.00' 8.00' 8.00' DATE REQUIRED PARKING: REQ'D SPACES = (# OF DWELLING UNITS) x (1.5) DWELLING UNITS: QUAD DOUBLES = 124 QUAD SINGLES = 16 RA = 12 RESIDENT MANAGER = 1 TOTAL UNITS = 152 REQ'D SPACES = (153) x (1.5) = 230 9.00' CHANGE DESCRIPTION 5/3/16 Add. 1 - Site Packagage Revisions 5/9/16 Add. 2 - Site Packagage Revisions 5/13/16 Add. 3 - Site Packagage Revisions PARKING SUMMARY: CURB & GUTTER 2 # 1 2 3 NEW RESIDENCE HALL Meridian Street Normal, AL for Alabama A&M University 1625 Broadway 4th Floor Nashville, TN 37203 Phone: (615) 386-9690 Fax: (615) 386-0528 www.moodynolan.com HANDICAP PARKING PROVIDED PARKING: PROVIDED SPACES = 254 SCALE: 1" = 10' 0 10' CONSULTANTS: Engineering Design Technologies, Inc 4245 Balmoral Dr, Ste 303 Huntsville, AL 35801 256.883.8496 20' 30' 1513 E.CLEVELAND AVE. SUITE 200B EAST POINT, GA 30344 (p) 404.305.0050 (f) 404.305.8868 www.chasmarchitecture.com Dwg. Coord.: Author Tech. Coord.: Checker Site Development Plan Sitework Package Structural Consulting Group 6250 Shiloh Rd Ste 20 Alpharetta, GA 30005 678.513.4242 www.sgc-atl.com 4site 7500 Memorial PKwy SW, Suite 209 Huntsville, AL 35802 256.539.1221 www.4siteinc.biz Proj. # C103 4/22/2016 © 2016 Moody/Nolan Inc. land planning civil engineering land surveying 7500 S. Memorial Pky., Ste. 209 Huntsville, AL 35802 phone 256.539.1221 fax 256.539.1220 www.4siteinc.biz landscape architecture 1 NOTE: 1. ALL UTILITY DETAILS, INCLUDING BEDDING, INSTALLATION, PIPE FITTINGS, ETC., SHOULD BE IN ACCORDANCE WITH THE HUNTSVILLE UTILITIES SPECIFICATIONS. 2 X X X 2. NEW GAS LINE FROM THE EXISTING MAIN TO THE METER IS TO BE INSTALLED BY HUNTSVILLE UTILITIES. NEW GAS LINE BEYOND THE METER TO THE BUILDING IS TO BE INSTALLED BY THE BUILDING CONTRACTOR. X X X DUMPSTER PAD X X X NEW FIBER OPTIC ROUTE (INSTALL TWO 2" CONDUITS PER ROUTE SHOWN; INSTALL PULL BOXES EVERY 100') X X X X X EX. SANITARY SEWER MAIN X X X X X X F/O F/O X X X F/O 3 NEW F.H. F/O X F/O X (THE SITE WORK CONTRACTOR WILL HAVE NO RESPONSIBILITY FOR THE INSTALLATION OF GAS SERVICE.) TIE-IN TO EX. FIBER OPTIC LINE (CONTRACTOR TO VERIFY LOCATION) 2 1 W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON W 1 EX. FIRE HYDRANT TO REMAIN W 5 LF 6" PVC @ 2.00% DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST 73 @ LF 6 1.4 " P 8% VC DUCTILE IRON 5.44' C.O. WITHIN 5' OF BLDG. (SEE PLUMBING PLAN) W 37.34' NEW SSMH TOP= 707.00 I.E. IN (N)= 699.12 (APPROXIMATE) I.E. IN (NW)= 699.32 I.E. IN (W)= 699.32 S W PF 142 LF 4" PVC @ 3.65% DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 5 W .00 AL ' K MERIDIAN ST. DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST W DUCTILE IRON W NEW RESIDENCE HALL F.F.E.= 708.50 W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 8" FIRE LINE TO EXTEND TO NW CORNER OF BLDG. DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 5.00' WALK W DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 37.54' W COORDINATE W/ M.E.P. ON CONNECTION TO BUILDING S VC 6" P% F L 65 2.98 @ 5 LF 6" PVC @ 2.00% EX SSMH TOP= 707.76 I.E. IN (N)= 697.46 I.E. IN (E)= 698.46 I.E. IN (W)= 698.46 I.E. OUT= 697.36 E OH F/O SET NEW POWER POLE 3 GAS DO NOT POLLUTE DRAINS TO WATERWAYS DO NOT POLLUTE DRAINS TO WATERWAYS F/O F/O 8" FIRE LINE GAS GAS F/O NEW GAS METER (SEE NOTE #2 ABOVE) WW W F/O WW GAS WW WW WATER VAULTS (INSTALL FDC BY BACKFLOW PREVENTER) GAS GAS GAS 3 F/O NEW GAS LINE TO SERVICE MECHANICAL YARD (SEE NOTE #2 ABOVE) F/O X F/O X F/O G NEW TRANSFORMER (SEE ELECTRICAL) X F/O W X F/O X X X X X X X NEW FIBER OPTIC ROUTE (INSTALL TWO 2" CONDUITS PER ROUTE SHOWN; INSTALL PULL BOXES EVERY 100') F/O X F/O W GAS F/O X UGE X F/O W W NYLOPLAST DUCTILE IRON X DO NOT POLLUTE DRAINS TO WATERWAYS 1 W NEW OVERHEAD ELECTRIC LINE X X X TIE-IN TO EX. FIBER OPTIC LINE (CONTRACTOR TO VERIFY LOCATION) W ND NEW UNDERGROU ELECTRIC LINE X F/O W GAS W F/O W GAS W W DUCTILE IRON X NYLOPLAST DUCTILE IRON TAPPING SLEEVE & VALVE 3" D.I. DOMESTIC WATER NYLOPLAST X "YARD HYDRANT" TO SERVICE MECHANICAL YARD X 1 1" IRRIGATION METER 1 NEW F.H. GAS W W C.O. WITHIN 5' OF BLDG. (SEE PLUMBING PLAN) 1 F.H. W/ VALVE EX. GAS MAIN (EXACT LOCATION UNKNOWN) EX. 8" CAST IRON WATER MAIN (APPROXIMATE) NEW FIBER OPTIC ROUTE (INSTALL TWO 2" CONDUITS PER ROUTE SHOWN; INSTALL PULL BOXES EVERY 100') EX. SANITARY SEWER MAIN X 2 2 SCALE: 1" = 30' 0 30' 60' 90' # 1 2 3 DATE CHANGE DESCRIPTION 5/3/16 Add. 1 - Site Packagage Revisions 5/9/16 Add. 2 - Site Packagage Revisions 5/13/16 Add. 3 - Site Packagage Revisions PRINT DATE: 4/15/2016 2:55:11 PM A360://Alabama University - New Residence Hall/15447_AAMU_ARCH - CORE.rvt FILE INFO: NEW RESIDENCE HALL Meridian Street Normal, AL for Alabama A&M University 1625 Broadway 4th Floor Nashville, TN 37203 Phone: (615) 386-9690 Fax: (615) 386-0528 www.moodynolan.com CONSULTANTS: Engineering Design Technologies, Inc 4245 Balmoral Dr, Ste 303 Huntsville, AL 35801 256.883.8496 1513 E.CLEVELAND AVE. SUITE 200B EAST POINT, GA 30344 (p) 404.305.0050 (f) 404.305.8868 www.chasmarchitecture.com Dwg. Coord.: Author Utility Plan Sitework Package Tech. Coord.: Checker Structural Consulting Group 6250 Shiloh Rd Ste 20 Alpharetta, GA 30005 678.513.4242 www.sgc-atl.com 4site 7500 Memorial PKwy SW, Suite 209 Huntsville, AL 35802 256.539.1221 www.4siteinc.biz Proj. # C104 4/22/2016 © 2016 Moody/Nolan Inc. land planning civil engineering land surveying 7500 S. Memorial Pky., Ste. 209 Huntsville, AL 35802 phone 256.539.1221 fax 256.539.1220 www.4siteinc.biz landscape architecture 2 BENCHMARK #1 N: 1558530.62 E: 434222.96 2 1 BENCHMARK #2 N: 1558511.03 E: 1558511.03 X X X 700 X NOTES: 1. SPOT ELEVATIONS ON MECHANICAL YARD ARE TO FINISHED GRADE OF CONC. PAD. 2. "CROWN" BUILDING PAD BY GRADING FROM EDGE UP 1.0% TO "PAD" ELEVATIONS SHOWN. X X X X 710 705 X 3. THE SITE CONTRACTOR SHALL BE RESPONSIBLE FOR PLACEMENT AND SPREADING OF ALL TOPSOIL REQUIRED FOR COMPLETION OF THE REQUIRED LANDSCAPING ONCE OTHER EARTHWORK ACTIVITIES ARE COMPLETED, INCLUDING PLACEMENT OF TOPSOIL OVER AREAS BACKFILLED AGAINST THE STORM SHELTER FOUNDATION WALLS UNDER THE BUILDING CONTRACTOR'S SCOPE OF WORK. X X 700 X X X X X 2 X X 706 FG 708.50 X X X X X 70 7 708 8 70 707 708 705 W X 70 8 5 70 X 70 70 4 3 2 70 70 70 1 0 X HP 707.62 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 2 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST 4. EXCESS MATERIAL GENERATED FROM EARTHWORK IS TO BE HAULED OFFSITE AS DIRECTED BY THE OWNER. W PAD 708.78 706 1 WALK (TYP) FG (TYP) 708.45 708.00 1 PAD 708.78 1 FG 707.78 FG 707.50 FG 706.58 FG 706.70 PAD 708.79 NYLOPLAST DUCTILE IRON HP 707.35 SITE BENCHMARK NO. 1 W 699 X W X 703 TOP STEP: 708.45 BOTTOM STEP: 706.95 DO NOT POLLUTE DRAINS TO WATERWAYS 70 1 702 1 707 X DUCTILE IRON FG 704.63 DO NOT POLLUTE DRAINS TO WATERWAYS HP 708.37 DO NOT POLLUTE DRAINS TO WATERWAYS X DO NOT POLLUTE DRAINS TO WATERWAYS 700 W FG 706.19 X X 706 X X X X X 700 707 706 DO NOT POLLUTE DRAINS TO WATERWAYS DO NOT POLLUTE DRAINS TO WATERWAYS DUCTILE IRON W 709 W WW W WW 710 3 FG 705.78 WW 709 709 6 708 707 70 700 700 WW 708 77 1010 FG 705.24 2 W NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS 703 704 W 696 X 697 707 X X X X LOWER EX. POWER POLE ELEVATION PER GRADING W FG 705.53 X X X X 6 95 709 W 705 BENCHMARK #3 N: 1558108.13 E: 434296.47 707 DUCTILE IRON 706 W 1 NYLOPLAST X DO NOT POLLUTE DRAINS TO WATERWAYS 706 70098 7 07 7 FG 707.56 HP 707.85 X 698 HP 707.85 W W FG 707.37 PAD 708.78 GAS W 696 695 W FG 705.63 695 1 GAS W 697 W S FG (TYP) 708.00 GAS W 709 HP 707.35 708 PAD 708.79 FG (TYP) 708.00 TOP STEP: 708.35 BOTTOM STEP: 706.85 NYLOPLAST DUCTILE IRON 699 1 WALK (TYP) 1 708.45 PAD 708.78 FG 707.80 70 9 NYLOPLAST DUCTILE IRON X X DUCTILE IRON 707 701 702 701 700 FG 704.63 NYLOPLAST 707 708 699 698 X NYLOPLAST DUCTILE IRON FG 708.08 DUCTILE IRON WALK (TYP) 706.85 7 70 FG 708.22 FG 708.43 TRAVERSE MAG NAIL ON THE EAST SIDE OF MERIDIAN STREET, APPROXIMATELY 75' NORTH OF THE EXISTING CREEK ELEV: 707.94 707 700 708 W 8 5 HP 707.95 NYLOPLAST 710 FG 708.45 7 SITE BENCHMARK NO. 3 DO NOT POLLUTE DRAINS TO WATERWAYS W DO NOT POLLUTE DRAINS TO WATERWAYS 9 MAG NAIL ON THE EAST SIDE OF MERIDIAN STREET, APPROXIMATELY 45' NORTH OF THE DRIVE ENTRANCE TO THE CRUMP AGRICULTURAL MECHANICS BUILDING ELEV: 709.05 708 08 1 SITE BENCHMARK NO. 2 EX. POWER POLE TO REMAIN 707 FG 708.14 FG 708.30 FG 708.38 70 NYLOPLAST DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS 88 7700 70 7 6 70 2 70 FG 705.03 70 X FG 704.63 X DO NOT POLLUTE DRAINS TO WATERWAYS 706 DO NOT POLLUTE DRAINS TO WATERWAYS 70 7 W 707 704 703 702 701 X FG 707.74 FG 708.60 W NEW RESIDENCE HALL F.F.E.= 708.50 X 697 HP 708.74 708.75 DUCTILE IRON 70 X DUCTILE IRON DUCTILE IRON NYLOPLAST 2 7 70 8 70 NYLOPLAST NYLOPLAST X X 698 FG 708.21 FG 708.08 X 698 697 FG 705.03 705.02 WALK (TYP) 708.45 X X 699 700 FG 704.63 S X DUCTILE IRON FG 707.71 707 NYLOPLAST FG 707.35 TRAVERSE NAIL ON THE WEST SIDE OF MERIDIAN STREET, APPROXIMATELY 65' NORTH OF THE DRIVE ENTRANCE TO THE CRUMP AGRICULTURAL MECHANICS BUILDING ELEV: 710.95 X HP 708.00 8 70 PF 1 700 705 706 # 1 2 3 DATE CHANGE DESCRIPTION 5/3/16 Add. 1 - Site Packagage Revisions 5/9/16 Add. 2 - Site Packagage Revisions 5/13/16 Add. 3 - Site Packagage Revisions SCALE: 1" = 30' 0 30' 60' 90' PRINT DATE: 4/15/2016 2:55:11 PM A360://Alabama University - New Residence Hall/15447_AAMU_ARCH - CORE.rvt FILE INFO: NEW RESIDENCE HALL Meridian Street Normal, AL for Alabama A&M University 1625 Broadway 4th Floor Nashville, TN 37203 Phone: (615) 386-9690 Fax: (615) 386-0528 www.moodynolan.com CONSULTANTS: Engineering Design Technologies, Inc 4245 Balmoral Dr, Ste 303 Huntsville, AL 35801 256.883.8496 1513 E.CLEVELAND AVE. SUITE 200B EAST POINT, GA 30344 (p) 404.305.0050 (f) 404.305.8868 www.chasmarchitecture.com Dwg. Coord.: Author Grading Plan Sitework Package Tech. Coord.: Checker Structural Consulting Group 6250 Shiloh Rd Ste 20 Alpharetta, GA 30005 678.513.4242 www.sgc-atl.com 4site 7500 Memorial PKwy SW, Suite 209 Huntsville, AL 35802 256.539.1221 www.4siteinc.biz Proj. # C105 4/22/2016 © 2016 Moody/Nolan Inc. land planning civil engineering land surveying 7500 S. Memorial Pky., Ste. 209 Huntsville, AL 35802 phone 256.539.1221 fax 256.539.1220 www.4siteinc.biz landscape architecture X X X 700 X X X X X 710 705 X X X X X X X X X X 5 X X X X X 70 7 707 708 708 705 W X 8 70 STR B1 TOP= 703.94 I.E. OUT= 701.19 X 70 8 70 706 70 4 70 3 70 2 70 70 1 0 X DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST STR A1 TOP= 706.12 I.E. OUT= 703.10 Structure Name COORDINATES Structure Details DUCTILE IRON RIM = 706.12 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST X DUCTILE IRON N: 1558407.94 E: 434202.78 Pipe - (190) 18" I.E. OUT = 703.10 41 LF 18" @ 0.50% 707 105 LF W18" @ 0.50% RIM = 705.55 NYLOPLAST DUCTILE IRON RIM = 705.55 W 7 70 8 70 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST STR C2 TOP= 707.70 I.E. IN (N)= 703.51 I.E. IN (SE)= 703.51 I.E. OUT= 703.41 RIM = 705.84 STR A3 TOP= 705.55 I.E. IN (N)= 702.46 I.E. IN (W)= 702.46 I.E. OUT= 702.36 NYLOPLAST DUCTILE IRON N: 1558226.62 Pipe - (168) 18" I.E. IN = 702.04 E: 434199.73 Pipe - (172) 15" I.E. IN = 702.04 Pipe - (169) 18" I.E. OUT = 701.94 A4 RIM = 705.79 N: 1558227.70 E: 434135.72 Pipe - (172) 15" I.E. OUT = 703.04 A4A NEW RESIDENCE HALL F.F.E.= 708.50 63 LF 18" @ 0.50% X 44 LF 15" @ 0.50% W DUCTILE IRON S 61 LF 18" @ 0.87% N: 1558294.02 E: 434136.83 Pipe - (171) 18" I.E. OUT = 702.99 A3A 707 STR A3A TOP= 705.74 I.E. OUT= 702.99 RIM = 705.74 DO NOT POLLUTE DRAINS TO WATERWAYS 706 DO NOT POLLUTE DRAINS TO WATERWAYS W 704 703 702 701 STR C2A TOP= 706.23 I.E. IN (STUB)= 703.83 4" ORIFICE= 703.73 I.E. OUT= 703.73 W93 LF 18" @ 0.50% 697 68 LF 18" @ 0.50% X X DUCTILE IRON STUB 8" HDPE 10 LF PVC FOR CONNECTION OF FOUNDATION DRAIN 707 700 698 699 X 1 NYLOPLAST N: 1558292.95 Pipe - (167) 18" I.E. IN = 702.46 E: 434200.85 Pipe - (171) 18" I.E. IN = 702.46 Pipe - (168) 18" I.E. OUT = 702.36 A3 PF STR B2 TOP= 704.86 I.E. IN= 700.66 I.E. OUT= 700.56 N: 1558364.39 Pipe - (190) 18" I.E. IN = 702.90 E: 434202.05 Pipe - (167) 18" I.E. OUT = 702.80 A2 STR A2 TOP= 705.55 I.E. IN= 702.90 I.E. OUT= 702.80 DO NOT POLLUTE DRAINS TO WATERWAYS X 703 702 70 1 W A1 RIM = 705.50 N: 1558110.07 Pipe - (169) 18" I.E. IN = 701.37 E: 434197.78 Pipe - (170) 24" I.E. OUT = 701.27 A5 8 70 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON X DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON 70 2 DUCTILE IRON 701 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DO NOT POLLUTE DRAINS TO WATERWAYS W 95 LF W 18" @ 0.50% 704 703 STR D1 TOP= 706.92 I.E. OUT= 703.13 3 B4 DO NOT POLLUTE DRAINS TO WATERWAYS NYLOPLAST DUCTILE IRON NYLOPLAST RIM = 701.95 DO NOT POLLUTE DRAINS TO WATERWAYS W DO NOT POLLUTE DRAINS TO WATERWAYS DUCTILE IRON W 59 LF 15" @ 1.93% X 47 LF 24" @ 0.50% WW X 700 X X X X X STR B5 HWALL TOP= 701.95 I.E. IN= 699.20 700 WW 710 X X X X X X X X X X X X X 695 W WW STR D2 HWALL TOP= 704.50 I.E. IN= 702.00 B5 HWALL STR A5 TOP= 705.50 I.E. IN= 701.37 I.E. OUT= 701.27 N: 1558195.18 E: 434008.49 Pipe - (183) 15" I.E. OUT = 704.57 RIM = 707.70 N: 1558239.85 Pipe - (181) 15" I.E. IN = 703.51 E: 433957.01 Pipe - (183) 15" I.E. IN = 703.51 Pipe - (182) 18" I.E. OUT = 703.41 C2 700 700 N: 1558063.08 E: 433846.84 Pipe - (180) 24" I.E. IN = 699.20 RIM = 706.75 C1 GAS W 695 WW 58 LF @ 0.5 24" 0% W X W X W X W 708 W X W GAS W 697 W 696 695 N: 1558210.36 Pipe - (178) 18" I.E. IN = 700.10 E: 433851.65 Pipe - (182) 18" I.E. IN = 700.10 Pipe - (179) 18" I.E. OUT = 700.00 3 RIM = 704.79 N: 1558112.83 Pipe - (179) 18" I.E. IN = 699.53 E: 433850.01 Pipe - (180) 24" I.E. OUT = 699.43 B3 W X RIM = 704.83 NYLOPLAST X N: 1558306.27 Pipe - (177) 18" I.E. IN = 700.66 E: 433853.26 Pipe - (178) 18" I.E. OUT = 700.56 B2 S DUCTILE IRON X RIM = 704.86 GAS W 702 701 700 699 698 X 708 STR C1 TOP= 706.75 I.E. OUT= 704.57 STR B4 TOP= 704.79 I.E. IN= 699.53 I.E. OUT= 699.43 N: 1558413.84 E: 433855.07 Pipe - (177) 18" I.E. OUT = 701.19 70 9 NYLOPLAST DUCTILE IRON X 700 708 N: 1558050.57 E: 434183.71 Pipe - (170) 24" I.E. IN = 700.98 RIM = 703.94 B1 114 LF 18" @ 0.50% X DUCTILE IRON STR B3 TOP= 704.83 I.E. IN (N)= 700.10 I.E. IN (E)= 700.10 I.E. OUT= 700.00 STR A4A TOP= 705.79 I.E. OUT= 703.04 6 @4L 1.6 F 1 6% 5" RIM = 703.73 A6 HWALL 707 W " LF 18 106 3.11% @ STR A4 TOP= 705.84 I.E. IN (N)= 702.04 I.E. IN (W)= 702.04 6" ORIFICE= 701.94 I.E. OUT= 701.94 61 LF 15" @ 1.64% STR A6 HWALL TOP= 703.73 I.E. IN= 700.98 RIM = 706.23 N: 1558286.86 E: 433957.80 Pipe - (181) 15" I.E. OUT = 703.73 C2A 705 706 RIM = 706.92 N: 1558119.96 E: 434037.60 Pipe - (184) 15" I.E. OUT = 703.13 D1 RIM = 704.50 D2 HWALL N: 1558058.64 E: 434042.96 Pipe - (184) 15" I.E. IN = 702.00 # 1 2 3 SCALE: 1" = 30' 0 30' 60' 90' PRINT DATE: 4/15/2016 2:55:11 PM A360://Alabama University - New Residence Hall/15447_AAMU_ARCH - CORE.rvt FILE INFO: PIPE RUN DATE CHANGE DESCRIPTION 5/3/16 Add. 1 - Site Packagage Revisions 5/9/16 Add. 2 - Site Packagage Revisions 5/13/16 Add. 3 - Site Packagage Revisions SIZE LENGTH SLOPE D1-D2 HWALL 15" 59 1.93% C1-C2 15" 64 1.66% C2A-C2 15" 44 0.50% A4A-A4 15" 61 1.64% A1-A2 18" 41 0.50% C2-B3 18" 106 3.11% B3-B4 18" 95 0.50% B2-B3 18" 93 0.50% B1-B2 18" 105 0.50% A3A-A3 18" 61 0.87% A4-A5 18" 114 0.50% A3-A4 18" 63 0.50% A2-A3 18" 68 0.50% B4-B5 HWALL24" 47 0.50% A5-A6 HWALL24" 58 0.50% NEW RESIDENCE HALL Meridian Street Normal, AL for Alabama A&M University 1625 Broadway 4th Floor Nashville, TN 37203 Phone: (615) 386-9690 Fax: (615) 386-0528 www.moodynolan.com CONSULTANTS: Engineering Design Technologies, Inc 4245 Balmoral Dr, Ste 303 Huntsville, AL 35801 256.883.8496 1513 E.CLEVELAND AVE. SUITE 200B EAST POINT, GA 30344 (p) 404.305.0050 (f) 404.305.8868 www.chasmarchitecture.com Dwg. Coord.: Author Storm Sewer Plan Sitework Package Tech. Coord.: Checker Structural Consulting Group 6250 Shiloh Rd Ste 20 Alpharetta, GA 30005 678.513.4242 www.sgc-atl.com 4site 7500 Memorial PKwy SW, Suite 209 Huntsville, AL 35802 256.539.1221 www.4siteinc.biz Proj. # C108 4/22/2016