March 13, 2008 12 Noon, Room 1506

advertisement

March 13, 2008

12 Noon, Room 1506

In attendance: See attached sheets

Central Utility Plant:

The loop trench, Phase 1, is finished in vicinity of Bldgs. 400/600/700

The loop trench, Phase 2, began in January 2008.

Parking Lot “D” will reopen before March 1, 2008.

New signs indicating what is going on have been installed, i.e. “your dollars at work”

Graduation will be held in the Grand Court

Plan of Work – 2007/08

Buildings 800/900/1000, IOB, CSSC, Athletic Fields and Parking Lots will all be under construction during the Spring Semester. The front of the campus will be heavily impacted.

IOB begins in late March

Parking Lot is hitting many unforeseen underground conditions.

Villas need to shut down one ramp a week early to connect storm drain from parking lot.

Lighting problem, no lights around building 500 will be fixed.

Lot J was temporarily cordoned off for the hammer throw/discus.

1700/1800 project may receive gren light as early as September.

Parking Status

Shut down of parking lot G/H happened on schedule

Increased Campus Security first week to help students find overflow parking

Heart of Bay church parking is for employees only – 255 spaces

Temporary “J” Lot is complete – 385 spaces

“J” lot is underutilized – 220 spaces

Communications include e-mails to employees with map to Heart of Bay, Website showing students how to get to “J” Lot, Faculty sharing maps and info with classes.

Heart of the Bay cleaning must be later due to church request not to disturb neighbors.

Chabot College

Facilities Committee Minutes – Pg. 2

March 13, 2008

Board of Trustees Agenda - March

Construction of Instructional Office Building

Central Utility Plant

Inspector of Record, Testing and Inspection

Itemized List Discussion:

- It was mentioned that there was a concern about the dust on campus, i.e. what is in the dust and is it dangerous? Following discussion pointed out that dust is an allergen, not a pathogen. All hazardous materials in our buildings and on our sites are removed by hazmat contractors and the areas are certified “clean” before construction activity is allowed to occur.

- It was asked would we inform the campus if we found an alien space ship while trenching for the central plant loop? Doug Horner responded that we most certainly would.

End of Meeting

Upcoming Fall schedule of meetings:

April 10 & 24

May 8 & 22

***To add agenda items please contact Doug Horner – CLPCCD