Acceptance Testing & Documentation to Support Validation Paul Hallman CEO Turnkey Modular Systems Inc. September 21st, 2015 What supports Validation For most equipment and systems Factory Acceptance Testing is the main focus of support used in the Validation of process equipment or systems. Acceptance Testing The question of what USER ACCEPTANCE TESTING (UAT) is, becomes very important as you reach a state of having equipment or systems delivered to a facility. The system or equipment is claimed to be constructed in a manner that has been defined by a User Requirement, and constructed or fabricated in a manner that meets the requirements of the industry and of your company specifically. You can ill afford to accept a system or piece of equipment that does not meet these requirements and as such, it is important and essential to execute a detailed list of acceptance requirements that will support your corporate validation effort. What is Acceptance Testing • User Acceptance Testing defines precisely and clearly what the user expects the system to do. UAT documents contain information about the operating environment, the required data for processing, and the functionality that the system should carry out. • Completed during a FAT and a SAT What is the difference between a FAT & a SAT? Any project that involves equipment being developed from a third party should have a FAT and SAT incorporated into the system life-cycle. If both the FAT and SAT are performed correctly is will lead to a much easier IQ/OQ process. What is a FAT • A FAT or Factory Acceptance Test is usually preformed at the vendor prior to shipping to a client. The vendor tests the system in accordance with the clients approved test plans and specifications to show that system is at a point to be installed and tested on site. • It’s an essential aspect of the whole system lifecycle and should be performed by experienced personnel. Time spent doing a proper FAT will lead to fewer problems when the equipment is installed. Summary - It is the partial commissioning and qualification of equipment and/or systems prior to their shipment from the fabricator’s site. Typical Items on a FAT FAT items to look out for include the following: • • • • • • • • • • Performed FAT Protocol Maintenance and User’s manual Recommended spare parts list Certificate of compliance As built technical drawings (electrical, mechanical, pneumatic & process schemes) Materials certificates/data sheets Main equipment data sheets Instruments calibration certificates Installation and construction details (Deadlegs, slope etc) Welding Processes qualification & Records What is a SAT • SAT is Site Acceptance Test of a system to ensure it is tested in accordance to client approved test plans and specifications & to show the system is installed properly and interfaces with other systems and peripherals in its working environment. Summary - Inspection and /or dynamic testing of the systems or major system components to support the qualification of an equipment system conducted and documented at the manufacturing site. Typical items on a SAT Below is a list of some items to be considered on a SAT: • • • • • • Finishing Visual check Main components visual check Utilities functionality and setting checks Functionality/Interlocks Verification (Mechanical & Software) Safety devices and interlocks check Operator’s training How to write a FAT Protocol 1. 2. 3. 4. 5. 6. 7. 8. 9. Define the Purpose of the FAT so as to ensure that the equipment is designed per the specs and to check the basic performance of the equipment Scope of the FAT Protocol Procedures 1. To check the equipment operation 2. To define the action to be taken when deviations take place 3. To define a list of documents to be checked Documentation – Write a list of documentation to be done during FAT Acceptance Criteria – Equipment and Accessories should be according to the PO and the equipment should be per the pre-designed parameters Verification Sheets – include Make, Model, Capacity, Design, Controls, PLC, Instruments, Safety Features, Documents Observed Deviations – Write the deviations observed during the FAT and list the corrective action and whether is it acceptable or now Conclusion – Conclude the overall FAT results and if it passed or failed Approval – Include signatures, departments and dates FAT – Therapure LAI Project 3D Modular Design 3 D Modular Design 3D Modular Design 3D Modular Design 3D Modular Design 3D Modular Design Factory Pictures Factory Pictures Factory Pictures Factory Pictures FAT PROTOCOL EXAMPLES FAT COMPLETED DOCUMENT EXAMPLE OTHER DOCUMENTS AND SUPPORT DETAILS IN A TURNOVER PACKAGE Welding Procedure Welder / Operator Identification Card Inspector Compliance Certificate Calibration Record TSSA Application Typical Spool Drawing and Map Visual Inspection Sheet Process Piping Weld Etching 1. 2. 3. 4. Spool # Welder ID / Weld # Date of Weld Heat # of Component Weld Joint Typical Documentation For Further Information: Contact: Paul Hallman Turnkey Modular Systems Inc. 8-4090 Ridgeway Drive, Mississauga, Ontario, Canada L4L 5X5 Mobile: 519-851-8006 Office: 905-608-8006 Ext 228 Fax: 905-608-8007 E-mail: phallman@tkmodular.com